Acumen Fuse World Tour 2012

71

Click here to load reader

description

Acumen has completed the first leg of the World Tour. This presentation is an in-depth overview of Acumen's solutions, as well as several Fuse use cases from Fuse clients

Transcript of Acumen Fuse World Tour 2012

Page 1: Acumen Fuse World Tour 2012

// Acumen Fuse World Tour

2012

Page 2: Acumen Fuse World Tour 2012

// World Tour Overview Acumen Fuse

◦  The tour ◦  10 countries: 24 locations

◦  Fuse & Fuse 360

◦  Fuse 3.1 launch ◦  Acumen Cloud™, New Schedule Cleanser™; New

forensics, enhanced P6 integration

Page 3: Acumen Fuse World Tour 2012

// Dr. Dan Patterson, PMP

◦  Legacy:

◦  20 years of PPM experience

◦  WelcomHome, WelcomRisk, TerraFirma

◦  Pertmaster

◦  Thought Leader:

◦  Project analytics

◦  Project Risk analysis

◦  S1>S5™ schedule maturity framework

◦  Founder of Acumen, inventor of Fuse

President and CEO, Acumen

Page 4: Acumen Fuse World Tour 2012

// Acumen

◦  Project Management Software Company

◦  Insight into challenges & use of

analytics to overcome them

◦  Core Concepts:

1.  Project success requires a sound plan

2.  Planning requires risk consideration

Proven Project Analytics

Product Offerings

Risk Workshops

Acumen Fuse®

Software Training

Realistic Scheduling

Critiqued

The Base

Risk-Adjusted

Optimized

Team-Aligned // S5

// S4

// S3

// S2

// S1

Page 5: Acumen Fuse World Tour 2012

// Schedule Maturity Framework Acumen S1 > S5

 S1  •  Schedule  Basis  • Owner/contractor  schedule  

S2  • Cri/qued  Schedule  •  Ensure  structural  integrity  

S3  • Risk-­‐Adjusted  Schedule  • Account  for  risk/uncertainty  

S4  • Op/mized  Target  Scenarios  •  Schedule  accelera>on  

S5  •  Team  Validated  Scenario  • Buy-­‐in  on  op>miza>on  0  

1  

2  

3  

4  

5  

6  

0   1   2   3   4   5   6  

Chan

ce  of  S

ucess  

Maturity  Level  

Measure quality through the Fuse Schedule Index™

Page 6: Acumen Fuse World Tour 2012

// Case Studies

1.  Owner/contractor alignment [S1>S2]

2.  Bidding competitiveness [S1>S2]

3.  Acceleration/risk reduction [S3>S5]

4.  Performance tracking

5.  Dispute resolution

6.  Portfolio analysis

The benefits of Fuse

May 16, 2012

Subcontractors   Contractors  

Joint  Venture   3rd  Party  Assessors  

Owners  

•  All leads to: •  More realistic, achievable plans

•  Many X faster/easier than manual approach

Page 7: Acumen Fuse World Tour 2012

// Acumen Fuse Platform

◦  Fuse: analytics platform

◦  Improves schedule quality

◦  Insight into performance

◦  Fuse 360: goal-based acceleration

◦  Schedule Acceleration

◦  Decision-support

Enterprise Project Analysis

May 16, 2012

Metric  Analyzer  

Logic  Analyzer  

Forensic  Analyzer  

Schedule  Cleanser  

Schedule  Accelerator  

Page 8: Acumen Fuse World Tour 2012

// Measuring Schedule Quality The Fuse Schedule Index™

Page 9: Acumen Fuse World Tour 2012

// Better Planning Drives Project Success Proven Correlation

0%  

10%  

20%  

30%  

40%  

50%  

60%  

70%  

80%  

90%  

100%  

0%   10%   20%   30%   40%   50%   60%   70%   80%   90%   100%  

Prob

ability  of  O

n-­‐Time  Co

mple/

on  

Fuse  Schedule  Index™  

Page 10: Acumen Fuse World Tour 2012

// Metric Analysis

Slice & Dice

May 16, 2012

Benefit:

" Pinpoint shortcomings

" Project characteristics

" Slice and dice

About:

" 300+ metrics

" Percentage: context

" Threshold: acceptability

Page 11: Acumen Fuse World Tour 2012

// Types of Project Metrics

Schedule  

• Logic  • Float  • Dura>on  

Cost  

• Overrun  • Capacity  • Burn  rates  

Performance  

• Status  • Completed  • Delayed  

Characteris>cs  

• Level  of  detail  • Constrained  • Riding  Data  Date  

Earned  Value  

• CPI/SPI  • Trending  • Earned  schedule  

Risk  

• Exposure  • Hot  spots  • Hidden  paths  

Fuse Metric Libraries

•  Project management best practices

•  Industry/corporate standards: PMI, AACE, NDIA

•  Fuse-specific: Logic Density™, Hotspot, Redundancy

•  Compliance: DCMA 14 Point, DoD

•  Create your own!

Page 12: Acumen Fuse World Tour 2012

// Customizable Metrics Fuse Metric Editor

Page 13: Acumen Fuse World Tour 2012

// Acumen-Specific Metrics

Logic  Density™  • Measure  of  complexity/completeness  

Logic  Hotspot™  • Timely  start?  

Float  Ra>o™  • Degree  of  flexibility  per  day  of  work  

Redundancy  Index™  • Non-­‐needed  logic  

Advanced Project Insight

Finish  Compliance™  • Accurate  measure  of  performance  

Insufficient  Detail™  • Ac>vity  V  project  dura>on  

Milestone  Ra>o™  • Detail  V  repor>ng  

Broad  Risk  Range  • Check  for  erroneous  risk  input  

Page 14: Acumen Fuse World Tour 2012

// Logic Density™

◦  Measure of complexity & soundness

◦  Dual-band threshold: 2 to 6…

◦  Determine Logic Hotspots™ in schedule

◦  Trending: determine timing of shortcomings

Integrity Check

More definition

needed

Page 15: Acumen Fuse World Tour 2012

// Fuse Schedule Cleanser™ Actionable Insight

Page 16: Acumen Fuse World Tour 2012

// Project Forensics Insight into Schedule Cleanse

May 16, 2012

16

Page 17: Acumen Fuse World Tour 2012

// Claims Analysis

◦  Advanced forensics

◦  Fuse gives meaning to the

impact of changes

◦  Pinpoints changes to critical/

driving path

◦  Every single project attribute

can be checked

◦  Calendar definition changes

Insight into project variances

May 16, 2012

Page 18: Acumen Fuse World Tour 2012

// Reporting

Executive Briefing!•  Summary of

analysis results!

Analyst Report!•  To do list!

Dashboard!•  Interactive

charts & graphs"

API & Custom Reports"•  Automation

of existing reports"

Publish Analysis Results

May 16, 2012

Page 19: Acumen Fuse World Tour 2012

// Integration

Schedule, Cost, Risk, Performance, EV

May 16, 2012

MS  Project  

P3/P6  

Open  Plan  

Asta   Cobra  Prism  G2  

PRA  

Excel/XML  

Na>ve  tool  not  required  

Page 20: Acumen Fuse World Tour 2012

// Case Study #1

•  Houston-based oil/gas owner

•  Objective:

•  More on-time completion for projects over $250MM

•  Encourage more mature contractor schedules

•  Overcome “brain drain” in scheduling

•  How achieved:

•  Mandated contractor Fuse Schedule Index of 75+

•  Gave contractor opportunity to self-assess

Owner/contractor Alignment

Page 21: Acumen Fuse World Tour 2012

// Case Study #1

◦  Metric analysis view

◦  Slice and dice analysis

◦  Executive briefing and Analyst reporting

◦  Logic analysis

◦  Schedule cleanser™

◦  Score comparison

◦  Forensic analyzer

◦  Executive dashboard

◦  Exporting fixed schedule

Fuse Modules

// Fuse Demo

Page 22: Acumen Fuse World Tour 2012

// Case Study #1

•  Outcome:

•  Contractor achieved 75+ Fuse Schedule Index

•  Schedule was more realistic

•  Schedule was earlier!

•  Owner gained confidence in the contractor

•  Better collaboration & alignment between stakeholders

Owner/contractor Alignment

Page 23: Acumen Fuse World Tour 2012

// Acumen Cloud™

◦  Communitized benchmarking

◦  Means of determining:

◦  Schedule quality?

◦  How this ranks with other projects?

◦  How does this align our project for on-time completion?

◦  100% anonymous, secure (SSL)

◦  Continuously getting more intelligent

◦  New libraries can be pushed to Fuse!

Project Benchmarking

Page 24: Acumen Fuse World Tour 2012

// Acumen Cloud™ Architecture

Knowledge  Base  

Dynamic Cloud Libraries Client-based

analysis Benchmarking

Fuse 3.1

Page 25: Acumen Fuse World Tour 2012

// Acumen Cloud The Fuse Schedule Index™

Page 26: Acumen Fuse World Tour 2012

// Case Study #2

•  EPC bids for a utility turnaround

•  Three competing bidders

•  Objective:

•  Owner wanting to make informed award decision

•  Cheapest? Fastest? Most achievable?

•  How Achieved:

•  Compared schedule, cost, quality metrics

•  Benchmarked using Acumen Cloud™

Bidding Competitiveness

Page 27: Acumen Fuse World Tour 2012

// Case Study #2

◦  Importing multiple scheduling platforms

◦  Timeline view

◦  Cost/duration comparison

◦  Driving logic analyzer

◦  Acumen Cloud benchmarking

Fuse modules

// Fuse Demo

Page 28: Acumen Fuse World Tour 2012

//

Page 29: Acumen Fuse World Tour 2012

//

Page 30: Acumen Fuse World Tour 2012

//

Page 31: Acumen Fuse World Tour 2012

//

Page 32: Acumen Fuse World Tour 2012

//

Page 33: Acumen Fuse World Tour 2012

//

Page 34: Acumen Fuse World Tour 2012

//

Page 35: Acumen Fuse World Tour 2012

//

Page 36: Acumen Fuse World Tour 2012

//

Page 37: Acumen Fuse World Tour 2012

//

Page 38: Acumen Fuse World Tour 2012

//

Page 39: Acumen Fuse World Tour 2012

//

Page 40: Acumen Fuse World Tour 2012

// Case Study #2

•  Outcome:

•  Contractor B fastest, cheapest but poorest quality

•  Contractor A cheapest but fundamental logic flaw

•  Contractor C was most expensive but…

•  Had highest quality score

•  Had a true continuous driving path

•  Had sound cash flow

•  Ranked highly with regards to benchmarking

•  Was awarded the contract!

Bidding Competitiveness

Page 41: Acumen Fuse World Tour 2012

// Case Study #3

◦  GasCom

◦  LNG Pipeline & Facility Owner

◦  Early FEED stage

◦  Project Details

◦  Readying for sanction approval

◦  Expected First Gas Date: Dec. 2013

◦  Gas sales contract already established

◦  Using Primavera P6

Schedule Acceleration/Risk Reduction

Realistic Scheduling

Critiqued

The Base

Risk-Adjusted

Optimized

Team-Aligned // S5

// S4

// S3

// S2

// S1

Page 42: Acumen Fuse World Tour 2012

// S1 > S2

◦  Sanction Board Requirements

◦  Risk-adjusted forecast P75

◦  Fuse Schedule Index 75+

◦  Project Status

◦  S1 showing Dec 13 first gas

◦  Risk assessment not yet conducted

Schedule Review

Realistic Scheduling

Critiqued

The Base

Risk-Adjusted

Optimized

Team-Aligned // S5

// S4

// S3

// S2

// S1

Page 43: Acumen Fuse World Tour 2012

// S1 > S2 Schedule Critique

◦  Validated multiple sub-projects

◦  Test to ensure true path to First Gas

◦  Analysis showed break in path around Early Works

◦  Fixing this, First Gas moved to the right by 2 months

◦  Schedule cleanse: further 3 months adjustment

Sound Basis of Schedule

May 16, 2012

Page 44: Acumen Fuse World Tour 2012

// Removal of Logic Redundancy Simplification of Schedule

8%  redundancy  

Removal of redundancy led to a cleaner, more robust schedule

Page 45: Acumen Fuse World Tour 2012

// S1 > S2

◦  S2 First Gas date: May 2014

◦  Schedule Critique Details:

◦  Missing Logic was added

◦  Lags converted to activities

◦  Float analysis

◦  Showed padding of early activities

Summary

Realistic Scheduling

Critiqued

The Base

Risk-Adjusted

Optimized

Team-Aligned // S5

// S4

// S3

// S2

// S1

5  months   S2: May 2014 S1: Dec 2013

Page 46: Acumen Fuse World Tour 2012

// Float Analysis

◦  S1 showed high float in early stage of project

◦  S2 resolved schedule showed the opposite

◦  Early acceleration opportunity went away

GasCom

0  

20  

40  

60  

Q1  2011  

Q2  2011  

Q3  2011  

Q4  2011  

Q1  2012  

Q2  2012  

Q3  2012  

Q4  2012  

Q1  2013  

Q2  2013  

Q3  2013  

Q4  2013  

Q1  2014  

Q2  2014  

Q3  2014  

Q4  2014  S1  Average  Float   S2  Average  Float  

Originally perceived opportunity

for making up lost time through

float absorption in early stage of

project

Resolved schedule not

offering early stage schedule

acceleration

Page 47: Acumen Fuse World Tour 2012

// S2 > S3

◦  Objective:

◦  Determine a P75 First Gas date

◦  Conducted Risk Workshop

Risk Analysis

Realistic Scheduling

Critiqued

The Base

Risk-Adjusted

Optimized

Team-Aligned // S5

// S4

// S3

// S2

// S1

Uncertainty  

Risk  Events  

Schedule  

Page 48: Acumen Fuse World Tour 2012

// GasCom Perception of Risk Exposure Risk Inputs & Outputs

0%  10%  20%  30%  40%  50%  60%  70%  

Team  Percep>on  

Actual  Risk  Hotspots  

Uncertainty Factor Best Case (Optimistic) Worst Case (Pessimistic) Very Conservative 50% 100%

Conservative 75% 105%

Realistic 90% 110%

Aggressive 95% 125%

Very Aggressive 100% 150%

Page 49: Acumen Fuse World Tour 2012

// Risk Insight Risk Inputs

Aggressive  •  Skew  to  the  right  

Conserva>ve  •  Skew  to  the  lef  

Broad  Risk  Range  •  Range  <>  dura>on  

Ques>onable  Range  •  Accidently  includes  risk  events  

No  Risk    • Missed  ranging  

Average  Risk  Range  •  Degree  of  uncertainty  

No  upside  •  Can  only  be  later  

No  Downside  •  Can  only  be  earlier  

Wrong  •  Inputs  don’t  align  

Page 50: Acumen Fuse World Tour 2012

//

Page 51: Acumen Fuse World Tour 2012

// Risk Insight Risk Exposure

High  cri>cality  •  Risk  indicator  

Hidden  cri>cal  paths  •  Unique  insight  

Risk  Hotspots™  •  Risky  &  complex  logic  

Schedule  risk  drivers  •  True  risk  metric  

High  Con>ngency  •  How  much  buffer  needed?  

Average  Risk  exposure  •  Risk  Trending/path  

Page 52: Acumen Fuse World Tour 2012

//

Page 53: Acumen Fuse World Tour 2012

//

◦  P75 risk-adjusted First Gas: Oct 2014

◦  10 months later than board expectations

◦  Identified key risk hot spots

◦  Long Lead procurement items

◦  Hidden path identified

◦  Driven by land acquisition delaying

pipeline early works

S2 > S3 Summary

Realistic Scheduling

Critiqued

The Base

Risk-Adjusted

Optimized

Team-Aligned // S5

// S4

// S3

// S2

// S1

S1: Dec 2013

S2: May 2014 5  

S3: Oct 2014 10  

Page 54: Acumen Fuse World Tour 2012

//

◦  Risk Mitigation:

◦  Response plan identified for key risks

◦  Response plans added to schedule

◦  Assessed cost/benefit of mitigation

◦  $100MM investment to save 1 month

S3 > S4 Getting back to Dec 2013

Realistic Scheduling

Critiqued

The Base

Risk-Adjusted

Optimized

Team-Aligned // S5

// S4

// S3

// S2

// S1

Page 55: Acumen Fuse World Tour 2012

//

◦  Schedule Acceleration details:

◦  LNG Pipeline ready for hookup: Feb 13

◦  LNG Facility ready to receive gas: Nov 13

◦  Focus needed:

◦  Accelerating the LNG facility

◦  Could afford to slow down pipeline/

field work by months…

S3 > S4 Getting back to Dec 2013

Realistic Scheduling

Critiqued

The Base

Risk-Adjusted

Optimized

Team-Aligned // S5

// S4

// S3

// S2

// S1

Page 56: Acumen Fuse World Tour 2012

// LNG Facility

◦  Criteria set drives acceleration

◦  Reduce duration

◦  More resources

◦  Changed calendars

◦  Contractor incentive

◦  Delay Train 2

Acceleration Criteria Set

LNG  Facility  

Script  Objec/ve  “accelerate  Facility  by  6  

months”  

Step  1  Accelerate  Jeoy  construc>on  

Step  2  Delay  Train  2  ac>vi>es  

Step  3  Introduce  6  day  working  week/larger  camp  

Page 57: Acumen Fuse World Tour 2012

// How did this work?

◦  CPM simulation

◦  Critical path focus

◦  Incremental push

◦  Prioritize

◦  Earliest/latest

◦  Longest durations

◦  Least resistance

Fuse 360 Acceleration

Page 58: Acumen Fuse World Tour 2012

//

◦  LNG Facility:

◦  Accelerated sufficiently

◦  No longer the driving path

◦  S4 Deterministic First Gas: Aug 2013

◦  4 months earlier than S1

◦  12 months earlier than S3

◦  P75 risk-adjusted: Feb 2014

◦  S5 Team Buy-in

◦  Final 2 months achieved through more

aggressive mitigation

S3 > S4 > S5 Summary

Realistic Scheduling

Critiqued

The Base

Risk-Adjusted

Optimized

Team-Aligned // S5

// S4

// S3

// S2

// S1

Page 59: Acumen Fuse World Tour 2012

// GasCom Case Study

◦  Fully vetted, bought-into schedule

◦  Risk-adjusted

◦  LNG Facility accelerated to align with pipeline

◦  Mitigation plan sponsored by board

◦  Sanction awarded!

The Result

S4: Accelerated Aug 1 2013

S1: Target 1st Gas Dec 1 2013

S2: Resolved Schedule May 1 2014

S3: Risk-Adjusted Oct 1 2014

P75 S4: Feb 2014

S5: Mitigated Dec 1 2013

Page 60: Acumen Fuse World Tour 2012

// GasCom First Gas Dates

0  

1  

2  

3  

4  

5  

6  

7  

8  

9  

10  

S1  -­‐  base   S2  -­‐  resolved   S3  -­‐  risk-­‐adjusted   S4  -­‐  accelerated   S5  -­‐  mi>gated  

0

5

10

2 0

P75  Sche

dule  Delay  From  Dec  2013  1st  G

as  (m

onths)  

Scenario  

Resolved, risk-adjusted,

accelerated, mitigated

Evolution of Schedule Model

May 16, 2012

60

Page 61: Acumen Fuse World Tour 2012

// Case Study #3

ü  Float analysis

ü  Risk Metrics

ü  Fuse 360

Fuse Modules

// Fuse 360 Demo

Page 62: Acumen Fuse World Tour 2012

// Acceleration Efficiency™

◦  2 day project acceleration

◦  Requires 2 days of reduction

◦  Acceleration Efficiency =2/2 100%

◦  2 day project acceleration

◦  Requires 2 days of reduction

◦  Acceleration Efficiency=2/3 67%

Example  2  

2 day project acceleration

2 day project acceleration

2 day activity reduction 2 day activity

reduction

1 day activity reduction 3

Measure of Acceleration Effort

Example  1  

Page 63: Acumen Fuse World Tour 2012

// Case Study #4: Measuring Project Performance

◦  Traditional measures include: ◦  Earned value: heavy time investment to implement

◦  Earned schedule: similar to EV

◦  % complete: what does this really tell us?

◦  Ahead/behind baseline: too granular a scale…

◦  Baseline Compliance™ ◦  Determine how close schedule is executed against baseline

◦  Measure of change during planning phase

◦  Measure of well the plan is being executed

◦  More than just date comparison

◦  Looks at period-compliance

Baseline Compliance™

May 16, 2012

Page 64: Acumen Fuse World Tour 2012

// Baseline Compliance Index™

Examines  how  many  ac>vi>es  fell  within  the  expected  

repor>ng  period  

Page 65: Acumen Fuse World Tour 2012

// Developing Baseline Compliance Index

Page 66: Acumen Fuse World Tour 2012

// Finish Compliance Index™

0%  20%  40%  

60%  

80%  

100%  

May 16, 2012

Page 67: Acumen Fuse World Tour 2012

//

Page 68: Acumen Fuse World Tour 2012

//

Page 69: Acumen Fuse World Tour 2012

// Better Planning Drives Project Success Proven Correlation

0%  

10%  

20%  

30%  

40%  

50%  

60%  

70%  

80%  

90%  

100%  

0%   10%   20%   30%   40%   50%   60%   70%   80%   90%   100%  

Prob

ability  of  O

n-­‐Time  Co

mple/

on  

Fuse  Schedule  Index™  

Page 70: Acumen Fuse World Tour 2012

//

Page 71: Acumen Fuse World Tour 2012

//

More information: White papers: www.projectacumen.com

Software Trial: www.projectacumen.com/trial

Twitter: @projectacumen

Email: [email protected]