ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious...

31
MC-0319059/ WP # 104827 ADDENDUM NO. 4 Page 1 of 3 THIS DOCUMENT AND ATTACHMENT(S) ARE AVAILABLE FOR DOWNLOAD AT HTTPS://HOSTING.PORTSEATTLE.ORG/PRMS/. AN EMAIL NOTIFICATION WAS SENT TO REGISTERED PLANHOLDERS. FAILURE TO ACKNOWLEDGE RECEIPT ON THE BID FORM DOES NOT AFFECT THE BIDDER'S OBLIGATION FOR COMPLIANCE. ADDENDUM NO. 4 TERMINAL 46 DOCK REHABILITATION AND IMPROVEMENTS PROJECT MC-0319059/ WP # 104827 at Terminal 46, Seattle WA DATE: December 13, 2017 ATTENTION TO PLANHOLDERS OF RECORD is called to the following revisions of the contract documents: I. Bid Package No Change II. Project Manual A. Table of Contents Addendum No. 3 REMOVE Table of Contents Addendum No. 3 and REPLACE with Table of Contents Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious Patching Addendum No. 3 REMOVE Section 03 30 53.13 - Marine Rehabilitation Cementitious Patching Addendum No. 3 and REPLACE with Section 03 30 53.13 - Marine Rehabilitation Cementitious Patching Addendum No. 4. C. Section 09 92 00 – Marine Rehabilitation Paints and Coatings REMOVE Section 09 92 00 – Marine Rehabilitation Paints and Coatings and REPLACE with Section 09 92 00 – Marine Rehabilitation Paints and Coatings Addendum No. 4. III. Project Drawings A. Drawing #46-1401 C6.11

Transcript of ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious...

Page 1: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

MC-0319059/ WP # 104827 ADDENDUM NO. 4 Page 1 of 3

THIS DOCUMENT AND ATTACHMENT(S) ARE AVAILABLE FOR DOWNLOAD AT HTTPS://HOSTING.PORTSEATTLE.ORG/PRMS/.

AN EMAIL NOTIFICATION WAS SENT TO REGISTERED PLANHOLDERS. FAILURE TO ACKNOWLEDGE RECEIPT ON THE BID FORM DOES NOT AFFECT THE BIDDER'S

OBLIGATION FOR COMPLIANCE.

ADDENDUM NO. 4

TERMINAL 46 DOCK REHABILITATION AND IMPROVEMENTS PROJECT MC-0319059/ WP # 104827

at Terminal 46, Seattle WA

DATE: December 13, 2017 ATTENTION TO PLANHOLDERS OF RECORD is called to the following revisions of the contract documents: I. Bid Package

No Change

II. Project Manual A. Table of Contents Addendum No. 3 REMOVE Table of Contents Addendum No. 3 and REPLACE with Table of Contents Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious Patching Addendum No. 3 REMOVE Section 03 30 53.13 - Marine Rehabilitation Cementitious Patching Addendum No. 3 and REPLACE with Section 03 30 53.13 - Marine Rehabilitation Cementitious Patching Addendum No. 4. C. Section 09 92 00 – Marine Rehabilitation Paints and Coatings REMOVE Section 09 92 00 – Marine Rehabilitation Paints and Coatings and REPLACE with Section 09 92 00 – Marine Rehabilitation Paints and Coatings Addendum No. 4.

III. Project Drawings A. Drawing #46-1401 C6.11

Page 2: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

MC-0319059/ WP # 104827 ADDENDUM NO. 4 Page 2 of 3

REMOVE Drawing #46-1401 C6.11 and REPLACE with Drawing #46-1401 C6.11 Addendum No. 4 B. Drawing #46-1401 C6.12 REMOVE Drawing #46-1401 C6.12 and REPLACE with Drawing #46-1401 C6.12 Addendum No. 4 C. Drawing #46-1401 C6.13 REMOVE Drawing #46-1401 C6.13 and REPLACE with Drawing #46-1401 C6.13 Addendum No. 4 D. Drawing #46-1401 C7.0 REMOVE Drawing #46-1401 C7.0 and REPLACE with Drawing #46-1401 C7.0 Addendum No. 4 E. Drawing #46-1401 S4.11 REMOVE Drawing #46-1401 S4.11 and REPLACE with Drawing #46-1401 S4.11 Addendum No. 4 F. Drawing #46-1401 S4.12 REMOVE Drawing #46-1401 S4.12 and REPLACE with Drawing #46-1401 S4.12 Addendum No. 4 G. Drawing #46-1401 S4.13 REMOVE Drawing #46-1401 S4.13 and REPLACE with Drawing #46-1401 S4.13 Addendum No. 4

Tina Hemingway Sr. Contracts Administrator

Date

Attachments: Table of Contents Addendum No. 4 Section 03 30 53.13 – Marine Rehabilitation Cementitious Patching Addendum No. 4 Section 09 92 00 – Marine Rehabilitation Paints and Coatings Addendum No. 4 Drawing #46-1401 C6.11 Addendum No. 4 Drawing #46-1401 C6.12 Addendum No. 4 Drawing #46-1401 C6.13 Addendum No. 4 Drawing #46-1401 C7.0 Addendum No. 4 Drawing #46-1401 S4.11 Addendum No. 4 Drawing #46-1401 S4.12 Addendum No. 4 Drawing #46-1401 S4.13 Addendum No. 4

December 13, 2017

Page 3: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

MC-0319059/ WP # 104827 ADDENDUM NO. 4 Page 3 of 3

END OF ADDENDUM NO. 4

Page 4: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

TABLE OF CONTENTS

MC-0319059 / WP #104827 Addendum No. 4 02/13/17

Terminal 46 Dock Rehabilitation and Improvement Project

TABLE OF CONTENTS

[Volume 1] DIVISION 0 BIDDING REQUIREMENTS, CONTRACT FORMS AND CONDITIONS OF THE CONTRACT

NUMBER DOCUMENT TITLE PREPARER 00 10 00 Advertisement for Bids (Addendum No. 1) 00 20 00 Instructions to Bidders 00 41 00 Bid Form 00 43 70 Subcontractor Work Listing 00 52 00 Agreement Forms (Addendum No. 1) 00 60 00 Bonds and Certificates Forms 00 70 00 General Conditions 00 80 00 Supplementary Conditions 00 80 10 Federal Supplementary Conditions 00 83 00 Civil Rights, Title VI, and Non-Discrimination (Addendum No. 1) 00 83 50 Training and Apprenticeship Program DIVISION 1 GENERAL REQUIREMENTS

NUMBER SECTION TITLE PREPARER 01 11 00 Summary of Work MW 01 14 14 Seaport Personnel Identification/Access Control (Addendum No. 2) MW 01 20 00 Measurement and Payment Procedures MW 01 25 00 Substitutions MW 01 31 00 Contractor’s Project Organization MW 01 31 13 Project Coordination MW 01 31 19 Project Meetings MW 01 32 16 Bar Chart Schedule MW 01 32 19 Preconstruction Submittals MW 01 33 00 Submittals MW 01 35 29 Safety Management MW 01 35 43 Environmental Regulatory Requirements MW 01 45 16.13 Contractor’s Quality Control Program MW 01 45 29 Independent Testing and Inspection Service (Owner) MW

Page 5: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

TABLE OF CONTENTS

MC-0319059 / WP #104827 Addendum No. 4 02/13/17

DIVISION 1 GENERAL REQUIREMENTS

NUMBER SECTION TITLE PREPARER 01 50 00 Temporary Facilities and Controls MW 01 57 13 TESC Planning and Execution MW 01 57 23 Pollution Prevention, Planning and Execution MW 01 71 13 Mobilization/Demobilization MW 01 71 23.16 Surveying MW 01 74 00 Cleaning MW 01 74 19 Construction Waste Management MW 01 77 00 Project Closeout MW 01 77 20 Public Works Project Closeout MW 01 78 29 As-Built Redline Drawings MW 01 78 36 Warranties and Bonds MW 01 78 39 Construction Document Management System MW DIVISION 2 EXISTING CONDITIONS

NUMBER SECTION TITLE PREPARER 02 41 13 Site Demolition AL 02 87 00 Fugitive and Silica Dust Control Procedures AL DIVISION 3 CONCRETE

NUMBER SECTION TITLE PREPARER 03 11 00 Concrete Forms (Addendum No. 2) (Addendum No. 3) AS 03 21 00 Concrete Reinforcement AS

03 30 00 Cast-in-Place Concrete AS

03 30 53.13 Marine Rehabilitation Cementitious Patching (Addendum No. 3)(Addendum No. 4) AS

03 31 29.13 Marine Rehabilitation Cast-in-Place Concrete AS 03 40 00 Precast Concrete AS 03 48 00 Precast Concrete Specialties AL 03 64 23 Epoxy Injected Concrete Rehabilitation AS

Page 6: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

TABLE OF CONTENTS

MC-0319059 / WP #104827 Addendum No. 4 02/13/17

DIVISION 5 METALS

NUMBER SECTION TITLE PREPARER 05 05 19 Post-Installed Concrete Anchors AS 05 05 23 Welding AS DIVISION 6 WOOD, PLASTICS AND COMPOSITES

NUMBER SECTION TITLE PREPARER 06 05 00 Plastics AS DIVISION 9 FINISHES

NUMBER SECTION TITLE PREPARER 09 92 00 Marine Rehabilitation Paints and Coatings (Addendum No. 4) AS DIVISION 32 EXTERIOR IMPROVEMENTS

NUMBER SECTION TITLE PREPARER 32 12 16 Bituminous Concrete Pavement AL 32 15 42 Crushed Stone Surfacing AL 32 17.23 Pavement Markings AL APPENDICES

NUMBER TITLE Appendix A Addendum No. 1 dated 11/22/2017, Addendum No. 2 dated 11/30/2017, Addendum No. 3

dated 12/7/2017, Addendum No. 4 dated 12/13/2017

Page 7: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 03 30 53.13 – Marine Rehabilitation Cementitious Patching

MC-0319059 / WP #104827 Addendum No. 4 03 30 53.13-1 Rev. 10/17

PART 1 GENERAL 1.01 SUMMARY

A. Description of Work 1. The “Cementitious Patching” work includes providing a structural concrete

system, in place. 2. The extent and location of the “Cementitious Patching” work is indicated on

drawings and described or referenced in project specifications. 1.02 REFERENCES

A. Definitions 1. The terms “Concrete Patch,” “Patch,” “Drypack,” and other variations of

these terms used in the context of Cementitious Patching refer to the assembly of the items and procedures required by this section, and the terms are substituted for brevity.

B. Governing Specifications, Codes, and Standards 1. American Concrete Institute (ACI)

a. ACI 117 – Specification for Tolerances for Concrete Construction and Materials and Commentary

b. ACI 301 – Specifications for Structural Concrete c. ACI 315 – Details and Detailing of Concrete Reinforcement d. ACI 318 – Building Code Requirements for Structural Concrete e. ACI 5006R – Guide to Shotcrete

2. American Society for Testing and Materials (ASTM) a. ASTM C42, Standard Test Method for Obtaining and Testing Drilled

Cores and Sawed Beams of Concrete 3. American Association of State Highway and Transportation Officials

(AASHTO) a. AASHTO T277 – Standard Method of Testing for Electrical

Indication of Concrete’s Ability to Resist Chloride Ion Penetration 4. Concrete Reinforcing Steel Institute (CRSI)

a. CRSI Manual of Standard Practice 5. The International Code Council (ICC)

a. International Building Code, as amended and modified by the City of Seattle, referred to hereafter as the Seattle Building Code (SBC).

6. In addition to complying with all pertinent codes and regulations, comply with all pertinent recommendations of “Specifications for Structural Concrete for Buildings,” publication ACl 301.

7. Where publication dates are not included or otherwise specified, latest publication at the time of Bid Opening shall govern.

Page 8: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 03 30 53.13 – Marine Rehabilitation Cementitious Patching

MC-0319059 / WP #104827 Addendum No. 4 03 30 53.13-2 Rev. 10/17

8. The provisions of the Contract, including the General Conditions, Supplementary Conditions and General Requirements, apply to the work as if specified in this section.

1.03 ADMINISTRATIVE REQUIREMENTS 1.04 SUBMITTALS

A. Preconstruction Submittals 1. The Contractor shall submit the following information to the Structural

Engineer prior to commencing any custom fabrication, ordering materials, shipping materials, or beginning dependent construction activities. a. Mix Designs: Submit the proposed design mix for each class of

concrete required for this portion of the Work, including the name and address of the proposed concrete supplier.

b. Manufacturer Data (1) Proposed curing methods, including manufacturer’s data for

items including, but not limited to, curing compounds and membranes.

(2) Product Data Sheets: Submit the manufacturer's name and catalog identification of additives.

(3) Manufacturer’s published literature for epoxy, grout, repair, and patch material data, including specifications, physical characteristics, installation instructions and performance data.

(4) Manufacturer’s published literature for admixtures including specifications, physical characteristics, installation instructions and performance data.

(5) The Contractor shall submit the concrete mix design, proposed method of placement, and evidence that the proposed design and placement method will produce the desired compressive strength at 28-days.

c. Manufacturing Tests d. Contractor Inspection and Testing e. Schedule

(1) Completion of Surface Prep (2) Application of Patching (3) Curing

2. Contractor shall not begin construction until receiving the Engineer’s approval of the above required submittals.

1.05 QUALITY ASSURANCE 1.06 DELIVERY, STORAGE, AND HANDLING 1.07 SPECIAL WARRANTY

Page 9: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 03 30 53.13 – Marine Rehabilitation Cementitious Patching

MC-0319059 / WP #104827 Addendum No. 4 03 30 53.13-3 Rev. 10/17

1.08 BIDDER-DESIGN PERFORMANCE REQUIREMENTS PART 2 PRODUCTS 2.01 PRODUCTS AND MATERIALS

A. Cementitious Patching 1. The specified patching materials shall be one of the following identified

products: a. SikaTop 123 PLUS by Sika b. MasterEmaco N 425 by BASF c. Engineer approved equal

B. Cleaning and Surface Preparation 1. Materials and debris collection methods utilized for surface and cleaning

shall adhere to environmental permit conditions and manufacturer specifications.

C. Other Materials 1. All other materials not specifically described but required for a complete

and proper installation of the work of this section shall be as selected by the Contractor subject to the approval of the Engineer.

2.02 OWNER-FURNISHED PRODUCTS AND MATERIALS 2.03 DELIVERY, STORAGE, AND HANDLING

A. The Contractor shall provide all shipping, handling, and storage required to produce the materials, on-site, prior to installation.

2.04 QUALITY ASSURANCE / QUALITY CONTROL A. Contractor shall comply with all written specifications of the manufacturer regarding

application of the specified system.

B. Inspection and Testing: The Contractor shall provide field or plant inspection and testing service as required to the satisfaction of the Engineer. Sampling and testing to assure compliance with the contract provisions shall be in accordance with Section 01 45 29 – Independent Testing and Inspection Service of these specifications.

C. Unless directly specified as unreinforced concrete, all concrete shall be reinforced with minimum steel as specified by the ACI 301.

PART 3 EXECUTION 3.01 INSTALLERS 3.02 EXAMINATION

A. Verification of Conditions 1. Prior to all work of this section, carefully inspect the installed work of all

other trades and verify that all such work is complete to the point where this installation may properly commence.

3.03 PREPARATION

Page 10: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 03 30 53.13 – Marine Rehabilitation Cementitious Patching

MC-0319059 / WP #104827 Addendum No. 4 03 30 53.13-4 Rev. 10/17

3.04 INSTALLATION A. Installation

1. Patch Application (reflected plan view) a. Apply cementitious patching per manufacturer recommendations.

3.05 REPAIR 3.06 QUALITY ASSURANCE / QUALITY CONTROL

A. Provide at least one person who shall be present at all times during execution of this portion of the work and who shall be thoroughly trained and experienced in placing the types of concrete specified and who shall direct all work performed under this section.

B. Thoroughly trained and experienced concrete finishers with a minimum of 5 years of experience shall be responsible for finishing of exposed surfaces.

C. Inspection and Testing: Any testing and inspection needed for quality control shall be in accordance with Section 01 45 29 - Independent Testing and Inspection Service. Tests conducted for the sole benefit of the Contractor shall be at the Contractor's expense.

3.07 PROTECTION 3.08 CLEANING 3.09 SYSTEM STARTUP 3.10 CLOSEOUT ACTIVITIES PART 4 MEASUREMENT AND PAYMENT 4.01 MEASUREMENT

A. “PC-III / BC-III” will be measured by each location (EA), in place, for the work. Measurement will be to the neat lines of the structure as indicated on the drawings 1. Typical installation size, by location, shall be assumed to be 0.12 cubic

feet. B. “D-I” will be measured by each location (EA), in place, for the work. Measurement

will be to the neat lines of the structure as indicated on the drawings 1. Typical installation size, by location, shall be assumed to be 0.12 cubic

feet. C. “Drop-In Anchor Rehab” will be measured as a lump sum (LS) which includes all

work required to rehabilitate drop-in anchors installed in the existing concrete. The bid item will include but is not limited to removal of existing drop-in anchors by chipping away existing concrete, cleaning exposed area, applying a cementitious mortar to patch the affected region, and all other related work not specifically described herein but indicated on the drawings. The bid item will include all related materials, labor, and equipment. 1. Typical installation size, by location indicated on the Drawings, shall be

assumed to be 0.09 cubic feet. 4.02 PAYMENT

Page 11: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 03 30 53.13 – Marine Rehabilitation Cementitious Patching

MC-0319059 / WP #104827 Addendum No. 4 03 30 53.13-5 Rev. 10/17

A. Payment will be made at the contract unit price stated in the Schedule of Unit Prices for “PC-III / BC-III” per location (EA). 1. The contract price shall be full compensation for furnishing all materials,

disposal of all demolished materials, equipment, tools, labor, and all items required to complete the work.

B. Payment will be made at the contract unit price stated in the Schedule of Unit Prices for “D-I” per location (EA). 1. The contract price shall be full compensation for furnishing all materials,

disposal of all demolished materials, equipment, tools, labor, and all items required to complete the work.

C. Payment will be made at the contract lump sum price stated in the Schedule of Unit Prices for “Drop-In Anchor Rehab.” 1. The contract price shall be full compensation for furnishing all materials,

disposal of all demolished materials, equipment, tools, labor, and all items required to complete the work.

D. All other work required to complete the work specified in this section, but not indicated specifically as a pay item, shall be considered a necessary and incidental work.

End of Section

Page 12: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 09 92 00 – Marine Rehabilitation Paints and Coatings

MC-0319059 / WP #104827 Addendum No. 4 09 92 00-1 Rev. 09/17

PART 1 GENERAL 1.01 SUMMARY

A. Description of Work 1. The work includes meeting the minimum requirements of providing the

pigmented film or coating with all pre-finishing work complete as indicated on the drawings or as noted within these specifications.

2. The extent and location of the “Marine Rehabilitation Paints and Coatings” work is indicated on drawings and described or referenced in project specifications.

B. General Requirements 1. The following items are incidental to completing the minimum requirements

described within this specification and referenced elsewhere within the Contract documents. The Contractor shall: a. Satisfy the minimum requirements described within this

specification in parallel with the requirements described elsewhere within the Contract Documents.

b. Provide all labor, equipment, and materials necessary to assemble a working and functional precast concrete system.

c. Provide labor, equipment, and materials incidental to the successful completion of the work as required by Contract Documents.

d. Compose and provide required submittals, test reports, and inspection reports to the approval of the Port.

1.02 REFERENCES A. Definitions

1. The terms, “steel preparation,” “concrete preparation,” “preparation work,” “prep,” “cleaning,” and other similar variations of these terms used in the context of Paints and Coatings work generally refer to the steps necessary to prepare a surface for the application of coating, and include foreign material removal, cleaning, etc., as described below.

2. The term “Coating” and other similar variations of this term used in the context of Paints and Coatings work generally refer to the protective film(s) applied to a surface.

3. The term “Coating System” and other variations of this term used in the context of Marine Rehabilitation Paints and Coatings refer to the assembly of the items and procedures required by this section, and the assembly of the items and procedures required by this section, and the terms are utilized for brevity.

B. Governing Specifications, Codes, and Standards 1. American Society for Testing and Materials (ASTM)

a. ASTM D6237, Standard Guide for Painting Inspectors 2. International Code Council (ICC)

Page 13: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 09 92 00 – Marine Rehabilitation Paints and Coatings

MC-0319059 / WP #104827 Addendum No. 4 09 92 00-2 Rev. 09/17

a. IBC, International Building Code as adopted by the City of Seattle (SBC).

3. Society for Protective Coatings (SSPC) a. SSPC PA Guide 11, Edge Protection b. SSPC SP-1, Solvent Cleaning c. SSPC SP-13, Surface Preparation of Concrete

4. National Association of Corrosion Engineers (NACE) 5. American Welding Society (AWS)

a. American Welding Society – Steel, ANSI/AWS D1.1, edition current as of Bid Date.

6. American Concrete Institute (ACI) a. Building Code Requirements for Structural Concrete and

Commentary 7. American Institute of Steel Construction (AISC)

a. Specification for Structural Steel Buildings (ANSI/AISC 360-05), including Supplements.

b. Steel Construction Manual, Thirteenth Edition (AISC) c. RCSC Specification for Structural Joints Using ASTM A325 or A490

Bolts (ANSI/AISC N690-06) d. Code of Standard Practice for Steel Buildings and Bridges (AISC

303-10), hereafter referred to as AISC Standards. 1.03 ADMINISTRATIVE REQUIREMENTS 1.04 SUBMITTALS

A. General 1. Submit the following information in addition to and in accordance with the

provisions of this Contract, requirements of this section, Section 01 33 00 – Submittals, General and Supplementary Terms and Conditions, Governing Specifications, Codes, and Standards, and applicable Related Work sections.

2. Acceptance of any submittal by the Engineer does not relieve the Contractor of the sole responsibility for completing work as defined in contract documents using acceptable materials and procedures.

3. The omission of components, quantities, or properties in submittals may result in the rejection of the submittal.

4. Each of the following submittals shall be submitted to and approved by the Engineer prior to site mobilization unless noted otherwise. Orders placed prior to Engineer approval are completed at the sole risk of the Contractor, and may result in rejected material. Rejected material must be replaced at no cost to the Port.

B. Schedule and Work Plan

Page 14: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 09 92 00 – Marine Rehabilitation Paints and Coatings

MC-0319059 / WP #104827 Addendum No. 4 09 92 00-3 Rev. 09/17

1. Contractor shall submit a projected work plan and schedule, outlining the intended installation procedures, locations, and equipment for use. a. Work plan must be current and available upon request from the

Port. b. Modifications to work plan shall be reviewed and approved by the

Engineer no less than 48 hours prior to implementation. c. Contractor shall describe the environmental requirements

necessary for a successful installation per manufacturer specification in each two-week weekly construction meeting, making specific reference to the following criteria: (1) Hazardous or flammable materials (2) Toxic materials (3) Atmospheric limitations for curing of coatings (4) Temperature, humidity, and wind requirements

C. Materials 1. Submit a complete list of products proposed for use on the Project,

including manufacturer certifications & product data sheets for cleaning products, primers, coating layers, sealants, finish coats, etc.

2. Material and material installation submittals shall be approved by the Engineer prior to ordering materials.

3. Submit manufacturers’ published literature for each of the specified products and accessories. Include the following: a. Manufacturer specifications, physical characteristics, instructions for

use, and performance data. b. Product description, limitations of use, recommended parameters,

and storage and exposure requirements. c. MSDS and job-safety materials d. In addition to the criteria, above, the following shall be clearly

identified on coating data sheets (1) Coating application instructions and medium (2) Coating thickness and number of coatings for maximum life (3) Coating cure times

(a) Data shall be presented as a table or graph, as a function of the following values. Data not shown in tables shall be interpolated. (i) Temperatures between 0°F and 90°F (ii) Relative humidity between 50% and 100%.

(b) Cure times shall indicate the time required for recoat (c) Cure times shall indicate the time required for

complete cure

Page 15: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 09 92 00 – Marine Rehabilitation Paints and Coatings

MC-0319059 / WP #104827 Addendum No. 4 09 92 00-4 Rev. 09/17

(4) Coating surface preparation requirements (5) Movement, transportation, storage requirements (6) Anticipated service life (7) Instructions for coating repair and replacement, and criteria

for each 4. Submit color samples/drawdowns to the Engineer for approval prior to

ordering materials. 5. Warranty

D. Installer Certifications 1. Cleaning and Surface Preparation Procedures & Materials

a. Procedures, containment practices, and manufacturer instructions. 2. Painting crew qualifications/certifications

a. The Contractor shall submit a case history demonstrating that personnel performing quality control and related functions are trained and qualified.

b. The Contractor shall provide a list of similar projects completed or ongoing at complex industrial/marine steel structures within the previous 18 months that support the Contractor’s suitability for certification. The list shall include the following: (1) Name, address, and principal contact(s) of facility owners,

general Contractors, or other clients, including specific contact information.

(2) Scope of coating and lining work performed (3) Product names of materials used (e.g., abrasives and

applied coatings and linings) (4) Equipment used for surface preparation and coating and

lining operations (5) Types and number of personnel used to supervise and

perform the work (6) Special requirements or special provisions (e.g.,

extraordinary safety or environmental compliance requirements; traffic control; other job-related restrictions).

E. Certificate of Compliance 1. The certificate of compliance shall be a letter stating that the Contractor

has reviewed the submitted manufacturer certifications and test reports, and that the materials being furnished for the project are in conformance with the applicable standards, specifications and project documents.

F. Inspection and Testing 1. Contractor inspector training and certification 2. Contractor inspection plan

Page 16: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 09 92 00 – Marine Rehabilitation Paints and Coatings

MC-0319059 / WP #104827 Addendum No. 4 09 92 00-5 Rev. 09/17

1.05 QUALITY ASSURANCE A. Codes and Standards: Where provisions of pertinent codes, standards, and

contract drawings conflict with these specifications, the more stringent provisions shall govern.

1.06 SPECIAL WARRANTY 1.07 BIDDER-DESIGN PERFORMANCE REQUIREMENTS PART 2 PRODUCTS AND MATERIALS 2.01 PRODUCTS AND MATERIALS

A. General 1. Contractor shall comply with all written specifications of the manufacturer

regarding application of the specified system.

2. All materials shall meet or exceed the minimum requirements listed by manufacturer specifications version current at the time of bid.

B. Surface Preparation and Cleaning 1. Materials and debris collection methods utilized for surface and cleaning

shall adhere to environmental permit conditions and manufacturer specifications.

C. Coating 1. Material

a. Coating shall be a surface tolerant, abrasion resistant, moisture-resistant, high solids epoxy or urethane coating, giving excellent long term anticorrosive protection, abrasion resistance, impact resistance, and adhesion to existing steel structure in or near the splash zone region of Puget Sound.

b. Coating materials shall be appropriate for application to prepared surfaces on galvanized steel, epoxy-coated steel, and concrete substrates.

c. Where the local environment does not provide suitable conditions for curing in a timely fashion, the Contractor shall provide the protective measures necessary to ensure a proper cure.

(1) Protection measures may include but are not limited to installations resisting heat, moisture, abrasion, and other deleterious environments.

d. The specified coating materials shall be one of the following identified products.

(1) BASF MasterProtect 8000 CI (2) Sika FerroGard 903 (3) Or Approved Equal

Page 17: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 09 92 00 – Marine Rehabilitation Paints and Coatings

MC-0319059 / WP #104827 Addendum No. 4 09 92 00-6 Rev. 09/17

2. Color a. The color selection will be made by the Engineer to match site color

standards, with additions from other standards as designated by the Engineer. (1) Color shall be assumed to be black. (2) Color selection is subject to the approval of the Engineer.

2.02 OWNER-FURNISHED PRODUCTS AND MATERIALS

2.03 DELIVERY, STORAGE, AND HANDLING

A. General

1. The Contractor shall provide all shipping, handling, and storage required to produce the materials, on-site, prior to installation.

B. Product Delivery, Handling, and Storage 1. Deliver paint materials in unbroken, unopened containers bearing

manufacturer labels. 2. Do not open containers or remove labels until the Engineer inspects and

approves each container for use. 3. The use and on-site storage of material in unlabeled containers is

prohibited. 4. All city, county, state, and federal safety requirements apply to the storage

and use of all materials. 2.04 QUALITY ASSURANCE / QUALITY CONTROL

A. A single product manufacturer shall be selected to provide all applied layers of coating, primers, thinners, cleaners, and other materials necessary to complete the project. If any of these products is not commercially available by the manufacturer, the manufacturer-approved and -recommended products shall be used.

B. All materials intended for use shall be stored, shipped, and handled within the environmental conditions required by manufacturer.

PART 3 EXECUTION 3.01 INSTALLERS 3.02 EXAMINATION 3.03 PREPARATION

A. Storage 1. Store materials in a dry location where the indicated ambient temperature

of storage is not less than 50°F, greater than 90°F, or exceeds minimum manufacturer specifications.

Page 18: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 09 92 00 – Marine Rehabilitation Paints and Coatings

MC-0319059 / WP #104827 Addendum No. 4 09 92 00-7 Rev. 09/17

B. Weather 1. Work area is exposed to a high degree of weather, both atmospheric and

marine. Acceptable work conditions are highly dependent on amicable tides, weather, waves, and other environmental factors. Although these factors change constantly, it is the responsibility of the Contractor to conservatively select appropriate installation windows based on available forecasts.

3.04 INSTALLATION A. Paints and Coatings shall be installed per manufacturer specifications. The

following steps shall be used as general guidance in the absence of more restrictive manufacturer requirements.

B. Surface Preparation and Cleaning 1. Preparation

a. Steel Surfaces (1) Steel surfaces shall be prepared to SSPC SP-3: Power

Tool Cleaning at a minimum. Where more stringent surface preparation requirements are required by manufacturer, manufacturer requirements apply.

(2) Surface shall be prepared to a 1 mil profile, unless the profile requirement is explicitly relieved by the manufacturer.

(3) Existing coatings shall be removed unless the new coatings have been explicitly approved for application to existing coatings by manufacturer.

(4) Any remaining coatings to exhibit a minimum of 300 psi adhesion to the substrate in accordance with ASTM D-4541 to be considered for overcoating. Additionally, overcoating must be explicitly allowed by manufacturer specification.

b. Concrete Surfaces (1) Concrete surfaces shall be prepared in accordance with

SSPC SP-13: Surface Preparation of Concrete at a minimum. Where more stringent surface preparation requirements are required by manufacturer, manufacturer requirements apply.

c. Bridging Coating Over Gaps, Cracks, and Crevices (1) The following criteria apply in the absence of manufacturer

data. (2) Pits due to corrosion shall be filled with mastic. (3) Gaps, cracks, and crevices larger in width than 1/8” shall be

filled with a marine-grade caulk/sealer prior to application of coatings.

(4) Gaps, cracks, and crevices larger in width than 1/4” shall be filled with a marine-grade backing prior to application of caulker/sealer.

Page 19: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 09 92 00 – Marine Rehabilitation Paints and Coatings

MC-0319059 / WP #104827 Addendum No. 4 09 92 00-8 Rev. 09/17

2. Cleaning a. After surface preparation is complete, carefully desalinate, scrub,

rinse with fresh water, and dry all surfaces prior to applying each coating.

b. Dust, dirt, soluble salts, organic growth, and other foreign material must be removed in compliance with manufacturer specification and in accordance with SSPC SP-1: Solvent Cleaning. (1) Surface shall cleaned prior to the application of each coat. (2) Surfaces shall be dried completely by compressed air prior

to coating application. c. Take care to ensure that adequate ventilation is provided at all

times when using solvents. 3. Application of Mastics at Steel Surfaces

a. Where sharp interfaces, large pits, and other discontinuities hinder the application of coatings, marine-grade mastics shall be applied as directed to ensure a binding coating system.

b. The required use of mastics is anticipated at high tide regions on piles and pile-to-pile connection interfaces.

c. Mastics may be required at other existing surface areas due to pitting.

C. Coating 1. Mixing

a. Mix and thin paint products in strict accordance with the manufacturer’s directions; mix and thin other materials in accordance with the “best” trade practices as approved.

b. Do not modify mix in any manner except upon specific approval of, and in the presence of, the Engineer.

2. Application Methods a. Use ample undiluted materials, spread evenly to the spread rate

and coating thickness identified by the manufacturer. (1) Do not exceed the maximum manufacturer's specified

spreading rate per gallon. (2) Thin coats may be subject to removal, recoating, or other

manufacturer-approved method of repair. b. Installer shall apply the paints in accordance with the

manufacturer’s specification as to the application, weather and temperature conditions. Provide “highest” quality workmanship.

c. Use clean equipment when applying paint. Where faulty or dirty brushes hinder the coating application, the Contractor shall clean or replace the equipment as directed by the Engineer to ensure a proper application.

Page 20: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 09 92 00 – Marine Rehabilitation Paints and Coatings

MC-0319059 / WP #104827 Addendum No. 4 09 92 00-9 Rev. 09/17

3. Application a. Coating shall be applied within 1 hour of cleaning to a dry surface to

minimize the opportunity of airborne chloride transmission to the surface.

b. Do not apply coating until previously applied coatings have thoroughly cured. The duration of time necessary for curing shall be determined by manufacturer specification and compared with the actual in-situ environmental conditions.

c. Accelerators may be used to shorten recoat times, in order to allow coats to be applied in one tidal cycle, unless accelerators reduce coating protection capabilities.

d. Coating shall be applied in accordance with SSPC-PA1 and the applicable standards and recommendations listed in Appendix A of this source, or above, whichever is more stringent. (1) Spread paint materials evenly and without runs, sags, laps,

or brush marks, without variations in color, texture, or sheen and without “holidays.”

(2) Edges, crevices, welds, intersections, and irregular surfaces shall be protected by stripe coating in accordance with the requirements of SSPC-PA 11.

(3) Stripe coat all welds, plate ends, edges, sharp changes in contour, nuts, bolts, and other irregular surfaces with manufacturer-selected primer of a color contrasting to final coats.

(4) Primer coats shall be completed with contrasting color from finish coats.

(5) Vary colors or sheens only between coats with contrasting colors and apply all coats to uniform thicknesses.

(6) Cut sharp lines against glass, coating boundaries, other materials and different colors.

e. Refinish any work judged defective at no additional cost to the Port of Seattle; repair all work damaged during the progress of the construction.

f. Leave finished surfaces clean, completely covered as directed, uniform in appearance and satisfactory to the Engineer.

4. Coating Details a. Coating thickness shall be the manufacturer-specified thickness to

provide maximum life. b. Number of coats shall be the manufacturer specified to provide

maximum life. c. The following values shall be used in the absence of approved

manufacturer-specified values. (1) Sealer (Concrete Surfaces)

Page 21: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 09 92 00 – Marine Rehabilitation Paints and Coatings

MC-0319059 / WP #104827 Addendum No. 4 09 92 00-10 Rev. 09/17

(a) Number of finish coats: 2 (self-priming coatings) (b) Minimum coat thickness: 11.8/10 mil (wet/dry) (c) Maximum coat thickness: 23.5/20 mil (wet/dry)

(2) Epoxy (Steel Surfaces) (a) Number of finish coats: 2 (self-priming coatings) (b) Minimum coat thickness: 11.8/10 mil (wet/dry) (c) Maximum coat thickness: 23.5/20 mil (wet/dry)

D. Curing 1. Cure time shall be determined by manufacturer specification, based on

local environmental conditions continuously monitored and logged near the project site.

2. NOAA site EBSW1 shall be used to track local weather conditions unless an alternate source of data is agreed upon by Contractor and Port of Seattle.

3. Where ‘minimum’ cure times are published separately from ‘suggested’ cure times, ‘suggested’ cure times shall be considered the minimum for this project.

E. Protection 1. Surface Preparation and Cleaning

a. It is expected that after surface preparation and cleaning is complete, the prepared surface is protected from water, salt, dirt, and other foreign materials.

b. If foreign materials reach the prepared surface prior to coating application, the surface is considered unsuitable for coating application. Contractor shall administer the steps necessary, as outlined above, to prepare the surface.

2. Coating a. Curing coatings shall be protected from wind, water, temperature,

insects, and other factors that detract from the performance of the coating.

b. Coatings applied or cured in environments outside of manufacturer published specifications shall be removed and reapplied.

3. Curing a. At times where the local environment is forecasted to be unsuitable

for curing according to manufacturer specification, Contractor shall provide the means necessary to protect the installed coatings for the duration of the curing.

b. Curing coatings shall be protected from water, salt, wind, temperature, humidity, and other deleterious effects.

Page 22: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 09 92 00 – Marine Rehabilitation Paints and Coatings

MC-0319059 / WP #104827 Addendum No. 4 09 92 00-11 Rev. 09/17

c. Use heat, temporary enclosures, splash guards, tarpaulins, drop cloths, or other methods necessary to shield completed work from deleterious effects for the duration of the curing.

d. Moisture typically conveyed through deck drains, scuppers, and other methods may be diverted to protect work. When water conveyance methods are modified, Contractor shall provide the means necessary to remove resulting water from the apron.

F. Repair 1. If a small surface requires a ‘touch-up,’ repair, or recoating, the

replacement coating system shall cover no less than a 6”x6” area, prepared and applied in compliance with the requirements of the original installation and manufacturer-specified repair methods. If the element requiring touch-up is less than 12 sq. in., the entire element shall be recoated.

G. Completion 1. Coated structure shall be rust-free at the time of beneficial occupancy, as

defined in contract documents. 3.05 DELIVERY AND STORAGE 3.06 QUALITY ASSURANCE

A. Craft Worker Qualifications 1. The Contractor shall have a written craft worker assessment and

proficiency monitoring program that defines procedures the company uses to initially qualify, train and at least annually evaluate and document the proficiency of all craft workers (i.e., persons performing repairs, surface preparation and coating and lining application) under its supervision The worker assessment program must meet the performance requirements of Mandatory Annex A of SSPC-QP1 and evidence of its implementation must be documented.

2. The program shall contain provisions to administer written tests and/or a hands-on evaluation to assess the skills of new hires that claim to have previous experience, or verify previous qualifications through a formal training or qualification program. Evaluation must include a hands-on skill evaluation using like equipment and products necessary for a complete installation.

3. Documentation of these programs shall be submitted upon request by the Engineer at no cost to the Port.

B. Technical Resources 1. Applicable standards and specifications for coating inspection work are

available to and used by field personnel. 2. The Contractor shall maintain a library of current technical standards (e.g.,

ASTM International, SSPC, NACE International), technical bulletins, publications, product data sheets, MSDSs and other technical references invoked by projects performed.

C. Leadership Qualifications

Page 23: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 09 92 00 – Marine Rehabilitation Paints and Coatings

MC-0319059 / WP #104827 Addendum No. 4 09 92 00-12 Rev. 09/17

1. Persons designated by the Contractor to perform quality control inspections in the field must have at least two years field experience in protective coatings and have successfully completed a training course approved by the Port (NACE, SSPC, MPI, or other applicable body). a. The course shall require 24 hours minimum contact time, including

hands-on training and assessment that covers subjects for coating inspection described in ASTM D 3276 applicable to the Contractor’s scope of work.

D. Inspection Procedures and Recording System 1. The Port of Seattle shall be present to inspect structural steel elements to

be coated at each inspection milestone. Steel elements generally include steel shapes, plates, connections, and connector items. a. The Port of Seattle inspector shall be given 24 hours of advanced

notice prior to each milestone. b. Inspection Milestones

(1) Completion of Rough Surface Preparation (2) Cleaning and Completion of Cleaning (3) Primer and Mastic Application and Completion of Application (4) Pre-Coating Surface Preparation (5) Coating Application (6) Protection Methods of each Applied Coating (7) Cured Coating

2. Testing Equipment a. Calibration of instruments used for inspection shall be performed

and documented in accordance with either the equipment manufacturer’s instructions or industry standards.

PART 4 MEASUREMENT AND PAYMENT 4.01 MEASUREMENT

A. “Marine Coating” will be measured as a lump sum (LS) which includes the marine coatings for the existing waterside crane rail beam, existing pile cap, existing bulkhead cap, existing deck panels where noted, new deck panels where noted, and all other related work not specifically described herein but indicated on the drawings. The bid item will include all related materials, labor, and equipment. “D-II” is covered under a separate bid item.

B. “D-II” will be measured as square feet (SF) as indicated on the drawings. The bid item will include all related materials, labor, and equipment.

4.02 PAYMENT A. Payment will be made at the contract lump sum price stated in the Schedule of

Unit Prices for “Marine Coating.” The contract price shall be full compensation for furnishing all materials, equipment, labor and all items required to complete the work.

Page 24: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification

DIVISION 3 - CONCRETE Section 09 92 00 – Marine Rehabilitation Paints and Coatings

MC-0319059 / WP #104827 Addendum No. 4 09 92 00-13 Rev. 09/17

B. Payment will be made at the contract square foot (SF) price stated in the Schedule of Unit Prices for “D-II.” The contract price shall be full compensation for furnishing all materials, equipment, labor and all items required to complete the work.

C. All other work required to complete the work specified in this section, but not indicated specifically as a pay item, shall be considered a necessary and incidental work.

End of Section

Page 25: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification
Page 26: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification
Page 27: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification
Page 28: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification
Page 29: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification
Page 30: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification
Page 31: ADDENDUM NO. 4 · Addendum No. 4 B. Section 03 30 53.13 - Marine Rehabilitation Cementitious PatchingAddendum No. 3 ... 1. American Concrete Institute (ACI) a. ACI 117 – Specification