Half yearly Compliance report for Environment and CRZ Clearance for the development of
Solid Cargo Port Terminal Phase – I and Phase – II.
Sr.
No. Specific Conditions Compliance
P2(i) All the conditions stipulated by Ministry of
Environment and Forests, Regional Office,
Western Region, Bhopal vide their latter No. 6-
GJ060/2006-BHO/1508, dtd., 16.6.2008 shall be
strictly adhered to
Complying with
P2(ii) All the conditions stipulated by Forest and
Environment Department, Govt. of Gujarat vide
their latter No.-FCA-1006(10-9)SF-76-K, dated.,
1.7.2008 dated 16.6.2008 shall be strictly
adhered to
Complying with
P2(iii) No reclamation will be carried out for the activity
Complied. Project has been developed within
existing land without any reclamation.
P2(iv) All the conditions stipulated by the Gujarat
Coastal Zone Management Authority including
Ministry of Environment and Forests clearance
dated 16.6.2008 under the Forest Conservation
Act shall complied.
Complying with
P2(v),
P1(i)
Sewage Treatment Plant should be included in
the project
Complied. Two Sewage Treatment Plant of
capacity 25 M3 / day and 2 M3 / day has been
installed and are in operations
P2(vi),
P1(ii)
Afforestation in 200 ha. with mangroves should
be undertaken under the project, as identified by
the Gujarat Forest Department
Mangrove afforestation has been carried out
in an area of 400 ha . Details are given below.
1. 100 ha near village Dandi,
Dist Surat– 2011
2. 50 ha near village Jakhau,
Dist Kutch – 2011
3. 50 ha near Padri bit,
Dist Bhavnagar – 2011
4. 200 ha near Malpur,
Dist Jambusar – 2013-14
P2(vii) Afforestation @1:3 shall be carried out in case of
any trees to be cut.
Complied. Details of afforestation were
submitted along with the half-yearly
compliance report dated 27th May, 2014 and
there is no further change.
P2(viii),
P1(iii)
The recommendations of the Risk Assessment
Report should be incorporated
Complied. Risk Assessment Report was
submitted along with compliance report dt.
20th February, 2008. The recommendation of
risk assessment are incorporated and
followed during construction and operation
phases.
P2(ix),
P1(v)
The materials for the filling and pavement
construction should be made available from
Complied. Construction of the project was
completed in February 2011.
Adani Petronet (Dahej) Port Private Limited
From : Oct,15 To : March,16
Page 3 of 14
Half yearly Compliance report for Environment and CRZ Clearance for the development of
Solid Cargo Port Terminal Phase – I and Phase – II.
Sr.
No. Specific Conditions Compliance
approved quarries
P2(x),
P1(vi)
Sufficient fixed and mobile firefighting system
should be provided exclusively for the terminal in
consultation with the local statutory bodies.
Complied. Details of the fire-fighting system
were submitted along with the half-yearly
compliance report dated 27.05.2014 and there
is no further change.
P2(xi),
P1(x)
All development in the port should be carried out
in accordance with the Coastal Regulation Zone
Notification, 1991 and approved Coastal Zone
Management Plan of Gujarat.
Complied. Construction has been completed
in February 2011 and same is carried out in
accordance with CRZ Notification 1991.
P2(xii), P1(xi)There shall be no withdrawal of ground water in
CRZ area for this project. The proponent should
ensure that as a result of the proposed
constructions, ingress of saline water into ground
water does not take place. Peizometers shall be
installed for regular monitoring for this purpose
at appropriate locations on the project site.
Complied. Ground water is not tapped in CRZ
area for the project.
Two Piezometers has been installed at
different locations inside port. Regular
monitoring of ground water level & quality is
being monitored through accredited
laboratory. Copies of reports are enclosed as
Annexure 1.
P2(xiii),
P1(xii)
The project shall not be commissioned till the
requisite water supply and electricity to the
project are provided by the PWD/Electricity
Department.
Project is commissioned after obtaining
permission from PWD and Electricity
Department.
1. GIDC permission dtd 19.02.2013
2. Electricity Department approval dtd
18.02.2011
P2(xiv),
P1(xiii)
Specific arrangements for rain water harvesting
shall be made in the project design and the rain
water so harvested shall be optimally utilized.
Details in this regard shall be furnished to this
Ministry’s Regional Office at Bhopal within 3
months
The feasibility study for rain water harvesting
was conducted. Report was submitted along
with the half-yearly compliance report dated
22.05.2015.
P2(xv),
P1(xv)
No land reclamation should be carried out for
this project.
Complied. Project has been developed within
existing land without any reclamation.
P2(xvi)
,P1(xvi)
Green buffer zone should be provided all around
the project area in consultation with local forest
department and report submitted to this
Ministry’s Regional Office at Bhopal.
Considering the expansion plan, Green belt is
being developed on periphery of the project
boundary. So far 6.0 ha of Green belt is
developed which mainly includes casuarina,
wasigtonia palm, cassia samiea,
__peltoforum, delonix regia, ficus sps.
P2(xvii)
,P1(xiv)
The facilities to be constructed in the CRZ area as
part of this project should be strictly in
conformity with the provisions of the CRZ
Complied. Construction of the project was
completed in February 2011 and same is in
conformity with the provisions of the CRZ
Adani Petronet (Dahej) Port Private Limited
From : Oct,15 To : March,16
Page 4 of 14
Half yearly Compliance report for Environment and CRZ Clearance for the development of
Solid Cargo Port Terminal Phase – I and Phase – II.
Sr.
No. Specific Conditions Compliance
Notification, 1991 as amended subsequently. Notification 1991..
P2(xviii),
P1(xvii)
No product other than those permissible in the
Coastal Regulation Zone Notification, 1991
should be stored in the Coastal Regulation Zone
area.
Complied. APPPL is handling dry cargo mainly
coal and other bulk cargos at designated
storage areasas per approval.
P1(iv) Location of general cargo berth should be taken
in to considerations with regard to location of
LNG terminal
Complied. General cargo berth (Solid Cargo
Port Terminal jetty) is approx. 500 m away
from the LNG jetty of Petronet LNG Ltd.
P1(vii) The wave tranquility study and the ship
maneuvering studies carried out should be taken
in to account while operating the Port.
Complied. Ship mooring study and wave
tranquility studies were carried out to
understand the wind wave and swell wave
conditions. The recommendations are being
regularly followed during port operations.
P1(viii) The project proponent should ensure that during
construction and operation of the port there will
be no impact on the livelihood of the fisherman.
The fisherman should be provided free access to
carry out the fishing activity.
Complied. There is no impact on fishermen
livelihood due to project activity and free
access to the “Pagadiya” fishermen has been
already provided. However, there is no
commercial fishing in the area.
P1(ix) All necessary precaution while undertaking
construction and operation of the port should be
taken keeping in view the bathymetric changes
caused due to cyclones.
Complied. Construction activities are
completed in February, 2011. APPPL has a
well-defined DMP and regular mock drills are
being conducted. DMP is also reviewed at
regular interval.
General Conditions
P2(i),
P1(i)
Construction of proposed structures shall be
undertaken meticulously conforming to the
existing Central/local rules and regulations
including Coastal Regulation Zone Notification
1991 & its amendments. All the construction
designs/drawings relating to the proposed
construction activities must have approvals of
the concerned state Government
Departments/Agencies.
Complied. All the development activities are
being taken up in accordance with the CRZ
notification, 1991 & its subsequent
amendments.
The approval for the project has been
obtained from concern government
department that is GMB as per their NOC
date 27 Jan 2006.
Necessary approval has been obtained from
GIDC for the setting of the project.
P2(ii),
P1(ii)
Adequate provision for infrastructure facilities
such as water supply, fuel, sanitation etc. should
be ensured for construction workers during the
construction phase of the project so as to avoid
felling of trees/mangroves and pollution of water
and the surrounding.
Complied. Construction of the project was
completed on February 2011.
Adani Petronet (Dahej) Port Private Limited
From : Oct,15 To : March,16
Page 5 of 14
Half yearly Compliance report for Environment and CRZ Clearance for the development of
Solid Cargo Port Terminal Phase – I and Phase – II.
Sr.
No. Specific Conditions Compliance
P2(iii),
P1(iii)
The project authorities must make necessary
arrangements for disposal of solid waste and for
the treatment of effluents by providing a proper
wastewater treatment plant outside the CRZ
area. The quality of treated effluents, solid
wastes and noise level etc. must conform to the
standards laid down by the competent
authorities including the Central/State Pollution
Control Board and the Union Ministry of
Environment and Forest under the
Environmental (Protection) Act, 1986, whichever
are more stringent.
The Project activity is not generating any
trade effluent.
The monitoring results for the period from
Oct,15 to March, 16 are enclosed as Annexure
– 1
P2(iv),
P1(iv)
The proponent shall obtain the requisite
consents for discharge of effluents and emission
under the Water (Prevention and Control of
Pollution) Act, 1974 and the Air (Preventio0n and
Control of Pollution) Act, 1981 form the Gujarat
State Pollution Control Board before
commissioning of the project and a copy of each
of these shall be sent to this Ministry.
Comlied. APPPL has obtained CC&A AWH
73359 from GPCB which is valid up to
16/7/2020.
P2(v),
P1(v)
The proponent shall provide for a regular
monitoring mechanism so as to ensure that the
treated effluents conform to the prescribed
standards. The record of analysis reports must be
properly maintained and made available for
inspection to the concerned State/Central
officials during their visits.
Complied. Domestic effluent is being treated
in STPs. The treated water confirming to the
norms is being used for horticulture purpose.
The monitoring results of the treated
wastewater from STP for the period from Oct
2015 – March 2016 are enclosed as Annexure
– 1
P2(vi),
P1(vi)
In order to carry out the environmental
monitoring during the operational phase of the
project, the project authorities should provide an
environmental laboratory well equipped with
standard equipment and facilities and qualified
manpower to carry out the testing of various
environmental parameters.
APPPL has engaged NABL accredited and
MoEF recognised laboratory for
environmental monitoring. The monitoring
results for the period from Oct 2015 – Mach
2016 are enclosed as Annexure – 1
P2(vii),
P1(vii)
The sand dunes and mangroves, if any on the site
should not be disturbed in any way.
Complying with
P2(viii),
P1(viii)
A copy of the clearance letter will be marked to
the concern Panchayat/local NGO, if any, from
whom any suggestion/representation has been
received while processing the proposal.
Complied.
P2(ix),
P1(ix)
The Gujarat State Pollution Control Board should
display a copy of the clearance letter at the
This condition does not belong to the project
proponent.
Adani Petronet (Dahej) Port Private Limited
From : Oct,15 To : March,16
Page 6 of 14
Half yearly Compliance report for Environment and CRZ Clearance for the development of
Solid Cargo Port Terminal Phase – I and Phase – II.
Sr.
No. Specific Conditions Compliance
Regional Office, District Industries Centre and
Collector’s Office/Tehsildar’s Office for 30 days.
P2(x),
P1(x)
The fund earmarked for environment protection
measures should be maintained in a separate
account and there should be no diversion of
these funds for any other purpose. A year-wise
expenditure on environmental safeguards should
be reported to this Ministry’s Regional Office at
Bhopal and the State Pollution Control Board.
Complied. Separate budget is allocated for
Environmental Management. Key
components of environment budget are
environmental Monitoring, STP’s (Operations
and Maintenance), Closed Conveyor System
Maintenance and etc. The allocation of
budget for Environment Cell for the FY 2015-
16 was approx. Rs. 126 lacs. Details of the
environmental budget and expenditure for
the FY 15-16 is enclosed as Annexure – 2
P2(xi),
P1(xi)
Full support should be extended to the officers of
this Ministry’s Regional Office at Bhopal and the
officers of the Central and State Pollution
Control Boards by the project proponents during
their inspection for monitoring purposes, by
furnishing full details and action plans including
the action taken reports in respect of mitigative
measures and other environmental protection
activities.
Complied. Full support is always extended to
the officers of Ministry/Regional Office, MoEF
as well as officers of Central and State
Pollution Control Board.
P2(xii),
P1(xii)
In case of deviation or alteration in the project
including the implementing agency, a fresh
reference should be made to this Ministry for
modification in the clearance conditions or
imposition of new ones for ensuring
environmental protection.
Noted and complied with.
P2(xiii),
P1(xiii)
This Ministry reserves the right to revoke this
clearance, if any of the conditions
stipulated are not complied with to the
satisfaction of the Ministry.
Noted.
P2(xiv),
P1(xiv)
This Ministry or any other competent authority
may stipulate any other additional conditions
subsequently, if deemed necessary, for
environmental protection, which shall be
complied with.
Noted.
Adani Petronet (Dahej) Port Private Limited
From : Oct,15 To : March,16
Page 7 of 14
Half yearly Compliance report for Environment and CRZ Clearance for the development of
Solid Cargo Port Terminal Phase – I and Phase – II.
Sr.
No. Specific Conditions Compliance
P2(xv),
P1(xv)
The project proponent should advertise at least
in two local newspapers widely circulated in the
region around the project, one of which shall be
in the vernacular language of the locality
concerned informing that the project has been
accorded environmental clearance and copies of
clearance letters are available with the State
Pollution Control Board and may also be seen at
Website of the Ministry of Environment & Forest
at http://www.envfornic.in .The advertisement
should be made within 7 days from the date of
issue of the clearance letter and a copy of the
same should be forwarded to the Regional Office
of this Ministry at Bhopal.
Complied. Advertisement of phase 1 approval
was published in Gujarati language in
“Sandesh” newspaper dated 01/09/2007 and
in English language in “GUJARAT
SAMACHAR” newspaper dated 11.9.2007.
Advertisement of phase 2 approval was
published in gujarati language in “Divya
Bhaskar” newspaper and in English language
in “The Times of India” dated 19/11/2008.
P2(xvi),
P1(xvi)
The Project proponents should inform the
Regional Office at Bhopal as well as the Ministry
the date of financial closure and final approval of
the project by the concerned authorities and the
date of start of Land Development Work.
Financial closure date of Project was 31st July
2007.
Existing Facility – construction started date
July 2007. Land development work for phase
II stared in Jan. 2009.
The approval for the project has been
obtained from concern government
department that is GMB as per their NOC
date 27 Jan 2006.
Necessary approval has been obtained from
GIDC for the setting of the project.
P2(xvii) Any appeal against this environment clearance
shall lie with the National Environment Appellate
Authority, if preferred, within a period of 30 days
as prescribed under Section 11 of the National
Appellate Act, 1997
Noted.
Adani Petronet (Dahej) Port Private Limited
From : Oct,15 To : March,16
Page 8 of 14
Compliance to the conditions stipulated in CRZ
clearance/ recommendation for proposed cargo
port terminal phase I and II at Dahej
Adani Petronet (Dahej) Port Private Limited
From : Oct,15 To : March,16
Page 9 of 14
Half yearly Compliance report for CRZ Clearance/recommendation for development of Solid Cargo
Port Terminal Phase – I and Phase – II
Sr. no. Conditions Status/Action taken
P2(1),
P1(1)
The provisions of the CRZ notification of 1991
and subsequent amendments issued from
time to time shall be strictly adhered to by the
APPL. No activity in contradiction to the
provisions of the CRZ Notification shall be
carried out by the APPL.
Complied. All the activities are being
complying with the provisions of the CRZ
notification and subsequent amendments.
P2(2),
P1(2)
All necessary permissions from different
Government Departments / agencies shall be
obtained by the APPL before commencing
the expansion activities.
Complied. All the necessary permissions have
been obtained by M/s. APPPL.
P2(3),
P1(5)
The APPL shall carry out the construction
activities either in the CRZ area or into the sea
/ estuary only after having the detailed study
with respect to chances of erosion / accretion
due to the proposed activities conducted
through the NIO and vetted through the
CWPRS and shall implement all necessary
steps / actions as may be suggested by these
institutes for mitigating the potential
negative impacts including the checking of
erosion and/or accretion in the region.
Further, the company shall have to have the
construction drawings approved for this
purpose through a competent agency before
undertaking any construction and/or enabling
activities at the site
Complied. Construction of the port was
completed in February 2011. All the
recommendations of the EIA for construction
phase were implemented.
P2(4),
P1(7)
The APPL shall have to face the consequences
whatsoever due to implementation of the
Kalpsar Project proposed by the Government
of Gujarat and shall have to take all necessary
actions as may be desired by the
Government, from time to time.
Noted
Adani Petronet (Dahej) Port Private Limited
From : Oct,15 To : March,16
Page 10 of 14
Half yearly Compliance report for CRZ Clearance/recommendation for development of Solid Cargo
Port Terminal Phase – I and Phase – II
Sr. no. Conditions Status/Action taken
P2(5),
P1(10)
No dredging and/or reclamation activity shall
be carried out in the CRZ area categorized as
CRZ I (i) and it shall have to be ensured that
the mangrove habitats and other ecologically
important and significant areas are not
affected due to any of the project activities.
No dredging/reclamation have been done in
CRZ I (i) .
There is no notified ecologically important
and significant area present in the project
vicinity.
P2(6),
P1(11)
No effluent or sewage shall be discharged into
the sea / creek or in the CRZ area and shall be
treated to conform to the norms prescribed
by the Gujarat Pollution Control Board and
would be reused / recycled within the plant
premises to the extract possible.
Complied. No effluent is being discharged
into the sea/creek. Domestic effluent is being
treated in STPs. The treated water confirming
to the norms is being used for horticulture
purpose.
P2(7),
P1(12)
All the recommendations and suggestions
given by the NIO in the Comprehensive
Environment Impact Assessment report for
conservation / protection and betterment of
environment shall be implemented strictly by
the APPL.
All the recommendations and suggestions
given by NIO are being complied.
P2(8),
P1(13)
The construction and operational activities
shall be carried out in such a way that there is
no negative impact on mangroves and other
coastal/marine habitat. The construction
activities shall be carried out only under the
constant supervision of the NIO.
Complied. Construction of the project was
completed on February 2011.
P2(9),
P1(14)
The APPL shall strictly ensure that no creeks
are blocked due to any activity at port and the
mangroves habitat are neither disturbed nor
destroyed due to any activity.
Complied. No creeks are blocked due to port
activity.
P2(10),
P1(15)
The APPL shall participate financially for any
common facility that may be established or
any common study that may be carried out
for the Gulf of Khambhat region for
environmental protection and/or
management purpose.
Noted. APPPL is committed for the
environment protection.
P2(11),
P1(16)
The construction debris and/or any other type
of waste shall not be disposed into the sea,
creek or in the CRZ areas. The debris shall be
removed from the construction site
immediately after the construction is over.
Complied. Construction of the project was
completed on February 2011. All the debris
has been removed.
Adani Petronet (Dahej) Port Private Limited
From : Oct,15 To : March,16
Page 11 of 14
Half yearly Compliance report for CRZ Clearance/recommendation for development of Solid Cargo
Port Terminal Phase – I and Phase – II
Sr. no. Conditions Status/Action taken
P2(12),
P1(17)
The construction camps shall be located
outside the CRZ area and the construction
labour shall be provided the necessary
amenities, including sanitation, water supply
and fuel and it shall be ensure that the
environmental conditions are not
deteriorated by the construction labours.
Complied. Construction of the project was
completed on February 2011.
P2(13),
P1(18)
The APPL shall prepare and regularly update
their Local Oil Spill Contingency and Disaster
Management Plan in consonance with the
National Oil Spill and Disaster Contingency
plan and shall submit the same to this
Department after having it vetted through
the India Coast Guard.
Noted and complied
Oil Spill Contingency Plan is submitted to
Coast Guard, Gandhinagar for verification
vide letter dated. 10/10/2012.
P2(14),P
1(19)
The APPL shall bear the cost of the external
agency that may be appointed by this
Department for supervision/monitoring of
proposed activities and the environmental
impacts of the proposed activities.
Noted
P2 (15) The mangrove plantation in 50 ha. of area on
Gujarat cost line shall be carried out by the
applicant in a phased manner in five years
Complied. Mangrove afforestation has been
carried out in an area of 400 ha. Details are
given below.
5. 100 ha near village Dandi,
Dist Surat– 2011
6. 50 ha near village Jakhau,
Dist Kutch – 2011
7. 50 ha near Padri bit,
Dist Bhavnagar – 2011
8. 200 ha near Malpur,
Dist Jambusar – 2013-14
P2 (16) The construction activities in the Forest land
and the Gauchar land shall be carried out as
per the permission accorded by the
concerned Authority for the said purpose
Complied. Construction of the project was
completed on February 2011.
Adani Petronet (Dahej) Port Private Limited
From : Oct,15 To : March,16
Page 12 of 14
Half yearly Compliance report for CRZ Clearance/recommendation for development of Solid Cargo
Port Terminal Phase – I and Phase – II
Sr. no. Conditions Status/Action taken
P1(3) The APPL shall take up massive mangrove
plantation in 200 ha of area in and around the
project site or at an alternative site to be
selected in consultation with this
Department.
Complied. Mangrove afforestation has been
carried out in an area of 400 ha. Details are
given below.
1. 100 ha near village Dandi,
Dist Surat– 2011
2. 50 ha near village Jakhau,
Dist Kutch – 2011
3. 50 ha near Padri bit,
Dist Bhavnagar – 2011
4. 200 ha near Malpur,
Dist Jambusar – 2013-14
P1(4) The approach road and trestle passing
through the forestland shall be constructed
only after obtaining necessary permissions
under the relevant forest laws including the
forest (Conservation) Act. further, no activity
shall be carried out in the forestland or in the
area having natural plantation / forest till all
mandatory clearances under various Forest
Acts including the Forests Conservation Act
obtained.
All the activities on forest land have been
started only after obtaining forest land
clearance.
P1(6) The project proponent shall have to make a
separate application and shall have to obtain
prior clearance under the CRZ Notification for
any activities other than those proposed and
got approved as part of this phase I activities.
Complied. APPPL had obtained
Environmental & CRZ Clearance on Nov 11,
2008 for phase 2.
P1(8) The project proponents shall ensure that the
local people shall be provided with an
alternative access to the sea in case the
existing access to Rock-Bund could not be
made available to them.
Alternative access to the sea is available
adjoining to the project site.
P1(9) The project proponents shall ensure that the
construction period shall be reduced by
proper planning and executing the
construction program in time-bound manner
to avoid any time over-run.
Complied. Construction of the project was
completed in February 2011.
P1(20) The jetty and most of the approach would be
supported on piles allowing adequate flow of
water without significant obstruction.
Complied. The jetty and most of the approach
of 1270 meter is supported on piles allowing
adequate flow of water without significant
obstruction.
General Conditions
P2(17),P
1(21)
The groundwater shall not be tapped by the
APPPL to meet with the water requirements
Complied. No ground water is being tapped
by APPPL and water demand is met through
Adani Petronet (Dahej) Port Private Limited
From : Oct,15 To : March,16
Page 13 of 14
Half yearly Compliance report for CRZ Clearance/recommendation for development of Solid Cargo
Port Terminal Phase – I and Phase – II
Sr. no. Conditions Status/Action taken
in any case. GIDC
P2(18),P
1(22)
The APPL shall take up massive green belt
development activities in consultation with
the Gujarat Institute of Desert Ecology/Forest
Department. A comprehensive plan for this
purpose has to be submitted to the Forests
and Environment Department.
Complied. Green belt is being developed in an
area of 6.0_ha including periphery of the
project boundary.
P2(19),P
1(23)
The APPL shall have to be contributing
financially for taking up the socio-economic
up-liftment activities in this region in
consultation with the Forests and
Environment Department and the District
Collector/District Development Officer.
Complied. The CSR activities are executed at
group level by Adani Foundation. Adani
Foundation is taking care of Social-economic
establishment activities and details of the
same for the period of Oct 2015–March 2016
is attached as Annexure – 3
P2(20),
P1(24)
A separate budget shall be earmarked for
environmental management and socio –
economic activities and details thereof shall
be furnished to this department as well as the
MoEF, GOI. The details with respect to the
expenditure from this budget head shall also
be furnished.
Complied. Separate budget is allocated for
Environmental Management and Socio
Economic activities.
• Key components of environment budget
are environmental Monitoring, STP’s
(Operations and Maintenance), Closed
Conveyor System Maintenance and etc. The
allocation of budget for Environment Cell
for the FY 2015-16 was approx. Rs. 126 lacs.
Details of the environmental budget and
expenditure for the FY 15-16 is enclosed as
Annexure – 2
• For Socio Economic activities funds are
being utilized in Education, Community
Health and Sustainable livelihood
development, Rural Infrastructure
development etc. Details with expenditure
is enclosed as Annexure – 3
P2(21),P
1(25)
A separate environmental management cell
with qualified personnel shall be created for
environmental monitoring and management
during construction and operational phases of
the project.
Complied. APPPL has a well structured
Environment Management Cell, staffed with
qualified manpower for implementation of
the Environment Management Plan.
P2(22),
P1(26)
Environmental Audit report indicating the
changes, if any, with respect to the baseline
environmental quality in the coastal and
marine environment shall be submitted every
year by the APPL to this Department as well
Sea water and sediment is being monitored
through NABL accredited agency. Monitoring
Report for the period Oct’15 to Mar’16 is
enclosed in Annexure 1
Adani Petronet (Dahej) Port Private Limited
From : Oct,15 To : March,16
Page 14 of 14
Half yearly Compliance report for CRZ Clearance/recommendation for development of Solid Cargo
Port Terminal Phase – I and Phase – II
Sr. no. Conditions Status/Action taken
as to the MoEF, GOI.
P2(23),P
1(28)
A six monthly report on compliance of the
condition mentioned in this letter shall have
to be furnished by the APPL on regular basis
to this Department.
Noted and Complied
.
P2(24),
P1(29)
Any other condition that may be stipulated by
this Department from time to time for
environmental protection/management
purpose shall also have to be complied with
by the APPL.
Noted.
P1(27) The APPL shall have to contribute financially
to support the National Green Corps scheme
being implemented in Gujarat by GEER
Foundation, Gandhinagar, in consultation
with Forests and Environment Department.
Complied. A request in this regard for asking
for the terms of Financial Contribution
submitted to the GEER Foundation vide letter
dated 17th April, 2009.
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
1
CONTENTS
Sr. No. Title Page No.
1 AMBIENT AIR QUALITY MONITORING 2
2 SEA WATER & SEA SEDIMENT MONITORING 15
3 PIEZOMETRIC WATER QUALITY ANALYSIS 24
4 STP WATER QUALITY MONITORING 26
5 NOISE MONITORING 27
6 STACK MONITORING 47
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
2
TABLE NO. 1.1 AMBIENT AIR QUALITY MONITORING LOCATIONS
SR.
NO. NAME OF LOCATION
1. NEAR MARINE BUILDING
2. NEAR PMC BUILDING
3. SUB STATION 7B BUILDING
4. GCPTL GATE
5. NEAR SILO POTA CABIN
6. S & S ENTERY GATE
PARAMETERS DETAILS:
PARAMETER UNIT LIMIT# TEST/SAMPLING METHOD
Particulate Matter (PM10) µg/m3 100 IS:5182(Part 23):Gravimetric CPCB -
Method (Vol.I,May-2011)
Particulate Matter (PM2.5) µg/m3 60 Gravimetric- CPCB - Method
(Vol.I,May-2011)
Lead as Pb µg/m3 1.0 CPCB Method
(Vol.I,May-2011)
Benzo (a) Pyrene (BaP)- particulate phase only
ng/m3 1.0 CPCB Method
(Vol.I,May-2011)
Arsenic as As ng/m3 6.0 CPCB Method
(Vol.I,May-2011)
Nickel as Ni ng/m3 20 CPCB Method
(Vol.I,May-2011)
Carbon Monoxide as CO mg/m3 4.0 NDIR Digital Gas Analyzer
Benzene as C6H6 µg/m3 5.0 IS 5182 (Part XI):2006/CPCB Method
Ammonia (NH3) µg/m3 400 CPCB Method
(Vol.I,May-2011)
Sulphur Dioxide (SO2) µg/m3 80 IS:5182(Part 2):
Improved West and Gaeke
Oxides of Nitrogen (NO2) µg/m3 80 IS:5182(Part 6):Modified Jacob &
Hochheiser (Na-Arsenite)
Ozone (O3) µg/m3 180 IS 5182 (PART IX) 1974/CPCB Method
(Vol.I,May-2011)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
3
TABLE NO. 1.2 AMBIENT AIR QUALITY MONITORING RESULTS – NEAR MARINE BUILDING
Date of Sampling
LOCATION 1 : NEAR MARINE BUILDING
PM10 PM2.5 Pb BaP As Ni CO C6H6 NH3 SO2 NOx O3
µg/m3
µg/m3
µg/m3
ng/m3
ng/m3
ng/m3
mg/m3
µg/m3
µg/m3
µg/m3
µg/m3
µg/m3
05/10/2015 80.18 42.65 BDL* BDL* BDL* BDL* 1.29 BDL* 27.47 28.47 27.83 26.78
06/10/2015 95.39 51.43 0.55 BDL* 2.34 10.66 1.02 BDL* 56.78 25.55 42.82 21.61
12/10/2015 85.52 39.72 BDL* BDL* BDL* BDL* 0.73 BDL* 30.83 12.57 39.43 23.2
13/10/2015 92.38 43.49 0.62 BDL* 2.45 10.38 0.94 BDL* 38.46 19.63 44.74 27.68
19/10/2015 79.19 35.69 BDL* BDL* BDL* BDL* 0.89 BDL* 39.68 21.59 36.39 30.37
20/10/2015 94.51 50.59 BDL* BDL* BDL* 10.29 1.13 BDL* 52.5 27.57 32.43 28.74
26/10/2015 89.4 45.58 0.54 BDL* BDL* BDL* 0.81 BDL* 47.62 18.57 38.64 22.65
27/10/2015 91.43 52.68 BDL* BDL* 2.18 10.58 0.65 BDL* 64.41 24.68 40.46 25.64
02/11/2015 81.49 44.74 BDL* BDL* BDL* BDL* 0.84 BDL* 47.92 25.36 36.57 25.57
03/11/2015 74.5 36.38 BDL* BDL* BDL* BDL* 1.19 BDL* 33.58 19.58 32.75 29.42
09/11/2015 91.52 51.43 0.58 BDL* 2.1 10.3 1.09 BDL* 49.15 21.5 42.54 21.47
10/11/2015 88.42 40.56 BDL* BDL* BDL* BDL* 0.68 BDL* 56.78 20.42 38.39 24.6
16/11/2015 94.52 53.33 0.68 BDL* BDL* 10.77 1.33 BDL* 23.2 23.44 40.52 28.62
17/11/2015 82.83 38.47 BDL* BDL* BDL* BDL* 0.77 BDL* 27.17 9.62 35.68 23.32
23/11/2015 90.89 52.68 0.54 BDL* 2.36 10.54 1.17 BDL* 54.64 22.6 29.49 26.46
24/11/2015 84.81 45.99 0.51 BDL* BDL* BDL* 0.86 BDL* 46.4 14.48 34.55 30.63
30/11/2015 95.52 54.36 0.72 BDL* 2.23 11.38 0.97 BDL* 32.36 15.49 39.88 27.43
01/12/2015 91.49 55.61 0.58 BDL* 2.22 10.82 1.01 BDL* 52.5 17.43 36.54 26.68
07/12/2015 79.52 42.65 BDL* BDL* BDL* BDL* 0.76 BDL* 29.7 22.36 31.36 31.91
08/12/2015 85.48 46.41 BDL* BDL* BDL* BDL* 0.62 BDL* 48.3 18.3 33.27 28.47
14/12/2015 72.71 34.7 BDL* BDL* BDL* BDL* 1.12 BDL* 36.6 21.67 28.65 24.24
15/12/2015 95.37 52.49 0.68 BDL* 2.54 10.42 0.89 BDL* 27.3 14.64 34.29 27.66
21/12/2015 88.39 40.56 BDL* BDL* BDL* BDL* 1.08 BDL* 45.9 19.66 39.54 29.68
22/12/2015 93.51 53.52 0.6 BDL* 2.42 11.67 1.25 BDL* 19.5 23.64 35.26 22.54
28/12/2015 81.58 41.39 BDL* BDL* BDL* BDL* 0.72 BDL* 24 20.37 30.57 25.2
29/12/2015 94.2 50.59 0.53 BDL* 2.18 10.51 0.81 BDL* 40.2 15.53 38.69 30.1
04/01/2016 86.3 48.5 BDL* BDL* BDL* BDL* 0.61 BDL* 27.47 22.53 28.65 22.66
05/01/2016 90.78 52.27 0.56 BDL* 2.36 10.48 0.53 BDL* 54.64 29.69 31.58 26.45
11/01/2016 82.5 41.39 BDL* BDL* BDL* BDL* 1.19 BDL* 62.27 19.66 35.69 28.57
12/01/2016 98.69 54.36 0.61 BDL* 2.77 11.28 0.76 BDL* 30.83 15.69 32.8 29.27
18/01/2016 75.69 44.51 BDL* BDL* BDL* BDL* 0.97 BDL* 41.21 23.45 26.73 25.35
19/01/2016 85.42 37.63 BDL* BDL* 2.42 BDL* 0.69 BDL* 68.07 16.46 37.56 30.29
25/01/2016 95.43 51.43 0.68 BDL* 2.64 10.52 0.95 BDL* 52.5 21.4 39.43 20.33
26/01/2016 78.43 43.49 BDL* BDL* BDL* BDL* 1.08 BDL* 21.67 25.6 33.27 27.59
01/02/2016 93.43 56.45 0.58 BDL* 2.18 10.3 1.33 BDL* 36.63 20.4 29.58 21.47
02/02/2016 70.87 39.72 BDL* BDL* BDL* BDL* 1.28 BDL* 40.6 25.7 39.58 27.65
08/02/2016 95.49 54.36 BDL* BDL* BDL* 10.43 1.51 BDL* 53.42 16.47 31.45 23.17
09/02/2016 80.41 37.63 BDL* BDL* 2.09 BDL* 1.1 BDL* 46.4 22.6 42.36 29.32
15/02/2016 76.53 40.73 BDL* BDL* BDL* BDL* 0.74 BDL* 23.81 19.44 32.52 26.63
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
4
16/02/2016 86.82 46.41 0.61 BDL* BDL* BDL* 1.2 BDL* 51.59 23.72 38.39 22.51
22/02/2016 96.38 57.7 0.74 BDL* 2.45 10.57 0.93 BDL* 26.25 13.61 27.71 30.13
23/02/2016 72.07 42.65 BDL* BDL* BDL* BDL* 1.34 BDL* 18.62 21.47 30.15 19.5
29/02/2016 89.39 36.38 0.51 BDL* 2.06 BDL* 0.66 BDL* 48.54 24.34 35.46 24.6
01/03/2016 78.6 40.56 BDL* BDL* BDL* BDL* 1.01 BDL* 38.16 19.43 38.58 25.69
07/03/2016 88.6 46.41 0.63 BDL* BDL* BDL* 1.17 BDL* 46.7 24.5 34.22 22.23
08/03/2016 72.3 38.47 BDL* BDL* BDL* BDL* 0.71 BDL* 20.45 17.42 29.2 29.71
14/03/2016 86.5 41.39 0.54 BDL* 2.38 10.2 0.85 BDL* 54.64 12.65 24.75 26.15
15/03/2016 94.31 53.75 0.76 BDL* 2.84 10.34 0.89 BDL* 39.38 21.75 31.56 30.51
21/03/2016 80.27 35.54 BDL* BDL* BDL* BDL* 1.24 BDL* 32.36 15.76 36.39 21.2
22/03/2016 91.08 50.59 0.52 BDL* 2.46 10.44 1.37 BDL* 44.57 22.45 30.23 23.52
28/03/2016 67.49 32.61 BDL* BDL* BDL* BDL* 1.33 BDL* 15.57 18.59 39.45 24.23
29/03/2016 85.62 36.38 0.61 BDL* 2.36 BDL* 1.08 BDL* 29.61 20.63 27.67 27.56
BDL: Below Detection Limit *: Lead as Pb (µg/m3): 0.5, Benzo (a) Pyrene (BaP)-particulate phase only (ng/m3): 0.5, Ammonia NH3 (µg/m3): 10,
Carbon Monoxide as CO (mg/m3): 0.1, Benzene as C6H6 (µg/m3): 2, Arsenic as As (ng/m3): 2
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
5
TABLE NO. 1.3 AMBIENT AIR QUALITY MONITORING RESULTS – NEAR PMC CANTEEN BUILDING
Date of
Sampling
LOCATION 2 : NEAR PMC CANTEEN BUILDING
PM10 PM2.5 Pb BaP As Ni CO C6H6 NH3 SO2 NOx O3
µg/m3
µg/m3
µg/m3
ng/m3
ng/m3
ng/m3
mg/m3
µg/m3
µg/m3
µg/m3
µg/m3
µg/m3
05/10/2015 67.8 36.52 BDL* BDL* BDL* BDL* 1.16 BDL* 31.79 15.7 41.56 21.42
06/10/2015 77.5 44.16 BDL* BDL* BDL* BDL* 0.69 BDL* 42.28 9.65 26.5 25.65
12/10/2015 96.49 50.53 0.54 BDL* 2.32 11.37 0.36 BDL* 20.68 7.43 21.1 27.64
13/10/2015 74.47 31.42 BDL* BDL* BDL* BDL* 0.79 BDL* 17.28 14.37 32.47 17.45
19/10/2015 82.08 42.46 BDL* BDL* BDL* BDL* 0.6 BDL* 22.53 17.39 27.3 20.39
20/10/2015 62.42 28.45 0.62 BDL* 2.23 BDL* 1.41 BDL* 33.64 16.49 25.43 24.5
26/10/2015 71.39 35.67 BDL* BDL* BDL* BDL* 0.55 BDL* 29.32 28.56 31.49 19.05
27/10/2015 58.6 24.63 BDL* BDL* BDL* BDL* 0.78 BDL* 13.58 11.4 39.41 28.55
02/11/2015 73.41 40.34 BDL* BDL* BDL* BDL* 0.38 BDL* 41.36 18.75 39.89 27.32
03/11/2015 85.41 42.46 0.57 BDL* 2.16 BDL* 0.6 BDL* 19.44 21.6 25.66 16.47
09/11/2015 74.42 36.52 BDL* BDL* BDL* BDL* 0.98 BDL* 36.11 6.62 22.64 18.47
10/11/2015 55.6 24.63 BDL* BDL* BDL* BDL* 0.81 BDL* 12.04 8.31 35.73 26.44
16/11/2015 67.52 30.57 BDL* BDL* BDL* BDL* 1.18 BDL* 29.32 12.34 37.62 17.69
17/11/2015 90.28 52.23 0.56 BDL* 2.42 10.17 0.37 BDL* 17.59 5.43 19.34 21.8
23/11/2015 60.49 34.82 BDL* BDL* BDL* BDL* 1.41 BDL* 28.7 13.74 23.56 24.63
24/11/2015 58.58 39.49 BDL* BDL* BDL* BDL* 0.57 BDL* 25.31 24.69 36.44 19.66
30/11/2015 72.01 26.33 BDL* BDL* BDL* BDL* 0.8 BDL* 15.12 11.54 29.54 22.44
01/12/2015 72.22 40.38 BDL* BDL* BDL* BDL* 0.9 BDL* 30.33 5.72 19.5 23.39
07/12/2015 65.52 36.52 BDL* BDL* BDL* BDL* 0.55 BDL* 35.79 16.7 36.41 27.57
08/12/2015 53.21 23.35 BDL* BDL* BDL* BDL* 0.73 BDL* 10.31 7.51 30.9 21.47
14/12/2015 87.2 41.61 BDL* BDL* 2.39 BDL* 0.66 BDL* 28.51 18.7 21.39 19.67
15/12/2015 70.7 30.57 BDL* BDL* BDL* BDL* 0.74 BDL* 13.04 10.75 25.17 29.47
21/12/2015 57.61 25.48 BDL* BDL* BDL* BDL* 1.29 BDL* 24.57 15.39 20.53 25.29
22/12/2015 64.5 37.37 BDL* BDL* BDL* BDL* 1.11 BDL* 34.58 11.42 32.39 28.69
28/12/2015 88.61 47.56 0.57 BDL* BDL* 10.56 0.34 BDL* 15.47 8.34 16.31 20.22
29/12/2015 56.81 29.72 BDL* BDL* BDL* BDL* 0.52 BDL* 21.53 22.76 31.47 18.42
04/01/2016 93.22 54.35 0.58 BDL* 2.08 10.25 0.31 BDL* 12.65 9.61 15.56 26.7
05/01/2016 56.88 21.23 BDL* BDL* BDL* BDL* 0.68 BDL* 39.5 17.43 29.38 21.59
11/01/2016 75.48 31.42 BDL* BDL* BDL* BDL* 0.8 BDL* 30.55 6.71 21.5 18.05
12/01/2016 61.51 35.67 BDL* BDL* BDL* BDL* 0.64 BDL* 19.44 11.35 24.63 20.43
18/01/2016 92.89 55.62 0.54 BDL* 2.46 10.33 0.57 BDL* 32.41 20.57 20.75 28.93
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
6
19/01/2016 59.21 28.45 BDL* BDL* BDL* BDL* 0.46 BDL* 24.69 24.51 30.67 24.39
25/01/2016 65.4 23.78 BDL* BDL* BDL* BDL* 1.26 BDL* 46.6 16.45 19.27 22.47
26/01/2016 70.37 36.52 BDL* BDL* BDL* BDL* 0.98 BDL* 38.27 12.53 28.62 19.18
01/02/2016 83.52 45.43 BDL* BDL* BDL* BDL* 0.48 BDL* 40.74 18.71 35.26 30.14
02/02/2016 66.71 28.02 BDL* BDL* BDL* BDL* 0.7 BDL* 28.7 17.31 20.44 18.53
08/02/2016 78.62 42.46 BDL* BDL* BDL* BDL* 1.02 BDL* 23.46 6.59 18.61 21.49
09/02/2016 54.21 21.66 BDL* BDL* BDL* BDL* 0.6 BDL* 18.52 10.74 28.55 25.16
15/02/2016 84.91 52.65 0.52 BDL* BDL* BDL* 0.38 BDL* 10.8 8.41 15.53 23.33
16/02/2016 58.58 26.75 BDL* BDL* BDL* BDL* 1.4 BDL* 41.05 19.44 22.5 28.55
22/02/2016 79.53 41.61 BDL* BDL* BDL* BDL* 0.79 BDL* 16.36 5.43 32.45 26.41
23/02/2016 67.51 36.52 BDL* BDL* BDL* BDL* 1.21 BDL* 33.64 12.64 24.89 24.68
29/02/2016 55.58 22.5 BDL* BDL* BDL* BDL* 0.84 BDL* 26.23 14.6 21.58 27.71
01/03/2016 51.8 27.6 BDL* BDL* BDL* BDL* 0.54 BDL* 14.51 10.69 25.57 20.3
07/03/2016 65.41 30.57 BDL* BDL* BDL* BDL* 1.28 BDL* 31.48 18.68 22.37 24.15
08/03/2016 82.43 47.56 0.54 BDL* BDL* BDL* 0.34 BDL* 10.49 7.43 39.55 18.47
14/03/2016 70.31 28.45 BDL* BDL* BDL* BDL* 0.74 BDL* 46.6 5.72 30.45 21.53
15/03/2016 53.59 21.66 BDL* BDL* BDL* BDL* 0.81 BDL* 21.6 13.44 34.53 27.56
21/03/2016 67.43 29.72 BDL* BDL* BDL* BDL* 0.69 BDL* 48.45 23.78 19.61 25.68
22/03/2016 75.38 46.71 BDL* BDL* BDL* BDL* 0.94 BDL* 33.33 6.52 24.57 22.71
28/03/2016 83.6 41.61 BDL* BDL* BDL* BDL* 1.16 BDL* 27.47 11.55 29.61 26.35
29/03/2016 58.61 25.48 BDL* BDL* BDL* BDL* 0.53 BDL* 32.71 17.58 32.45 19.2
BDL: Below Detection Limit *: Lead as Pb (µg/m3): 0.5, Benzo (a) Pyrene (BaP)-particulate phase only (ng/m3): 0.5, Ammonia NH3 (µg/m3): 10, Carbon Monoxide as CO (mg/m3): 0.1, Benzene as C6H6 (µg/m3): 2, Arsenic as As (ng/m3): 2
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
7
TABLE NO. 1.4 AMBIENT AIR QUALITY MONITORING RESULTS - SUB STATION 7B BUILDING
Date of
Sampling
LOCATION 3 : SUB STATION 7B BUILDING
PM10 PM2.5 Pb BaP As Ni CO C6H6 NH3 SO2 NOx O3
µg/m3
µg/m3
µg/m3
ng/m3
ng/m3
ng/m3
mg/m3
µg/m3
µg/m3
µg/m3
µg/m3
µg/m3
05/10/2015 94.59 51.37 0.56 BDL* BDL* 11.11 0.54 BDL* 18.33 23.47 22.31 23.22
06/10/2015 83.47 47.25 BDL* BDL* BDL* BDL* 0.93 BDL* 27.96 29.67 37.7 30.43
12/10/2015 61.48 28.61 BDL* BDL* BDL* 10.5 0.92 BDL* 23.92 20.37 34.73 20.28
13/10/2015 82.38 37.6 BDL* BDL* BDL* BDL* 0.42 BDL* 43.81 12.67 36.46 26.05
19/10/2015 91.52 48.46 0.61 BDL* 2.16 10.35 0.53 BDL* 13.36 24.44 33.12 25.53
20/10/2015 88.42 45.38 BDL* BDL* BDL* BDL* 0.47 BDL* 42.57 22.73 21.46 27.22
26/10/2015 95.52 54.18 0.64 BDL* 2.49 BDL* 1.12 BDL* 38.53 25.47 44.51 29.08
27/10/2015 78.5 40.31 BDL* BDL* BDL* BDL* 0.58 BDL* 29.52 15.49 23.69 21.74
02/11/2015 51.51 36.39 BDL* BDL* BDL* BDL* 0.52 BDL* 29.52 15.68 23.83 21.63
03/11/2015 69.48 32.51 0.52 BDL* BDL* BDL* 0.54 BDL* 11.19 17.72 28.41 24.47
09/11/2015 79.42 41.18 BDL* BDL* BDL* BDL* 0.87 BDL* 23.61 25.34 35.06 27.62
10/11/2015 80.41 33.42 BDL* BDL* BDL* BDL* 0.58 BDL* 25.17 18.44 22.57 22.61
16/11/2015 90.26 50.55 0.62 BDL* BDL* 10.3 0.53 BDL* 15.85 20.56 20.97 25.48
17/11/2015 54.62 24.4 BDL* BDL* BDL* BDL* 0.92 BDL* 19.89 16.42 32.45 26.59
23/11/2015 82.41 48.11 0.62 BDL* BDL* BDL* 0.48 BDL* 35.11 19.65 21.54 29.71
24/11/2015 89.79 55.05 0.54 BDL* BDL* BDL* 1.13 BDL* 32.62 21.41 41.47 23.63
30/11/2015 78.6 35.96 BDL* BDL* BDL* BDL* 0.42 BDL* 37.29 9.61 33.43 20.6
01/12/2015 78.6 45.38 BDL* BDL* BDL* BDL* 0.8 BDL* 19.24 22.67 30.54 28.54
07/12/2015 52.38 27.74 BDL* BDL* BDL* BDL* 0.46 BDL* 25.65 12.65 20.45 25.87
08/12/2015 76.62 42.48 BDL* BDL* BDL* BDL* 0.53 BDL* 40.31 10.44 36.54 24.4
14/12/2015 68.4 28.41 BDL* BDL* BDL* BDL* 0.49 BDL* 10.38 16.59 23.82 30.54
15/12/2015 89.42 41.36 BDL* BDL* BDL* BDL* 0.38 BDL* 30.54 8.39 28.28 23.55
21/12/2015 79.6 37.67 BDL* BDL* BDL* BDL* 0.5 BDL* 29.62 17.65 38.46 27.85
22/12/2015 87.75 46.38 BDL* BDL* BDL* BDL* 0.47 BDL* 13.74 13.54 17.73 18.54
28/12/2015 70.52 38.58 BDL* BDL* BDL* BDL* 0.82 BDL* 17.41 15.61 29.5 22.71
29/12/2015 88.43 48.38 BDL* BDL* BDL* BDL* 1 BDL* 26.57 19.42 35.89 20.48
04/01/2016 73.55 43.67 BDL* BDL* BDL* BDL* 0.74 BDL* 19.57 17.75 32.37 19.8
05/01/2016 80.63 33.38 0.51 BDL* BDL* BDL* 0.44 BDL* 44.43 11.44 36.54 27.62
11/01/2016 71.19 37.28 BDL* BDL* BDL* BDL* 0.72 BDL* 15.54 25.68 28.82 23.49
12/01/2016 93.19 45.54 0.54 BDL* 2.2 10.12 0.32 BDL* 34.49 9.59 21.53 24.72
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
8
18/01/2016 70.47 39.69 BDL* BDL* BDL* BDL* 0.38 BDL* 12.43 18.44 31.57 22.9
19/01/2016 94.38 50.52 0.62 BDL* 2.15 10.35 0.88 BDL* 29.52 21.64 35.59 18.62
25/01/2016 83.75 46.38 BDL* BDL* BDL* BDL* 0.45 BDL* 32.94 19.74 30.42 29.46
26/01/2016 54.57 29.48 BDL* BDL* BDL* BDL* 0.4 BDL* 16.47 15.56 17.62 26.15
01/02/2016 68.51 38.53 BDL* BDL* BDL* BDL* 0.39 BDL* 28.59 14.73 19.77 28.44
02/02/2016 56.27 24.71 BDL* BDL* BDL* BDL* 0.47 BDL* 10.56 11.39 26.35 24.23
08/02/2016 65.59 29.48 BDL* BDL* BDL* BDL* 0.88 BDL* 13.67 21.59 23.3 26.51
09/02/2016 86.45 42.62 0.52 BDL* BDL* BDL* 0.98 BDL* 25.17 18.52 30.92 23.5
15/02/2016 61.32 32.59 BDL* BDL* BDL* BDL* 0.87 BDL* 17.4 15.59 27.55 21.26
16/02/2016 77.42 37.67 BDL* BDL* BDL* BDL* 0.56 BDL* 29.52 13.76 28.64 25.63
22/02/2016 85.63 46.38 BDL* BDL* BDL* BDL* 0.4 BDL* 30.45 8.76 18.27 20.7
23/02/2016 50.57 27.74 BDL* BDL* BDL* BDL* 0.49 BDL* 14.6 16.38 15.57 18.27
29/02/2016 73.51 30.4 BDL* BDL* BDL* BDL* 0.54 BDL* 38.53 9.33 31.15 29.31
01/03/2016 84.37 48.38 BDL* BDL* BDL* BDL* 0.88 BDL* 20.51 9.71 29.48 22.8
07/03/2016 76.5 34.68 BDL* BDL* BDL* BDL* 0.52 BDL* 25.79 12.64 25.74 29.61
08/03/2016 58.61 28.61 BDL* BDL* BDL* BDL* 0.78 BDL* 13.67 14.7 37.62 23.42
14/03/2016 81.58 37.6 BDL* BDL* BDL* BDL* 0.38 BDL* 32.31 21.72 16.72 25.37
15/03/2016 70.63 42.62 BDL* BDL* BDL* BDL* 0.5 BDL* 26.72 18.69 23.65 28.7
21/03/2016 54.31 23.55 BDL* BDL* BDL* BDL* 0.95 BDL* 16.16 10.55 26.36 30.71
22/03/2016 63.5 38.58 BDL* BDL* BDL* BDL* 0.72 BDL* 10.25 19.44 21.25 26.74
28/03/2016 92.39 52.45 0.55 BDL* 2.26 10.22 0.9 BDL* 22.68 15.47 24.53 20.64
29/03/2016 66.84 29.54 BDL* BDL* BDL* BDL* 0.37 BDL* 40.39 13.58 18.58 24.1
BDL: Below Detection Limit *: Lead as Pb (µg/m3): 0.5, Benzo (a) Pyrene (BaP)-particulate phase only (ng/m3): 0.5, Ammonia NH3 (µg/m3): 10, Carbon Monoxide as CO (mg/m3): 0.1, Benzene as C6H6 (µg/m3): 2, Arsenic as As (ng/m3): 2
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
9
TABLE NO. 1.5 AMBIENT AIR QUALITY MONITORING - GCPTL GATE
Date of
Sampling
LOCATION 4 : GCPTL Gate
PM10 PM2.5 Pb BaP As Ni CO C6H6 NH3 SO2 NOx O3
µg/m3
µg/m3
µg/m3
ng/m3
ng/m3
ng/m3
mg/m3
µg/m3
µg/m3
µg/m3
µg/m3
µg/m3
05/10/2015 65.38 36.44 BDL* BDL* BDL* BDL* 0.95 BDL* 10.84 13.73 37.04 20.6
06/10/2015 90.42 54.68 BDL* BDL* 2.14 10.31 0.56 BDL* 33.76 22.4 21.21 19.39
12/10/2015 78.5 35.6 BDL* BDL* BDL* BDL* 0.39 BDL* 16.42 23.64 27.86 22.47
13/10/2015 56.51 22.2 BDL* BDL* BDL* BDL* 0.66 BDL* 25.09 7.44 28.57 24.56
19/10/2015 73.37 38.53 BDL* BDL* BDL* BDL* 0.44 BDL* 18.9 15.73 39.65 28.45
20/10/2015 58.42 29.32 BDL* BDL* BDL* BDL* 1.03 BDL* 29.43 9.61 35.54 22.42
26/10/2015 64.54 29.86 BDL* BDL* BDL* BDL* 0.45 BDL* 24.47 12.48 25.64 26.42
27/10/2015 97.89 55.29 0.54 BDL* BDL* 10.96 0.7 BDL* 40.58 18.74 35.77 23.32
02/11/2015 67.12 31.41 BDL* BDL* BDL* BDL* 0.76 BDL* 25.09 10.5 19.3 18.76
03/11/2015 78.53 28.6 BDL* BDL* BDL* BDL* 0.44 BDL* 15.8 12.51 36.55 22.5
09/11/2015 85.82 48.59 BDL* BDL* 2.02 BDL* 0.78 BDL* 28.19 18.42 19.53 24.59
10/11/2015 95.52 38.53 0.58 BDL* 2.36 10.21 0.7 BDL* 33.15 15.54 31.52 19.49
16/11/2015 61.74 37.7 BDL* BDL* BDL* BDL* 0.96 BDL* 46.47 10.49 34.52 30.52
17/11/2015 70.59 32.67 BDL* BDL* BDL* BDL* 0.46 BDL* 38.41 19.48 25.64 28.62
23/11/2015 55.77 28.6 BDL* BDL* BDL* BDL* 1.05 BDL* 25.09 6.59 32.79 22.23
24/11/2015 63.39 36.44 BDL* BDL* BDL* BDL* 0.45 BDL* 20.44 9.55 24.56 20.71
30/11/2015 53.59 22.62 BDL* BDL* BDL* BDL* 0.65 BDL* 29.74 13.52 26.94 18.69
01/12/2015 83.43 51.52 BDL* BDL* 2.24 BDL* 0.69 BDL* 23.44 15.71 16.71 18.61
07/12/2015 60.32 31.55 BDL* BDL* BDL* BDL* 0.65 BDL* 20.4 8.42 25.48 29.29
08/12/2015 96.43 55.29 0.68 BDL* 2.24 10.47 0.64 BDL* 27.7 6.73 26.78 26.32
14/12/2015 77.33 36.44 BDL* BDL* BDL* BDL* 0.39 BDL* 19.48 10.68 31.13 22.67
15/12/2015 68.41 33.51 BDL* BDL* BDL* BDL* 0.6 BDL* 23.44 12.67 22.32 21.53
21/12/2015 52.41 19.27 BDL* BDL* BDL* BDL* 0.95 BDL* 19.48 5.73 28.04 19.52
22/12/2015 76.51 41.64 BDL* BDL* BDL* BDL* 0.84 BDL* 39.58 7.45 21.25 24.2
28/12/2015 58.41 28.48 BDL* BDL* BDL* BDL* 0.41 BDL* 30.44 17.57 26.78 29.1
29/12/2015 65.72 30.58 BDL* BDL* BDL* BDL* 0.4 BDL* 16.74 12.8 21.17 27.13
04/01/2016 59.32 34.35 BDL* BDL* BDL* BDL* 0.36 BDL* 34.07 20.43 25.52 21.57
05/01/2016 72.47 29.44 BDL* BDL* BDL* BDL* 0.54 BDL* 29.43 7.47 21.58 18.15
11/01/2016 52.54 20.52 BDL* BDL* 2.49 BDL* 0.58 BDL* 25.4 17.48 16.37 25.88
12/01/2016 69.18 28.48 BDL* BDL* BDL* BDL* 0.5 BDL* 13.63 22.67 29.53 22.76
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
10
18/01/2016 81.54 32.25 BDL* BDL* BDL* BDL* 0.29 BDL* 26.33 12.7 37.54 19.29
19/01/2016 63.51 22.62 BDL* BDL* BDL* BDL* 0.33 BDL* 18.28 14.48 19.8 26.09
25/01/2016 54.51 30.7 BDL* BDL* BDL* BDL* 1.09 BDL* 21.68 6.68 26.67 24.51
26/01/2016 84.54 49.42 BDL* BDL* BDL* BDL* 0.7 BDL* 43.68 8.75 35.71 20.57
1/02/2016 62.27 33.51 BDL* BDL* BDL* BDL* 0.55 BDL* 23.23 9.68 24.32 23.42
2/02/2016 74.51 31.13 BDL* BDL* BDL* BDL* 0.36 BDL* 45.54 14.46 32.57 21.57
8/02/2016 60.38 35.18 BDL* BDL* BDL* BDL* 0.72 BDL* 19.21 19.37 35.52 22.5
9/02/2016 59.15 24.71 BDL* BDL* BDL* BDL* 0.41 BDL* 15.18 12.67 17.76 20.64
15/02/2016 67.52 37.28 BDL* BDL* BDL* BDL* 0.42 BDL* 30.67 17.69 21.17 18.57
16/02/2016 51.67 22.62 BDL* BDL* BDL* BDL* 1.35 BDL* 18.59 5.41 31.48 26.82
22/02/2016 72.63 32.39 BDL* BDL* BDL* BDL* 0.63 BDL* 12.08 20.44 25.4 24.43
23/02/2016 61.84 30.58 BDL* BDL* BDL* BDL* 0.82 BDL* 38.72 7.54 19.54 27.69
29/02/2016 80.62 46.49 BDL* BDL* BDL* BDL* 0.65 BDL* 21.37 6.6 15.7 19.59
1/03/2016 58.73 30.58 BDL* BDL* BDL* BDL* 0.36 BDL* 26.33 7.44 16.55 18.3
7/03/2016 71.72 25.66 BDL* BDL* BDL* BDL* 0.98 BDL* 14.56 9.74 29.29 26.31
8/03/2016 63.71 32.25 BDL* BDL* BDL* BDL* 0.39 BDL* 29.43 12.66 19.68 21.87
14/03/2016 76.51 29.74 BDL* BDL* BDL* BDL* 0.55 BDL* 38.72 18.36 23.25 20.6
15/03/2016 65.69 34.35 BDL* BDL* BDL* BDL* 0.57 BDL* 17.35 5.41 28.4 25.88
21/03/2016 74.6 38.53 BDL* BDL* BDL* BDL* 0.44 BDL* 37.48 13.34 38.67 23.25
22/03/2016 59.41 31.55 BDL* BDL* BDL* BDL* 0.65 BDL* 15.18 17.37 34.61 19.61
28/03/2016 61.37 26.39 BDL* BDL* BDL* BDL* 0.76 BDL* 30.36 6.6 32.46 22.53
29/03/2016 72.62 33.51 BDL* BDL* BDL* BDL* 0.48 BDL* 20.75 8.73 22.69 29.32
BDL: Below Detection Limit *: Lead as Pb (µg/m3): 0.5, Benzo (a) Pyrene (BaP)-particulate phase only (ng/m3): 0.5, Ammonia NH3 (µg/m3):
10, Carbon Monoxide as CO (mg/m3): 0.1, Benzene as C6H6 (µg/m3): 2, Arsenic as As (ng/m3): 2
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
11
TABLE NO. 1.6 AMBIENT AIR QUALITY MONITORING RESULTS - NEAR SILO POTA CABIN
Date of
Sampling
LOCATION 5 : NEAR SILO POTA CABIN
PM10 PM2.5 Pb BaP As Ni CO C6H6 NH3 SO2 NOx O3
µg/m3
µg/m3
µg/m3
ng/m3
ng/m3
ng/m3
mg/m3
µg/m3
µg/m3
µg/m3
µg/m3
µg/m3
05/10/2015 91.39 48.53 0.52 BDL* 2.06 10.32 0.62 BDL* 15.11 9.54 30.18 22.48
06/10/2015 70.29 40.44 BDL* BDL* BDL* BDL* 0.34 BDL* 17.58 12.35 35.17 25.8
12/10/2015 80.23 44.7 BDL* BDL* BDL* BDL* 0.49 BDL* 13.26 14.55 21.2 18.4
13/10/2015 68.42 28.52 BDL* BDL* BDL* BDL* 0.4 BDL* 19.74 10.01 25.53 20.41
19/10/2015 54.47 21.71 BDL* BDL* BDL* BDL* 0.33 BDL* 26.22 13.53 20.44 17.58
20/10/2015 69.51 31.5 BDL* BDL* BDL* BDL* 0.96 BDL* 38.25 20.69 22.5 27.72
26/10/2015 77.22 41.72 BDL* BDL* BDL* BDL* 0.25 BDL* 20.36 16.48 19.3 24.41
27/10/2015 64.98 35.33 BDL* BDL* BDL* BDL* 0.41 BDL* 18.51 8.65 16.56 21.48
02/11/2015 58.79 23.41 BDL* BDL* BDL* BDL* 0.89 BDL* 20.05 12.38 26.4 23.47
03/11/2015 62.41 27.67 BDL* BDL* BDL* BDL* 0.32 BDL* 21.9 10.37 18.53 19.24
09/11/2015 54.53 20.43 BDL* BDL* BDL* BDL* 0.33 BDL* 14.81 9.58 31.85 22.48
10/11/2015 63.38 28.52 BDL* BDL* BDL* BDL* 0.41 BDL* 15.11 14.57 24.45 17.47
16/11/2015 72.42 45.55 0.56 BDL* BDL* BDL* 0.62 BDL* 12.65 6.64 29.34 20.68
17/11/2015 57.5 21.71 BDL* BDL* BDL* BDL* 0.49 BDL* 10.8 11.76 19.56 18.44
23/11/2015 66.22 31.5 BDL* BDL* BDL* BDL* 0.94 BDL* 30.54 16.72 39.47 27.57
24/11/2015 73.48 29.37 BDL* BDL* BDL* BDL* 0.25 BDL* 16.35 13.72 17.52 25.54
30/11/2015 65.29 30.65 BDL* BDL* BDL* BDL* 0.4 BDL* 42.57 7.5 23.38 28.61
01/12/2015 52.62 30.65 BDL* BDL* BDL* BDL* 0.3 BDL* 11.52 8.74 26.13 20.2
07/12/2015 71.62 38.74 BDL* BDL* BDL* BDL* 0.79 BDL* 16.37 10.45 29.37 19.79
08/12/2015 61.9 34.48 BDL* BDL* BDL* BDL* 0.37 BDL* 19.7 12.54 18.46 22.72
14/12/2015 54.58 23.41 BDL* BDL* BDL* BDL* 0.27 BDL* 15.46 9.67 35.52 27.28
15/12/2015 60.52 27.67 BDL* BDL* BDL* BDL* 0.7 BDL* 33.65 6.65 19.15 18.41
21/12/2015 70.52 32.35 BDL* BDL* BDL* BDL* 0.85 BDL* 44.56 14.55 24.29 21.14
22/12/2015 68.42 25.54 BDL* BDL* BDL* BDL* 0.56 BDL* 10.31 5.4 28.61 25.48
28/12/2015 51.47 18.3 BDL* BDL* BDL* BDL* 0.44 BDL* 22.74 13.45 21.54 30.28
29/12/2015 72.03 39.59 BDL* BDL* BDL* BDL* 0.22 BDL* 13.34 17.67 25.42 29.35
04/01/2016 52.68 28.52 BDL* BDL* BDL* BDL* 0.41 BDL* 24.68 14.65 21.54 17.51
05/01/2016 63.1 30.65 BDL* BDL* BDL* BDL* 0.3 BDL* 21.59 21.74 17.21 23.47
11/01/2016 58.59 26.39 BDL* BDL* BDL* BDL* 0.25 BDL* 12.65 9.51 25.64 19.94
12/01/2016 74.48 32.35 BDL* BDL* BDL* BDL* 0.6 BDL* 37.02 7.53 18.58 18.97
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
12
18/01/2016 56.9 29.37 BDL* BDL* BDL* BDL* 0.23 BDL* 18.51 10.42 34.76 29.63
19/01/2016 68.47 34.48 BDL* BDL* BDL* BDL* 0.18 BDL* 15.42 20.53 24.16 21.41
25/01/2016 73.58 38.31 BDL* BDL* BDL* BDL* 0.73 BDL* 40.41 12.65 20.41 28.59
26/01/2016 61.49 31.5 BDL* BDL* BDL* BDL* 0.47 BDL* 11.72 6.59 27.81 25.62
01/02/2016 72.51 41.72 BDL* BDL* BDL* BDL* 0.66 BDL* 19.43 11.51 32.52 20.68
02/02/2016 61.52 25.12 BDL* BDL* BDL* BDL* 0.27 BDL* 15.73 8.74 29.21 25.71
08/02/2016 54.77 31.5 BDL* BDL* BDL* BDL* 0.3 BDL* 10.49 10.36 21.62 30.27
09/02/2016 65.42 27.67 BDL* BDL* BDL* BDL* 0.22 BDL* 12.34 15.68 24.53 18.9
15/02/2016 58.72 19.58 BDL* BDL* BDL* BDL* 0.5 BDL* 20.98 12.61 18.26 28.2
16/02/2016 66.58 32.35 BDL* BDL* BDL* BDL* 0.89 BDL* 34.24 9.76 35.37 19.5
22/02/2016 56.47 29.37 BDL* BDL* 2.16 BDL* 0.71 BDL* 22.52 6.58 15.67 29.59
23/02/2016 78.58 23.41 BDL* BDL* BDL* BDL* 0.57 BDL* 11.41 14.55 23.78 22.66
29/02/2016 64.61 26.39 BDL* BDL* BDL* BDL* 0.37 BDL* 16.35 16.81 38.7 26.32
01/03/2016 69.52 24.69 BDL* BDL* BDL* BDL* 0.21 BDL* 10.49 15.5 22.61 28.22
07/03/2016 56.31 21.71 BDL* BDL* BDL* BDL* 0.82 BDL* 27.76 7.47 19.55 19.52
08/03/2016 77.73 44.7 BDL* BDL* BDL* BDL* 0.49 BDL* 17.27 19.58 26.17 24.42
14/03/2016 57.32 25.54 BDL* BDL* 2.16 BDL* 0.7 BDL* 22.52 14.66 20.31 30.41
15/03/2016 76.8 38.74 BDL* BDL* BDL* BDL* 0.33 BDL* 13.57 16.68 38.33 22.28
21/03/2016 61.28 22.56 BDL* BDL* BDL* BDL* 0.27 BDL* 42.57 8.39 23.26 20.23
22/03/2016 70.29 41.72 BDL* BDL* BDL* BDL* 0.47 BDL* 28.38 10.68 18.67 25.3
28/03/2016 88.71 45.55 BDL* BDL* BDL* BDL* 0.66 BDL* 12.34 13.71 21.67 18.26
29/03/2016 78.52 39.59 BDL* BDL* BDL* BDL* 0.6 BDL* 16.35 9.71 28.24 21.14
BDL: Below Detection Limit *: Lead as Pb (µg/m3): 0.5, Benzo (a) Pyrene (BaP)-particulate phase only (ng/m3): 0.5, Ammonia NH3 (µg/m3): 10, Carbon Monoxide as CO (mg/m3): 0.1, Benzene as C6H6 (µg/m3): 2, Arsenic as As (ng/m3
): 2
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
13
TABLE NO. 1.7 AMBIENT AIR QUALITY MONITORING RESULTS - S & S ENTERY GATE
Date of
Sampling
LOCATION 6 : S & S ENTRY GATE
PM10 PM2.5 Pb BaP As Ni CO C6H6 NH3 SO2 NOx O3
µg/m3
µg/m3
µg/m3
ng/m3
ng/m3
ng/m3
mg/m3
µg/m3
µg/m3
µg/m3
µg/m3
µg/m3
05/10/2015 88.61 45.59 BDL* BDL* BDL* BDL* 0.74 BDL* 43.2 19.62 32.66 18.57
06/10/2015 68.39 36.39 BDL* BDL* BDL* BDL* 0.85 BDL* 37.07 15.3 40.5 27.47
12/10/2015 70.69 32.62 BDL* BDL* BDL* 10.14 1.17 BDL* 38.29 21.58 44.37 25.38
13/10/2015 62.51 39.32 BDL* BDL* BDL* BDL* 0.57 BDL* 32.34 22.63 39.53 30.36
19/10/2015 96.68 54.37 BDL* BDL* 2.44 10.49 1.08 BDL* 42.68 28.58 43.51 24.45
20/10/2015 79.57 38.48 BDL* BDL* BDL* BDL* 0.77 BDL* 18.38 12.32 38.46 29.66
26/10/2015 90.57 50.61 0.58 BDL* 2.34 10.17 0.63 BDL* 41.66 20.61 34.81 20.58
27/10/2015 84.3 46.43 BDL* BDL* BDL* BDL* 1.0 BDL* 46.26 27.42 31.86 26.42
02/11/2015 88.39 48.52 BDL* BDL* BDL* BDL* 1.01 BDL* 52.39 20.63 33.55 29.44
03/11/2015 92.32 54.37 0.63 BDL* 2.34 10.7 1.08 BDL* 38.6 24.63 40.56 27.62
09/11/2015 65.88 37.22 BDL* BDL* BDL* BDL* 0.82 BDL* 30.63 12.56 38.52 25.48
10/11/2015 90.4 46.43 0.52 BDL* 2.48 10.48 1.0 BDL* 45.59 23.5 29.32 28.79
16/11/2015 85.4 41.41 BDL* BDL* BDL* BDL* 0.71 BDL* 35.89 15.37 26.54 22.89
17/11/2015 63.41 26.35 BDL* BDL* BDL* BDL* 1.15 BDL* 32.47 21.37 42.59 30.2
23/11/2015 76.72 40.57 BDL* BDL* BDL* BDL* 0.74 BDL* 48.4 9.68 37.5 21.76
24/11/2015 94.53 52.7 0.68 BDL* 2.24 11.54 0.61 BDL* 37.37 16.53 31.57 26.61
30/11/2015 86.41 47.68 0.62 BDL* BDL* 10.4 0.55 BDL* 27.26 18.61 36.94 24.49
01/12/2015 64.51 37.64 BDL* BDL* BDL* BDL* 0.78 BDL* 24.69 13.67 33.46 31.48
07/12/2015 85.91 46.43 BDL* BDL* 2.16 BDL* 0.96 BDL* 46.36 17.37 42.57 23.44
08/12/2015 90.57 55.63 0.66 BDL* 2.26 10.25 0.88 BDL* 35.83 20.46 38.39 29.53
14/12/2015 83.58 45.59 0.52 BDL* BDL* BDL* 0.94 BDL* 42.58 23.65 40.52 26.62
15/12/2015 76.49 34.72 BDL* BDL* BDL* BDL* 0.48 BDL* 18.75 16.74 31.53 27.71
21/12/2015 94.53 48.52 0.68 BDL* 2.54 10.61 0.68 BDL* 38.54 21.53 34.18 24.33
22/12/2015 80.9 32.62 0.52 BDL* BDL* BDL* 0.63 BDL* 27.4 18.33 39.46 30.18
28/12/2015 95.51 53.54 BDL* BDL* BDL* BDL* 1.02 BDL* 41.25 11.68 35.71 28.52
29/12/2015 77.49 42.66 BDL* BDL* BDL* BDL* 0.57 BDL* 32.52 14.39 41.54 25.82
04/01/2016 80.53 38.48 BDL* BDL* BDL* BDL* 0.84 BDL* 46.56 12.58 42.57 24.61
05/01/2016 95.98 41.41 0.64 BDL* 2.58 10.61 0.71 BDL* 64.33 26.58 37.32 29.47
11/01/2016 66.12 36.39 BDL* BDL* 2.18 BDL* 0.96 BDL* 54.53 14.53 31.31 21.57
12/01/2016 79.5 40.57 BDL* BDL* BDL* BDL* 1.05 BDL* 42.68 20.69 35.49 26.61
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
14
18/01/2016 86.69 51.45 BDL* BDL* BDL* BDL* 0.77 BDL* 48.18 25.65 40.43 30.32
19/01/2016 75.52 42.66 BDL* BDL* BDL* BDL* 0.52 BDL* 36.15 15.36 43.47 23.43
25/01/2016 88.49 47.68 0.6 BDL* BDL* BDL* 1.42 BDL* 26.65 24.71 33.24 25.37
26/01/2016 92.42 52.7 0.54 BDL* 2.54 10.2 1.28 BDL* 30.33 19.67 39.28 22.62
01/02/2016 87.48 49.35 BDL* BDL* BDL* BDL* 0.87 BDL* 51.77 18.32 41.93 19.66
02/02/2016 92.52 54.37 0.62 BDL* BDL* 10.27 0.94 BDL* 62.49 21.31 35.75 29.23
08/02/2016 85.49 48.94 BDL* BDL* 2.26 BDL* 1.16 BDL* 46.26 14.75 26.18 28.14
09/02/2016 70.81 32.62 BDL* BDL* BDL* BDL* 0.61 BDL* 30.72 20.46 38.64 26.26
15/02/2016 94.52 58.56 0.56 BDL* 2.32 10.71 0.98 BDL* 39.45 10.56 36.38 22.71
16/02/2016 81.68 42.66 BDL* BDL* BDL* BDL* 1.52 BDL* 22.98 24.65 29.24 30.18
22/02/2016 90.57 50.61 BDL* BDL* BDL* 10.27 1.24 BDL* 36.76 16.45 39.55 18.55
23/02/2016 83.88 46.43 BDL* BDL* BDL* BDL* 1.55 BDL* 25.73 19.63 33.54 25.89
29/02/2016 93.51 41.41 0.6 BDL* 2.28 10.46 0.85 BDL* 54.53 22.46 42.61 23.5
01/03/2016 72.68 37.64 BDL* BDL* BDL* BDL* 0.64 BDL* 32.78 17.75 33.73 30.68
07/03/2016 94.63 38.48 0.68 BDL* 2.42 10.41 1.41 BDL* 18.99 21.74 39.5 28.71
08/03/2016 88.49 53.54 0.76 BDL* BDL* BDL* 0.87 BDL* 36.15 8.34 35.15 26.33
14/03/2016 92.32 46.43 0.62 BDL* 2.56 10.14 1.15 BDL* 65.64 16.48 38.18 22.73
15/03/2016 86.69 49.35 0.51 BDL* 2.06 BDL* 0.73 BDL* 43.65 11.43 36.66 24.27
21/03/2016 95.7 43.5 0.6 BDL* BDL* 10.48 0.86 BDL* 54.53 19.76 32.28 29.47
22/03/2016 85.1 55.63 BDL* BDL* 2.16 BDL* 1.07 BDL* 37.68 13.58 26.56 20.48
28/03/2016 76.68 35.55 BDL* BDL* BDL* BDL* 1.45 BDL* 42.28 24.59 34.49 25.9
29/03/2016 90.33 50.61 0.82 BDL* 2.68 10.32 0.93 BDL* 25.43 10.42 37.21 23.65
BDL: Below Detection Limit *: Lead as Pb (µg/m3): 0.5, Benzo (a) Pyrene (BaP)-particulate phase only (ng/m3): 0.5, Ammonia NH3 (µg/m3): 10, Carbon Monoxide as CO (mg/m3):0. 1, Benzene as C6H6 (µg/m3): 2, Arsenic as As (ng/m3): 2
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
15
SEA WATER MONITORING (OCTOBER 2015 TO MARCH 2016)
PARAMETER DETAILS:
SR. NO.
TEST PARAMETERS UNIT TEST/SAMPLING METHOD
1 pH -- IS3025 (P11)83Re.02
2 Temperature oC IS3025(P9)84Re.02
3 Total Suspended Solids mg/L IS3025(P17)84Re.02
4 BOD (3 Days @ 27 oC) mg/L IS 3025 (P44)1993 Re.03Edition2.1
5 Dissolved Oxygen mg/L IS3025(P38)89Re.99
6 Salinity ppt APHA 2550 B
7 Oil & Grease mg/L APHA(22ndEdi)5520D
8 Nitrate as NO3 mg/L IS3025(P34)88
9 Nitrite as NO2 mg/L IS3025(P34)88 NEDA
10 Ammonical Nitrogen as NH3 mg/L IS3025(P34)88Cla.2.3
11 Phosphates as PO4 mg/L APHA(22ndEdi) 4500 C
12 Total Nitrogen mg/L IS3025(P34)88
13 Petroleum Hydrocarbon µg/L PLPL-TPH
14 Total Dissolved Solids mg/L IS3025(P16)84Re.02
15 COD mg/L APHA(22ndEdi) 5520-D Open Reflux
16 Oxidisable Particular Organic Carbon % SOP – PLPL - 06
A Flora and Fauna
17.1 Primary Productivity mgC/L/day APHA (22nd Edi) 10200-J
B Phytoplankton
18.1 Chlorophyll mg/m3 APHA (22nd Edi) 10200-H
18.2 Phaeophytin mg/m3 APHA (22nd Edi) 10200-H
18.3 Cell Count Unit x 103/L APHA (22nd Edi) 10200-H
18.4 Name of Group Number and name of group species of each group
-- APHA (22nd Edi) 10200-H
C Zooplanktons
19.1 Abundance (Population) no/m2 APHA (22nd Edi) 10200-G
19.2 Name of Group Number and name of
group species of each group -- APHA (22nd Edi) 10200-G
19.3 Total Biomass ml/100 m3 APHA (22nd Edi) 10200-G
D Microbiological Parameters
20.1 Total Bacterial Count CFU/ml IS 5402:2002
20.2 Total Coliform /ml APHA(22ndEdi)9221-D
20.3 E.coli /ml IS:1622:1981Edi.2.4(2003-05)
20.4 Enterococcus species /ml IS:15186:2002
20.5 Salmonella species /ml IS:5887(P-3)
20.6 Shigella species /ml IS:1887(P-7)
20.7 Vibrio species /ml IS:5887(P-5)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
16
TABLE 2.1 RESULTS SEA WATER SOUTH SIDES
27/10/2015 23/11/2015 28/12/2015 25/01/2016 16/02/2016 28/03/2016
SR. NO.
TEST PARAMETERS
UNIT RESULT
SURFACE BOTTOM SURFACE BOTTOM SURFACE BOTTOM SURFACE BOTTOM SURFACE BOTTOM SURFACE BOTTOM
1 pH -- 8.22 8.3 7.95 8.03 8.13 8.29 7.92 8.12 7.96 8.02 8.22 8.3
2 Temperature oC 29 30 29 30 29 29 29 30 29 30 29 30
3 Total Suspended Solids
mg/L 410 502 280 320 320 440 360 420 282 340 212 288
4 BOD (3 Days @ 27 oC)
mg/L BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL*
5 Dissolved Oxygen
mg/L 5.6 4.8 5.4 4.8 5.4 4.4 5.2 4.6 5.4 4.8 5.6 4.6
6 Salinity ppt 39.04 39.96 36.5 37.4 38.9 39.8 39.12 40.04 36.4 37.6 38.44 39.82
7 Oil & Grease mg/L BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL*
8 Nitrate as NO3 mg/L 0.352 0.581 0.44 0.62 0.52 0.6 0.47 0.58 0.442 0.64 0.293 0.556
9 Nitrite as NO2 mg/L 0.045 0.024 0.026 0.014 0.044 0.029 0.035 0.019 0.027 0.016 0.031 0.013
10 Ammonical Nitrogen as NH3
mg/L 0.24 0.258 0.6 0.5 0.46 0.58 0.52 0.63 0.592 0.5 0.195 0.204
11 Phosphates as PO4
mg/L 0.56 0.32 0.439 0.512 0.063 0.067 0.34 0.41 0.44 0.513 0.131 0.081
12 Total Nitrogen mg/L 0.637 0.863 1.6 1 1.027 1.217 1.03 1.23 1.061 1.156 0.519 0.773
13 Petroleum Hydrocarbon
µg/L 6 BDL* 0.92 BDL* 3 BDL* BDL* BDL* 0.94 BDL* BDL* BDL*
14 Total Dissolved Solids
mg/L 45920 46570 37335 39020 46830 47360 45050 46890 37660 38930 46190 47480
15 COD mg/L 29 19 24 19 26 20 24 19 28 24 28 19
16 Oxidisable Particular Organic Carbon
% 0.48 0.22 0.6 0.26 0.43 0.37 0.54 0.18 0.62 0.28 0.64 0.32
A Flora and Fauna
17.1 Primary Productivity
mgC/L/day
1.688 0.45 1.57 0.56 2.47 0.788 1.68 0.22 2.7 0.338 2.07 0.405
B Phytoplankton
18.1 Chlorophyll mg/m3
1.709 0.134 2.1 0.45 2.67 0.748 2.51 0.88 3.12 0.881 2.964 0.668
18.2 Phaeophytin mg/m3
0.347 1.754 BDL* 1.21 BDL* 0.71 BDL* 0.57 BDL* 2.17 BDL* 1.39
18.3 Cell Count Unit x 103/L
210 59 225 46 245 52 210 90 249 66 263 53
--
Name of Group Number and name of group species of each group
--
Bacillariophyceae
Bacillariophyceae
Bacillariophyceae
Bacillariophyceae
Bacillariophyceae
Bacillariophyceae
Bacillariophyceae
Bacillariophyceae
Bacillariophyceae
Bacillariophyceae
Bacillariophyceae
Bacillariophyceae
Coscinodiscus sp.
Fragillaria sp.
Amphora sp.
Fragillaria sp.
Asterionella sp.
Fragillaria sp.
Nitzschia sp.
Navicula sp. Nitzschia
sp. Navicula sp. Amphora sp.
Synedra sp.
Navicula sp.
Gyrosigma sp.
Biddulphia sp.
Nitzschia sp.
Gomphonema sp.
Nitzschia sp.
Synedra sp. Fragillaria
sp. Synedra sp.
Fragillaria sp.
Synedra sp. Nitzschia
sp.
Nitzschia sp.
Nitzschia sp.
Asterionella sp.
Synedra sp. Pinnularia
sp. Pinnularia
sp. Navicula sp.
Biddulphia sp.
Navicula sp. Pleurosigma
sp. Navicula sp.
Coscinodiscus sp.
Rhizosolenia sp.
Biddulphia sp.
Cocconeis sp.
Pleurosigma sp.
Thallasionema sp.
Gyrosigma sp.
Fragillaria sp.
Melosira sp. Fragillaria
sp. Pinnularia
sp. Nitzschia sp.
Pinnularia sp.
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
17
Pinnularia sp.
Green Algae Fragillaria
sp. Gomphone
ma sp. Fragillaria
sp. Cyclotella
sp. Coscinodisc
us sp. Nitzschia sp.
Coscinodiscus sp.
Nitzschia sp. Coscinodisc
us sp. Fragillaria
sp.
Cymbella sp.
Ulothrix sp. Rhizosolenia
sp. Cyanophyce
ae
Biddulphia sp.
Cyanophyce
ae
Rhizosolenia sp.
Cyanophyce
ae
Rhizosolenia sp.
Green Algae Cyclotella
sp. Rhizosoleni
a sp. Green
algae Chlorella sp.
Thallasionema sp.
Oscillatoria sp.
Cyanophyce
ae
Microcystis sp.
Gyrosigma sp.
Microcystis sp.
Cymbella sp.
Chlorella sp. Melosira sp. Cyanophyc
eae
Chlorella sp.
Cyanophyce
ae
Cyanophyce
ae Green Algae
Phormidium sp.
Spirulina sp. Asterionella
sp. Anabaena
sp. Thallasione
ma sp. Pandorina
sp. Pleurosigma
sp. Oscillatoria
sp. Pandorina
sp. Oscillatoria
sp. Microcystis
sp. Chlorella sp.
Oscillatoria sp.
Green Algae Cyanophyce
ae --
Cyanophyce
ae --
Thallasionema sp.
Green
Algae
Pediastrum sp.
-- Anabaena
sp. Pandorina
sp. Microcystis
sp. Ankistrodes
mus sp. Oscillatoria
sp. --
Oscillatoria sp.
-- Skeletonem
a sp. Pediastrum
sp. Cyanophyc
eae -- Green Algae -- Green Algae Chlorella sp. Nostoc sp. -- Nostoc sp. --
Tabellaria sp.
Scenedesmus sp.
Oscillatoria sp.
-- Ankistrodes
mus sp. -- Chlorella sp.
Scenedesmus sp.
Green Algae -- Green Algae -- Cyanophyce
ae --
Anabaena sp.
-- Hydrodictyo
n sp. --
Oedogonium sp.
-- Chlorella sp. -- Chlorella sp. -- Microcystis
sp. --
-- -- Pediastrum
sp. --
Pandorina sp.
-- Pandorina
sp. --
Scenedesmus sp.
-- Spirulina sp. --
-- -- Scenedesm
us sp. -- Volvox sp. --
Pediastrum sp.
-- Ulothrix sp. -- Green Algae --
-- -- -- -- -- -- -- -- -- -- Hydrodictyo
n sp. --
-- -- -- -- -- -- -- -- -- -- Pandorina
sp. --
19.1 Abundance (Population)
no/m2
280 120 240 100 160 40 220 40 263 38 240 80
19.2
Name of Group Number and name of group species of each group species of each group
--
Copepods Gastropods Copepods Chaetognat
hes Copepods Crustaceans Copepods Nematodes Mysids Nematodes Copepods
Polychaete
worms
Decapods Ostracods Polychaete
worm Copepods
Polychaete worm
Copepods Isopods Foraminifera
ns Isopods Gastropods Decapods Krill
Crustaceans
Krill Krill Decapods Crustaceans -- Nematodes -- Nematodes -- Polychaete
worms Crustacean
s
Gastropods
Cyclops Crustaceans -- Ostracods -- Polychaete
worms --
Polychaete worms
-- Gastropods --
Ostracods -- Ctenophora -- -- -- -- -- Echinoderm
s -- Snail --
Cyclops -- Ostracods -- -- -- -- -- Hydrozoa -- Nematodes --
19.3 Total Biomass ml/100 m3
95 15 92.5 12 72.58 4.7 80 10 93.6 14.5 113 10.14
D Microbiological Parameters
20.1 Total Bacterial Count
CFU/ml
1910 1760 1420 1060 1280 1020 1420 1280 1400 1100 1960 2060
20.2 Total Coliform /ml Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent
20.3 E.coli /ml Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent
20.4 Enterococcus species
/ml Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent
20.5 Salmonella species
/ml Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent
20.6 Shigella species /ml Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent
20.7 Vibrio species /ml Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
18
TABLE 2.2 RESULTS SEA WATER NORTH SIDE
27/10/2015 23/11/2015 28/12/2015 25/01/2016 16/02/2016 28/03/2016
SR. NO. TEST PARAMETERS UNIT
RESULT SURFACE BOTTOM SURFACE BOTTOM SURFACE BOTTOM SURFACE BOTTOM SURFACE BOTTOM SURFACE BOTTOM
1 pH -- 8.18 8.33 7.96 8.11 8.19 8.33 7.85 8.08 7.98 8.12 8.21 8.32
2 Temperature oC 28 29 29 30 28 29 29 30 29 30 29 30
3 Total Suspended Solids
mg/L 320 430 340 400 240 320 280 330 350 410 258 336
4 BOD (3 Days @ 27 oC)
mg/L BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL*
5 Dissolved Oxygen mg/L 5.6 4.4 5.4 4.4 5.2 4.8 5.4 4.6 5.2 4.6 5 4.4
6 Salinity ppt 36.82 37.44 35.8 37.1 37.26 38.81 37.22 38.36 35.64 37.18 35.86 36.44
7 Oil & Grease mg/L BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL* BDL*
8 Nitrate as NO3 mg/L 0.535 0.734 0.54 0.74 0.477 0.646 0.39 0.61 0.549 0.747 0.061 0.092
9 Nitrite as NO2 mg/L 0.033 0.018 0.03 0.02 0.081 0.055 0.031 0.014 0.034 0.027 0.021 0.017
10 Ammonical Nitrogen as NH3
mg/L 0.388 0.462 0.38 0.48 0.307 0.316 0.44 0.53 0.407 0.481 0.596 0.819
11 Phosphates as PO4 mg/L 0.699 0.518 0.322 0.346 0.766 0.459 0.21 0.24 0.322 0.336 0.086 0.063
12 Total Nitrogen mg/L 0.956 1.214 0.92 1.22 0.865 1.017 0.87 1.16 0.99 1.255 0.67 0.92
13 Petroleum Hydrocarbon
µg/L BDL* BDL* BDL* BDL* 1.4 BDL* BDL* BDL* 0.7 BDL* 1.8 BDL*
14 Total Dissolved Solids
mg/L 42896 43458 36622 38680 44080 45120 43530 44010 36844 37990 43060 43660
15 COD mg/L 24 19 19 14 26 18 19 14 24 14 24 14
16 Ox disable Particular Organic Carbon
% 0.81 0.56 0.46 0.23 0.7 0.32 0.72 0.51 0.46 0.22 0.84 0.48
A Flora and Fauna
17.1 Primary Productivity mgC/L
/day 1.35 0.225 1.35 0.225 2.58 0.563 2.47 0.45 2.13 0.788 1.91 0.338
B Phytoplankton
18.1 Chlorophyll mg/m3 1.682 0.214 1.549 0.107 2.51 0.774 2.48 0.8 2.59 0.828 3.017 0.828
18.2 Phaeophytin mg/m3 0.299 1.599 0.526 1.78 BDL* 0.833 BDL* 0.806 BDL* 1.84 BDL* 1.45
18.3 Cell Count Unit x 103/L
196 67 210 53 244 48 259 58 220 51 252 63
18.4
Name of Group Number and name of group species of each group
--
Bacillarioph
yceae
Bacillarioph
yceae
Bacillarioph
yceae
Bacillarioph
yceae
Bacillarioph
yceae
Bacillarioph
yceae
Bacillarioph
yceae
Bacillarioph
yceae
Bacillarioph
yceae
Bacillarioph
yceae
Bacillarioph
yceae
Bacillarioph
yceae
Biddulphia sp.
Gyrosigma sp.
Biddulphia sp.
Navicula sp. Asterionella
sp. Fragillaria
sp. Nitzschia
sp. Navicula sp.
Fragillaria sp.
Nitzschia sp.
Asterionella sp.
Navicula
sp.
Coscinodiscus sp.
Coscinodiscus sp.
Cocconeis sp.
Nitzschia sp.
Coscinodiscus sp.
Cocconeis sp.
Navicula sp. Fragillaria
sp. Nitzschia
sp. Synedra sp.
Biddulphia sp.
Nitzschia
sp.
Asterionella sp.
Fragillaria sp.
Pinnularia sp.
Fragillaria sp.
Fragillaria sp.
Pleurosigma sp.
Synedra sp. Gyrosigma
sp. Synedra sp.
Pinnularia sp.
Cocconeis sp.
Fragillaria
sp.
Gyrosigma sp.
Cyclotella sp.
Synedra sp. Gomphone
ma sp. Gomphone
ma sp. Synedra sp.
Pleurosigma sp.
Rhizosolenia sp.
Coscinodiscus sp.
Coscinodiscus sp.
Navicula sp. Rhizosoleni
a sp.
Navicula sp. Green algae Rhizosoleni
a sp. Pinnularia
sp. Pleurosigma
sp. Cyanophyce
ae
Cyclotella sp.
Coscinodiscus sp.
Cyclotella sp.
Fragillaria sp.
Nitzschia sp.
Pinnularia
sp.
Nitzschia Chlorella Melosira sp. Cyanophyce Rhizosolenia Anabaena Achnanthes Cyanophyce Thallasiosir Cyanophyce Rhizosoleni Cyanophyc
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
19
sp. sp. ae sp. sp. sp. ae a sp. ae a sp. eae
Green algae Pandorina
sp. Coscinodisc
us sp. Oscillatoria
sp. Thallasiosira
sp. Oscillatoria
sp. Asterionella
sp. Anabaena
sp. Achnanthes
sp. Oscillatoria
sp. Tabellaria
sp. Oscillatoria
sp.
Volvox sp. Hydrodictyo
n sp. Cyanophyce
ae Green Algae
Cyanophyceae
Green Algae Cyanophyce
ae Microcystis
sp. Rhizosoleni
a sp. Microcystis
sp. Cymbella
sp. Microcystis
sp.
Scenedesmus sp.
-- Oscillatoria
sp. Chlorella sp.
Oscillatoria sp.
Oedogonium sp.
Oscillatoria sp.
-- Cyanophyce
ae Green Algae
Cyanophyceae
Green Algae
Hydrodictyon sp.
-- Anabaena
sp. Ulothrix sp. Nostoc sp.
Hydrodictyon sp.
microcystis sp.
-- microcystis
sp. Chlorella
sp. Microcystis
sp. Ankistrodes
mus sp.
Cyanophyceae
-- Microcystis
sp. Scenedesm
us sp. Spirulina sp.
Pandorina sp.
Green Algae -- Oscillatoria
sp. --
Oscillatoria sp.
--
Oscillatoria sp.
-- Green Algae -- Green Algae Ulothrix sp. Chlorella
sp. -- Nostoc sp. -- Green Algae --
Spirulina sp. -- Pediastrum
sp. -- Chlorella sp. --
Pediastrum sp.
-- Green Algae -- Ankistrodes
mus sp. --
-- -- Ulothrix sp. -- Hydrodictyo
n sp. --
Pandorina sp.
-- Pediastrum
sp. --
Chlorella sp.
--
-- -- Pandorina
sp. --
Pediastrum sp.
-- -- -- Pandorina
sp. -- Ulothrix sp. --
-- -- -- -- Volvox sp. -- -- -- Chlorella
sp. -- -- --
C Zooplanktons
19.1 Abundance (Population)
no/m2 260 140 220 80 225 75 260 80 238 63 320 60
19.2
Name of Group Number and name of group species of each group species of each group
--
Copepods Gastropods Ctenophore
s Rotifers
Ctenophore
s Ostracods
Echinoderm
s
Polychaete
worms
Echinoderm
s
Polychaete
worms Copepods Nematodes
Ostracods Krill Decapods Cyclops Decapods Gastropods Decapods Isopods Mysids Nematodes Ostracods Gastropods
Nematodes Crustaceans Ostracods Fish egg Ostracods -- Gastropods -- Gastropods Gastropods Gastropods Crustacean
s
Polychaete Daphnia Gastropods Copepods Gastropods -- Rotifers -- Isopods -- Krill --
Isopods -- Polychaete
worms -- Rotifers -- -- --
Polychaete
worms -- Cyclops --
Chaetognat
hs -- -- -- Crustaceans -- -- -- -- -- Nematodes --
19.3 Total Biomass ml/100
m3 89 11 82.8 9.5 85.24 6.9 79.5 7.4 86.9 18 123 10.96
D Microbiological Parameters
20.1 Total Bacterial Count
CFU/ml 1540 1370 1660 1220 1260 1080 1380 1220 1650 1210 2290 2390
20.2 Total Coliform /ml Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent
20.3 E.coli /ml Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent
20.4 Enterococcus species
/ml Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent
20.5 Salmonella species /ml Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent
20.6 Shigella species /ml Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent
20.7 Vibrio species /ml Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent Absent
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
20
SEDIMENT MONITORING (OCTOBER 2015 TO MARCH 2016)
PARAMETER DETAILS:
SR. NO.
TEST PARAMETERS UNIT TEST/SAMPLING
METHOD
1 Organic Matter % FCO: 2006
2 Phosphorus as P mg/kg APHA(22ndEdi) 4500 C
3 Texture -- --
4 Petroleum Hydrocarbon mg/kg PLPL-TPH
5 Heavy Metals
5.1 Aluminum as Al % AAS APHA 3111 B
5.2 Total Chromium as Cr+3 mg/kg AAS 3111B
5.3 Manganese as Mn mg/kg AAS APHA 3111 B
5.4 Iron as Fe % AAS APHA(22ndEdi)3111 B
5.5 Nickel as Ni mg/kg AAS APHA(22ndEdi)3111 B
5.6 Copper as Cu mg/kg AAS APHA(22ndEdi)3111 B
5.7 Zinc as Zn mg/kg AAS APHA(22ndEdi)3111 B
5.8 Lead as Pb mg/kg AAS APHA(22ndEdi)3111 B
5.9 Mercury as Hg mg/kg AAS APHA- 3112 B
6 Benthic Organisms
6.1 Macrobenthos (No and name of groups present, No and name of species of each group present)
-- APHA (22nd Edi) 10500-C
6.2 MeioBenthos(No and name of groups present, No and name of species of each group present)
-- APHA (22nd Edi) 10500-C
6.3 Population no/m2 APHA (22nd Edi) 10500-C
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
21
TABLE 2.3 RESULTS SEA SEDIMENT SOUTH SIDE
SR. NO.
TEST PARAMETERS UNIT 27/10/2015 23/11/2015 28/12/2015 25/01/2016 16/02/2016 28/03/2016
SEA SEDIMENT SOUTH SIDE
1 Organic Matter % 0.714 0.58 0.69 0.48 0.617 0.72
2 Phosphorus as P mg/kg 178 190 189 211 193 210
3 Texture -- Sandy Silt Sandy Silt Sandy Silt Sandy Silt Sandy Silt Sandy Silt
4 Petroleum Hydrocarbon mg/kg BDL* BDL* BDL* BDL* BDL* BDL*
5 Heavy Metals
5.1 Aluminum as Al % 5.47 5.4 5.41 5.21 5.43 5.23
5.2 Total Chromium as Cr+3 mg/kg 101 116 137 119 117 119
5.3 Manganese as Mn mg/kg 625 660 778 563 657 819
5.4 Iron as Fe % 2.76 2.36 2.4 2.51 2.33 2.89
5.5 Nickel as Ni mg/kg 40.75 44 53.98 46.67 44.4 61.98
5.6 Copper as Cu mg/kg 50.08 36 46.64 38.88 36.56 49.99
5.7 Zinc as Zn mg/kg 139 160 141 148 163 150
5.8 Lead as Pb mg/kg 2.02 1.86 1.9 1.77 1.88 1.74
5.9 Mercury as Hg mg/kg BDL* BDL* BDL* BDL* BDL* BDL*
6 Benthic Organisms
6.1 Macrobenthos (No and name of groups present, No and name of species of each group present)
--
Polychaete worms Polychaete worms Crustaceans Mysids Mysids Polychaete worms
Mysids Isopods Isopods Echinoderms Isopods Bivalves
Isopods Decapods Decapods Decapods Decapods Echinoderms
Crabs -- Mysids -- Polychaete worms Prawns
Decapods -- -- -- -- --
6.2 MeioBenthos (No and name of groups present, No and name of species of each group present)
-- Nematodes Nematodes Nematodes Foraminiferans Nematodes Foraminiferans
Foraminiferans Copepods Copepods -- Ciliates Hydrozoa
6.3 Population no/m2 440 337 481 377 357 692
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
22
TABLE 2.4 RESULTS SEA SEDIMENT NORTH SIDE
SR. NO.
TEST PARAMETERS UNIT 27/10/2015 23/11/2015 28/12/2015 25/01/2016 16/02/2016 28/03/2016
SEA WATER NORTH SIDE
1 Organic Matter % 0.853 0.54 0.745 0.628 0.605 0.835
2 Phosphorus as P mg/kg 170 160 220 179 191 189
3 Texture -- Sandy Silt Sandy Silt Sandy Silt Sandy Silt Sandy Silt Sandy Silt
4 Petroleum Hydrocarbon mg/kg BDL* BDL* BDL* BDL* BDL* BDL*
5 Heavy Metals
5.1 Aluminum as Al % 5.63 5.44 5.35 5.51 5.43 5.65
5.2 Total Chromium as Cr+3 mg/kg 87.96 118 93.98 92.74 117 101
5.3 Manganese as Mn mg/kg 659 666 701 627 665 705
5.4 Iron as Fe % 1.85 1.88 2.13 1.75 2.39 2.87
5.5 Nickel as Ni mg/kg 48.44 38 48.11 50.2 46.79 61.99
5.6 Copper as Cu mg/kg 38.72 52 55.98 42.77 38.21 40.01
5.7 Zinc as Zn mg/kg 147 140 162 163 161 172
5.8 Lead as Pb mg/kg 2.02 1.72 2.07 2.08 2 1.6
5.9 Mercury as Hg mg/kg BDL* BDL* BDL* BDL* BDL* BDL*
6 Benthic Organisms
6.1 Macrobenthos (No and name of groups present, No and name of species of each group present)
--
Decapods Decapods Decapods Polychaete worms Polychaete worms Polychaete worms
Crabs Mysids Anthozoans Mysids Decapods Crabs
Anthozoans Isopods Isopods Isopods Isopods Isopods
Echinoderms Amphipods -- -- Echinoderms Decapods
Copepods -- -- -- -- --
Bryozoans -- -- -- -- --
6.2 MeioBenthos (No and name of groups present, No and name of species of each group present)
-- Foraminiferans Foraminiferans Nematodes Nematodes Foraminiferans
Copepods Copepods Ostracods Foraminiferans Copepods
-- -- Hydrozoa -- -- --
6.3 Population no/m2 377 288 385 440 317 503
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
23
PIEZOMETER WATER QUALITY MONITORING
(OCTOBER 2015 TO MARCH 2016)
PARAMETERS DETAILS:
SR.
NO. TEST PARAMETER UNIT TEST/SAMPLING METHOD
1 Temperature oC IS3025(P9)84Re.02
2 pH -- IS3025(P11)83Re.02
3 Total Dissolved Solids mg/L IS3025(P16)84Re.02
4 Salinity ppt APHA 2520B
5 Chloride as Cl mg/L IS3025(P32)88Re.99
6 Depth of Water Level from Ground Level meter --
7 Status of Tide** -- --
TABLE NO. 4.1 RESULTS OF ANALYSIS OF PIEZOMETER WATER QUALITY MONITORING [OCTOBER 2015 TO
MARCH 2016]
SR.
NO
SAMPLING LOCATION Near Sub Station 7B
TEST PARAMETER UNIT
RESULTS
Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16
27/10/15 23/11/15 07/12/15 25/01/16 29/02/16 28/03/16
1 Temperature oC 29 29 29 29 30 29
2 pH -- 8.45 8.5 8.26 8.39 8.43 8.36
3 Total Dissolved Solids mg/L 1334 1390 1311 1239 1288 1416
4 Salinity ppt 0.397 0.415 0.26 0.187 0.193 0.2
5 Chloride as Cl mg/L 218 229 145 103 106 111
6 Depth of Water Level from Ground Level
meter 2.5 2 2 2 2.2 2
7 Status of Tide** -- High Tide High Tide High Tide Low Tide Low Tide High Tide
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
24
SR.
NO
Sampling Location Near QHSE Office
TEST PARAMETER UNIT
RESULTS
Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16
27/10/15 23/11/15 07/12/15 25/01/16 29/02/16 28/03/16
1 Temperature oC 30 30 30 29 30 29
2 pH -- 8.29 8.15 8.31 8.61 8.42 8.4
3 Total Dissolved Solids mg/L 1881 1801 1619 1438 1510 1490
4 Salinity ppt 1.06 0.948 0.72 0.657 0.682 0.686
5 Chloride as Cl mg/L 589 524 399 363 377 379
6 Depth of Water Level from
Ground Level meter 3 2.5 2.5 2.5 2.3 2.1
7 Status of Tide** -- High Tide High Tide High Tide Low Tide Low Tide High Tide
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
25
STP QUALITY MONITORING
(OCTOBER 2015 TO MARCH 2016)
TEST PARAMETER UNIT TEST/ SAMPLING METHOD
pH -- IS3025(P11)83Re.02
Total Suspended Solids mg/L IS3025(P17)84Re.02
BOD (3 Days @ 27 oC) mg/L IS3025 P44)1993 Re.03Edition2.1
Residual Free Chlorine mg/L APHA(22ndEdi)4500 Cl
TABLE NO.5.1 RESULTS OF STP WATER [October 2015 – March 2016]
TEST PARAMETER UNIT RESULTS
Date of Sampling 27/10/2015 23/11/2015 07/12/2015 25/01/2016 29/02/2016 28/03/2016
Sampling Location STP OUTLET
pH -- 7.09 7.19 7.23 6.96 8.01 7.94
Total Suspended Solids mg/L 20 26 26 26 24 28
BOD (3 Days @ 27 oC) mg/L 12 19 19 14 16 19
Residual Free Chlorine mg/L 0.5 0.5 0.5 0.6 0.8 0.7
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
26
NOISE LEVEL MONITORING
(OCTOBER 2015 TO MARCH 2016) TABLE NO. 6.1 RESULTS OF BEHIND QHSE OFFICE DAY TIME NOISE
Sampling
Location
October-15 November-15 December-15 January-16 February-16 March-16
Behind QHSE Office
Date of Monitoring
1/10/2015 2/11/2015 1/12/2015 1/01/2016 1/02/2016 1/03/2016
6:00-7:00 54.8 57.4 44.8 44.2 45.5 41.8
7:00-8:00 55.6 55.2 45.9 48.6 48.7 43.4
8:00-9:00 57.9 60.8 50.3 50 49.2 48.4
9:00-10:00 60.3 58.3 51.9 55.2 57.7 52.3
10:00-11:00 63.8 62.3 55.8 55.9 56.3 54.8
11:00-12:00 65.9 66 58.3 60 62.5 60.5
12:00-13:00 68.7 69.5 59.4 63.3 60.3 62.3
13:00-14:00 69.3 72.3 61.3 63.6 62.8 64.8
14:00-15:00 70.4 70.8 63.4 65.5 65 66.9
15:00-16:00 69.5 66.5 65.9 66.5 66.2 67.8
16:00-17:00 68.3 69.9 68.9 67.1 66.6 68.9
17:00-18:00 67.7 69.3 69.3 67.2 66.9 69.1
18:00-19:00 66.4 68.3 66.4 62.8 63.5 63.7
19:00-20:00 65.5 62.2 64.8 62.1 59.3 62.1
20:00-21:00 64.9 66.2 63.7 61.6 62.9 60.8
21:00-22:00 62.8 64.7 62.4 59.8 57.7 60
LIMIT :-75 dB(A)
TABLE NO. 6. 2 RESULTS OF BEHIND QHSE OFFICE NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
Behind QHSE Office
Date of
Monitoring
01 &
02/10/2015
02 &
03/11/2015
01 &
02/12/2015
01 &
02/01/2016
01 &
02/02/2016
01 &
02/03/2016
22:00-23:00 62.5 60.6 61.9 56.3 57.2 59.3
23:00-00:00 61.3 62.1 58.3 53.8 53.9 58.4
00:00-01:00 60.8 62.6 56.2 50.2 50.6 56.4
01:00-02:00 58.2 59.4 54.8 52.4 50.3 54.3
02:00-03:00 56.3 56.2 52.7 47.5 46.7 53.2
03:00-04:00 55.9 56.4 49.3 46.8 47.3 50.4
04:00-05:00 54.7 54.8 47.4 43.2 42.6 50
05:00-06:00 53.2 51.6 45.3 42.4 43.8 48.3
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
27
TABLE NO. 6.3 RESULTS OF PMC OFFICE BACK SIDE DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
PMC OFFICE BACK SIDE
Date of Monitoring
2/10/2015 3/11/2015 2/12/2015 2/1/2016 2/2/2016 2/3/2016
6:00-7:00 53.2 52.7 43.2 46.1 48.7 40.9
7:00-8:00 55.7 55.7 44.8 47.8 49 41.8
8:00-9:00 56.9 58.5 48.9 51.4 50.8 47.3
9:00-10:00 59.3 60.3 52.1 57.5 57.8 49.2
10:00-11:00 61.7 61.7 53.8 57.5 55.2 53.1
11:00-12:00 64.9 62.3 59.2 60.5 59.9 59.4
12:00-13:00 67.3 67.3 61.9 62.1 64.6 62.4
13:00-14:00 69.8 68.2 63.4 64.1 66.6 64.8
14:00-15:00 71.5 73.1 64.3 63.7 60.7 67.3
15:00-16:00 70.6 67.6 66.4 67.4 64.7 68.9
16:00-17:00 69.5 67.1 67.4 68.6 66.1 69.3
17:00-18:00 68.4 68.6 68.1 66.8 67.6 68.4
18:00-19:00 66.5 66.2 66 65.8 62.9 66.5
19:00-20:00 65.8 63.8 65.2 62.8 63 65.3
20:00-21:00 64.9 64.1 63.2 63 64.8 62.8
21:00-22:00 62.1 64.1 62.7 59.3 60.7 61.4
LIMIT :-75 dB(A)
TABLE NO. 6. 4 RESULTS OF PMC OFFICE BACK SIDE NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
PMC OFFICE BACK SIDE
Date of
Monitoring
02 &
03/10/2015
03 &
04/11/2015
02 &
03/12/2015
02 &
03/01/2016
02 &
03/02/2016
02 &
03/03/2016
22:00-23:00 61.7 63 61.7 60 63 60.2
23:00-00:00 60.9 60.4 59.2 55.3 53.6 58.3
00:00-01:00 59.3 57.2 57.3 53.1 54.7 57.4
01:00-02:00 58.4 55.3 55.4 53.7 54.4 53.6
02:00-03:00 57.2 54.7 53.9 51.8 53.5 52.7
03:00-04:00 55 54.4 50.1 48.3 45.7 51.8
04:00-05:00 54.6 51.3 48.3 46.8 45.3 50.7
05:00-06:00 52.9 52 45.9 46.1 46.8 47.3
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
28
TABLE NO. 6.5 RESULTS OF SUB STATION - 6 BACK SIDE DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
SUB STATION - 6 BACK SIDE
Date of Monitoring
3/10/2015 4/11/2015 3/12/2015 4/1/2016 3/2/2016 3/3/2016
6:00-7:00 56.3 53.3 44.7 43.3 41.7 41.7
7:00-8:00 57.9 60 45.7 44.4 43.2 42.9
8:00-9:00 59.3 61.6 48.3 49.8 52.6 45.8
9:00-10:00 62.4 61.4 51.4 51.9 53.3 49
10:00-11:00 63.7 65.2 55.2 54 56.3 52.3
11:00-12:00 65.6 64.4 59.1 57.8 57.4 56.9
12:00-13:00 68.5 67.2 62.4 62.7 61.1 58.2
13:00-14:00 69.7 69.5 65.6 62.7 65.1 61.3
14:00-15:00 71.6 69.3 67.9 66.3 68.9 64.3
15:00-16:00 72.8 73.2 68.3 68.7 71 67.4
16:00-17:00 69.5 71.7 69.3 70.9 73.3 69.3
17:00-18:00 68 66.6 67.3 66.8 64 68.6
18:00-19:00 67.3 65.2 65.8 69 70.3 67.3
19:00-20:00 66.4 67.2 64.2 63.8 62.1 66.1
20:00-21:00 64.5 66.4 62.9 64.7 64.5 64.2
21:00-22:00 62 58.5 61.8 62.5 61.2 62.3
LIMIT :-75 dB(A)
TABLE NO. 6.6 RESULTS OF SUB STATION - 6 BACK SIDE NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
SUB STATION - 6 BACK SIDE
Date of
Monitoring
03 &
04/10/2015
03 &
04/11/2015
03 &
04/12/2015
03 &
04/01/2016
03 &
04/02/2016
03 &
04/03/2016
22:00-23:00 62.8 65.4 60.3 58.5 55.5 61.3
23:00-00:00 61.9 61.5 58.7 60.1 60.8 60.2
00:00-01:00 60.5 61.6 56.9 56.9 58.6 60
01:00-02:00 59.4 58.1 54.3 55.7 56.8 58.7
02:00-03:00 57.2 60 52.1 54.4 55.5 54.6
03:00-04:00 56.8 56.5 50.8 52.9 50.7 52.7
04:00-05:00 54.9 57.4 47.4 46.8 45.3 51.9
05:00-06:00 53.6 56.1 44.2 45.9 45.3 48.6
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
29
TABLE NO. 6.7 RESULTS OF SUB STATION - 8 (MARINE BUILDING) DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
SUB STATION - 8 (MARINE BUILDING)
Date of
Monitoring 3/10/2015 4/11/2015 3/12/2015 4/1/2016 3/2/2016 3/3/2016
6:00-7:00 52.7 54.3 46.2 43.6 42 42.3
7:00-8:00 54.9 52.1 47.9 47 48.2 44.8
8:00-9:00 58.7 55.4 51.4 48.4 47.5 46.9
9:00-10:00 62.9 61.5 53.9 52.7 55.7 48.7
10:00-11:00 65.4 64.6 55.4 55.3 55.1 51.4
11:00-12:00 66.8 67.1 59.2 57.1 55.9 54.8
12:00-13:00 67.3 64 61.3 61.2 59.1 56.7
13:00-14:00 68.5 66.2 64.8 63.2 60.3 60.4
14:00-15:00 70.8 72.6 66.3 64.1 65.6 65.7
15:00-16:00 71.9 69.4 69.4 66.9 64.5 68.4
16:00-17:00 69.3 70.4 68.7 66.8 66.9 69.3
17:00-18:00 68.5 67.3 67.1 69 68.2 68.5
18:00-19:00 67.9 69.4 66.9 67.2 65.6 66.4
19:00-20:00 66 64.9 64.6 66.2 63.5 65.5
20:00-21:00 65.2 62.4 62.8 63.8 64.6 63.6
21:00-22:00 64.3 62 61.9 58.1 57.2 61.7
LIMIT :-75 dB(A)
TABLE NO. 6.8 RESULTS OF SUB STATION - 8 (MARINE BUILDING) NIGHT TIME NOISE
Sampling
Location
October-15 November-15 December-15 January-16 February-16 March-16
SUB STATION - 8 (MARINE BUILDING)
Date of Monitoring
05 &
06/10/2015
05 &
06/11/2015
04 &
05/12/2015
05 &
06/01/2016
04 &
05/02/2016
04 &
05/03/2016
22:00-23:00 61.3 58.9 60.6 57.5 54.6 60.3
23:00-00:00 60.7 62.1 59.3 57.4 56.1 59.4
00:00-01:00 59.6 57 56.2 54 56.2 57.6
01:00-02:00 58.4 57.7 53.8 55.3 55.8 55.3
02:00-03:00 57.2 58.5 51.7 52.1 51.8 52.8
03:00-04:00 55.5 54.8 50.1 51.7 53 50.3
04:00-05:00 53.1 54.5 49.3 47.2 46.4 49.7
05:00-06:00 51.7 48.2 48.2 47.1 47.4 46.7
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
30
TABLE NO. 6.9 RESULTS OF NEAR SUB STATION - 7B DAY TIME NOISE
Sampling
Location
October-15 November-15 December-15 January-16 February-16 March-16
NEAR SUB STATION - 7B
Date of Monitoring
06/10/2015 06/11/2015 05/12/2015 06/01/2016 05/02/2016 05/03/2016
6:00-7:00 51.3 48.5 45.1 42.9 45.2 43.4
7:00-8:00 53.7 51.4 48.3 46.3 46 45.4
8:00-9:00 56.9 53.5 49.1 47.1 50 48.9
9:00-10:00 60.5 62.1 51.6 50.6 49.7 49.1
10:00-11:00 63.9 64 54.9 54.9 57 50.9
11:00-12:00 65.7 64.3 58.7 60.6 62.2 52.8
12:00-13:00 68.4 65.5 60.2 61.6 60.9 54.9
13:00-14:00 69.3 70.4 63.4 63.2 63.4 60.1
14:00-15:00 71.5 70.1 64.8 66.5 64.3 66.3
15:00-16:00 72 70.3 67.3 67.7 64.7 68.4
16:00-17:00 69.9 72.4 68.4 71.3 72.7 67.1
17:00-18:00 69 71.3 67.5 67.4 66.5 67.5
18:00-19:00 68.5 71.3 65.3 65.6 65.5 66.4
19:00-20:00 66.2 69.2 63.8 66.4 65.1 63.2
20:00-21:00 64.3 62.4 61.9 63.4 65.1 62.1
21:00-22:00 63.9 63 60.8 63 62.7 60.8
LIMIT :-75 dB(A)
TABLE NO. 6.10 RESULTS OF NEAR SUB STATION - 7B NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
NEAR SUB STATION - 7B
Date of Monitoring
06 &
07/10/2015
06 &
07/11/2015
05 &
06/12/2015
06 &
07/01/2016
05 &
06/02/2016
05 &
06/03/2016
22:00-23:00 62.3 64.5 59.7 59.8 62.7 59.4
23:00-00:00 61.5 61.9 58.6 58.3 56.2 58.3
00:00-01:00 60.9 57.8 56.2 54.5 56.6 57.6
01:00-02:00 58.7 58.7 54.3 55.5 52.7 54.2
02:00-03:00 56.3 56.7 50.2 50.5 49.6 51.8
03:00-04:00 54.2 52.2 48.9 47.9 49.5 49.3
04:00-05:00 53.6 50.4 47.1 43.7 41.9 47.7
05:00-06:00 52.9 54.3 45.3 44.8 44.8 45.3
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
31
TABLE NO. 6.11 RESULTS OF JS -1 (NEAR LAKHIGAM) DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
JS -1 (NEAR LAKHIGAM)
Date of Monitoring
07/10/2015 07/11/2015 07/12/2015 07/01/2016 06/02/2016 03/07/2016
6:00-7:00 50.7 51.8 42.8 49.3 52.2 41.9
7:00-8:00 57.9 55.5 43.9 44.6 43.1 42.8
8:00-9:00 61.7 59.5 45.8 49.2 50.7 47.4
9:00-10:00 62.3 62.8 49.3 54.4 53.5 49.3
10:00-11:00 65.4 63.2 52.9 55.9 54.8 51.6
11:00-12:00 67.3 70 55.9 60.5 58.4 53.8
12:00-13:00 69.5 71.6 57.8 61.5 61.1 54.9
13:00-14:00 70.4 68.9 60.8 63.5 65.9 61.5
14:00-15:00 71.9 70.3 63.4 66 66.9 62.6
15:00-16:00 72.6 72.4 65.9 68 68.8 68.8
16:00-17:00 70.7 73.6 67.8 67.2 69.8 67.3
17:00-18:00 69.3 67.8 66.9 71 71.6 69.8
18:00-19:00 67.7 68.5 64.8 69.5 67.7 68.3
19:00-20:00 65.9 67.2 62.7 68.1 70.5 66.5
20:00-21:00 64.3 63.6 61 66 63.2 64.3
21:00-22:00 63.8 66 60.5 64.4 62.7 62.1
LIMIT :-75 dB(A)
TABLE NO. 6.12 RESULTS JS -1 (NEAR LAKHIGAM) NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
JS -1 (NEAR LAKHIGAM)
Date of
Monitoring
07 &
08/10/2015
07 &
08/11/2015
07 &
08/12/2015
07 &
08/01/2016
06 &
07/02/2016
07 &
08/03/2016
22:00-23:00 63 59.9 59.3 62.2 65.1 61.4
23:00-00:00 62.7 62.4 58.3 58.2 59.4 60.2
00:00-01:00 61.3 63.7 55.3 59 59 58.4
01:00-02:00 60.4 61.8 54.7 53 51.5 56.2
02:00-03:00 58.4 61.1 52.9 51.8 54.4 54.7
03:00-04:00 55.2 55.3 50.1 51.3 48.7 52.8
04:00-05:00 54.5 53.8 49.3 48.3 46.4 51.6
05:00-06:00 53.7 55.6 47.4 45.6 47.8 49.3
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
32
TABLE NO. 6.13 RESULTS OF BEHIND S.S. - 11 (SILO) DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
BEHIND S.S. - 11 (SILO)
Date of Monitoring
08/10/2015 09/11/2015 08/12/2015 08/01/2016 08/02/2016 03/07/2016
6:00-7:00 53.1 52.9 43.7 47.9 48.2 40.3
7:00-8:00 57.5 55.5 45.9 47 44.4 41.9
8:00-9:00 60.4 62.2 48.3 51 50.6 47.9
9:00-10:00 62.4 62.7 51.6 52.1 53 49.2
10:00-11:00 64.3 66.6 54.9 55.4 56.5 50.8
11:00-12:00 66.2 62.7 58.2 58.5 59.7 54.9
12:00-13:00 68.5 65.4 59.4 63.8 65.4 56.8
13:00-14:00 69.4 72.1 61.2 62 61.3 60.9
14:00-15:00 69.9 72.4 63.5 64.7 65.3 64.8
15:00-16:00 70.8 69.9 65.9 68.2 70.1 65.8
16:00-17:00 69.7 69.8 67 69.3 68.5 68.3
17:00-18:00 68.5 71.4 66.5 68.9 70 66.5
18:00-19:00 66.2 67.3 65.2 69 67.7 64.3
19:00-20:00 64.3 65.2 63.8 67.8 66.7 63.2
20:00-21:00 63.4 63.9 62.4 64.5 63.2 62.1
21:00-22:00 62.5 64.2 61.9 61.2 62.5 60.3
LIMIT :-75 dB(A)
TABLE NO. 6.14 RESULTS BEHIND S.S. - 11 (SILO) NIGHT TIME NOISE
Sampling
Location
October-15 November-15 December-15 January-16 February-16 March-16
BEHIND S.S. - 11 (SILO)
Date of Monitoring
08 &
09/10/2015
09 &
10/11/2015
08 &
09/12/2015
08 &
09/01/2016
08 &
09/02/2016
08 &
09/03/2016
22:00-23:00 62.4 63.2 59 59.5 61.2 59.8
23:00-00:00 61.9 63.6 59.1 54.4 53.6 58.2
00:00-01:00 60.3 60.7 57.2 53.6 53.6 57.6
01:00-02:00 59.4 61.9 55.3 50 52.1 55.3
02:00-03:00 57.6 56 53.1 47.7 49 52.4
03:00-04:00 55.4 55.4 50.4 46.1 47.1 48.7
04:00-05:00 53 53.6 48.7 45.3 43.5 46.2
05:00-06:00 52.8 55.8 45.2 45.9 47.1 45.3
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
33
TABLE NO. 6.15 RESULTS OF NEAR S & S ENTRY GATE (DAHEJ ROAD) DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
NEAR S & S ENTRY GATE (DAHEJ ROAD)
Date of
Monitoring 09/10/2015 10/11/2015 09/12/2015 09/01/2016 09/02/2016 03/07/2016
6:00-7:00 55.9 53.8 41.4 44.4 43.5 45.4
7:00-8:00 57.8 60.8 43.4 46.4 46 47.8
8:00-9:00 60.7 63.7 46.9 53.7 54.9 49.3
9:00-10:00 62.5 59.2 50.8 56.8 59.2 50.2
10:00-11:00 64.4 66.9 52.4 60.6 59.3 54.3
11:00-12:00 65.3 67.9 59.3 60.8 61.3 56.9
12:00-13:00 67.2 67.6 61.4 62.6 61.3 52.6
13:00-14:00 68.3 66.7 62.8 62.9 60.4 57.8
14:00-15:00 70.5 68.9 63.4 67.3 65.6 60.3
15:00-16:00 71.6 74.2 65.7 67.2 68.9 62.5
16:00-17:00 70.5 72.9 68.9 68 70.7 64.9
17:00-18:00 69.3 70.7 67.4 67.2 68.2 68.7
18:00-19:00 67 70 66.2 61.8 59.3 66.2
19:00-20:00 65.4 68.3 65.4 60.7 59.9 64.3
20:00-21:00 63.6 65.9 63.2 59.9 61.9 62.9
21:00-22:00 62.9 60.5 61.4 56.5 53.8 61
LIMIT :-75 dB(A)
TABLE NO. 6.16 RESULTS NEAR S & S ENTRY GATE (DAHEJ ROAD) NIGHT TIME NOISE
Sampling
Location
October-15 November-15 December-15 January-16 February-16 March-16
NEAR S & S ENTRY GATE (DAHEJ ROAD)
Date of
Monitoring
09 &
10/10/2015
10 &
11/11/2015
09 &
10/12/2015
09 &
10/01/2016
09 &
10/02/2016
09 &
10/03/2016
22:00-23:00 61.9 59 59.3 57.8 55.7 60.8
23:00-00:00 60.4 61.7 58.4 57.4 57.1 60.1
00:00-01:00 59.5 61.4 56.2 55.6 54 57.3
01:00-02:00 58.3 55.4 54.9 52 49.6 55
02:00-03:00 56.2 57.1 52.8 51.4 52.4 52.7
03:00-04:00 54.7 51.2 50.7 51.3 53.6 50.6
04:00-05:00 52.6 52.7 47.3 50.9 50.8 48.7
05:00-06:00 51.9 52.1 44.2 50.1 50.2 46.2
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
34
TABLE NO. 6.17 RESULTS OF GCPTL GATE DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
GCPTL GATE
Date of Monitoring
10/10/2015 11/11/2015 10/12/2015 11/01/2016 10/02/2016 03/07/2016
6:00-7:00 54.7 51.8 44.7 46.7 45.9 44.8
7:00-8:00 55.3 56.7 45.9 45.2 46.1 46.9
8:00-9:00 57.9 60.5 47.8 47.7 46.8 49.1
9:00-10:00 59.3 58.2 50.9 49.5 49.1 50.3
10:00-11:00 62.2 65.2 53.2 56.3 57.4 52.9
11:00-12:00 64.5 64.1 57.8 56.4 53.5 54.8
12:00-13:00 68 68.7 59.7 61.8 63.8 56.9
13:00-14:00 69.5 70.4 61.4 63.3 65.2 60.3
14:00-15:00 71.2 71.7 65.4 66.8 64 63.8
15:00-16:00 72.6 71.9 68.9 67.8 69.1 64.5
16:00-17:00 70.6 72 69.7 68.2 66.1 66.8
17:00-18:00 69.1 70 68.2 68.4 67 68.7
18:00-19:00 68.7 69 67 69.5 67.6 67.5
19:00-20:00 66.9 68.3 65 66.7 69.5 66.4
20:00-21:00 64.4 61.6 64.9 64.2 62.3 63.2
21:00-22:00 62.5 62.8 62.8 63.4 61.9 62.5
LIMIT :-75 dB(A)
TABLE NO. 6.18 RESULTS GCPTL GATE NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
GCPTL GATE
Date of
Monitoring
10 &
11/10/2015
11 &
12/11/2015
10 &
11/12/2015
11 &
12/01/2016
10 &
11/02/2016
10 &
11/03/2016
22:00-23:00 62 60.5 61.4 60.7 61 61.3
23:00-00:00 61.6 61.3 60.3 59.4 61.2 59.8
00:00-01:00 60.4 63 58.7 57.9 57.1 57.4
01:00-02:00 59.6 57.9 56.4 55.4 55.7 55.3
02:00-03:00 57.3 55.2 50.3 53.3 51.7 52.7
03:00-04:00 55.9 56.6 49.4 53.1 50.4 50.6
04:00-05:00 53.2 52.5 45.3 50.3 51.2 48.7
05:00-06:00 52.7 50.2 43.2 47 44 45.9
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
35
TABLE NO. 6.19 RESULTS OF LAKHI VILLAGE (PRIMARY SCHOOL) DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
LAKHI VILLAGE (PRIMARY SCHOOL)
Date of Monitoring
12/10/2015 12/11/2015 11/12/2015 12/01/2016 11/02/2016 03/07/2016
6:00-7:00 51.4 50.9 42.8 40.9 40.8 41.9
7:00-8:00 52.7 50.8 44.7 45.9 47.9 42.7
8:00-9:00 54.9 53.9 49.1 46.1 43.6 44.6
9:00-10:00 56.8 54.8 51.7 54 54.1 48.7
10:00-11:00 59.2 61 54.9 57.4 59.9 50.6
11:00-12:00 61.5 60.1 58.9 60.1 62.3 52.8
12:00-13:00 63.7 64.9 60.4 62.7 60.1 57.9
13:00-14:00 65.1 64.2 62.9 64.9 62.9 61.4
14:00-15:00 68.7 66.6 65.3 64.9 63.3 64.9
15:00-16:00 69.4 72.4 67.9 66.3 67.6 65.3
16:00-17:00 70.3 66.8 68.3 71.3 69.1 66.6
17:00-18:00 68.5 71.1 67.4 69.2 67 68.9
18:00-19:00 67.3 66.6 66.3 67.9 69.6 69.3
19:00-20:00 65.1 67.6 64.9 66.7 68.8 67.2
20:00-21:00 64.9 66.2 63.8 62.8 65.4 66.5
21:00-22:00 63.7 61.9 61.2 62.7 63.9 64.4
LIMIT :-75 dB(A)
TABLE NO. 6.20 RESULTS LAKHI VILLAGE (PRIMARY SCHOOL) NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
LAKHI VILLAGE (PRIMARY SCHOOL)
Date of
Monitoring
12 &
13/10/2015
12 &
13/11/2015
11 &
12/12/2015
12 &
13/01/2016
11 &
12/02/2016
11 &
12/03/2016
22:00-23:00 62.5 60.1 60.4 61.2 62 62.7
23:00-00:00 61.7 61.1 59.3 61.3 59.1 60.2
00:00-01:00 60.3 57.9 55.3 56.1 57.6 57.8
01:00-02:00 59.3 62 54.9 56.2 58.1 56.4
02:00-03:00 58.1 55.5 52.7 54.6 56 53.2
03:00-04:00 56.3 57.4 50.3 53.7 52.3 50.7
04:00-05:00 54.1 51.8 48.9 49.5 46.7 47.8
05:00-06:00 52.7 50.8 46.5 46.8 46 45.3
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
36
TABLE NO. 6.21 RESULTS OF ERMS WORKSHOP DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
ERMS WORKSHOP
Date of Monitoring
13/10/2015 13/11/2015 12/12/2015 13/01/2016 02/12/2016 03/12/2016
6:00-7:00 54.1 55.2 44.8 43.9 41.3 40.9
7:00-8:00 52.7 52.2 45.9 48.8 48.9 41.8
8:00-9:00 54.9 54.7 50.3 51.2 51.4 47.3
9:00-10:00 56.8 57.4 51.9 57.1 55.3 49.2
10:00-11:00 59.2 55.7 55.8 59.8 59.2 53.1
11:00-12:00 61.5 60.7 57.9 59.5 57.8 59.4
12:00-13:00 63.7 63.8 58.3 62.8 60.5 62.4
13:00-14:00 65.1 63.4 59.4 63.4 63.5 64.8
14:00-15:00 68.7 70.4 61.3 67 68.7 67.3
15:00-16:00 69.4 71.2 63.1 68.6 67.1 68.9
16:00-17:00 70.3 71.3 65.9 69.1 72.1 69.3
17:00-18:00 68.5 68.9 68.7 67.5 68.3 68.4
18:00-19:00 67.3 64.9 69.3 65.6 67.4 66.5
19:00-20:00 65.1 66.8 66.4 64.7 62.1 65.3
20:00-21:00 64.9 66.8 64.8 62.8 64.6 62.8
21:00-22:00 63.7 63.8 63.7 62.1 61.4 61.4
LIMIT :-75 dB(A)
TABLE NO. 6.22 RESULTS OF ERMS WORKSHOP NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
ERMS WORKSHOP
Date of
Monitoring
13 &
14/10/2015
13 &
14/11/2015
12 &
13/12/2015
13 &
14/01/2016
12 &
13/02/2016
12 &
13/03/2016
22:00-23:00 62 61.2 61.9 59.2 57.2 62.7
23:00-00:00 61.6 59.3 58.3 61.3 59.3 60.2
00:00-01:00 60.4 62 56.2 59.7 59.8 57.8
01:00-02:00 59.6 61.6 54.8 56.8 57.6 56.4
02:00-03:00 57.3 54.5 52.7 52.5 52.5 53.2
03:00-04:00 55.9 58.4 49.3 52.6 53.7 50.7
04:00-05:00 53.2 50.7 47.4 48 48.7 47.8
05:00-06:00 52.7 53.6 45.3 48.1 48.9 45.3
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
37
TABLE NO. 6.23 RESULTS OF BEHIND PUMP HOUSE DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
BEHIND PUMP HOUSE
Date of Monitoring
14/10/2015 14/11/2015 14/12/2015 15/01/2016 13/02/2016 14/03/2016
6:00-7:00 54.7 57.6 46.2 48.9 47.4 42.3
7:00-8:00 55.3 53.8 47.9 46.8 47.7 44.8
8:00-9:00 57.9 60.9 51.4 51.8 49.7 46.9
9:00-10:00 59.3 61.5 53.9 56.3 53.9 48.7
10:00-11:00 62.2 59.9 55.4 55.3 55.1 51.4
11:00-12:00 64.5 66.8 57.4 59.7 61.5 54.8
12:00-13:00 68 68.3 59.2 59.4 57.3 56.7
13:00-14:00 69.5 66 61.3 61.7 60.3 60.4
14:00-15:00 71.2 68.4 64.8 66.3 67 65.7
15:00-16:00 72.6 74.9 66.3 68.1 66.5 68.4
16:00-17:00 70.6 69.2 69.4 69.6 68.3 69.3
17:00-18:00 69.1 68.6 68.7 66.3 67.1 68.5
18:00-19:00 68.7 66.7 67.1 67.7 68.2 66.4
19:00-20:00 66.9 63.7 66.9 65.5 67.8 65.5
20:00-21:00 64.4 63.6 64.6 63.5 65.9 63.6
21:00-22:00 62.5 62.7 62.8 61.4 61.8 61.7
LIMIT :-75 dB(A)
TABLE NO. 6.24 RESULTS OF BEHIND PUMP HOUSE NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
BEHIND PUMP HOUSE
Date of
Monitoring
14 &
15/10/2015
14 &
15/11/2015
14 &
15/12/2015
15 &
16/01/2016
13 &
14/02/2016
14 &
15/03/2016
22:00-23:00 62.5 64.9 60.8 58.1 58.2 60.8
23:00-00:00 61.7 63.4 59.3 58.1 60.7 60.2
00:00-01:00 60.3 61.6 56.2 53.4 50.9 57.4
01:00-02:00 59.3 59.7 53.8 51.9 51.1 55.8
02:00-03:00 58.1 57.5 51.7 49.4 47 52.7
03:00-04:00 56.3 55.5 50.1 49.1 49.7 50.6
04:00-05:00 54.9 51.8 49.3 47.7 50.6 47.8
05:00-06:00 53.1 51.9 48.2 48.2 48.5 46.3
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
38
TABLE NO. 6.25 RESULTS OF ROCK BOND APPROACH (JETTY) DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
ROCK BOND APPROACH (JETTY)
Date of Monitoring
15/10/2015 16/11/2015 15/12/2015 16/01/2016 15/02/2016 15/03/2016
6:00-7:00 54.2 54.7 41.4 47.1 48.7 41.8
7:00-8:00 57.8 56.8 43.4 49 51.6 43.4
8:00-9:00 60.7 61.2 46.9 50.3 52.2 48.7
9:00-10:00 62.5 63.5 50.8 56.2 55.3 52.3
10:00-11:00 64.4 64.1 52.4 56.3 55.6 54.8
11:00-12:00 65.3 67.1 56.8 60 59 60.5
12:00-13:00 67.2 65.4 59.3 63.1 66 62.3
13:00-14:00 68.2 66.3 61.4 63 65.9 64.8
14:00-15:00 70.5 73.5 62.8 67 69 66.9
15:00-16:00 71.6 70.7 63.4 68 66.9 67.8
16:00-17:00 70.5 67.2 65.7 70.4 71.8 68.9
17:00-18:00 69.3 68.7 68.9 67.4 65.7 69.1
18:00-19:00 67 65 67.4 66.5 65 63.7
19:00-20:00 65.4 64.7 66.2 65.4 65.3 62.1
20:00-21:00 63.6 65 65.4 63.6 63.4 60.8
21:00-22:00 62.9 64.2 63.2 64.1 61.9 60.1
LIMIT :-75 dB(A)
TABLE NO. 6.26 RESULTS ROCK BOND APPROACH (JETTY) NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
ROCK BOND APPROACH (JETTY)
Date of
Monitoring
15 &
16/10/2015
16 &
17/11/2015
15 &
16/12/2015
16 &
17/01/2016
15 &
16/02/2016
15 &
16/03/2016
22:00-23:00 61.9 64.2 59.3 62.5 63.3 61.3
23:00-00:00 60.4 56.9 58.4 58.8 57.4 59.8
00:00-01:00 59.5 62.5 56.2 60.1 59.1 57.4
01:00-02:00 58.3 58.1 54.9 55.1 53.8 55.3
02:00-03:00 56.2 57.7 52.8 53.1 54.1 52.7
03:00-04:00 54.7 51.2 50.7 51.1 53.2 50.8
04:00-05:00 52.6 50.5 47.3 48.9 48.4 48.9
05:00-06:00 51.9 53.3 44.2 51.3 52.4 45.6
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
39
TABLE NO. 6.27 RESULTS OF NEW GATE DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
NEW GATE
Date of
Monitoring 16/10/2015 17/11/2015 16/12/2015 18/01/2016 16/02/2016 16/03/2016
6:00-7:00 53.1 52.8 44.7 46.6 45.2 41.9
7:00-8:00 57.5 59 45.9 49.3 48.5 42.8
8:00-9:00 60.4 57.4 47.8 55.2 53.9 47.4
9:00-10:00 62.4 60.2 50.9 56.2 54.1 49.3
10:00-11:00 64.3 63.7 53.2 59.4 58.4 51.6
11:00-12:00 66.2 64.8 55.9 63.5 60.8 53.8
12:00-13:00 68.5 68.1 57.8 62.6 62.1 54.9
13:00-14:00 69.4 71.9 59.7 65.9 63.4 61.5
14:00-15:00 69.9 68.3 61.4 67.8 68.8 62.6
15:00-16:00 70.8 71.4 62.9 69.3 72.3 64.8
16:00-17:00 69.7 67.6 67.8 66.9 67 67.3
17:00-18:00 68.5 65.2 69.7 69.4 69.3 69.8
18:00-19:00 66.2 68.4 68.2 68.7 68.5 68.3
19:00-20:00 64.3 64.7 67.3 63.7 65.6 66.5
20:00-21:00 63.2 64.2 65 66.1 65 64.3
21:00-22:00 62.5 62 64.9 64 61.7 62.1
LIMIT :-75 dB(A)
TABLE NO. 6.28 RESULTS OF NEW GATE NIGHT TIME NOISE
Sampling
Location
October-15 November-15 December-15 January-16 February-16 March-16
NEW GATE
Date of Monitoring
16 &
17/10/2015
17 &
18/11/2015
16 &
17/12/2015
18 &
19/01/2016
16 &
17/02/2016
16 &
17/03/2016
22:00-23:00 62.4 60.3 61.4 62.9 63.3 59.8
23:00-00:00 61.9 61.7 60.3 59.8 61.4 58.2
00:00-01:00 60.3 62.6 59.3 54.6 54.9 57.6
01:00-02:00 59.4 60.4 56.4 52.5 54.6 55.3
02:00-03:00 57.6 54.3 50.3 50.8 51.7 52.4
03:00-04:00 55.4 55.5 49.4 50.9 50.9 49.3
04:00-05:00 53 53.8 44.8 49.5 47.8 47.7
05:00-06:00 52.8 54.4 43.7 47.8 47.1 45.3
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
40
TABLE NO. 6.29 RESULTS OF SECURITY BARRIER GATE DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
SECURITY BARRIER GATE
Date of Monitoring
17/10/2015 18/11/2015 17/12/2015 19/01/2016 17/02/2016 17/03/2016
6:00-7:00 50.7 50.1 45.1 45.4 47.2 40.3
7:00-8:00 57.9 55.2 48.3 52.2 53.4 41.9
8:00-9:00 61.7 60.8 49.4 54 52.7 47.9
9:00-10:00 62.3 59.8 51.6 54.8 56.9 49.2
10:00-11:00 65.4 63.3 54.9 56.9 57.9 50.8
11:00-12:00 67.3 65.2 56.8 61.9 64.9 54.9
12:00-13:00 69.5 71 58.7 61.6 60.1 56.8
13:00-14:00 70.4 69.2 60.2 65.8 66.5 60.9
14:00-15:00 71.9 72.1 63.4 65.5 67.6 64.8
15:00-16:00 72.6 72.8 64.9 67.8 68.4 65.8
16:00-17:00 70.7 70.6 67.3 69.1 69.9 68.3
17:00-18:00 69.3 67.9 68.4 67.3 69.1 66.5
18:00-19:00 67.7 70.3 67.5 65.3 65.9 64.3
19:00-20:00 65.9 63.3 65.3 66.5 68.5 63.2
20:00-21:00 64.3 62.9 63.8 63.6 61.1 62.1
21:00-22:00 63.8 62.3 61.9 62.6 63.3 60.3
LIMIT :-75 dB(A)
TABLE NO. 6.30 RESULTS OF SECURITY BARRIER GATE NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
SECURITY BARRIER GATE
Date of
Monitoring
17 &
18/10/2015
18 &
19/11/2015
17 &
18/12/2015
19 &
20/01/2016
17 &
18/02/2016
17 &
18/03/2016
22:00-23:00 63 64.6 59.7 59 61.6 59.3
23:00-00:00 62.7 63.9 58.6 57.2 55.6 58.4
00:00-01:00 61.3 61 56.2 58.2 55.3 56.4
01:00-02:00 60.4 58.7 54.3 56.9 57.4 54.3
02:00-03:00 58.4 55.2 50.2 54.2 55.3 53.2
03:00-04:00 55.2 53.6 48.9 50.1 52.3 50.4
04:00-05:00 53.5 54.8 47.1 48.3 46.9 50
05:00-06:00 52.7 55.5 45.3 47.4 45.6 48.3
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
41
TABLE NO. 6.31 RESULTS OF JS – 2 DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
JS – 2
Date of Monitoring
19/10/2015 19/11/2015 18/12/2015 20/01/2016 18/02/2016 18/03/2016
6:00-7:00 51.3 53 44.7 44.2 42 43.4
7:00-8:00 53.7 54.5 45.7 46.6 48.9 45.4
8:00-9:00 56.9 54.7 48.3 48.7 51.2 48.9
9:00-10:00 60.5 60.3 51.4 53.9 51.1 47.1
10:00-11:00 63.9 63.4 55.2 54.8 56.4 50.9
11:00-12:00 65.7 65.7 58.9 57.8 60.3 52.8
12:00-13:00 68.4 71 59.1 62.3 63.4 54.9
13:00-14:00 69.3 66.9 62.4 64.9 64.6 60.1
14:00-15:00 71.5 73.8 65.6 65.3 67.2 66.3
15:00-16:00 72 69.4 67.9 70.1 69.7 68.4
16:00-17:00 69.9 69.8 68.3 68.2 70.7 69.1
17:00-18:00 69 66.8 69.2 70.1 70.2 67.5
18:00-19:00 68.5 70.6 67.3 68.8 69.4 66.4
19:00-20:00 66.2 65.2 65.8 64.6 64.9 63.2
20:00-21:00 64.3 65.9 64.2 63.9 66.9 62.1
21:00-22:00 63.9 66.3 62.9 62.3 63.9 60.8
LIMIT :-75 dB(A)
TABLE NO. 6.32 RESULTS OF JS – 2 NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
JS – 2
Date of
Monitoring
19 &
20/10/2015
19 &
20/11/2015
18 &
19/12/2015
20 &
21/01/2016
18 &
19/02/2016
18 &
19/03/2016
22:00-23:00 62.3 64.8 60.3 61.4 59.3 60.2
23:00-00:00 61.5 60.1 58.7 60.8 63.1 58.3
00:00-01:00 60.9 59.7 56.9 58.7 57.8 57.4
01:00-02:00 58.7 58.5 54.3 57.5 57.5 53.6
02:00-03:00 56.3 53.1 52.1 49.3 49 52.7
03:00-04:00 54.2 51.6 50.8 49.7 51.4 51.8
04:00-05:00 53.2 55.4 47.4 49.9 51.2 50.7
05:00-06:00 52.9 52.2 44.2 45 42.5 47.3
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
42
TABLE NO. 6.33 RESULTS OF RAILWAY DEAD END DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
RAILWAY DEAD END
Date of Monitoring
20/10/2015 20/11/2015 19/12/2015 21/01/2016 19/02/2016 19/03/2016
6:00-7:00 52.7 53 43.8 47 45.6 41.7
7:00-8:00 54.9 53.2 44.7 46.6 45 42.9
8:00-9:00 58.7 61.1 49.1 51.1 49.6 45.8
9:00-10:00 62.9 61.4 51.7 53.9 51 49
10:00-11:00 65.4 64.2 54.9 56.7 53.7 52.3
11:00-12:00 66.8 67 56.4 59.1 56.9 56.9
12:00-13:00 67.3 67.3 58.9 59.2 56.4 58.2
13:00-14:00 68.5 66.3 60.4 62.6 60.4 61.3
14:00-15:00 70.8 69.4 62.9 64.4 63.8 64.5
15:00-16:00 71.9 69.5 65.3 68.3 67.1 67.4
16:00-17:00 69.3 67.2 67.9 67.9 68.1 69.3
17:00-18:00 68.5 68.2 68.3 69.1 66.8 68.6
18:00-19:00 67.9 66.3 67.4 69.9 69.6 67.3
19:00-20:00 66 67.2 66.3 68.7 71 66.1
20:00-21:00 65.2 64.4 64.9 67.4 68.5 64.2
21:00-22:00 63.4 60.3 63.8 65.2 64.8 62.3
LIMIT :-75 dB(A)
TABLE NO. 6.34 RESULTS OF RAILWAY DEAD END NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
RAILWAY DEAD END
Date of
Monitoring
20 &
21/10/2015
20 &
21/11/2015
19 &
20/12/2015
21 &
22/01/2016
19 &
20/02/2016
19 &
20/03/2016
22:00-23:00 61.3 57.9 60.4 61.4 58.8 61.3
23:00-00:00 60.7 58.8 59.3 57.8 57.1 60.2
00:00-01:00 59.6 57.7 55.3 56.3 56.4 60
01:00-02:00 58.4 56.8 54.9 53.1 52.6 58.7
02:00-03:00 57.2 53.9 52.7 50.8 53 54.6
03:00-04:00 55.5 56.2 50.3 51.5 54.1 52.7
04:00-05:00 53.1 51.9 48.9 50.2 49.7 51.9
05:00-06:00 52.7 54.4 46.5 46.4 46.8 48.6
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
43
TABLE NO. 6.35 RESULTS OF S AND S YARD (SOUTH) DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
S AND S YARD (SOUTH)
Date of Monitoring
21/10/2015 21/11/2015 21/12/2015 22/01/2016 20/02/2016 21/03/2016
6:00-7:00 56.3 58.4 42.7 42.2 42.9 45.4
7:00-8:00 57.9 59.8 45.9 46.3 44.6 47.8
8:00-9:00 59.3 61.9 48.3 47.5 45.5 49.3
9:00-10:00 62.4 63.8 51.6 48.9 49.8 50.2
10:00-11:00 63.7 61 54.9 53.7 52.9 54.3
11:00-12:00 65.6 63.1 57.8 54.5 54.7 56.9
12:00-13:00 68.5 65.9 58.2 60.7 60.8 52.6
13:00-14:00 69.7 71.7 59.4 60.7 57.7 57.8
14:00-15:00 71.6 72.5 61.2 64.3 62.6 60.3
15:00-16:00 72.8 72.5 63.5 64.9 64.8 62.5
16:00-17:00 69.5 70 65.9 67.4 68.4 64.9
17:00-18:00 68 68.9 67 68.4 65.6 68.7
18:00-19:00 67.3 69.8 66.5 68 70.3 66.2
19:00-20:00 66.4 66.1 65.2 66.1 68.6 64.3
20:00-21:00 64.5 63.4 63.8 65.6 66.2 62.9
21:00-22:00 62.9 59.6 62.4 61.4 61.1 61
LIMIT :-75 dB(A)
TABLE NO. 6.36 RESULTS OF S AND S YARD (SOUTH) NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
S AND S YARD (SOUTH)
Date of
Monitoring
21 &
22/10/2015
21 &
22/11/2015
21 &
22/12/2015
22 &
23/01/2016
20 &
21/02/2016
21 &
22/03/2016
22:00-23:00 62.8 63 59.6 62.6 60.4 59.4
23:00-00:00 61.9 60.4 58.2 58.3 56.4 58.3
00:00-01:00 60.5 62.8 56.3 55 53.8 57.6
01:00-02:00 59.4 60.2 55.2 50.4 53.3 54.2
02:00-03:00 57.2 60.2 53.1 50.3 51.9 51.8
03:00-04:00 56.8 55.9 50.4 50.3 49.3 49.3
04:00-05:00 54.9 52.6 48.7 46.6 48.4 47.7
05:00-06:00 53.6 52.3 45.2 44.8 43.2 48.3
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
44
TABLE NO. 6.37 RESULTS OF S AND S YARD (NORTH) BOUNDARY WALL DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
S AND S YARD (NORTH) BOUNDARY WALL
Date of Monitoring
22/10/2015 23/11/2015 22/12/2015 23/01/2016 22/02/2016 22/03/2016
6:00-7:00 53.2 51.2 42.8 45.2 43.2 41.9
7:00-8:00 55.7 55.9 43.9 46.4 48.2 42.7
8:00-9:00 56.9 59.4 45.8 50.9 52.2 44.6
9:00-10:00 59.3 56.9 49.3 51.1 48.6 48.7
10:00-11:00 61.7 64.5 52.9 55.1 52.1 50.6
11:00-12:00 64.9 61.4 54.8 56.4 59.4 52.8
12:00-13:00 67.3 68 55.9 62.1 59.8 57.9
13:00-14:00 69.8 68.9 57.8 62.7 64.3 61.4
14:00-15:00 71.5 71.8 60.8 65.9 66.5 64.9
15:00-16:00 70.6 68.1 63.4 65.7 68.7 65.3
16:00-17:00 69.5 69 65.9 67.6 66 66
17:00-18:00 68.4 68.1 67.8 68.4 68.7 68.9
18:00-19:00 66.5 63 66.9 69.3 67.2 69.3
19:00-20:00 65.8 64.4 64.8 65.5 65 67.2
20:00-21:00 64.8 61.9 62.7 67.1 65.5 66.8
21:00-22:00 62.1 62.4 61 62.6 65.3 64.5
LIMIT :-75 dB(A)
TABLE NO. 6.38 RESULTS OF S AND S YARD (NORTH) BOUNDARY WALL NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
S AND S YARD (NORTH) BOUNDARY WALL
Date of
Monitoring
22 &
23/10/2015
23 &
24/11/2015
22 &
23/12/2015
23 &
24/01/2016
22 &
23/02/2016
22 &
23/03/2016
22:00-23:00 61.7 62.1 59.3 63.5 63.8 60.3
23:00-00:00 60.9 59.7 58.4 59.6 59 59.4
00:00-01:00 59.3 59.5 55.3 57.4 56.5 57.6
01:00-02:00 58.4 58.1 54.7 57.4 58.7 55.3
02:00-03:00 57.2 54.6 52.9 52 50.3 52.8
03:00-04:00 55.2 52.2 50.1 52.3 51.4 50.3
04:00-05:00 54.5 52.9 49.3 48.1 46.1 49.7
05:00-06:00 52.3 50.6 47.4 46.6 48.7 46.7
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
45
TABLE NO. 6.39 RESULTS OF LAKHI VILLAGE (BELOW CONVEYER BELT) DAY TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
LAKHI VILLAGE (BELOW CONVEYER BELT)
Date of Monitoring
23/10/2015 24/11/2015 23/12/2015 25/01/2016 23/02/2016 23/03/2016
6:00-7:00 54.8 56.4 43.2 44 44.5 44.8
7:00-8:00 55.6 53.5 44.8 45.2 46.6 46.9
8:00-9:00 57.9 58.1 48.9 50.1 51.6 49.1
9:00-10:00 60.3 58.2 52.1 50.9 50.3 50.3
10:00-11:00 63.8 61.5 53.8 55.4 55.9 52.9
11:00-12:00 65.9 67.9 56.7 58.5 55.6 54.8
12:00-13:00 68.7 70.1 59.2 58.9 56.5 56.9
13:00-14:00 69.3 70 61.9 61.6 63.9 60.3
14:00-15:00 70.4 72 63.4 64.1 64.1 63.8
15:00-16:00 69.5 69.4 64.3 67.9 69.5 64.5
16:00-17:00 68.3 70.2 66.4 68 66.7 66.8
17:00-18:00 67.7 65 67.4 67.4 70.2 68.7
18:00-19:00 66.4 64.1 68.1 68.1 70.6 67.5
19:00-20:00 65.5 67.9 66 69 66.5 66.4
20:00-21:00 64.9 64.6 65.2 67.7 67.5 63.2
21:00-22:00 62.8 65 63.2 64 62.1 62.5
LIMIT :-75 dB(A)
TABLE NO. 6.40 RESULTSOF LAKHI VILLAGE (BELOW CONVEYER BELT) NIGHT TIME NOISE
Sampling Location
October-15 November-15 December-15 January-16 February-16 March-16
LAKHI VILLAGE (BELOW CONVEYER BELT)
Date of
Monitoring
23 &
24/10/2015
24 &
25/11/2015
23 &
24/12/2015
25 &
26/01/2016
23 &
24/02/2016
23 &
24/03/2016
22:00-23:00 62.5 59.7 61.7 65.5 68.3 61.8
23:00-00:00 61.3 60.1 59.3 60.9 62.1 60.3
00:00-01:00 60.8 58.6 57.3 61 60.4 60.1
01:00-02:00 58.2 55.5 55.4 55 56.2 58.6
02:00-03:00 56.3 57.1 53.9 50.8 48.7 54.2
03:00-04:00 55.9 57.4 50.1 51.6 53.4 52.6
04:00-05:00 54.7 55.1 48.3 49.4 47.6 51.8
05:00-06:00 53.2 55.9 45.9 49.9 52.4 48.5
LIMIT :-70 dB(A)
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
46
STACK MONITORING (OCTOBER 2015 TO MARCH 2016)
PARAMETER DETAILS:
Table no. 7.1 Result of DG stack monitoring
SR.
NO. TEST PARAMETER UNIT
DG SET # 1 MRSS (SS5) 125 KVA
27/10/2015 26/01/2016
1 Particulate Matter mg/Nm3 16.83 30.5
2 Sulfur Dioxide as SO2 ppm 6.15 8.6
3 Oxides of Nitrogen as NOX ppm 34.71 29.55
4 Non Methyl Hydro Carbon (NMHC) mg/m3 BDL* BDL*
5 Carbon Monoxide mg/m3 5.61 6.11
DG Noise Leq dB (A) 71.5 70.3 BDL*: Below Detection Limit, Minimum Detection Limit: Hydro Carbon: 75 mg/m3, Results on 11 % O2 Correction when Oxygen is greater than 11 %
SR.
NO. TEST PARAMETER UNIT
DG SET # 2 SS7B 125 KVA
27/10/2015 26/01/2016
1 Particulate Matter mg/Nm3 20.46 18.55
2 Sulfur Dioxide as SO2 ppm 5.22 7.41
3 Oxides of Nitrogen as NOX ppm 30.58 35.96
4 Non Methyl Hydro Carbon (NMHC) mg/m3 BDL* BDL*
5 Carbon Monoxide mg/m3 8.96 8.41
DG Noise Leq dB (A) 71.5 73.2 68.1 BDL*: Below Detection Limit, Minimum Detection Limit: Hydro Carbon: 75 mg/m3, Results on 11 % O2 Correction when Oxygen is greater than 11 %
Sr. No. Sampling Location Unit Test/Sampling Method
1 Particulate Matter mg/Nm3 IS:11255 (Part-1) : 1985
2 Sulphur Dioxide ppm IS:11255 (Part-2) : 1985
3 Oxide of Nitrogen ppm IS: 11255 (Part-7) : 2005
4 Carbon Monoxide (CO) mg/m3 Digital Gas Analyzer
5 Non Methyl Hydro Carbon (NMHC) mg/m3 Gas Chromatography
Annexure 1 (Environment Clearance Compliance report Oct 2015 to March 2016)
47
SR.
NO. TEST PARAMETER UNIT
DG SET # 3 Marine (SS8)125 KVA
27/10/2015 26/01/2016
1 Particulate Matter mg/Nm3 40.72 23.54
2 Sulfur Dioxide as SO2 ppm 6.35 5.49
3 Oxides of Nitrogen as NOX ppm 35.19 32.55
4 Non Methyl Hydro Carbon (NMHC) mg/m3 BDL* BDL*
5 Carbon Monoxide mg/m3 7.31 7.16
DG Noise Leq dB (A) 70.8 66.2 B BDL*: Below Detection Limit, Minimum Detection Limit: Hydro Carbon: 75 mg/m3, Results on 11 % O2 Correction when Oxygen is greater than 11 %
SR.
NO. TEST PARAMETER UNIT
DG SET # 4 Silo (SS11)125 KVA
27/10/2015 26/01/2016
1 Particulate Matter mg/Nm3 24.72 26.81
2 Sulfur Dioxide as SO2 ppm 7.49 6.49
3 Oxides of Nitrogen as NOX ppm 38.28 26.3
4 Non Methyl Hydro Carbon (NMHC) mg/m3 BDL* BDL*
5 Carbon Monoxide mg/m3 4.29 4.48
DG Noise Leq dB (A) 69.4 68.4 BDL*: Below Detection Limit, Minimum Detection Limit: Hydro Carbon: 75 mg/m3, Results on 11 % O2 Correction when Oxygen is greater than 11 %
Annexure – 2
Environment Expenditure & Budget for F.Y. 2015-16
SN
No Activity/ Category
Budget Expenditure
(INR) (INR)
1 Environmental Study / Audit and Consultancy -- 14.61
2 Legal & Statutory Expenses 0.20 3.14
3 Environmental Monitoring Services 18.0 18.0
4 Mangrove Plantation 0.0 0.0
5 Hazardous Waste Management & Disposal 0.50 0.75
6 Greenbelt Development and Plantation 19.60 19.76
7 O&M of Pollution control measures 41.36 38.95
8 Environment Day Celebration 1.50 1.60
9 Treatment and Disposal of Bio-Medical Waste 1.80 1.92
Total Amount (INR) 82.96 98.73
Capital Expenditure
1 Organic waste converter (kitchen waste & garden debris ) 8.0 8.0
2 Trailer mounted fog canon 15.5 16.0
3 Environment Information Board 3.0 2.75
4 Horticulture (Green Belt Development) 10.63 10.50
5 Flow Meter - Engg. Services 6.0 5.85
Total Amount (INR) 43.13 43.10
Annexure 3
ADANI FOUNDATION, DAHEJ
CSR ACTIVITY DETAILS (OCTOBER 2015 TO MARCH 2016)
Sr.
No Month Action Items
Budge
t
Utilize
d
(INR
Lacs)
Beneficiaries
Direct
Beneficiaries
Indirect
Beneficiaries Access Beneficiaries
EDUCATION 1 Jan ‘16 Strengthenin
g Pragna
Project
1.55 313 Students 994 Students -
2 Feb ‘16 Port
Exposure
Visit
0.47 336 Students &
Teachers
- -
COMMUNITY HEALTH 3 All Year
Round
Medical
Health Care
Unit
20.00 7609 Patients
from 12 different
villages/locations
- The remainder
population of 13168
from these 12
different
villages/locations
who could have
availed the benefits
of MHCU, but did
not.
SUSTAINABLE LIVELIHOOD DEVELOPMENT 4 Mar ‘16 Initiatives
for Fisher
Folk
Communitie
s (Fishing
Net
Distribution)
2.92 85 Fishermen 340
Dependent
family
members of
these
fishermen
-
5 Feb ‘16 Swachhata
Abhayan
1.77 4000 Students &
Staff from 8
Primary Schools,
13 Aanganwadis
and 3 High
Schools
- -
6 Jan ‘16 Community
Engagemen
t
Programme
s
0.55 156 Participants - -
RURAL INFRASTRUCTURE DEVELOPMENT 7 Dec ‘15 Solar Street
Lights at 2.15 1100 distinct - The population from
Lakhabava
Temple - devotees who’d
visited the temple
during late
evening hours
during FY 15-16
nearby villages who
could have availed
the benefits of this
facility, but did not
8 Feb ‘16 Constructio
n of 7
houses at
Luwara
village
14.71 35 inhabitants of
these newly built
houses
- -
9 Mar ‘16 Construction
of 10 Houses
at Lakhigam
Village
8.87 50 inhabitants of
these newly built
houses
- -
10 Feb ‘16 Renovating
Primary
School at
Ambetha
5.12 198 Students - -
11 Jan ‘16 Solar Street
Lights at
Rukhneshwar
Mahadev
Temple
2.15 3357 distinct
devotees who’d
visited the temple
during FY 2015-16
- The population from
nearby villages who
could have availed
the benefits of this
facility, but did not. 12 Oct ‘15 Renovating
38 Houses of
Navinagri
34.26 190 inhabitants of
these renovated
houses
- -
Total 94.52 17429
Beneficiaries
1334 Indirect
Beneficiaries
13168 Access
Beneficiaries
Glimpse of CSR activity by Adani Foundation Team for APDPPL
Education
The core focus of this domain is on below parameters:
• Efforts to improve the quality of education
• Education of girls
• Encourage community participation through meetings and trainings
• Maximum (100%) enrollment and retention in schools
Sustainable
Livelihood
Development
Community
Health
Education
Rural
Infrastructure
Development
Port Exposure Visit:-
AF - Dahej team facilitated a study tour visit of Adani
Petronet Port Pvt. Ltd (Dahej) for the students studying in
nearby village schools.
COMMUNITY HEALTH
Mobile Health Care Unit & Health Awareness Program
The team has deployed a Mobile Health Care Unit, scheduled to visit villages in the closed vicinity of the
Adani Petronet Port, for provision of basic healthcare/medical services to the patients
AF Dahej team carried out a Hygiene & Sanitation awareness campaign in Aanganwadi at Lakhigam-
Navinagri.
SUSTAINABLE LIVELIHOOD DEVELOPMENT
Initiatives for Fisher Folk Communities
AF Dahej team drove this program by distributing fishing nets to 85 fishermen from Navinagri
(Lakhigam) and Jageshwar. The motive behind this drive was to uplift the fishermen by helping them
endure their livelihood/source of income to support themselves and their families, thereby enhancing
the social and economic life of these fishermen.
Swachhata Abhayan & Community Engagement Programmes
Cleanliness Drive for Swachh Bharat - AF (Dahej) team offered material/ancillaries support associated
with cleanliness and hygiene, to improve the hygiene and sanitation levels in these villages
Solar Street Lights at Lakhabava Temple & Construction of 10 Houses at Lakhigam
Renovation of 38 Houses at Navinagri & Renovation of Primary School at Ambheta