Activated Sludge Design Startup Operation Monitoring

download Activated Sludge Design Startup Operation Monitoring

of 52

Transcript of Activated Sludge Design Startup Operation Monitoring

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    1/52

    Activated Sludge Design, Startup, Operation, Monitoringand Troubleshooting

    Ohio Water Environment Association Plant Operations Workshop Columbus, Ohio

    September 1, 2010

    Phil Anderson Operations Specialist

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    2/52

    Design - Activated Sludge Design Team Treatment Goals Activated Sludge Processes Engineering Standards

    Preliminary Treatment Tertiary Treatment

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    3/52

    Treatment Goals BOD Removal

    Dissolved wastes are consumed as food by theactivated sludge microbes and converted to biomass,water, carbon dioxide, and other gases

    Nitrification The process through which ammonia is oxidized tonitrite and nitrate

    Denitrification

    A process by which nitrates and nitrites are convertedto gaseous end products, primarily nitrogen gas.

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    4/52

    Activated Sludge Processes

    Conventional CBOD Removal Plug or Step Feed

    Single-Stage NitrificationOxidation Ditch - Vertical LoopReactor Extended AerationMBR

    BNR

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    5/52

    Additional Processes Preliminary Treatment

    Screening

    Grit Removal Tertiary Treatment

    Filters Solids Handling Recycle Flows

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    6/52

    Design EngineeringStandards

    Design of Municipal WastewaterTreatment Plants WEF Manual of

    Practice No. 8

    Wastewater Engineering, Treatment ,Disposal, ReuseMetcalf & Eddy

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    7/52

    Design Engineering Standards

    Recommended Standards for Wastewater Facilities

    Policies for the Design, Review, and Approval of Plans andSpecifications for Wastewater Collection and Treatment

    Facilities

    MEMBER STATES AND PROVINCEIllinois Indiana Iowa Michigan Minnesota Missouri

    New York Ohio Ontario Pennsylvania Wisconsin

    Ten States Standards

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    8/52

    Process Design

    Physical Aeration Tank Capacity - lbs.

    CBOD/1000 CF of Aeration Temperature Summer/Winter Final Settling Circular Center Feed or

    Peripheral Feed

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    9/52

    Process Design

    Chemical

    Ammonia Loading - Nitrification Phosphorous Loading & Removal pH & Alkalinity

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    10/52

    Process Design

    Biological CBOD Loading 15lbs 40 lbs D.O. in Aeration - 1.1 CBOD 4.6 NH3 MLSS, MLVSS, RAS

    F/M Ratio - 0.5 1.0 2.0 MCRT Days

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    11/52

    NitrificationNH3 NO2- NO3-

    Nitrosomonas, Nitrobacter Aerobic process (in the presence of DO) 4.6 lbs O 2 required per lb ammonia-

    nitrogen

    7.14 lb alkalinity is consumed per poundof ammonia nitrogen

    pH sensitive with optimal range between7.5 and 8.6

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    12/52

    DenitrificationNO3- NO2- NO N2O N2

    Anoxic process (not in the presence of DO) Nitrification can decrease pH Denitrification recovers 3.57 lb alkalinity per lb of

    nitrogen removed

    DO is consumed by nitrification anddenitrification recovers 2.9 lb per lb of nitrogenremoved

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    13/52

    Plant Startup Contractor Wants to push to startup What are Ohio EPA expectations? Manufacturer Checkout Operator Training Are You Ready What additional processes are available

    Do you and your Engineer have a ProcessControl Plan

    Are you seeding the aeration tanks?

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    14/52

    Plant Operation Summer/Winter Dry Weather/Wet Weather

    DO Control RAS Rate - % 0f Influent Flow Chemical Feed Wasting Sludge Biological & Chemical

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    15/52

    Summer Verses WinterSummerMCRT - 22.17 days

    F/M Ratio - 0.13BOD Loading Rate - 16.5lbs./1,000 cf

    Required MCRT No.2 - 7.6 days

    DT for BOD Oxidation - 13.20hoursDT for NH3 Oxidation - 2.64hours

    Aeration Tanks Required - 4.0

    MLSS - 3,000 mg/lMLVSS - 2,100 mg/l

    WinterMCRT - 35.47 days

    F/M Ratio - 0.08BOD Loading Rate - 16.5lbs./1,000 c.f.

    Required MCRT No.2 - 13.7

    daysDT for BOD Oxidation - 13.15hoursDT for NH3 Oxidation = 2.71hours

    Aeration Tanks Required - 4.0

    MLSS - 4,800 mg/lMLVSS - 3,360 mg/l

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    16/52

    Plant Operation Summer/Winter Dry Weather/Wet Weather

    DO Control RAS Rate - % 0f Influent Flow Chemical Feed Wasting Sludge Biological & Chemical

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    17/52

    Plant Monitoring Regular Rounds Visual Aeration Tanks & FST

    Blowers/Aerators RAS Pumps

    Clarity of the Effluent

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    18/52

    Plant Monitoring SCADA Trending Flow, DO, ORP, pH Regular Rounds Visual

    Trending Instruments - Flow, DO,ORP, pH

    Lab Data MLSS, RAS, Settling Microbiology

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    19/52

    Troubleshooting Foaming Bulking

    Solids Loss Turbid Effluent Odor No CBOD or Ammonia Removal

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    20/52

    Holy Crap!!

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    21/52

    Observation of Settlometer Test

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    22/52

    Characteristic Sludge Settling

    0

    200

    400

    600

    800

    1000

    0 30 60 90 120 150 180

    Time (minutes)

    S S V FastNormal

    Slow

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    23/52

    Length of Settleometer Test

    Normal - 30 minutes to 2hours - until completecompaction

    Extended - until thesludge begins to rise

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    24/52

    Look Under the Microscope

    http://www.usabluebook.com/showproduct.aspx?productid=277108
  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    25/52

    The Bugs - Good/Bad/Ugly

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    26/52

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    27/52

    Nocardia

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    28/52

    Microthrix parvicella

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    29/52

    Filaments 1851 and 0041

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    30/52

    Filament Type 0092

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    31/52

    Filament type 0092

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    32/52

    WWTP: WWTP By:

    Phil Anderson [email protected] Summer Summary

    Operation: Activated Sludge Date: Summer 2009 3,000 MLSS, mg/l MCRT 7.30 days

    20.0 Degrees C F/M Ratio 0.24

    MEAN CELL RESIDENCE TIME (MCRT) 7.1 pH BOD Loading Rate 33.54lbs./1,000 c.f.

    5.0 D.O. Aeration Required MCRT No.1 3.61 days

    20.0 Influent Ammonia 1.7 Effluent Ammonia Required MCRT No.2 3.93 days

    INPUT DATA: 6 Aeration Tanks On Line DT for BOD Oxidation 6.02hours

    a 2.827 (MG) - Aeration tank volume (total) 0.471 Aeration Tank MG Each DT for NH3 Oxidation 1.49hours

    b 2,250 (mg/l) - Mixed liquor VOLATILE suspended solids (MLVSS) Aeratio n Tank Vol Req uired 2.38MG

    c 0.033 (MGD) - Daily flowrate of waste activated sludge (WAS) [See below] Aeratio n Tank s Requir ed 5.05

    d 10,000 (mg/l) - WAS suspended solids Aeratio n Tank s On Line 6.00

    e 7.600 (MGD) - Plant flow MLSS 3,000mg/l

    f 10 (mg/l) - Effluent suspended solids MLVSS 2,250 mg/l

    Nitrifiers (8% of MLVSS) 180 mg/l

    SUPPLEMENTAL CALCULATIONS (MLVSS):

    a 3,000 (mg/l) Assumed mixed liquor suspended solids (MLSS) EFF LIMIT

    b 75.0 (%) - Assumed percent volatile CBOD Weekly 15 mg/l

    2,250 (mg/l) - MLVSS TSS Weekly 18 mg/l

    WASTE SLUDGE VOLUME: Fecal Weekly 2,000 (S Only)

    a 0.70 Assumed sludge yield (lb. SS generated/lb. BOD removed) Ammonia WK 1.7 mg/l (S Only)

    b 7.600 (MGD) - Plant flow Ammonia Winter WK NA

    c 200 (mg/l) - BOD concentration entering aeration tanks P Weekly 1.5 mg/l

    d 10 (mg/l) - BOD concentration following settling

    e 8,430 lbs. biological sludge/day

    f 10.0 (mg/l) -chemical sludges produced

    h 634 lbs. chemical (Fe/AL) sludge generated/day

    i 9,064 Total lbs. WAS/day

    j 10,000 (mg/l) - Assumed WAS concentration (Note: 10,000 mg/l = 1.0%)

    k 0.109 (MGD) -W aste activated sludge quantity

    MCRT 7.30 days F/M Ratio = 0.24

    BOD Loading Rate = 33.5 lbs./1,000 c.f.

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    33/52

    WWTP: WWTP By:Phil Anderson [email protected] Winter Summary

    Operation: Activated Sludge Date: Winter 4,500 MLSS, mg/l MCRT 10.95 days

    11.0 Degrees C F/M Ratio 0.16

    MEAN CELL RESIDENCE TIME (MCRT) 7.0 pH BOD Loading Rate 33.54lbs./1,000 c.f.

    4.0 D.O. Aeration Required MCRT No.1 12.00 days

    20.0 Influent Ammonia 4.0 Effluent Ammonia Required MCRT No.2 8.66 days

    INPUT DATA: 6 Aeration Tanks On Line DT for BOD Oxidation 10.96hours

    a 2.827 (MG) - Aeration tank volume (total) 0.471 Aeration Tank MG Each DT for NH3 Oxidation 2.13hours

    b 3,375 (mg/l) - Mixed liquor VOLATILE suspended solids (MLVSS) Aeratio n Tank Vol Req uired 3.47MG

    c 0.109 (MGD) - Daily flowrate of waste activated sludge (WAS) [See below] Aeratio n Tank s Requir ed 7.36

    d 10,000 (mg/l) - WAS suspended solids Aeratio n Tank s On Line 6.00

    e 7.600 (MGD) - Plant flow MLSS 4,500mg/l

    f 10 (mg/l) - Effluent suspended solids MLVSS 3,375 mg/l

    Nitrifiers (8% of MLVSS) 270 mg/l

    SUPPLEMENTAL CALCULATIONS (MLVSS):

    a 4,500 (mg/l) Assumed mixed liquor suspended solids (MLSS) EFFLUENT LIMITS

    b 75.0 (%) -Assumed percent volatile CBOD Weekly 15 mg/l

    3,375 (mg/l) - MLVSS TSS Weekly 18 mg/l

    Fecal Weekly 2,000 (S Only)

    WASTE SLUDGE VOLUME: Ammonia WK 1.7 mg/l (S Only)

    a 0.70 Assumed sludge yield (lb. SS generated/lb. BOD removed) Ammonia Winter WK NA

    b 7.600 (MGD) - Plant flow P Weekly 1.5 mg/l

    c 200 (mg/l) - BOD concentration entering aeration tanks

    d 10 (mg/l) - BOD concentration following settling

    e 8,430 lbs. biological sludge/day

    f 10.0 (mg/l) -chemical sludges produced

    h 634 lbs. chemical (Fe/AL) sludge generated/day

    i 9,064 Total lbs. WAS/day

    j 10,000 (mg/l) - Assumed WAS concentration (Note: 10,000 mg/l = 1.0%)

    k 0.109 (MGD) -W aste activated sludge quantity

    MCRT 10.95 days F/M Ratio = 0.16

    BOD Loading Rate = 33.5 lbs./1,000 c.f.

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    34/52

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    P e r c e n t

    ( % )

    MCRT (Days)

    Figure 1 Effect of MCRT On Nitrification

    Nitrification Efficiency %

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    35/52

    0.00

    0.10

    0.20

    0.30

    0.40

    0.50

    0.60

    1 2 3 4 5 6 7 8 9 10

    F / M

    R a t i o

    MCRT, Days

    Figure 2 Relationship Between MCRT and F/M Ratio

    Ratio

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    36/52

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    20

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

    A m m o n n i a , m g /

    l

    Time (in 1/4 Hours)

    Figure 3 Ammonia Removal vs Time

    Ammonia

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    37/52

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    P e r c e n t

    ( % )

    Temperature (C)

    Figure 4 Effect of Temperature On Nitrification

    Removal Rate %

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    38/52

    0.00

    0.02

    0.04

    0.06

    0.08

    0.10

    0.12

    1 2 3 4 5 6

    L b . N

    H / L b . M L S S / D a y

    Dissolved Oxygen

    Figure 5 Effect of D.O. on Nitrification

    NH3 Oxidation Rate

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    39/52

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    1 2 3 4 5 6 7 8 9 10

    P r e c e n t

    ( % )

    pH

    Figure 6 Effect of pH on Nitrification

    Maximum Nitrification Rate (%)

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    40/52

    0

    50

    100

    150

    200

    250

    300

    350

    400

    1 2 3 4 5

    A l k a l i n i t y

    m g /

    l

    Influent Ammonia (mg/l x 10)

    Figure 7 Alkalinity Used in Nitrification

    Alkalinity Required mg/l

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    41/52

    Maumee River WWTP

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    42/52

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    43/52

    DO Probe

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    44/52

    Single Stage Blower

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    45/52

    Center Feed FST

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    46/52

    Center Feed FST

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    47/52

    Peripheral Feed FST

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    48/52

    Peripheral Feed FST

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    49/52

    Center Feed FST

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    50/52

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    51/52

    [email protected]

    QUESTIONS???

  • 8/11/2019 Activated Sludge Design Startup Operation Monitoring

    52/52