Activities and organization during LS1 Site Engineering group - GS department

11
Activities and organization during LS1 Site Engineering group - GS department Luigi Scibile GS-SE 12.06.2012 Special LS1 day on 12 June 2012, EDMS: 1224239 1

description

Activities and organization during LS1 Site Engineering group - GS department. Luigi Scibile GS-SE. Agenda. Activities structure GS-SE Planned Items GS-SE group contributions Organization Closing remarks. Activities(1 /3). - PowerPoint PPT Presentation

Transcript of Activities and organization during LS1 Site Engineering group - GS department

Page 1: Activities  and organization during  LS1 Site  Engineering  group - GS department

1

Activities and organization during LS1Site Engineering group - GS department

Luigi Scibile GS-SE

12.06.2012 Special LS1 day on 12 June 2012, EDMS: 1224239

Page 2: Activities  and organization during  LS1 Site  Engineering  group - GS department

Special LS1 day on 12 June 2012, EDMS: 1224239 2

Agenda

• Activities structure

• GS-SE Planned Items• GS-SE group contributions

• Organization • Closing remarks

12.06.2012

Page 3: Activities  and organization during  LS1 Site  Engineering  group - GS department

Special LS1 day on 12 June 2012, EDMS: 1224239 3

Activities(1/3)• The works are structured in three types of activities:

34 plan items - 76 group contributions – 25 big, 42 medium, 45 small

– Large civil engineering works for the realisation of new buildings, roads and shielding structures (for example, the works for increasing the radiation shielding on the PS extraction region, New building and shaft EAR2 in nTOF, etc.)

– Maintenance of the infrastructures only accessible during the long shutdowns (for example: tunnel floors and drains, underground sanitary equipment, roofs of operational buildings, etc.)

– Civil engineering works required by equipment groups in their activities during the long shutdown (for example: creation of slabs, excavation of trenches, concrete coring, shielding walls, etc.).

12.06.2012

Page 4: Activities  and organization during  LS1 Site  Engineering  group - GS department

Special LS1 day on 12 June 2012, EDMS: 1224239 4

Activities(2/3)• Large civil engineering works (1/2):

– NEW BUILDINGS• HIE – ISOLDE cooling : New building and related facitilies 198-199• New building and shaft EAR2 in nTOF• ELENA - Extension of blg 193• New LHCb control room and data center• CMS SL53 (new offices, conference room, visitors gallery)• LIU-SPS 200 MHz RF Upgrade, New RF Building BAF3 - New building construction

follow-up• Construction of blg 774• NEW BUILDING 107

12.06.2012

Page 5: Activities  and organization during  LS1 Site  Engineering  group - GS department

Special LS1 day on 12 June 2012, EDMS: 1224239 5

Activities(3/3)• Large civil engineering works (2/2):

– EXTENSIONS/RENOVATIONS• CCC repowering - CE work package bdg 874• PS access - CE works for the new access system for the PS• ISOLDE - extension of target storage area (bdg 179)• Renovation of blg 192• Facade carbonatation treatment - 168-20-21; 30-112• B38 works following safety inspection

– ROADS/SHIELDINGS• Civil Engineering for Increasing the Radiation Shielding on the Route Goward

Passage over the PS• Civil Engineering for Increasing the Radiation Shielding on the PS extraction

region

12.06.2012

Page 6: Activities  and organization during  LS1 Site  Engineering  group - GS department

Special LS1 day on 12 June 2012, EDMS: 1224239 6

Example - Shielding Septum

12.06.2012

Page 7: Activities  and organization during  LS1 Site  Engineering  group - GS department

Special LS1 day on 12 June 2012, EDMS: 1224239 7

Example – CE works PS access

12.06.2012

Page 8: Activities  and organization during  LS1 Site  Engineering  group - GS department

Special LS1 day on 12 June 2012, EDMS: 1224239 8

Organization

12.06.2012

4

1

2

3

Page 9: Activities  and organization during  LS1 Site  Engineering  group - GS department

Special LS1 day on 12 June 2012, EDMS: 1224239 9

Organization

12.06.2012

Page 10: Activities  and organization during  LS1 Site  Engineering  group - GS department

Special LS1 day on 12 June 2012, EDMS: 1224239 10

Pending

• Some activities are still pending waiting for clarifications on the requirements.

• Examples:– Rebuild the access road of BA buildings. – Works on the cranes.– Metallic structures.

12.06.2012

Page 11: Activities  and organization during  LS1 Site  Engineering  group - GS department

Special LS1 day on 12 June 2012, EDMS: 1224239 11

Closing remarks

12.06.2012

• The large civil engineering works have been planned and the preparation of the call for tenders are in progress.

• The last projects that have been approved (SL53 and LHCb control room) will need some extra effort to fit them in the schedule.

• For the small works, a three months notice would be ideal to organize the intervention of the contractors.

• The current list of activities can JUST fit with the available resources (~50FTE) with accurate balancing.