ADJUSTING THE UPPER AUGER
J&M Manufacturing419-375-2376
284 Railroad St.
2
Extend the auger into the unload position. Engage the upper auger into the lower auger by rotating the driveline.
Extend The Auger Parts Description
3
1.25” Hex Nut 1.25” Hex Nut
4 Hole Flange Bearing
Pipe SpacerHeadpan
Parts Description
4
1/8”-3/16”
Untighten the 1-1/4” Hex Nut at least an 1/4”.
Tighten the 1-1/4” Hex Nut until it is tight against the 4 hole fl ange bearing.
Tighten the 1-1/4” Hex Nut until there is a 1/8” to 3/16” gap inbetween the 4 hole fl ange bearing and the headpan.
1
2 3
Adjustment