Cyclone Damage Photograph & House Proposed Photograph
CHODAVARAM MANDAL
AT
ADDURU VILLAGE (73 Houses) CHODAVARAM MANDAL,
VISAKHAPATNAM District, A.P
TOTAL HOUSES –73
PROJECT COST :- 290.54Lakhs
A.P.STATE HOUSING CORPORATION LIMITED
VISAKHAPATNAM DISTRICT
NEW NTR HOUSING PROGRAMME
CYCLONE REHABILITATION
Preamble:
HUDHUD cyclone has occurred on and devastedalmost entire
area of 4 coastal districts of Andhra Pradesh. Srikakulam,
Vizianagaram, Visakhapatnam and East Godavari were badly hit by
the cyclone and the worst hit to Visakhapatnam City. As per records
of IMD Hyderabad till date, all cyclones made landfall in the plains
and semi-urban areas along the Indian coast.Hudhud not only
emerged as first high intensity cyclonic storm in 2014 to make
landfall at wind speeds of 206 kmph, but also the third highest
intensity cyclonic storm out of the 515 cyclonic storms that
developed in either the Bay of Bengal or the Arabian Sea since
1891. Heavy damages were occurred for Infrastructure, Housing,
Companies and other public and private properties. Most of the
people have become homeless.
Regarding restoration and cyclone relief operations, Apart
from plunging the Department in to action, many voluntary
organizations and many people have contributed services and
financial assistance, supplied material etc. Many corporate
companies have also come forward to give support the shelter less
poor and broadly the cyclone victims. They have also made
proposals to provide cyclone resistant and seismic resistant buildings
along with infrastructure to bring to normal status.
Keeping in view of the hardship being faced by the victims the
Govt., have taken a decision to develop colonies with the assistance
from NGOs, VoluntaryOrganization, Multi National companies etc for
a quick relief to the affected families.
1
Damages reported during the Hudhud Cyclone in ADDURU Panchayat:
Mandal PanchayatNo of
HousesTotal
CHODAVARAM ADDURU 73 73
Hence, a comprehensive development with Housing and
Infrastructure Project proposal is prepared with a view to sustain Cyclone
damages in feature.
CYCLONE RECONSRUCTION PROGRAMMEPROJECT PROPOSAL
I.1 Location:
The Village is situated at 8 Km from CHODAVARAM Mandal
And 22 Km from Anakapalli city.
The village is connected by rail network at a distance of 22 Kms.
(In case of rehabilitation, share about proposed relocation site & infrastructure also)
I.2 About the Village:
Rivers, water sources for Drinking /Agriculture etc.
People’s development in cultural and economic areas.
Abundant availability/Scarce availability wrt construction of houses,
development of people
I.3 Topography:
2
The village is located on fairly sloping ground with a general fall
from North-East to South-West. The nature of the soils is generally
Rocky/hard gravel/sandy/clayey/loamy/mixed soils etc. below the ground.
The ground water table is at about 25 mt - 30 mt below the ground
level. The maximum summer temperature rises as high as 42C.
I.4 Demographical features.
The population is 2300 as per 2011 census, out of which male
population is 1174 and Female population is 1126 and having ………….
wards, in this village .literacy peoples are 1173
Statement enclosed.
I 5.The existing Infra Structure:
The existing village with its present level of development is
analyzed in the following paras with a reference to Population, Housing,
Slums, Water supply, educational and medical facilities and other
infrastructure facilities.
a) Population and Housing:
ADDURU (DPR) village is having population of 2300 as per2011
census and having 698 households existing in the village. According to
the condition of the house the statistics are as follows.
(Good Livable 625 And dilapidated condition 73.)
Statement enclosed.
b) Details of Surveys and PRA exercise :
3
Preliminary reconnaissance survey is conducted to capture the
demographic, infrastructure data etc. for which the Door to Door house
hold surveys has become vital. Identified the families who fall below
poverty line as well as sanctions of pensions etc.
1. It is proposed to accommodate in the existing colony with scattered
manner duly utilizing the existing infrastructure and proposing to
bridge the gap in the existing infrastructure development for
creating habitable conditions.
c)Road Net work and connectivity in the Village:
ADDURU
The Village has total roads of length 3.5 KMs, of which 1 KMs are gravel roads,1KMs are WBM roads 0 KMs are BT Roads ,1.5 KMs are CC Roads and balance KMs are earthen roads.
Statement enclosed.
d)Water Supply:
Protected water supply with 0 Public Taps and 0 individual supply
connections are available. In addition to 39 hand pumps are already
available in this village.
e)Drainage:
Village provided drainage facility system. The village has Drainage
facility Drains Length 1.5 Km. Requires further 2 The line estimates are
prepared and enclosed.
f)Education Facilities:
4
1 M.P.U.P Schools 0 Z.P.Schooland 0 Urdhu School are existing.The
student teacher ratio is 28:1 Apart from this 0 private institutes are
available. Statement enclosed.
g)Medical Relief:
One Government hospital & First aid centers etc are available
within the vicinity 0.5 Km Distance.
Street Electrification facility provided. The total length of
streets in this village 5.5 km.
“Statement enclosed”
Infrastructure Estimate Proposals:
Provisions of comprehensive infrastructure facilities are aimed and the
line estimate proposals are prepared for Water supply, Street
Electrification, Individual and community Sanitation, Roads etc.,.
Construction of Cyclone resistant Buildings for Weaker Sections
CYCLONE RESISTANT FEATURES PROPOSED
Dwelling unit with a plinth area of 30 Sqmt. along with bath-cum-
toilet of 2.75 Sqmt. is proposed.
The houses are to be constructed with RCC frame.
Basement height is fixed as 1 mt. above ground level to avoid
inundation.
Plinth level beam has been provided for the structural stability.
Lintel level beam is also provided for anchorage between wall and
roof slabs.
The size of the house site shall be not less than 80 Sqyds
A staircase is provided to have an access to the roof slab.
Parapet wall is proposed around the slab for safety.
5
Internal electrification has been proposed.
Flooring and internal plastering is also proposed.
Salient features of Dwelling Unit Design:
Accommodation:
Multipurpose room of size 9’.00’’ x 11’.2’’.
Bed room of size 9’.00’’ x 9’.10’’
Kitchen of size 9’.00’’ x 5’.0’’.
Bath / toilet of size 6’.00’’ x 4’.0’’.
Verandahof Size 9’.4’’ x 4’.0’’.
Internal Infrastructure:
a. Internal Electrification
b. Sanitary arrangements
c. Ceramic flooring
Mode of Execution:
Execution through Builders / NGOs./CBOs/External Agencies
In this mode of construction the cost of construction per house with
cyclone resistant features would be Rs.3.98 lakh. This is mainly due
to addition of statutory provisions and fulfillment of the conditions.
The estimated cost for construction of houses through tender
contract system would be @ Rs.1124/- per sft. i.e.,
Rs.3,98,000/-.This is mainly due to provision of VAT 5%, Labourcess
1%, QC charges 1.5%, tender premium 5%, Additional PS charges
4.5%, Overheads& Builder’s profit 14% to fulfill the conditions by
the Builder.
PLINTH AREA COST ANALYSIS OF RURAL HOUSING
6
Description Construction of building by Contractor
Building With Electrification Including Toilet
Estimated cost355000 364000 398000
(inRs.)Plinth area
324 324 354(insft.)
Total rate1096 1123 1124
(inRs./sft.)
RURAL UNIT COST BREAK UP (Component wise)
Sl No DetailsAmount(in Rs)
1 Cost per House 278000.00
2 Toilet 26000.00
Sub Total 304000.00
Add Provisions
3 Provision towards VAT 5% 15200.00
4 Provision towards Labourcess 1% 3040.00
5 Provision towards QC &Consulteny charges @ 2.5%
7600.00
6 Provision towards Tender Premium @5% 15200.00
7 Provision Towards PS charges3% 9120.00
8 Unforeseen Items 1280.00
Total (Excluding OHC) 355440.00
9 Add Over Head Charges @14% 42560.00
Total Cost per House 398000.00
detailed estimate has been prepared and enclosed (Annexure-I)
Proposed financing Pattern:
7
GOI Share :Rs 56,250/-
Swatch Bharat Abhiyan :Rs 12,000/-
Ben.Contribution : Rs 1,750/-
World Bank Share : Rs 199000/-
State Govt. Share : Rs 129000/-
___________Total Rs 3,98,000/- ____________
INFRASTRUCTURE:
Infrastructure requirements has been assessed for scattered
housing and cluster housing separately. Estimates have been prepared
for provision of Water supply, Drainages, Roads, Electrification separately.
Details of Amount Required For Provision of Infrastructure
OPTION –I
• Infrastructure with WBM roads, masonry drains, water supply and
solar street lighting would cost Rs.80,000/- per plot.
Laying of WBM Roads = Rs.27,000/-
Construction of masonry drains = Rs.27,000/-
Drinking water facility = Rs.16,000/-
Solar Street lighting = Rs.10,000/-
Total = Rs.80,000/-
• Wherever leveling is required an additional amount of Rs.69,600/-
per plot is required for leveling.
OPTION –II
• Infrastructure with CC roads, CC drains, water supply and solar
street lighting would cost Rs.1,02,000/- per plot.
Laying of CC Roads = Rs.38,000/-
Construction of CC drains = Rs.38,800/-
8
Drinking water facility = Rs.16,000/-
Solar Street lighting = Rs.10,000/-
Total = Rs.1,02,800/-
Name of the District VISAKHAPATNAMName of the Division NARSIPATNAMName of the Mandal CHODAVARAMName of the Village ADDURUScheme & Year Phase IAY-2014-15(CRP)
No.of Houses Damaged 73Caste Wise break up of
Damaged houses
SC ST BC OC Min
0 0 73 0 0
Habitation wise No.of Houses Proposed
Layout Scattered Total
ADDURU 0 7373
Caste wise breakup of HousesProposed
73
Caste Wise break up of HousesProposed
SC – 0 ST - 0 BC – 73 OC – 0 Min - 0
• Solar lighting for individual houses with 1 KV off grid power would
cost Rs.2.47 Lakh per house and 30% of the cost would be
subsidized by MNRE, GoI.
9
HOUSING REQUIREMENT AND PROJECT PROPOSAL AT A GLANCE
Requirement of funds (Rs. in Lakhs)
HousingNo. of houses
GOI SBA BCWorld Bank Share
State Govt.Share
Total
ADDURU73 41.06 8.76 1.28 145.27 94.17 290.54
Habitation-II 0 0 0 0 0 0
Habitation-III 0 0 0 0 0 0
Habitation-IV 0 0 0 0 0 0
Habitation-V 0 0 0 0 0 0
Total : 73 41.06 8.76 1.28 145.27 94.17 290.54
Infrastructure 0WS Drainage Roads
Street Lighting
Leveling Total
0 0 0 0 0
Total:
73 41.06 8.76 1.28 145.27 94.17 290.54
10
PROPOSED MODALITIES FOR EXECUTION
Nodal agency will be identified for coordination between the NGOs /
VOs / CBOs & Corporate and the Government.
Standard dwelling unit plan and specifications has been finalized for
both Rural and Urban areas duly incorporating cyclone resistant
features.
An MOU is to be entered by the designated nodal agency with the
NGO/CBO/External agency for taking up the projects.
A Technical Committee will be constituted for finalization of the
specifications and evaluation of bid proposals submitted by the
companies/NGOs/CBOs.
Government may examine supply of raw materials particularly
cement, steel & sand at reasonable prices.
Abstract of Funds requirement:
SL No Description of item Qty./No/ Estimate cost in lakhs.
Remarks
Housing 73290.54
Drinking Water 0 0 0
Drainage 0 0 0
WBM Roads 0 0 0
Solar Street Lighting 0 0 0
Total: 73290.54