ACS STATUS Linda Smith (thanks to David Golimowski for providing the slides)

8
ACS STATUS QuickTime™ and a TIFF (Uncompressed) decompressor are needed to see this picture. Linda Smith (thanks to David Golimowski for providing the slides)

Transcript of ACS STATUS Linda Smith (thanks to David Golimowski for providing the slides)

Page 1: ACS STATUS Linda Smith (thanks to David Golimowski for providing the slides)

ACS STATUS

QuickTime™ and aTIFF (Uncompressed) decompressor

are needed to see this picture.

Linda Smith

(thanks to David Golimowski for providing the slides)

Page 2: ACS STATUS Linda Smith (thanks to David Golimowski for providing the slides)

ACS was repaired in EVA 3: four circuit boards in CEB were replaced and a new LVPS was installed.

Page 3: ACS STATUS Linda Smith (thanks to David Golimowski for providing the slides)

Part 1: WFC CEB-R FT

• Criterion: At least one WFC CCD is operational and can be read out through at least one amplifier

Result: Both CCDs and all four amps are operational

• Criterion: At least one WFC CCD amplifier operates with RN~10 e- Result: All amps operate with read noise 3.0–3.6 e- (prescan only) in

DSI mode assuming gain=1

• The WFC TECs can cool focal plane to its max set point (-66.7 C) while operating at < max power, thus operational T < -81 C is achievable (Passed)

• Shutter operates (Passed)

• FW2 can be rotated and FW1 left in open position (Passed)

• WFC commanding and data readout, storage, and dump are possible (Passed)

Page 4: ACS STATUS Linda Smith (thanks to David Golimowski for providing the slides)

Part 1: WFC CEB-R FT

Four-amp bias frame (DSI)Bias level: 2260-2600 DNRN: 3.0-3.6 e- (prescan) 3.9-4.4 e- (image area)

Four-amp lamp frame (F814W, DSI)Signal level: 22000-26000 DNNearly identical to Jan 2007 flat!

Page 5: ACS STATUS Linda Smith (thanks to David Golimowski for providing the slides)

Part 2: ACS-R System FT

• Initial execution halted due to HRC electrical short

* +35V and +15V did not come up properly & backpower current was higher than expected (~2.2 A vs. ~1.2-1.4 A)

• Reran System FT with all HRC commanding deleted

* WFC DSI images showed same RN as in CEB-R FT* WFC C&S images showed pre-Jan 2007 RN levels* SBC dark exposure improperly truncated but nevertheless

demonstrated that valid science image can be acquired and that SBC functionality has been preserved

• Two baseline O-mode images were obtained to verify oscilloscope functionality (not part of formal pass/fail criteria)

Page 6: ACS STATUS Linda Smith (thanks to David Golimowski for providing the slides)

Part 2: ACS-R System FT

• Criterion: At least one WFC CCD is operational and can be read out through at least one amplifier

Result: Both CCDs and all four amps are operational

• Criterion: At least one WFC CCD amplifier operates with RN~10 e- Result: All amps operate with read noise 3.0–3.5 e- (DSI) and 4.0–

4.6 e- (C&S)

• The WFC TECs can cool focal plane to its max set point (-66.7 C) while operating at < max power, thus operational T < -81 C is achievable (Passed)

• Shutter operates (Passed)

• FW1 can be rotated and FW2 left in open position (Passed)

• WFC commanding and data readout, storage, and dump are possible (Passed)

Page 7: ACS STATUS Linda Smith (thanks to David Golimowski for providing the slides)

Part 2: ACS-R System FT

Four-amp bias frame (C&S)Bias level: 4750-5000 DNRN: 4.0-4.6 e- (prescan) 4.8-5.5 e- (image area)

SBC, ~35 sec flat, -50 V on MCP Signal level: 0 DNNo interference or noise detected

Page 8: ACS STATUS Linda Smith (thanks to David Golimowski for providing the slides)

Thumbs-Up Around the World (and Above It!)