ADDENDUM #01 03.13.2019 Miami University Mosler Hall E ... Hall E-Learning... · Miami University...

54
real estate / project management / strategic planning / architectural design / construction management www.SHYFTcollective.com ADDENDUM #01 03.13.2019 Miami University Mosler Hall E-Learning SHYFT PROJECT # 218-192 The information contained in this Addendum modifies, supplements or replaces information contained in the Project Manual and on the Drawings and is hereby made a part of the Contract Documents. Acknowledge receipt of this Addendum by placing the appropriate addendum number in the blank on the Bid Form. SPECIFICATION REVISIONS: SECTION 01 10 00 – SUMMARY i. Part 1 - 1.05 CONTRACTOR USE OF SITE AND PREMISES a. Item 4 under paragraph C has been removed. SECTION 01 40 00 – QUALITY REQUIREMENTS i. PART 1 – 1.05 TESTING AND INSPECTION AGENCIES AND SERVICES a. Entire paragraph removed. ii. PART 1 – 3.02 MOCK UPS a. Entire paragraph removed. iii. PART 1 – 3.04 TESTING AND INSPECTION a. Entire paragraph removed. SECTION 01 50 00 – TEMPORARY FACILITIES AND CONTROLS i. Refer to re-issued section. SECTION 08 71 00 – DOOR HARDWARE i. Refer to re-issued section. SECTION 27 24 00 – AUDIO/VISUAL SYSTEMS i. Refer to re-issued section. DRAWING REVISIONS: G001 – GENERAL PROJECT INFO a) Added campus map to sheet. AD103 – PARTIAL THIRD FLOOR DEMOLITION PLANS a) Dimensions were added to locate new wall opening.

Transcript of ADDENDUM #01 03.13.2019 Miami University Mosler Hall E ... Hall E-Learning... · Miami University...

  • real estate / project management / strategic planning / architectural design / construction management

    www.SHYFTcollective.com

    ADDENDUM #01 03.13.2019

    Miami University Mosler Hall E-Learning

    SHYFT PROJECT # 218-192

    The information contained in this Addendum modifies, supplements or replaces information contained in the Project

    Manual and on the Drawings and is hereby made a part of the Contract Documents.

    Acknowledge receipt of this Addendum by placing the appropriate addendum number in the blank on the Bid

    Form.

    SPECIFICATION REVISIONS:

    SECTION 01 10 00 – SUMMARY

    i. Part 1 - 1.05 CONTRACTOR USE OF SITE AND PREMISES

    a. Item 4 under paragraph C has been removed.

    SECTION 01 40 00 – QUALITY REQUIREMENTS

    i. PART 1 – 1.05 TESTING AND INSPECTION AGENCIES AND SERVICES

    a. Entire paragraph removed.

    ii. PART 1 – 3.02 MOCK UPS

    a. Entire paragraph removed.

    iii. PART 1 – 3.04 TESTING AND INSPECTION

    a. Entire paragraph removed.

    SECTION 01 50 00 – TEMPORARY FACILITIES AND CONTROLS

    i. Refer to re-issued section.

    SECTION 08 71 00 – DOOR HARDWARE

    i. Refer to re-issued section.

    SECTION 27 24 00 – AUDIO/VISUAL SYSTEMS

    i. Refer to re-issued section.

    DRAWING REVISIONS:

    G001 – GENERAL PROJECT INFO

    a) Added campus map to sheet.

    AD103 – PARTIAL THIRD FLOOR DEMOLITION PLANS

    a) Dimensions were added to locate new wall opening.

  • real estate / project management / strategic planning / architectural design / construction management

    www.SHYFTcollective.com

    A103 – PARTIAL THIRD FLOOR PLAN

    a) Revised wall layout and updated dimensions at rooms 316H, 316I and 316J.

    b) Added coded note 9 to note where to align face of wall.

    c) Added coded note 10 regarding sound insulation at existing wall.

    d) Elevation D11 added to Meeting Room 316E.

    e) Revised wall type designation at walls in Entry 316.

    f) Revised door hardware sets and added comment for card reader.

    A123 – PARTIAL THIRD FLOOR RCP

    a) Revised coded note 1 to call out wall mounted short throw projector instead of ceiling mounted.

    b) Added coded note 2 to align ceiling grid where noted.

    c) Added coded note 3 for ceiling post mount for TV in Training 316H.

    d) Revised ceiling grids.

    A500 – INTERIOR ELEVATIONS

    a) Added Elevations General Notes.

    b) Revised storefront dimensions for elevation A7.

    c) Updated interior elevation A3 for increased room width.

    d) Revised white board dimension on interior elevation D15.

    e) Added interior elevation D11 to show whiteboard wall in Meeting Room 316E.

    f) Added base cabinet section detail D7.

    A803 – PARTIAL THIRD FLOOR FINISH PLAN

    a) Revised wall layout at rooms 316H, 316I and 316J.

    b) Added coded note 4 to Coded Note Legend.

    c) Added coded note 5 to Coded Note Legend.

    d) Revised Room Finish Schedule.

    e) Added item to Finish Legend.

    f) Added location for P3 wall color at Entry 316.

    g) Added notes to Finish Plan for clarification of carpet installation in Corridor 316A.

    FP1 – PARTIAL THIRD FLOOR FIRE PROTECTION PLAN

    a) Clouded areas where scope was revised.

    HD1- PARTIAL THIRD FLOOR HVAC DEMOLITION PLAN

    a) Provided insulated caps at removed ductwork.

    b) Existing wall mounted transfer duct is to be removed. General contractor to patch wall.

  • real estate / project management / strategic planning / architectural design / construction management

    www.SHYFTcollective.com

    H1- PARTIAL THIRD FLOOR HVAC PLAN

    a) Relocated VAV boxes now have new three-way control valves.

    b) VAV 3-3 no longer serves room 316. That is now served from VAV 3-2. The VAV box schedule has been

    updated.

    c) Transfer above 316M has been removed. There is an existing transfer in the corridor wall already.

    d) Manual air vent has been added to the drawings.

    e) Three-way control valve has been added to the drawings

    f) Duct layout has been revised to be a radius elbow at the end of the run.

    g) One ball valve and on circuit setter has been added to the new branch piping serving the renovated

    space.

    h) Note added to VAV box schedule to update BAS graphics to contain new and relocated VAV boxes.

    i) Thermostat relocated in room 316H.

    j) Thermostat for VAV 3-5 has been added to room 316F.

    ED1 – THIRD FLOOR ELECTRICAL DEMOLITION PLAN

    a) Added note to relocate devices for TV in corridor to new TV location.

    E1 – THIRD FLOOR LIGHTING PLAN

    a) Shifted light fixtures in room 316H.

    b) Relocated light switch to adjacent wall.

    c) Revised EX1 in room 316 to be ceiling mounted.

    d) Shifted light fixtures in room 316B.

    E2 – THIRD FLOOR POWER PLAN

    a) Relocated devices for corridor TV to new TV location.

    b) Added poke thru device in room 316B.

    c) Removed one receptacle to 316H to avoid window conflict.

    d) Added ceiling mounted TV and mount to Floor Device/AV Legend for TV in room 316H.

    e) Added electric strike and card reader to door 316.

    E5 – ELECTRICAL DETAILS

    a) Added access control door elevation.

    RFIs – Q & A:

    1. From the third level FFE, what is the dimension to the underside of the fourth level deck?

    Response: 10’-7” – Underside of Beam

    11’-10.5” – Underside of Concrete Structure

    13’-0” – Underside of Slab

    2. Please confirm CAD files for coordination will be provided at no cost to the awarded bidder and their

    subcontractors.

    Response: Shyft Collective will charge twenty five dollars ($25) for each CAD file requested. Prater does

    not have a cost associated with providing CAD files.

  • real estate / project management / strategic planning / architectural design / construction management

    www.SHYFTcollective.com

    3. Please confirm there is no cost associated with using the Miami Project Tracking/Management System.

    Response: There is no licensing or initiation fee for contractors to use Miami's e-Builder project tracking

    system.

    4. Please confirm the ceiling tile will be installed to the face of the existing windows and shade pockets are

    to be fastened to the CMU jambs below the acoustic ceiling.

    Response: This is correct.

    5. Please confirm that the projectors will be wall mounted requiring blocking and not ceiling mount as detail

    shows.

    Response: The projectors will be wall mounted requiring blocking.

    6. TV in rm. 316H appears to be on sitting on casework. What should be done with TV for base bid. Should

    it be wall mounted? And at what location?

    Response: The TV will be post mounted from the ceiling. See note on sheet A123 and E2.

    7. There was a request for information regarding approved cabling contractors.

    Response: The list is included in Division 27 Appendix C.

    8. There was a request for information regarding what items would be removed prior to start of construction.

    Response: University furniture and equipment will be removed prior to start of construction.

    ATTACHMENTS:

    • Pre-Bid Meeting Minutes

    • Specs:

    01 50 00 – Temporary Facilities and Controls

    08 71 00 – Door Hardware 27 24 00 – Audio/Visual System

    • Drawings:

    G001, AD103, A103, A123, A500, A803

    FP1

    HD1, H1

    ED1, E1, E2, E5

    END OF ADDENDUM

  • DN DNUP UP

    KIT KITCHENKO KNOCKOUT

    L LENGTHLAB LABORATORYLAM LAMINATELAV LAVATORYLF LINEAR FOOTLGTH LENGTHLH LEFT HANDLL LIVE LOADLLH LONG LEG HORIZONTALLLV LONG LEG VERTICALLT LIGHTLTG LIGHTING

    MAS MASONRYMAT MATERIALMAX MAXIMUMMDF MEDIUM DENSITY FIBERBOARDMDO MEDIUM DENSITY OVERLAYMECH MECHANICALMED MEDIUMMEMB MEMBRANEMEZZ MEZZANINEMFR MANUFACTURERMH MANHOLEMIN MINIMUMMISC MISCELLANEOUSMO MASONRY OPENINGMT MARBLE TILEMTD MOUNTEDMTG MOUNTINGMTL METALMUL MULLION

    CLPL

    & ANDL ANGLE@ AT# NUMBER / POUND

    CENTERLINEPROPERTY LINE

    AB ANCHOR BOLTABV ABOVEAC AIR CONDITIONING /

    AIR CONDITIONERACOUS ACOUSTICALACT ACOUTIC CEILING TILEAD AREA DRAINADJ ADJACENT / ADJUSTABLEAFC ABOVE FINISH CEILINGAFF ABOVE FINISH FLOORAGGR AGGREGATEALT ALTERNATEALUM ALUMINUMAP ACCESS PANELAPP'D APPROVEDAPPROX APPROXIMATEAPT APARTMENTARCH ARCHITECT / ARCHITECTURALASB ASBESTOSASPH ASPHALTAV AUDIO VISUAL

    BC BOTTOM OF CURBBD BOARDBET BETWEENBIT BITUMINOUSBLDG BUILDINGBLKG BLOCKINGBM BEAM / BENCHMARKBOS BOTTOM OF STEELBOT BOTTOMBRG BEARINGBSMT BASEMENTBUR BUILT UP ROOF

    CAB CABINETCB CATCH BASINCEM CEMENTCIP CAST IN PLACECI CURB INLETCJ CONTROL JOINTCL CENTERLINECLG CEILINGCLOS CLOSETCLR CLEARCM CONSTRUCTION MANAGERCMU CONCRETE MASONRY UNITCNSK COUNTERSUNKCO CLEANOUTCOL COLUMNCONC CONCRETECONN CONNECTIONCONST CONSTRUCTIONCONT CONTINUOUS / CONTINUECONTR CONTRACTORCORR CORRIDOR / CORRUGATEDCPT CARPETCRS COURSECT CERAMIC TILECTR CENTERCW COLD WATER

    E EASTEA EACHEC ELECTRICAL CONTRACTOREF EXHAUST FAN / EACH FACEEIFS EXTERIOR INSULATION

    FINISH SYSTEMEJ EXPANSION JOINTEL ELEVATION (ABOVE GRADE)ELECT ELECTRICALELEV ELEVATION (BUILDING ELEVATION)ELV ELEVATOREMER EMERGENCYENCL ENCLOSUREEP ELECTRICAL PANEL /

    EDGE OF PAVEMENTEQ EQUALEQUIP EQUIPMENTEST ESTIMATEEW EACH WAYEWC ELECTRIC WATER COOLEREXH EXHAUSTEXP EXPANSIONEXPO EXPOSEDEXIST EXISTINGEXT EXTERIOR

    FA FIRE ALARMFD FLOOR DRAINFDN FOUNDATIONFE FIRE EXTINGUISHERFEC FIRE EXTINGUISHER CABINETFF FINISH FLOORFHC FIRE HOSE CABINETFIN FINISH OR FINISHEDFLR FLOORFLG FLASHINGFLUOR FLUORESCENTFO FACE OFFP FIREPROOFFRMG FRAMINGFRP FIBER REINFORCED PLASTICFT FOOT OR FEETFTG FOOTINGFURN FURNACEFURR FURRINGFWC FABRIC WALLCOVERING

    QT QUARRY TILEQTY QUANTITY

    R RADIUS / RISERRA RETURN AIRRB RUBBER BASERD ROOF DRAINREF REFRIGERATOR / REFERENCEREINF REINFORCEDREQ'D REQUIREDRES RESILIENTREV REVISIONRH RIGHT HANDRM ROOMRMV REMOVERO ROUGH OPENINGROW RIGHT OF WAYRWL RAIN WATER LEADER

    UNF UNFINISHEDUNO UNLESS NOTED OTHERWISEUR URINAL

    VCT VINYL COMPOSITION TILEVB VAPOR BARRIER / VINYL BASEVERT VERTICALVEST VESTIBULEVIF VERIFY IN FIELDVWC VINYL WALL COVERING

    W WEST / WIDTHWF WIDE FLANGEW/ WITHW/O WITHOUTWC WATER CLOSETWD WOODWI WROUGHT IRONWP WATERPROOFWR WATER RESISTANTWSCT WAINSCOTWT WEIGHTWTR WATERWWF WELDED WIRE FABRIC

    YD YARD / YARD DRAIN

    JAN JANITORJBOX JUNCTION BOXJST JOISTJT JOINT

    ID INSIDE DIAMETERIN INCHINCL INCLUDEINSUL INSULATIONINT INTERIORINV INVERT

    GA GAGE / GAUGEGALV GALVANIZEDGB GRAB BARGC GENERAL CONTRACTORGEN GENERALGFI GROUND FAULT INTERRUPTGFRC GLASS FIBER REINFORCED

    CONCRETEGFCMU GROUND FACE CONCRETE

    MASONRY UNITGL GLASS OR GLAZINGGND GROUNDGYP GYPSUMGWB GYPSUM WALLBOARD

    SYMBOLS

    A

    B

    C

    E

    F

    M

    K

    J

    I

    G

    Q

    R

    U

    V

    W

    Y

    ABBREVIATIONS SYMBOLS LEGEND INDEX OF DRAWINGS

    VICINITY MAP

    N

    ALUMINUM

    GLASS - SMALL SCALE

    ACOUSTIC CEILING

    BRICK

    CONCRETE

    CONCRETE MASONRY

    CONCRETE (SURFACE)

    EARTH

    GLASS - LARGE SCALE

    GRANULAR FILL

    WOOD - FINISHED

    GYPSUM BOARD

    INSULATION - BATT

    INSULATION - RIGID

    PLYWOOD

    STEEL

    WOOD - ROUGH FRAMING

    WOOD - ROUGH BLOCKING

    L

    MATERIALS LEGEND

    PC PRE-CASTPERF PERFORATEDPL PLATE / PROPERTY LINEPLAM PLASTIC LAMINATEPLAS PLASTICPLBG PLUMBINGPLYWD PLYWOODPNL PANELPORC PORCELAINPOS POINT OF SALEPR PAIRPSF POUNDS PER SQUARE FOOTPSI POUNDS PER SQUARE INCHPT PAINT / PRESSURE TREATEDPTD PAINTEDPVC POLYVINYL CHLORIDEPVMT PAVEMENTPWR POWER

    P

    S SOUTHSA SUPPLY AIRSAN SANITARYSC SOLID CORE / SEALED CONCRETESCHED SCHEDULESD SMOKE DETECTOR / STORM DRAINSECT SECTIONSHTG SHEATHINGSHR SHOWERSHT SHEETSHT'G SHEATHINGSIM SIMILARSLV SHORT LEG VERTICALSPEC SPECIFICATIONSPKR SPEAKERSQ SQUARESS STAINLESS STEELSSK SERVICE SINKSTA STATIONSTD STANDARDSTL STEELSTM STEAMSTOR STORAGESTRUCT STRUCTURALSUSP SUSPENDEDSV SHEET VINYLSY SQUARE YARDSYM SYMMETRICAL

    T TREADT&B TOP AND BOTTOMT&G TONGUE AND GROOVETC TOP OF CURBTEL TELEPHONETHK THICK(NESS)TOF TOP OF FOOTINGTOS TOP OF STEELTOW TOP OF WALLTP TOP OF PAVEMENTTS TUBE STEELTV TELEVISIONTW TOP OF WALLTYP TYPICALTZ TERRAZZO

    S

    T

    N NORTHNIC NOT IN CONTRACTNO NUMBERNOM NOMINALNTS NOT TO SCALE

    OA OVERALLOBS OBSCUREOC ON CENTEROD OUTSIDE DIAMETEROFC OFFICEOH OVERHEADOPNG OPENINGOPP OPPOSITEOSB ORIENTED STRAND BOARD

    O

    N

    H HEIGHT / HIGHHB HOSE BIBHC HOLLOW COREHDBD HARDBOARDHDCP HANDICAP / HANDICAPPEDHDO HIGH DENSITY OVERLAYHDR HEADERHDW HARDWAREHDWD HARDWOODHGT HEIGHTHM HOLLOW METALHORIZ HORIZONTALHR HOUR / HANDRAILHTG HEATINGHVAC HEATING, VENTILATING, AIR

    CONDITIONINGHW HOT WATER

    H

    DBL DOUBLEDEMO DEMOLISHDEPT DEPARTMENTDET DETAILDF DRINKING FOUNTAINDIA DIAMETERDIM DIMENSIONDISP DISPENSERDIV DIVISIONDL DEAD LOADDN DOWNDO DOOR OEPNINGDS DOWNSPOUTDW DISHWASHERDWG DRAWING

    D

    GENERAL PROJECT NOTES

    1. REFER TO PROJECT SPECIFICATIONS FOR GENERAL REQUIREMENTS, SUPPLEMENTAL CONDITIONS, ALTERNATES AND OTHER ITEMS APPLICABLE TO THE SCOPE OF WORK. THE DRAWINGS AND SPECIFICATIONS COMBINED FORM THE BASIS OF THE CONTRACT DOCUMENTS WHICH OUTLINE THE WORK REQUIRED BY THIS CONTRACT. NOTIFY ARCHITECT (A/E) OF ANY DISCREPANCIES AND REQUEST A FORMAL INTERPRETATION PRIOR TO BEGINNING TO PROCURE ANY MATERIAL OR BEGIN ANY ASSOCIATED WORK.

    2. THE TERM "CONTRACTOR" REFERS TO THE "GENERAL CONTRACTOR" (GC) IN REGARDS TO ROLES AND RESPONSIBILITIES OUTLINED IN THE DRAWINGS AND SPECIFICATIONS. THE GC SHALL BE THE SOLE PARTY RESPONSIBLE FOR DEFINING SCOPES OF WORK FOR SUBCONTRACTORS COMPLETING WORK OUTLINED IN THESE CONTRACT DOCUMENTS.

    3. ALL WORK AND MATERIALS SHALL CONFORM TO THE REQUIREMENTS OF ALL APPLICABLE FEDERAL, STATE AND LOCAL CODES AND ORDINANCES.

    4. GC SHALL SCHEDULE AND ARRANGE FOR ALL REQUIRED LEGAL INSPECTIONS.

    5. GC SHALL NOTE THE UNIVERSITY WILL OCCUPY ADJACENT AREAS FOR PERFORMANCE OF NORMAL BUSINESS ACTIVITIES DURING CONSTRUCTION. GC SHALL TAKE ALL PRECAUTIONS NECESSARY TO PROTECT ADJACENT SPACES, EQUIPMENT, SERVICES, ETC., FROM DAMAGE DURING THE WORK. COORDINATE DEMOLITION AND CONSTRUCTION WORK TO ALLOW ADJACENT AREAS TO REMAIN OPERATIONAL AND SECURED. MAKE PROVISIONS TO PREVENT MIGRATION OF DEMOLITION OR CONSTRUCTION CONTAMINANTS INTO THE OCCUPIED AREAS. EMERGENCY EXIT PATHS SHALL BE MAINTAINED AT ALL TIMES.

    6. THE GC SHALL EXAMINE THE SITE AND PORTIONS THEREOF WHICH AFFECT THE WORK AND SHALL VERIFY ALL EXISTING DIMENSIONS AND CONDITIONS. NO ADDITIONAL EXPENSE SHALL BE ALLOWED WHICH RESULTS FROM THE FAILURE TO PERFORM THIS EXAMINATION.

    7. EXCEPT FOR ITEMS OR MATERIALS INDICATED TO BE REUSED, REINSTALLED, OR OTHERWISE INDICATED TO REMAIN, DEMOLISHED MATERIALS SHALL BECOME GC'S PROPERTY AND SHALL BE IMMEDIATELY REMOVED FROM THE PROJECT SITE AND PROPERLY DISPOSED OF.

    8. ALL MATERIALS, FIXTURES AND EQUIPMENT INDICATED IN THE CONSTRUCTION DOCUMENTS SHALL BE NEW, U.N.O.

    9. DO NOT SCALE FROM THE DRAWINGS. THE ARCHITECT SHALL BE NOTIFIED OF ANY CONFLICTS IN DIMENSIONING.

    10. ALL NEW / EXISTING FINISHED AND PATCHED SURFACES SHALL BE SMOOTH, CONTINUOUSLY FREE OF IMPERFECTIONS AND IN PROPER CONDITION TO RECEIVE THE SPECIFIED FINISH. PATCHED AREAS SHALL MATCH THE ADJACENT MATERIALS IN CONSTRUCTION AND FINISH. REMOVAL, REPLACEMENT AND/OR PATCHING OF GYPSUM BOARD OR PLASTER IN PARTITIONS TO REMAIN SHALL BE PROVIDED AT ALL LOCATIONS NECESSARY TO COMPLETE THE FULL SCOPE OF WORK. TEMPORARILY SUPPORTING, REMOVAL, AND/OR REPLACEMENT OF CEILING ASSEMBLY COMPONENTS SHALL BE PROVIDED AT ALL LOCATIONS NECESSARY TO COMPLETE THE FULL SCOPE OF WORK.

    11. PATCH AND REPAIR AREAS WITHIN THE SCOPE OF THE PROJECT AND ADJACENT TO THE PROJECT LIMITS WHICH HAVE BEEN AFFECTED BY THE WORK.

    12. PROVIDE ALL REQUIRED BLOCKING, FURRING AND BACKING FOR ANY WALL MOUNTED FIXTURES, SHELVING AND ACCESSORIES. ALL WOOD BLOCKING, NAILERS, GROUNDS, AND PLYWOOD TO BE NON-COMBUSTIBLE.

    A101

    1

    11

    1

    A101

    1Ref

    G15: S2S

    XX

    XX

    X

    1

    A101

    1A101

    XXX

    1

    1

    150 SF

    OCC LOADOCC

    A-1

    NAME 101

    XX

    BUILDING SECTION

    N

    XX'-XX"

    PLAN View Name1/8" = 1'-0"1

    AREA NAME

    150 SF

    0 8' 16' 20'12'

    1

    11A B

    2SHEET NUMBER

    DETAIL NUMBER

    SHEET NUMBER

    DETAIL NUMBER

    SHEET NUMBER

    DETAIL NUMBER

    SHEET NUMBER

    DETAIL NUMBER

    SHEET NUMBER

    DETAIL NUMBER

    SHEET NUMBER

    DETAIL NUMBER

    DETAIL NUMBER

    WALL SECTION

    DETAIL SECTION

    DETAIL / FLOOR PLAN CALLOUT

    EXTERIOR ELEVATION

    INTERIOR ELEVATION

    WINDOW / CURTAIN WALL ELEVATION

    VERTICAL ELEVATION / LEVEL MARK

    LEVEL NAME

    ELEVATION

    ELEVATION ABOVESEA LEVEL

    SPOT ELEVATION

    REVISION CLOUD & TAG

    VIEW TITLE

    DRAWING TYPE

    DRAWING NAME

    DRAWING SCALE

    DETAIL NUMBER

    GRAPHIC SCALE

    GRIDS HEADS / LINES

    ROOM TAGS

    ROOM OCCUPANCY TAG

    AREA TAG

    WALL TYPE TAG

    WINDOW TYPE TAG

    DOOR TYPE TAG

    CODED NOTE / ACCESSORY TAG

    1

    CEILING TAG

    CURTAIN PANEL TYPE TAG

    FURNITURE / EQUIPMENT TAG

    CASEWORK TAG

    NORTH ARROW

    MATCHLINE / VIEW REFERENCE

    FLOOR

    BASE

    NORTH

    EAST

    SOUTH

    WEST

    REMARKS

    ROOM NAME

    XXXXXX-XX

    XXX-XX

    XXX-XX

    XXX-XX

    XXX-XX

    XXX-XX

    XXX-XX

    KEYNOTE

    00 00 00.XX00KEYNOTE TEXT

    ROOM FINISH TAG

    XX XX'-XX"

    LEVEL

    XXX'-XX"(XXX'-XX")

    1

    A101

    Ref1

    A101

    Ref

    1

    A101

    Ref

    1

    A101

    Ref

    1

    A101

    Ref

    1

    /1 A101

    EXPOSEDXX

    VARIESXX

    SUB-DIVISION

    SPECIFICATIONDIVISION

    UNIQUE IDENTIFIER(MAY NOT DIRECTLY REFER TO SPECSUB-SECTION)

    SHEET NUMBER

    ROOM NAME

    XXXAREA

    XXX

    ROOM NAME

    XXXXXX

    DESCRIPTION

    FINISH TAG

    #

    Cabinet Type

    CLG. TYPE FIN. CEILING HEIGHT (A.F.F.)

    REFERENCETARGET

    OWNER ROOM NUMBER

    MOSLER HALL

    CODE SUMMARY

    MOSLER HALL FOOTPRINT

    N

    CAMPUS MAP

    MOSLER HALL

    A500D11

    GOVERNING BUILDING CODES

    USE AND OCCUPANCY CLASSIFICATION

    BUILDING HEIGHTS, AREAS AND CONSTRUCTION TYPE

    TYPE

    BUILDING CODE

    USE GROUP

    TITLE & EDITION

    REQUIREMENTS SECTION

    B (BUSINESS) SECTION 302

    2017 OHIO BUILDING CODE (OBC)

    CONSTRUCTION TYPE

    REQUIREMENTS CHAPTER/SECTION/TABLE

    2,200 SF (3RD FLOOR)AREA OF RENOVATION

    EXISTING USE

    FIRE AND SMOKE PROTECTION FEATURES

    AUTOMATIC SPRINKLER SYSTEMS

    REQUIREMENTS SECTION

    FULLY SUPPRESSED

    REQUIRED

    FIRE ALARM AND DETECTION SYSTEMS PROVIDED

    SECTION 906

    SECTION 907

    PORTABLE FIRE EXTINGUISHERS

    GENERAL INFORMATION

    PROJECT SITE ADDRESS

    PLUMBING CODE

    MECHANICAL CODE

    ELECTRICAL CODE

    ENERGY CODE

    ACCESSIBILITY

    2015 INTERNATIONAL ENERGY CONSERVATION CODE (IECC)

    2017 OHIO PLUMBING CODE (OPC)

    2017 OHIO MECHANICAL CODE (OMC)

    2017 NATIONAL ELECTRICAL CODE (NEC)

    TYPE 2A

    2009 ICC ANSI A117.1

    MOSLER HALL1601 UNIVERSITY BLVDHAMILTON, OH 45011

    SECTION 602

    PROPOSED USE

    FIRE CODE 2017 OHIO FIRE CODE (OFC)

    B (NO CHANGE)

    SECTION 903

    B

    89,810 SF TABLE 503EXISTING BUILDING

    Date

    Drawn By

    Checked By

    Project Number

    15 E Gay St.Suite 2AColumbus, OH 43215www.shyftcollective.com

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    G001

    GENERALPROJECT INFO

    MIA

    MI U

    NIV

    ER

    SIT

    Y

    MO

    SL

    ER

    HA

    LL E

    -LE

    AR

    NIN

    G

    DS

    JD

    03/13/19

    218-192

    16

    01 U

    NIV

    ER

    SIT

    Y B

    LV

    DH

    AM

    ILT

    ON

    , O

    H 4

    501

    1

    No.

    Issue/R

    evis

    ion/S

    ubm

    issio

    nD

    ate

    BID

    & P

    ER

    MIT

    SE

    T0

    2/1

    5/ 1

    9

    1A

    DD

    EN

    DU

    M 0

    10

    3/1

    3/ 1

    9

    AREA OF WORK

    G000 COVER SHEET

    G001 GENERAL PROJECT INFO

    AD103 PARTIAL THIRD FLR DEMO PLANS

    A103 PARTIAL THIRD FLOOR PLAN

    A123 PARTIAL THIRD FLOOR RCP

    A500 INTERIOR ELEVATIONS

    A803 PARTIAL THIRD FLR FINISH PLAN

    A903 PARTIAL THIRD FLR FURN PLAN

    FP1 PARTIAL 3RD FLOOR FIRE PROTECTION PLAN

    FP2 FIRE PROTECTION NOTES & DETAILS

    HD1 PARTIAL 3RD FLOOR HVAC DEMOLITION PLAN

    H1 PARTIAL 3RD FLOOR HVAC PLAN

    ED1 PARTIAL 3RD FLOOR ELECTRICAL DEMOLITION PLAN

    E1 PARTIAL 3RD FLOOR LIGHTING PLAN

    E2 PARTIAL 3RD FLOOR POWER PLAN AND ONE-LINE

    E4 ELECTRICAL DETAILS AND SCHEDULES

    E5 ELECTRICAL DETAILS

    E6 A/V RISERS AND DETAILS

    E7 A/V RISERS AND DETAILS

    E8 A/V RISERS AND DETAILS

    E9 A/V RISERS AND DETAILS

    STEVEN REYNOLDSEXP 12-31-19ARC. 1315878

    THIRD FLOOR PLAN

    N.T.S.

    1

  • 1

    ROOM 320

    ROOM318

    ROOM316

    ROOM 323

    ROOM 324

    1

    2

    1 12 2 2

    3

    3 3

    3

    344

    445 5

    5

    2

    2

    2

    222 2 2 2

    10'-10 3/4" 4'-10 3/4"4'-10 3/4"

    1

    DEMO PLAN GENERAL NOTES

    1. REFER TO GENERAL PROJECT NOTES ON DRAWING G001 FOR MORE INFO.

    2. REFER TO MEP DRAWINGS FOR ADDITIONAL DEMOLITION SCOPE OF WORK.

    3. SALVAGE AND TURN OVER TO UNIVERSITY FOR STORAGE AND RE-USE ALL FOUR FOOT

    LED LAMPS.

    4. SEPARATE CONTRACTOR WILL BE COMPLETING ABATMENT OF EXISTING FLOORING AND

    MASTIC. THIS CONTRACTOR WILL THEN NEED TO PROVIDE FLOOR PREP FOR NEW FINISH

    FLOORING.

    CODED NOTE LEGEND

    1. EXISTING EXTERIOR CMU WALL.

    2. EXISTING EXTERIOR WINDOWS. REMOVE ALL INTERIOR WINDOW SHADES AT EXISTING

    WINDOWS.

    3. EXISTING INTERIOR WALL TO REMAIN. REFER TO ARCH PLAN FOR LOCATIONS WHERE

    WALL SHALL BE SOUND INSULATED & EXTENDED TO DECK ABOVE.

    4. REMOVE EXISTING PORTION OF WALL SHOWN DASHED.

    5. REMOVE EXISTING DOOR AND FRAME ASSEMBLY IN ITS ENTIRETY.

    6. REMOVE EXISTING CEILING GRID AND LIGHTS IN THEIR ENTIRETY.

    ROOM 323

    ROOM 324

    ROOM 320

    ROOM318 ROOM

    3166

    6

    6

    1/4" = 1'-0"

    PARTIAL THIRD FLOOR DEMO PLANA1

    Date

    Drawn By

    Checked By

    Project Number

    15 E Gay St.Suite 2AColumbus, OH 43215www.shyftcollective.com

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    AD103

    PARTIAL THIRDFLR DEMO PLANS

    MIA

    MI U

    NIV

    ER

    SIT

    Y

    MO

    SL

    ER

    HA

    LL E

    -LE

    AR

    NIN

    G

    DS

    JD

    03/13/19

    218-192

    16

    01 U

    NIV

    ER

    SIT

    Y B

    LV

    DH

    AM

    ILT

    ON

    , O

    H 4

    501

    1

    No.

    Issue/R

    evis

    ion/S

    ubm

    issio

    nD

    ate

    BID

    & P

    ER

    MIT

    SE

    T0

    2/1

    5/ 1

    9

    1A

    DD

    EN

    DU

    M 0

    10

    3/1

    3/ 1

    9

    N

    1/4" = 1'-0"

    PARTIAL THIRD FLOOR DEMO RCPH1N

    STEVEN REYNOLDSEXP 12-31-19ARC. 1315878

  • 1. REFER TO GENERAL PROJECT NOTES ON DRAWING G001 FOR MORE INFO.

    2. ALL DIMENSIONS ARE TO FACE OF WALL (UNLESS NOTED OTHERWISE).

    3. SEE FINISH PLAN AND SCHEDULE FOR ADDITIONAL INFORMATION OF LOCATIONS AND TYPES OF FINISH MATERIALS.

    4. INSULATION MUST EXTEND FULL HEIGHT OF PARTITION. WHERE SOUND ATTENUATION BATTS ARE INDICATED IN PARTITIONS, INSTALL ACOUSTIC SEALANT AT BOTH SIDES, ALONG THE TOP AND BOTTOM, AND AT INTERSECTING PARTITIONS.

    5. REFER TO ALL OTHER DAWINGS INCLUDED IN CONTRACT DOCUMENTS; REMOVAL, REPLACEMENT AND PATCHING OF ANY EXISTING INTERIOR CONSTRUCTION REQUIRED TO COMPLETE ALL WORK SHALL BE PROVIDED.

    FLOOR PLAN GENERAL NOTES

    CODED NOTE LEGEND

    INTERIOR PARTITION TAG LEGEND

    1. ALIGN.

    2. ALL AREAS WHERE MILLWORK, WHITEBOARDS OR AV EQUIPMENT IS NOTED SHALL RECEIVE BLOCKING BETWEEN STUDS, TYPICAL. COORDINATE WITH AV DRAWINGS.

    3. PROVIDE CEILING MOUNT FOR TV. CENTER IN ROOM.

    4. PREPARE EXISTING WALL FOR APPLICATION OF NEW FINISH.

    5. PROVIDE WINDOW SHADE AT PERIMETER WINDOWS. SHADES TO FIT INTO EXISTING POCKET AT EACH WINDOW.

    6. PROVIDE (7) 2-TIER LOCKERS. (1) LOWER LOCKER TO BE ADA COMPLIANT.

    7. EXTEND MTL STUD WALL AND 5/8" GYP ON BOTH SIDES TO UNDERSIDE OF DECK.

    8. INFILL PORTION OF WALL TO MATCH ADJACENT WALL THICKNESS AND FINISH.

    9. ALIGN FACE OF NEW PARTITION WITH EXISTING JAMB.

    10. ADD SOUND INSULATION TO EXISTING WALL AT EXTENTS SHOWN.

    12'-4

    1/2

    "

    5'-0

    "

    5'-0"12'-0" 9'-6" 12'-3 1/4"

    9'-0

    "

    11'-2"

    9'-0

    "10

    '-10

    1/2"

    25'-3 3/4"

    283 SF

    TRAINING

    316H

    128 SF

    OFFICE

    316G128 SF

    OFFICE

    316F

    108 SF

    OFFICE

    316I

    108 SF

    OFFICE

    316J

    118 SF

    OFFICE

    316L152 SF

    COURSE PRODUCTION

    316M

    18 SF

    STORAGE

    316K

    146 SF

    ENTRY

    316

    324 323

    VIF

    152 SF

    MEETING ROOM

    316E

    173 SF

    OFFICE

    316D

    121 SF

    ONE BUTTON

    316B101 SF

    STORAGE

    316C

    8'-6 5/8"

    12'-2

    1/8

    "

    12'-10 7/8"REF

    311 SF

    CORRIDOR

    316A

    PRINTER

    11'-6

    "

    5'-6 5/8"

    316G

    316F

    316E

    316D

    316C

    316B

    316

    316M

    316L

    316K

    316J

    316I

    316H

    A500A11

    A500

    A15

    A500A3

    A500 D15

    A500

    A7

    10'-9 5/8"

    3'-6

    "

    6'-0"

    6'-0"

    3'-0

    7/8

    "

    G3: S-S

    G3: S-SG3: S-SG3: S-S

    G3: S-S

    G3: S-S

    G3: S-S

    G3: S-S G3: S-S

    F3: A--

    G3: A--

    G3: A--

    G3: S-S G3: S-S

    G4: S-S

    G4: S-S

    G3: S-S

    G3: S-S

    G3: S-S

    G3: S-S

    G4: S-S G3: S-S

    F3: A--

    10'-8"

    12'-0"

    1

    2

    2

    2

    2

    2

    22

    2

    3

    4

    4

    4

    4

    4

    4

    5

    5

    5

    5

    5 555

    7

    7 8

    8

    TVT

    V

    WH

    ITE

    BO

    AR

    D

    TV

    TV

    TV

    TV

    TV

    WH

    ITE

    BO

    AR

    D

    TV

    TV

    2

    ALTERNATE #3: REFER TO SECTION 01 23 00 IN THE SPECIFICATIONS FOR MORE DETAIL.

    ALTERNATE #1: REFER TO SECTION 01 23 00 IN THE SPECIFICATIONS FOR MORE DETAIL.

    ALTERNATE #2: REFER TO SECTION 01 23 00 IN THE SPECIFICATIONS FOR MORE DETAIL.

    5

    F3: S-S7

    77

    7

    1

    9

    2'-2

    "

    9

    11

    101

    A500D11

    1

    1

    1

    TYPE F

    SEE SCHEDULE SEE SCHEDULE

    5" 5"

    SE

    E S

    CH

    ED

    ULE

    SE

    E S

    CH

    ED

    ULE

    5"10

    "

    TYPE G3TYPE FG

    DOOR PANEL TYPE LEGEND

    SEE SCHEDULE

    SE

    E S

    CH

    ED

    ULE

    3'-6

    "2'

    -10"

    6" 6"

    TYPE 1

    SEE SCHEDULE

    2"S

    EE

    SC

    HE

    DU

    LE

    DOOR FRAME TYPE LEGEND

    3 5/8"

    G3: C--

    G3: A--

    G3: S--

    ( 1 HR. RATED - U.L. DESIGN U465 )

    GYPSUM PARTITION = ONE LAYER OF 5/8" GWB, BOTH SIDES

    4 7/8"

    G3: P--

    INTERIOR PARTITION LEGEND

    3 5/8"

    F3 C--

    F3 A--

    F3: S--

    4 1/4"

    F3: P--

    ONE LAYER OF 5/8" GWB, ONE SIDE

    CEILING LINE

    FLOOR LINE

    UNDERSIDE OF DECK

    4" T

    YP

    2 1/2"

    G4: C--

    G4: A--

    G4: S--

    7 1/4"

    G4: P--

    1" GAP BETWEEN STUDS

    PARTITION HEIGHT:C = TO CEILINGA = ABOVE CEILINGS = TO STRUCTUREP = PARTIAL HEIGHT

    FIRE RATING: 1, 2, 3 OR 4 HOURS = SMOKE

    ANCILLARY DESIGNATION: S = SOUND INSULATIONT = THERMAL INSULATION

    OO:000

    PARTITION TYPE(REFER TO FLOOR PLANS)

    'X' = 12" MIN. IF DOOR HAS BOTH A CLOSER AND LATCH.

    DOOR CLEARANCES

    60"

    MIN

    .

    18" MIN.

    FRONT APPROACH, PULL SIDE FRONT APPROACH, PUSH SIDE

    HINGE APPROACH, PULL SIDE HINGE APPROACH, PUSH SIDE

    LATCH APPROACH, PULL SIDE LATCH APPROACH, PUSH SIDE

    'X' 48"

    MIN

    .

    'X'

    'Y'

    'Y'

    42"

    MIN

    22" MIN.

    'Y'

    48"

    MIN

    .

    'Y'

    42"

    MIN

    24" MIN 24" MIN.

    'X' = 36" MIN. IF 'Y' = 60" MIN.'X' = 42" MIN. IF 'Y' = 54" MIN.

    'Y' = 48" MIN. IF DOOR HAS BOTH A CLOSER AND LATCH

    'Y' = 54" MIN. IF DOOR HAS BOTH A CLOSER AND LATCH

    'Y' = 48" MIN. IF DOOR HAS BOTH A CLOSER AND LATCH

    Date

    Drawn By

    Checked By

    Project Number

    15 E Gay St.Suite 2AColumbus, OH 43215www.shyftcollective.com

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A103

    PARTIAL THIRDFLOOR PLAN

    MIA

    MI U

    NIV

    ER

    SIT

    Y

    MO

    SL

    ER

    HA

    LL E

    -LE

    AR

    NIN

    G

    DS

    JD

    03/13/19

    218-192

    16

    01 U

    NIV

    ER

    SIT

    Y B

    LV

    DH

    AM

    ILT

    ON

    , O

    H 4

    501

    1

    No.

    Issue/R

    evis

    ion/S

    ubm

    issio

    nD

    ate

    BID

    & P

    ER

    MIT

    SE

    T0

    2/1

    5/ 1

    9

    1A

    DD

    EN

    DU

    M 0

    10

    3/1

    3/ 1

    9

    1/4" = 1'-0"

    THIRD FLOOR PLAN - E-LEARNINGA1

    DOOR SCHEDULE

    DOOR FRAME

    FIRERATING HDW SET REMARKS

    NUMBER ROOM NAME WIDTH HEIGHT MATERIAL TYPE MATERIAL TYPE

    316 ENTRY 3'-0" 7'-0" AL A15/A500 AL A15/A500 07 PROVIDE CARD READER

    316B ONE BUTTON 3'-0" 7'-0" WD F HM 1 06

    316C STORAGE 3'-0" 7'-0" WD F HM 1 04

    316D OFFICE 3'-0" 7'-0" WD G3 HM 1 02 PROVIDE MANUAL ROLLER SHADE

    316E MEETING ROOM 3'-0" 7'-0" WD FG HM 1 02

    316F OFFICE 3'-0" 7'-0" WD G3 HM 1 02 PROVIDE MANUAL ROLLER SHADE

    316G OFFICE 3'-0" 7'-0" WD G3 HM 1 02 PROVIDE MANUAL ROLLER SHADE

    316H TRAINING 3'-0" 7'-0" AL A7/A500 AL A15/A500 01

    316I OFFICE 3'-0" 7'-0" WD G3 HM 1 02 PROVIDE MANUAL ROLLER SHADE

    316J OFFICE 3'-0" 7'-0" WD G3 HM 1 02 PROVIDE MANUAL ROLLER SHADE

    316K STORAGE 3'-0" 7'-0" WD F HM 1 03

    316L OFFICE 3'-0" 7'-0" WD G3 HM 1 02 PROVIDE MANUAL ROLLER SHADE

    316M COURSE PRODUCTION 3'-0" 7'-0" WD G3 HM 1 05 PROVIDE MANUAL ROLLER SHADE

    N

    STEVEN REYNOLDSEXP 12-31-19ARC. 1315878

    A7/A500

    1

    1

  • NOTE: COORDINATE ARCHITECTURAL REFLECTED CEILING PLANS WITH THEMECHANICAL AND ELECTRICAL DRAWINGS FOR NUMBER OF, AND LOCATIONS.OF, AND TYPES OF FIXTURES AND GRILLES. NOT ALL ITEMS SHOWN ON LEGENDMAY BE PRESENT IN PROJECT.

    A1 ACOUSTIC CEILING TYPE 1: 2'x2' LAY-IN CEILING

    CODED NOTE LEGEND

    1. REFER TO GENERAL PROJECT NOTES ON DRAWING G001 FOR MORE INFO.

    2. FINISHED CEILING HEIGHTS ARE MARKED FROM TOP OF FINISH FLOOR, U.N.O.

    3. HVAC DIFFUSERS AND LIGHT FIXTURES SHOWN FOR GENERAL INTENT ONLY, REFER TO HVAC AND ELECTRICAL DRAWINGS FOR MORE INFO.

    4. COORDINATE LOCATION OF ALL CEILING MOUNTED OR RECESSED MECHANICAL, ELECTRICAL, PLUMBING, FIRE SUPPRESSION AND TECHNOLOGY COMPONENTS PRIOR TO ROUGH-IN. ARCHITECT SHALL BE NOTIFIED OF ANY CONFLICTS PRIOR TO BEGINNING ROUGH-IN.

    5. FACE OF BULKHEADS ARE TO ALIGN WITH FACE OF ADJACENT WALLS TO WHICH BULKHEADS ARE PARALLEL , U.N.O. OR DIMENSIONED OTHERWISE.

    6. ALL GYPSUM BOARD SOFFITS & CEILINGS TO BE PAINTED FLAT CEILING WHITE, U.N.O.

    7. CEILING GRIDS ARE CENTERED ON ROOM, U.N.O. OR DIMENSIONED.

    8. WHERE EXIT SIGNS OCCUR OVER A DOOR OR PAIR OF DOORS, CENTER SIGN ON DOOR OPENING.

    9. ALL CEILING DEVICES TO BE CENTERED IN TILE, U.N.O.

    RCP GENERAL NOTES

    XX XX'-XX"

    E1 EXPOSED STRUCTURE ABOVE

    2x2 LIGHT FIXTURE(SHADING DENOTES EMERGENCY FIXTURE)

    EXIT LIGHT WITH DIRECTIONAL ARROW

    EXIT LIGHT

    SUPPLY DIFFUSER

    EXHAUST/RETURN GRILLE

    CEILING TAG WITH HEIGHT

    RCP LEGEND

    1. WALL MOUNTED SHORT-THROW PROJECTOR, ROUGH-IN BY GC AND PROJECTOR BY AV CONTRACTOR; COORDINATE LOCATION WITH WHITEBOARD PROJECTION SURFACE AND ALL CEILING MOUNTED/RECESSED COMPONENTS.

    2. ALIGN CEILNG GRID.

    3. CEILING POST MOUNT FOR TV.

    1x4 LIGHT FIXTURE(SHADING DENOTES EMERGENCY FIXTURE)

    A1 9'-0"

    A1 9'-0"

    A1 9'-0"A1 9'-0"

    A1 9'-0"

    A1 9'-0"

    A1 9'-0"

    A1 9'-0"A1 9'-0"

    A1 9'-0"

    283 SF

    TRAINING

    316H128 SF

    OFFICE

    316G128 SF

    OFFICE

    316F

    108 SF

    OFFICE

    316I

    108 SF

    OFFICE

    316J 118 SF

    OFFICE

    316L

    152 SF

    COURSE PRODUCTION

    316M

    18 SF

    STORAGE

    316K 146 SF

    ENTRY

    316

    152 SF

    MEETING ROOM

    316E

    173 SF

    OFFICE

    316D

    121 SF

    ONE BUTTON

    316B101 SF

    STORAGE

    316C

    311 SF

    CORRIDOR

    316A

    E1 13'-0"

    A1 9'-0" A1 9'-0"

    324 323

    11

    TV

    1

    9"

    EQ

    EQ

    2

    3

    1/4" = 1'-0"

    PARTIAL THIRD FLOOR RCPA1

    Date

    Drawn By

    Checked By

    Project Number

    15 E Gay St.Suite 2AColumbus, OH 43215www.shyftcollective.com

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A123

    PARTIAL THIRDFLOOR RCP

    MIA

    MI U

    NIV

    ER

    SIT

    Y

    MO

    SL

    ER

    HA

    LL E

    -LE

    AR

    NIN

    G

    DS

    JD

    03/13/19

    218-192

    16

    01 U

    NIV

    ER

    SIT

    Y B

    LV

    DH

    AM

    ILT

    ON

    , O

    H 4

    501

    1

    No.

    Issue/R

    evis

    ion/S

    ubm

    issio

    nD

    ate

    BID

    & P

    ER

    MIT

    SE

    T0

    2/1

    5/ 1

    9

    1A

    DD

    EN

    DU

    M 0

    10

    3/1

    3/ 1

    9

    N

    STEVEN REYNOLDSEXP 12-31-19ARC. 1315878

    1

  • THIRD FLOOR

    120'-0"

    CORRIDOR

    1'-1"

    4'-11 3

    /4"

    1'-3"

    8'-9"

    RECESSED LOCKERS, 15WX15D

    ACCESSIBLE LOCKER

    THIRD FLOOR

    120'-0"

    NEW INTERIOR STOREFRONT

    VINYL FILM PROVIDED BY OTHERS

    2"

    7'-0"

    2" 3'-0" 2" 2'-6" 2" 5'-10" 2"

    12'-0"

    EXISTING CEILING

    2'-6"

    THIRD FLOOR

    120'-0"2'-0" 4'-0" 4'-0"

    DOUBLE DOOR/DRAWER BASE CABINET

    PLASTIC LAMINATE COUNTER, BACK AND SIDESPLASH TO BE PL2

    EXISTING WINDOW

    EXISTING COLUMN

    UNDERCOUNTER REFRIGERATOR PROVIDED BY OWNER

    FILLER PANEL

    FINISHED END PANEL

    APRON

    NEW WINDOW SHADE

    ADJUSTABLE SHELF

    BASE

    D7

    A500

    THIRD FLOOR

    120'-0"

    WALL MOUNTED WHITEBOARD, 60WX60H

    SINGLE DOOR TALL STORAGE CABINET

    DOUBLE DOOR TALL STORAGE CABINET

    3'-6"2'-0"

    7'-0"

    2'-0"

    5'-0"

    FINISHED END PANEL

    FILLER PANELFILLER PANEL

    FINISHED END PANEL

    ADJUSTABLE SHELF

    BASE

    5'-0"

    1

    1

    THIRD FLOOR

    120'-0"

    NEW INTERIOR STOREFRONT

    2"

    7'-0"

    10'-8"

    2"3'-6"2"3'-6"2"3'-0"2"

    NEW CEILING

    1

    G3: S-S

    1. REFER TO GENERAL PROJECT NOTES ON DRAWING G001 FOR MORE INFO.

    2. SEE FINISH PLAN AND SCHEDULE FOR ADDITIONAL INFORMATION OF LOCATIONS AND

    TYPES OF FINISH MATERIALS.

    ELEVATIONS GENERAL NOTES

    4"

    VA

    RIE

    S

    REFER TO ELEVATIONS AND FINISH SCHEDULE FOR FINISHES

    SCHEDULED BASE

    ADJUSTABLE MELAMINE SHELF STANDARDS W/ BRACKETS

    DOOR

    FIRE RETARDANT TREATED WOOD BLOCKING TYP.(VERIFY LOCATIONS, TYP.)

    SHIM

    SHIM

    SEALANT, TYP.

    NOTE: ALL INTERIOR SURFACESTO BE MELAMINE

    BACKSPLASH AT SOME LOCATIONS SEE ELEVATIONS

    FULL DEPTH SUBTOP

    SEPARATE BASE ASSEMBLY

    3/4

    "6"

    1 1

    /2"

    SE

    E E

    LE

    VA

    TIO

    NS

    4"

    06 41 16 W

    06 41 16 W

    THIRD FLOOR

    120'-0"

    2'-0"

    5'-0"

    WALL MOUNTED WHITEBOARD, 72WX60H

    WALL BASE6'-0"

    SHORT THROW PROJECTOR CENTERED ABOVE WHITEBOARD

    Date

    Drawn By

    Checked By

    Project Number

    15 E Gay St.Suite 2AColumbus, OH 43215www.shyftcollective.com

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A500

    INTERIORELEVATIONS

    MIA

    MI U

    NIV

    ER

    SIT

    Y

    MO

    SL

    ER

    HA

    LL E

    -LE

    AR

    NIN

    G

    DS

    JD

    03/13/19

    218-192

    16

    01 U

    NIV

    ER

    SIT

    Y B

    LV

    DH

    AM

    ILT

    ON

    , O

    H 4

    501

    1

    No.

    Issue/R

    evis

    ion/S

    ubm

    issio

    nD

    ate

    BID

    & P

    ER

    MIT

    SE

    T0

    2/1

    5/ 1

    9

    1A

    DD

    EN

    DU

    M 0

    10

    3/1

    3/ 1

    9

    1/4" = 1'-0"

    INTERIOR ELEVATION - LOCKERSA11 1/4" = 1'-0"

    INTERIOR ELEVATION - ENTRYA151/4" = 1'-0"

    INTERIOR ELEVATION - TRAINING BASE CABA3

    1/4" = 1'-0"

    INTERIOR ELEVATION - TRAINING TALL CABD15

    1/4" = 1'-0"

    INTERIOR ELEVATION - CONF ENTRYA7

    STEVEN REYNOLDSEXP 12-31-19ARC. 1315878

    1

    1" = 1'-0"

    BASE CABINET WITH DRAWERD7

    1

    1/4" = 1'-0"

    INTERIOR ELEVATION - MEETING ROOMD11

    1

  • 1. REFER TO FINISH LEGEND ON SHEET A803 AS WELL AS SPECIFICATIONS FOR INFORMATION CONCERNING FINISHES.

    2. PAINTED HOLLOW METAL DOORS AND FRAMES TO BE PAINTED P2 UNLESS NOTED OTHERWISE. REFER TO THE DOOR SCHEDULE FOR MATERIAL, FINISH AND COLOR INFORMATION.

    3. WHERE RESILIENT BASE IS SPECIFIED (VINYL OR RUBBER) PROVIDE COVE PROFILE BASE HEIGHT AND COLOR TO BE AS INDICATED ON FINISH LEGEND.

    4. REFER TO REFLECTED CEILING PLANS, FINISH LEGEND, AND SPECIFICATIONS FOR ALL CEILING MATERIAL AND FINISH INFORMATION.

    5. PROVIDE APPROPRIATE METAL OR VINYL TRANSITION STRIPS AT ALL FLOORING MATERIAL CHANGES. SUBMIT PROPER SHOP DRAWINGS FOR APPROVAL. SEE FINISH PLANS, DETAILS AND SPECIFICATIONS FOR ADDITIONAL INFORMATION.

    6. WALL PAINT INDICATED FOR STOREFRONT WALL LOCATIONS APPLIES TO ALL ASSOCIATED DRYWALL COMPONENTS (CURBS, HEADERS, BULKHEADS, ETC.) AND SHOULD NOT BE APPLIED TO STOREFRONT WALL COMPONENTS OR GLASS.

    7. ALL WALLS TO BE PAINTED P1 U.N.O

    8. ALL CASEWORK TO BE PL1 U.N.O

    GENERAL NOTES - FINISH

    CODED NOTE LEGEND

    1. CARPET TO CONSIST OF A MIX 50% CPT1 AND 50% CPT3

    2. CARPET TO CONSIST OF A MIX 75% CPT1 AND 25% CPT3

    3. CARPET TO CONSIST OF A MIX 90% CPT1 AND 10% CPT3

    4. ALIGN START OF CARPET TILE WITH FACE OF TOE KICK.

    5. ALIGN TILE PATTERN IN CORRIDOR TO TRAINING ROOM.

    283 SF

    TRAINING

    316H

    128 SF

    OFFICE

    316G128 SF

    OFFICE

    316F

    108 SF

    OFFICE

    316I

    108 SF

    OFFICE

    316J

    118 SF

    OFFICE

    316L152 SF

    COURSE PRODUCTION

    316M

    18 SF

    STORAGE

    316K

    146 SF

    ENTRY

    316

    152 SF

    MEETING ROOM

    316E

    173 SF

    OFFICE

    316D

    121 SF

    ONE BUTTON

    316B101 SF

    STORAGE

    316C

    311 SF

    CORRIDOR

    316A

    P3

    P3

    P3

    P3

    CPT1CPT1 CPT1

    CPT1

    CPT1CPT1

    CPT1

    CPT1CPT1

    CPT1

    CPT1

    CPT1

    CPT1

    CPT1 CPT3

    CPT1

    CPT3

    CPT1

    1

    CPT1 CPT3

    2

    CPT1 CPT3

    33

    P2

    EQ

    EQ

    CENTERLINE OF ROOM

    P3

    P3

    LAID PERPENDICULAR TO CORRIDOR

    FULL TILES

    CPT2

    4

    5 1

    1

    1

    1

    Date

    Drawn By

    Checked By

    Project Number

    15 E Gay St.Suite 2AColumbus, OH 43215www.shyftcollective.com

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A803

    PARTIAL THIRDFLR FINISH PLAN

    MIA

    MI U

    NIV

    ER

    SIT

    Y

    MO

    SL

    ER

    HA

    LL E

    -LE

    AR

    NIN

    G

    J.DAVIS

    R.HUCEK

    03/13/19

    218-192

    16

    01 U

    NIV

    ER

    SIT

    Y B

    LV

    DH

    AM

    ILT

    ON

    , O

    H 4

    501

    1

    1/4" = 1'-0"

    PARTIAL THIRD FLOOR FINISH PLANA1

    No.

    Issue/R

    evis

    ion/S

    ubm

    issio

    nD

    ate

    1A

    DD

    EN

    DU

    M 0

    10

    3/1

    3/ 1

    9

    N

    FINISH LEGEND

    FINISH TYPE TAG MANUFACTURER STYLE COLOR/FINISH SIZE COMMENTS

    ACCOUSTICAL CEILING TILE ACT1 USG FROST ACOUSTICALPANELS

    WHITE 2X2 LAY-IN

    CARPET CPT1 INTERFACE DRIFTWOOD 104856 LINDEN 25CM X 1M ASHLAR INSTALLATION USINGTACTILES

    CARPET CPT2 INTERFACE SHIVER ME TIMBERS 103922 SYCAMORE 25CM X 1M ASHLAR INSTALLATION USINGTACTILES

    CARPET CPT3 INTERFACE ON LINE 103801 POPPY 25CM X 1M ASHLAR INSTALLATION USINGTACTILES

    PAINT P1 PPG PPG1001-4 FLAGSTONE

    PAINT P2 PPG PPG1001-5 DOVER GREY

    PAINT P3 PPG TO MATCH SHERWIN WILLIAMS SW7588 SHOW STOPPER

    PLASTIC LAMINATE PL1 WILSONART PREMIUM LAMINATE,TEXTURED GLOSS

    7942K-07 COCOBALA

    PLASTIC LAMINATE PL2 WILSONART STANDARD LAMINATE,MATTE FINISH

    D381-60 FASHION GREY

    RESILIENT BASE RB1 ROPPE RUBBER WALL BASE 148 STEEL GRAY 4", WITH TOE COVE PROFILE

    ROOM FINISH SCHEDULE

    ROOM NUMBER ROOM NAME FLOOR BASE

    WALLS

    COMMENTSN S E W

    316 ENTRY CPT* RB1 P* P3 P1 P3 *SEE PLAN

    316A CORRIDOR CPT* RB1 P* P* P* P1 *SEE PLAN

    316B ONE BUTTON CPT1 RB1 P1 P1 P1 P1

    316C STORAGE CPT1 RB1 P1 P1 P1 P1

    316D OFFICE CPT1 RB1 P2 P1 P1 P1

    316E MEETING ROOM CPT1 RB1 P1 P2 P1 P1

    316F OFFICE CPT1 RB1 P2 P1 P1 P1

    316G OFFICE CPT1 RB1 P1 P2 P1 P2

    316H TRAINING CPT* RB1 P1 P1 P2 P1 *SEE PLAN

    316I OFFICE CPT1 RB1 P1 P1 P1 P2

    316J OFFICE CPT1 RB1 P1 P1 P2 P1

    316K STORAGE CPT1 RB1 P1 P1 P1 P1

    316L OFFICE CPT1 RB1 P1 P2 P1 P1

    316M COURSE PRODUCTION CPT1 RB1 P1 P1 P1 P1

    STEVEN REYNOLDSEXP 12-31-19ARC. 1315878

    1

    1

    1

    1

  • 03

    /13

    /19

    03/13/19

  • 03

    /13

    /19

    03/13/19

  • 03/13/19

    03

    /13

    /19

  • Date

    Drawn By

    Checked By

    Project Number

    15 East Gay StreetSuite 2AColumbus, OH 43215www.shyftcollective.com

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    MIA

    MI U

    NIV

    ER

    SIT

    Y

    MO

    SLE

    R H

    ALL E

    -LE

    AR

    NIN

    G

    PEA

    PEA

    03/13/19

    218-192

    MO

    SL

    ER

    HA

    LL

    HA

    MIL

    TO

    N,

    OH

    No

    .Is

    sue

    /Re

    visi

    on

    /Su

    bm

    issi

    on

    Da

    te

    BID

    & P

    ER

    MIT

    SE

    T0

    2/1

    5/1

    9A

    DD

    EN

    DU

    M 0

    10

    3/1

    3/1

    91

    PARTIAL 3RD FLOORELECTRICALDEMOLITION PLAN

    ED1

  • Date

    Drawn By

    Checked By

    Project Number

    15 East Gay StreetSuite 2AColumbus, OH 43215www.shyftcollective.com

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    MIA

    MI U

    NIV

    ER

    SIT

    Y

    MO

    SLE

    R H

    ALL E

    -LE

    AR

    NIN

    G

    PEA

    PEA

    03/13/19

    218-192

    MO

    SL

    ER

    HA

    LL

    HA

    MIL

    TO

    N,

    OH

    No

    .Is

    sue

    /Re

    visi

    on

    /Su

    bm

    issi

    on

    Da

    te

    BID

    & P

    ER

    MIT

    SE

    T0

    2/1

    5/1

    9A

    DD

    EN

    DU

    M 0

    10

    3/1

    3/1

    91

    PARTIAL 3RD FLOORLIGHTINGPLAN

    E1

    ···

    ···

  • Date

    Drawn By

    Checked By

    Project Number

    15 East Gay StreetSuite 2AColumbus, OH 43215www.shyftcollective.com

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    MIA

    MI

    UN

    IVE

    RS

    ITY

    MO

    SL

    ER

    HA

    LL

    E-L

    EA

    RN

    ING

    PEA

    PEA

    03/14/19

    218-192

    MO

    SLE

    R H

    ALL

    HA

    MIL

    TO

    N, O

    H

    No.

    Issu

    e/R

    evi

    sion/S

    ubm

    issi

    on

    Date

    BID

    & P

    ER

    MIT

    SE

    T02/1

    5/1

    9A

    DD

    EN

    DU

    M 0

    103/1

    4/1

    91

    PARTIAL 3RD FLOORPOWER PLANAND ONE-LINE

    E2

  • Date

    Drawn By

    Checked By

    Project Number

    15 East Gay StreetSuite 2AColumbus, OH 43215www.shyftcollective.com

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    A

    B

    C

    D

    E

    F

    G

    H

    J

    K

    L

    M

    N

    P

    Q1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    MIA

    MI

    UN

    IVE

    RS

    ITY

    MO

    SL

    ER

    HA

    LL

    E-L

    EA

    RN

    ING

    PEA

    PEA

    03/14/19

    218-192

    MO

    SLE

    R H

    ALL

    HA

    MIL

    TO

    N, O

    H

    No.

    Issu

    e/R

    evi

    sion/S

    ubm

    issi

    on

    Date

    BID

    & P

    ER

    MIT

    SE

    T02/1

    5/1

    9A

    DD

    EN

    DU

    M 0

    103/1

    4/1

    91

    ELECTRICALDETAILS

    E5

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    01 50 00TEMPORARY FACILITIES AND CONTROLS

    Page 1 of 6

    SECTION 01 50 00TEMPORARY FACILITIES AND CONTROLS

    PART 1 GENERAL1.01 SECTION INCLUDES

    A. Temporary utilities: Electricity, lighting, heat, ventilation, gas.B. Temporary telecommunications services.C. Temporary sanitary facilities.D. Temporary Controls: Barriers and enclosures.E. Security requirements.F. Vehicular access and parking.G. Waste removal facilities and services.H. Project identification sign.I. Field offices.

    1.02 REFERENCE STANDARDSA. ASTM E84 - Standard Test Method for Surface Burning Characteristics of Building Materials.B. ASTM E90 - Standard Test Method for Laboratory Measurement of Airborne Sound

    Transmission Loss of Building Partitions and Elements.1.03 GENERAL

    A. Install temporary facilities and utilities in conformance with State and Local Codes and requirements if use of existing facilities is revoked.

    B. Trade Contractors to obtain and pay for required applications, permits and inspections.C. Maintenance: Temporary facilities and utilities are to be maintained and kept in good operating

    condition. Maintenance men necessary to perform this work shall be provided in accordance with requirements. Maintenance time will include normal working hours for all trades and start up and shut down overtime as required.

    D. Removals: Subject to approval of General Contractor, contractor providing temporary facilities or services shall remove same when no longer required or when their function is replaced by authorized use of permanent facilities. Other removal time may be directed by General Contractor.

    E. Install temporary work in such a manner as not to interfere with the permanent construction.F. Disclaimer: Specific administrative and procedural minimum actions are specified in this

    section, as extension of provisions in General Conditions and other contract documents. These requirements have been included for special purposes as indicated. Nothing in this section is intended to limit types and amounts of temporary work required, and no omission from this section will be recognized as an indication by Architect, Engineer or General Contractor that such temporary activity is not required for successful completion of the work and compliance with requirements of contract documents. Provisions of this section are applicable to, but not by way of limitation, utility services, construction facilities, security/protection provisions, and support facilities.

    1.04 TEMPORARY UTILITIESA. Owner will provide the following:

    1. Electrical power , consisting of connection to existing facilities.2. Water supply, consisting of connection to existing facilities.

    B. Provide and pay for all ventilation required for construction purposes. Mechanical contractor shall utilize base building HVAC system to provide ventilation and conditioning.1. General Responsibilities: Temporary heating responsibilities and equipment types relate

    to the extent of building enclosure and work performed as follows:

    https://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%2520E84http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%2520E90

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    01 50 00TEMPORARY FACILITIES AND CONTROLS

    Page 2 of 6

    C. Ventilation: The Mechanical Contractor shall provide ventilation for the building and to prevent building up of harmful dusts and fumes and to remove excess moisture. During warm weather, provide an adequate supply of fresh air (minimum 1 to 1-1/2 air changes per hour) when necessary to properly ventilate for moisture, dust, fumes from paints, cements, or adhesives in tightly enclosed area where natural ventilation will not be sufficient. Ventilation requirements may be supplemented by the building's permanent HVAC system but primary responsibility rests with the designated trade contractor. Contractor is responsible for maintaining HVAC system in its existing condition. Record conditions with Owner before beginning work. Provide temp filter media. Provide replacement filters in system if temp media does not work. Permanent filters to be replaced at the end of the project. Specify location, quantity and types of filters with University at start of work.1. Mechanical Trade Contractor Responsibilities:

    a. Maintain as to temperatures and ventilation required for work in various parts of the building as follows:1) Stored Materials: As recommended by manufacturer.2) Installed Materials: As recommended by manufacturer for the length of time

    following installation.b. Maintain that portion of any floor thereof which has been constructed, or partly

    constructed, at a temperature and humidity that will ensure against damage due to warping, buckling, excessive shrinkage, etc., and adequate ventilation until the permanent HVAC system is operating. Trade Contractor will be responsible for damage to work under other contracts due to smoke or other damage caused by improper temporary heating.

    c. Installation, connection, operation, and maintenance of temporary heating and ventilating devices to be performed by tradesmen proficient in the skills required and meet requirements of applicable regulator agencies.

    d. Temperature Requirements:1) Provide temperatures required in various parts of the buildings as specified

    herein below:2) All Trades: provide the range of temperatures required for temporary heat, so

    the temperature as recommended by the manufacturer of the material concerned is maintained while such materials as mentioned above are stored in the building or being installed, and for the length of time recommended following installation. In those portions of the building where work is in progress or completed, it must be protected from freezing if subject to damage there from.

    2. During General Contract Work: Provide the following:a. During installation of gypsum wallboard or gypsum lath, a temperature of not less

    than 55 deg F during working hours, and a temperature of at least 40 deg F at all other times throughout the heating season.

    b. Wall before plaster work or joint work for gypsum wall board begins and continuous throughout setting and drying periods, a temperature range between 50 and 75 deg F shall be maintained day and night. During this period, no finish woodwork, resilient flooring or flexible wall coverings shall be installed or stored in the buildings, and no finish painting or applying of finish wall coatings shall be undertaken.

    c. For a period of 10 days previous to the placing of interior wood finish and throughout the placing of this and other interior finishing, varnishing, painting, etc., and until final acceptance of the work or until fully occupied by the Owner, provide sufficient heat to produce a temperature of not less than 60 deg F.

    3. Prior to Final Inspection:a. Replace temporary filters with new filters. Provide 2 temporary media filters over

    all return and transfer ducts within the construction area. Remove all upon completion of work.

    b. Thoroughly clean coils and other equipment.c. Clean traps and devices, adjust and renew any and all materials and equipment not

    functioning correctly.

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    01 50 00TEMPORARY FACILITIES AND CONTROLS

    Page 3 of 6

    d. Vacuum clean the duct system. Cover ends of all open ductwork during construction.

    e. Restore equipment to like new condition.D. Temporary light and power:

    1. Each Trade Contractor:a. Provide and pay for its own extensions for lights or power tools beyond the receptacle

    outlets provided below.2. Electrical Trade Contractor:

    a. Provide temporary light and power distribution for construction purposes for all trades including the cost of running temporary service from the utility supply. The temporary lighting and power system shall comply with all applicable OSHA regulations.1) Temporary power to be sufficient to operate all "light tools" and equipment

    (electric arc welders excluded) and permanent building equipment including elevators and HVAC system.

    2) Additional temporary power required by other trades to be furnished, at their cost, up to the power available.

    3. Temporary lighting distribution to be made from the temporary panels indicated above. Each circuit shall consist of "pigtail" receptacles on 20 foot centers with 200 watt lamps installed in every other receptacle leaving the alternate receptacles for added concentration of lighting as needed. Wire fixtures with #8 AWG wire and suspend at least 10'-6" above the floor at height as determined by GC.a. As interior partitions are erected, revise the temporary lighting arrangements so that

    not less than 1 lamp is provided in each space if needed for work or required for safety. Also, install lights as directed by General Contractor, in smaller areas where required to provide adequate light for work being carried out in the space.

    b. Receptacle Outlets: See temporary light and power.c. Furnish and install 200 Watt lamps for general circuit lighting and all fuses as may be

    required for a complete job.d. Replace lamps, fuses, including theft, throughout the life of the project.e. Install and maintain a reasonably balanced system and take current readings on the

    feeders at regular intervals as required. Correct any serious phase unbalance.f. Protect the installation against weather damage, normal operations of other trades,

    and other persons on the site. Be responsible for the proper use and maintenance of temporary wiring systems until they are removed.

    1.05 TELECOMMUNICATIONS SERVICESA. Provide, maintain, and pay for telecommunications services to field office at time of project

    mobilization.B. Telecommunications services shall include:

    1. Windows-based personal computer dedicated to project telecommunications, with necessary software and laser printer.

    2. Internet Connections: Minimum of one; DSL modem or faster.1.06 TEMPORARY SANITARY FACILITIES

    A. Use of existing facilities is permitted. Facilities to be cleaned and limited to area designated by owner.

    1.07 BARRIERSA. Provide barriers to prevent unauthorized entry to construction areas, to prevent access to areas

    that could be hazardous to workers or the public, to allow for owner's use of site and to protect existing facilities and adjacent properties from damage from construction operations .

    B. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    01 50 00TEMPORARY FACILITIES AND CONTROLS

    Page 4 of 6

    1.08 INTERIOR ENCLOSURESA. Provide temporary partitions as indicated to separate work areas from Owner-occupied areas,

    to prevent penetration of dust and moisture into Owner-occupied areas, and to prevent damage to existing materials and equipment.

    B. Construction: Framing and gypsum board sheet materials with closed joints and sealed edges at intersections with existing surfaces:1. STC rating of 35 in accordance with ASTM E90.2. Maximum flame spread rating of 25 in accordance with ASTM E84.

    C. Provide all shoring and bracing required for safety and proper execution of the work. Remove the items when the work is completed.

    D. Paint all surfaces exposed to view from Owner-occupied areas.1.09 PROTECTION OF INSTALLED WORK

    A. Protect installed work and provide special protection to protect work by other contractors.B. Provide temporary and removable protection for installed products. Control activity in

    immediate work area to minimize damage.C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.D. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement

    of heavy objects by protecting with durable sheet materials.E. Prohibit traffic or storage on waterproofed or roofed surfaces. When traffic or activity is

    necessary, obtain recommendation for protection from waterproofing or roofing material manufacturer.

    F. Prohibit traffic from landscaped areas.1.10 SECURITY

    A. Provide security and facilities to protect Work, and Owner's operations from unauthorized entry, vandalism, or theft.

    B. Coordinate with Owner's security program.1.11 VEHICULAR ACCESS AND PARKING

    A. Comply with regulations relating to use of streets and sidewalks, access to emergency facilities, and access for emergency vehicles.

    B. Coordinate access and haul routes with governing authorities and Owner.C. Provide traffic control at critical areas of haul routes to regulate traffic, to minimize interference

    with public traffic.D. Provide and maintain access to fire hydrants, free of obstructions. Leave fire lanes and aisles to

    fire fighting equipment unobstructed at all times. Do not pile material in front of fire equipment, fire doors, or hydrants.

    E. Designated existing on-site roads may be used for construction traffic.F. Parking for Contractor's firm owned vehicles is limited, in number and location, to parking

    spaces designated by Owner. No parking or obstructing egress to and from Parking Areas will be allowed unless authorized by Owner.

    G. Parking of private vehicles of workers shall be in an area allocated by the Owner.H. Traffic and parking regulations of the Owner and the City are applicable and violators are

    subject to fines for infractions.1.12 WASTE REMOVAL

    A. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition. Locate in area designated by Owner and General Contractor.

    B. Carts, trucks, etc. used to transport materials shall be loaded in a safe manner. Materials shall not protrude beyond the sides of conveyance used.

    http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%2520E90https://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%2520E84

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    01 50 00TEMPORARY FACILITIES AND CONTROLS

    Page 5 of 6

    C. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless otherwise approved by the authorities having jurisdiction.

    D. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.

    E. Materials shall not be thrown or dropped from scaffolds or other overhead areas.F. Gasoline or other highly flammable liquids shall not be brought inside facilities.G. Spills of any materials creating hazards shall be cleaned up immediately.

    1.13 HAUL ROUTESA. Haul routes shall be designated by Owner.B. Confine construction traffic to designated route.C. Provide traffic control at critical areas of haul routes to regulate traffic, to minimize interference

    with public traffic.1.14 PROJECT IDENTIFICATION

    A. Provide project identification sign of design, construction, and location approved by Owner.B. No other signs are allowed without Owner permission except those required by law.

    1.15 FIELD OFFICESA. Office: Weathertight, with lighting, electrical outlets, heating, cooling equipment, and equipped

    with sturdy furniture and drawing display table.1. Review proposed location within Project Site with Owner2. Provide space for Project meetings, with table and chairs to accommodate 12 persons.

    B. Field Offices shall be maintained until final acceptance and then be removed by the responsible party, no later than fifteen (15) days after acceptance of building, unless the General Contractor orders or approves earlier removal.

    C. Expenses:1. General Contractor: All expenses in connection with his Field Offices, including the

    installation costs and use of telephones, heat, air-conditioning, light, water and janitor service shall be paid for by the General Contractor and will be fully reimbursed by to the Owner.

    2. Prime or Trade Contractors: All expenses associated with their offices including utility installation costs shall be included in their bid.

    3. Toll Costs: All long distance calls to be paid for by party placing call including Architect, Owner's representative, and contractors.

    D. Each Trade Contractor: To keep a complete set of drawings, and specifications kept marked up to date with revision, Addenda, as-built drawings, and all permits and approved shop drawings on file.

    1.16 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLSA. Remove temporary utilities, equipment, facilities, materials, prior to Date of Substantial

    Completion inspection.B. Clean and repair damage caused by installation or use of temporary work.C. Restore existing facilities used during construction to original condition.

    PART 2 PRODUCTS - NOT USEDPART 3 - EXECUTION3.01 USE OF PERMANENT SYSTEMS AND FACILITIES

    A. Obtain written agreement with Owner, establishing start of warranties and conditions of use:1. Systems complete, with utility connections and safety devices.2. Automatic controls operational.

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    01 50 00TEMPORARY FACILITIES AND CONTROLS

    Page 6 of 6

    3. Temporary filters and items required for protection of equipment and finishes are in place.B. Replace items damaged during temporary service use.

    3.02 TOOL AND EQUIPMENT USEA. All tools and equipment must conform to OSHA Safety Code and State Codes. All contractors’

    equipment must be removed upon completion of the job.B. Necessary precaution and protection is to be exercised to prevent fires and damage from falling

    sparks from welding and cutting operations.3.03 CLEAN-UP AND MATERIAL MOVING

    A. Keep working area as clean as possible at all times. Do not allow refuse and debris to accumulate. All refuse and debris must be removed from work area by contractor each day and disposed of in a legal dumping site.

    B. Each Trade Contractor and their subcontractors shall do their own clean-up, move materials that are in the way of construction, and repair and replace damage they do.

    C. If the above work is not accomplished in a reasonable length of time, the Owner will do the required work. Cost of the work will be charged to the Trade Contractor.

    D. Each Contractor shall do all cleaning of finish surfaces relative to their work prior to acceptance of their work. Each Contractor shall comply with all special cleaning instructions contained in the Specification.

    END OF SECTION

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    08 14 16FLUSH WOOD DOORS

    Page 1 of 21

    SECTION 087100

    DOOR HARDWARE

    PART 1 - GENERAL

    1.1 RELATED DOCUMENTS

    A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

    1.2 SUMMARY

    A. Section includes:

    1. Mechanical hardware for:a. Swinging doors.

    2. Field verification, preparation and modification of existing doors and frames to receive new door hardware.

    B. Exclusions: Unless specifically listed in hardware sets, hardware is not specified in this section for:

    1. Windows2. Cabinets (casework), including locks in cabinets3. Signage4. Toilet accessories5. Overhead doors

    C. Related Sections:

    1. Division 01 Section “Alternates” for alternates affecting this section.2. Division 07 Section “Joint Sealants” for sealant requirements applicable to

    threshold installation specified in this section.3. Division 09 sections for touchup finishing or refinishing of existing openings modified

    by this section.

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    08 14 16FLUSH WOOD DOORS

    Page 2 of 21

    1.3 REFERENCES

    A. UL - Underwriters Laboratories

    1. UL 10B - Fire Test of Door Assemblies2. UL 10C - Positive Pressure Test of Fire Door Assemblies3. UL 1784 - Air Leakage Tests of Door Assemblies4. UL 305 - Panic Hardware

    B. DHI - Door and Hardware Institute

    1. Sequence and Format for the Hardware Schedule2. Recommended Locations for Builders Hardware3. Key Systems and Nomenclature

    C. ANSI - American National Standards Institute

    1. ANSI/BHMA A156.1 - A156.29, and ANSI/BHMA A156.31 - Standards for Hardware and Specialties

    1.4 SUBMITTALS

    A. General:

    1. Submit in accordance with Conditions of Contract and Division 01 requirements.2. Highlight, encircle, or otherwise specifically identify on submittals deviations from

    Contract Documents, issues of incompatibility or other issues which may detrimentally affect the Work.

    3. Prior to forwarding submittal, comply with procedures for verifying existing door and frame compatibility for new hardware, as specified in PART 3, “EXAMINATION” article, herein.

    B. Action Submittals:

    1. Product Data: Product data including manufacturers’ technical product data for each item of door hardware, installation instructions, maintenance of operating parts and finish, and other information necessary to show compliance with requirements.

    2. Samples for Verification: If requested by Architect, submit production sample or sample installations of each type of exposed hardware unit in finish indicated, and tagged with full description for coordination with schedule.

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    08 14 16FLUSH WOOD DOORS

    Page 3 of 21

    a. Samples will be returned to supplier in like-new condition. Units that are acceptable to Architect may, after final check of operations, be incorporated into Work, within limitations of key coordination requirements.

    3. Door Hardware Schedule: Submit schedule with hardware sets in vertical format as illustrated by Sequence of Format for the Hardware Schedule as published by the Door and Hardware Institute. Indicate complete designations of each item required for each door or opening, include:

    a. Door Index; include door number, heading number, and Architects hardware set number.

    b. Opening Lock Function Spreadsheet: List locking device and function for each opening.

    c. Type, style, function, size, and finish of each hardware item.d. Name and manufacturer of each item.e. Fastenings and other pertinent information.f. Location of each hardware set cross-referenced to indications on Drawings.g. Explanation of all abbreviations, symbols, and codes contained in schedule.h. Mounting locations for hardware.i. Door and frame sizes and materials.j. Name and phone number for local manufacturer's representative for each product.

    1) Submittal Sequence: Submit door hardware schedule concurrent with submissions of Product Data, Samples, and Shop Drawings. Coordinate submission of door hardware schedule with scheduling requirements of other work to facilitate fabrication of other work that is critical in Project construction schedule.

    4. Key Schedule:

    a. After Keying Conference, provide keying schedule listing levels of keying as well as explanation of key system's function, key symbols used and door numbers controlled.

    b. Use ANSI/BHMA A156.28 “Recommended Practices for Keying Systems” as guideline for nomenclature, definitions, and approach for selecting optimal keying system.

    c. Provide 3 copies of keying schedule for review prepared and detailed in accordance with referenced DHI publication. Include schematic keying diagram and index each key to unique door designations.

    d. Index keying schedule by door number, keyset, hardware heading number, cross keying instructions, and special key stamping instructions.

    e. Provide one complete bitting list of key cuts and one key system schematic illustrating system usage and expansion.1) Forward bitting list, key cuts and key system schematic directly to Owner,

    by means as directed by Owner.f. Prepare key schedule by or under supervision of supplier, detailing Owner’s

    final keying instructions for locks.

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    08 14 16FLUSH WOOD DOORS

    Page 4 of 21

    5. Templates: After final approval of hardware schedule, provide templates for doors, frames and other work specified to be factory prepared for door hardware installation.

    C. Informational Submittals:

    1. Qualification Data: For Supplier, Installer and Architectural Hardware Consultant.2. Product Certificates for electrified door hardware, signed by manufacturer:

    a. Certify that door hardware approved for use on types and sizes of labeled fire-rated doors complies with listed fire-rated door assemblies.

    3. Certificates of Compliance:a. Certificates of compliance for fire-rated hardware and installation instructions if

    requested by Architect or Authority Having Jurisdiction.b. Installer Training Meeting Certification: Letter of compliance, signed by Contractor,

    attesting to completion of installer training meeting specified in “QUALITY ASSURANCE” article, herein.

    4. Product Test Reports: For compliance with accessibility requirements, based on evaluation of comprehensive tests performed by manufacturer and witnessed by qualified testing agency, for door hardware on doors located in accessible routes.

    5. Warranty: Special warranty specified in this Section.

    D. Closeout Submittals:

    1. Operations and Maintenance Data : Provide in accordance with Division 01 and include:

    a. Complete information on care, maintenance, and adjustment; data on repair and replacement parts, and information on preservation of finishes.

    b. Catalog pages for each product.c. Name, address, and phone number of local representative for each manufacturer.d. Parts list for each product.e. Final approved hardware schedule, edited to reflect conditions as-installed.f. Final keying scheduleg. Copies of floor plans with keying nomenclatureh. As-installed wiring diagrams for each opening connected to power, both low voltage

    and 110 volts.i. Copy of warranties including appropriate reference numbers for manufacturers to

    identify project.

    1.5 QUALITY ASSURANCE

    A. Product Substitutions: Comply with product requirements stated in Division 01 and as specified herein.

    1. Where specific manufacturer’s product is named and accompanied by “No Substitute,” including make or model number or other designation, provide product specified. (Note:

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    08 14 16FLUSH WOOD DOORS

    Page 5 of 21

    Certain products have been selected for their unique characteristics and particular project suitability.)

    a. Where no additional products or manufacturers are listed in product category, requirements for “No Substitute” govern product selection.

    2. Where products indicate “acceptable manufacturers” or “acceptable manufacturers and products”, provide product from specified manufacturers, subject to compliance with specified requirements and “Single Source Responsibility” requirements stated herein.

    B. Supplier Qualifications and Responsibilities: Recognized architectural hardware supplier with record of successful in-service performance for supplying door hardware similar in quantity, type, and quality to that indicated for this Project and that provides certified Architectural Hardware Consultant (AHC) available to Owner, Architect, and Contractor, at reasonable times during the Work for consultation.

    1. Warehousing Facilities: In Project's vicinity.2. Scheduling Responsibility: Preparation of door hardware and keying schedules.3. Engineering Responsibility: Preparation of data for electrified door hardware, including

    Shop Drawings, based on testing and engineering analysis of manufacturer's standard units in assemblies similar to those indicated for this Project.

    4. Coordination Responsibility: Coordinate installation of electronic security hardware with Architect and electrical engineers and provide installation and technical data to Architect and other related subcontractors.

    C. Installer Qualifications: Qualified tradesmen, skilled in application of commercial grade hardware with record of successful in-service performance for installing door hardware similar in quantity, type, and quality to that indicated for this Project.

    D. Architectural Hardware Consultant Qualifications: Person who is experienced in providing consulting services for door hardware installations that are comparable in material, design, and extent to that indicated for this Project and meets these requirements:

    1. For door hardware, DHI-certified, Architectural Hardware Consultant (AHC).2. Can provide installation and technical data to Architect and other related subcontractors.3. Can inspect and verify components are in working order upon completion of installation.4. Capable of producing wiring diagrams.5. Capable of coordinating installation of electrified hardware with Architect and electrical

    engineers.

    E. Single Source Responsibility: Obtain each type of door hardware from single manufacturer.

    1. Provide electrified door hardware from same manufacturer as mechanical door hardware, unless otherwise indicated.

    2. Manufacturers that perform electrical modifications and that are listed by testing and inspecting agency acceptable to authorities having jurisdiction are acceptable.

    F. Fire-Rated Door Openings: Provide door hardware for fire-rated openings that complies with NFPA 80 and requirements of authorities having jurisdiction. Provide only items of door

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    08 14 16FLUSH WOOD DOORS

    Page 6 of 21

    hardware that are listed and are identical to products tested by Underwriters Laboratories, Intertek Testing Services, or other testing and inspecting organizations acceptable to authorities having jurisdiction for use on types and sizes of doors indicated, based on testing at positive pressure and according to NFPA 252 or UL 10C and in compliance with requirements of fire-rated door and door frame labels.

    G. Electrified Door Hardware: Listed and labeled as defined in NFPA 70, Article 100, by testing agency acceptable to authorities having jurisdiction.

    H. Means of Egress Doors: Latches do not require more than 15 lbf (67 N) to release latch. Locks do not require use of key, tool, or special knowledge for operation.

    I. Accessibility Requirements: For door hardware on doors in an accessible route, comply with governing accessibility regulations cited in “REFERENCES” article, herein.

    1. Provide operating devices that do not require tight grasping, pinching, or twisting of wrist and that operate with force of not more than 5 lbf (22.2 N).

    2. Maximum opening-force requirements:

    a. Interior, Non-Fire-Rated Hinged Doors: 5 lbf (22.2 N) applied perpendicular to door.b. Sliding or Folding Doors: 5 lbf (22.2 N) applied parallel to door at latch.c. Fire Doors: Minimum opening force allowable by authorities having jurisdiction.

    3. Bevel raised thresholds with slope of not more than 1:2. Provide thresholds not more than 1/2 inch (13 mm) high.

    4. Adjust door closer sweep periods so that, from open position of 70 degrees, door will take at least 3 seconds to move to 3 inches (75 mm) from latch, measured to leading edge of door.

    J. Keying Conference: Conduct conference at Project site to comply with requirements in Division 01.

    1. Attendees: Owner, Contractor, Architect, Installer, Owner's security consultant, and Supplier’s Architectural Hardware Consultant.

    2. Incorporate keying conference decisions into final keying schedule after reviewing door hardware keying system including:

    a. Function of building, flow of traffic, purpose of each area, degree of security required, and plans for future expansion.

    b. Preliminary key system schematic diagram.c. Requirements for key control system.d. Address for delivery of keys.

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    08 14 16FLUSH WOOD DOORS

    Page 7 of 21

    K. Pre-installation Conference: Conduct conference at Project site.

    1. Review and finalize construction schedule and verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays.

    2. Inspect and discuss preparatory work performed by other trades.3. Review required testing, inspecting, and certifying procedures.

    L. Coordination Conferences:

    1. Installation Coordination Conference: Prior to hardware installation, schedule and hold meeting to review questions or concerns related to proper installation and adjustment of door hardware.

    a. Attendees: Door hardware supplier, door hardware installer, Contractor.b. After meeting, provide letter of compliance to Architect, indicating when meeting

    was held and who was in attendance.

    1.6 DELIVERY, STORAGE, AND HANDLING

    A. Inventory door hardware on receipt and provide secure lock-up for hardware delivered to Project site.

    B. Tag each item or package separately with identification coordinated with final door hardware schedule, and include installation instructions, templates, and necessary fasteners with each item or package.

    1. Deliver each article of hardware in manufacturer’s original packaging.

    C. Project Conditions:

    1. Maintain manufacturer-recommended environmental conditions throughout storage and installation periods.

    2. Provide secure lock-up for door hardware delivered to Project, but not yet installed. Control handling and installation of hardware items so that completion of Work will not be delayed by hardware losses both before and after installation.

    D. Protection and Damage:

    1. Promptly replace products damaged during shipping.

    2. Handle hardware in manner to avoid damage, marring, or scratching. Correct, replace or repair products damaged during Work.

    3. Protect products against malfunction due to paint, solvent, cleanser, or any chemical agent.

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    08 14 16FLUSH WOOD DOORS

    Page 8 of 21

    E. Deliver keys and permanent cores to Owner by registered mail or overnight package service.

    1.7 COORDINATION

    A. Coordinate layout and installation of floor-recessed door hardware with floor construction. Cast anchoring inserts into concrete. Concrete, reinforcement, and formwork requirements are specified in Division 03.

    B. Installation Templates: Distribute for doors, frames, and other work specified to be factory prepared. Check Shop Drawings of other work to confirm that adequate provisions are made for locating and installing door hardware to comply with indicated requirements.

    C. Existing Openings: Where hardware components are scheduled for application to existing construction or where modifications to existing door hardware are required, field verify existing conditions and coordinate installation of door hardware to suit opening conditions and to provide proper door operation.

    D. Direct shipments not permitted, unless approved by Contractor.

    1.8 WARRANTY

    A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of door hardware that fail in materials or workmanship within specified warranty period.

    1. Warranty Period: Years from date of Substantial Completion, for durations indicated.

    a. Closers:1) Mechanical: 30 years.

    b. Exit Devices:1) Mechanical: 3 years.

    c. Locksets:1) Mechanical: 3 years.

    d. Continuous Hinges: Lifetime warranty.e. Key Blanks: Lifetime

    2. Warranty does not cover damage or faulty operation due to improper installation, improper use or abuse.

    1.9 MAINTENANCE

    A. Maintenance Tools:

    1. Furnish complete set of special tools required for maintenance and adjustment of hardware, including changing of cylinders.

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityHamilton, Ohio

    08 14 16FLUSH WOOD DOORS

    Page 9 of 21

    PART 2 - PRODUCTS

    2.1 MANUFACTURERS

    A. The Owner requires use of certain products for their unique characteristics and particular project suitability to insure continuity of existing and future performance and maintenance standards. After investigating available product offerings Awarding Authority has elected to prepare proprietary specifications. These products are specified with the notation: “No Substitute.”

    1. Where “No Substitute” is noted, submittals and substitution requests for other products will not be considered.

    B. Approval of manufacturers and/or products other than those listed as “Scheduled Manufacturer” or “Acceptable Manufacturers” in the individual article for the product category shall be in accordance with QUALITY ASSURANCE article, herein.

    C. Approval of products from manufacturers indicated in “Acceptable Manufacturers” is contingent upon those products providing all functions and features and meeting all requirements of scheduled manufacturer’s product.

    D. Hand of Door: Drawings show direction of slide, swing, or hand of each door leaf. Furnish each item of hardware for proper installation and operation of door movement as shown.

    E. Where specified hardware is not adaptable to finished shape or size of members requiring hardware, furnish suitable types having same operation and quality as type specified, subject to Architect's approval.

    2.2 MATERIALS

    A. Fasteners

    1. Provide hardware manufactured to conform to published templates, generally prepared for machine screw installation.

    2. Furnish screws for installation with each hardware item. Finish exposed (exposed under any condition) screws to match hardware finish, or, if exposed in surfaces of other work,

  • SHYFT Collective

    Mosler Hall E-LearningMiami UniversityMiddletown, Ohio

    08 71 00DOOR HARDWARE

    Page 10 of 21

    to match finish of this other work including prepared for paint surfaces to receive painted finish.

    3. Provide concealed fasteners for hardware units exposed when door is closed except when no standard units of type specified are available with concealed fasteners. Do not use thru-bolts for installation where bolt head or nut on opposite face is exposed in other work unless thru-bolts are required to fasten hardware securely. Review d