Presentation - Acquisition of Interest in Belo Monte Hydro Plant
Acquisition of partial interest
description
Transcript of Acquisition of partial interest
![Page 1: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/1.jpg)
![Page 2: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/2.jpg)
•Acquisition of partial interest
![Page 3: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/3.jpg)
![Page 4: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/4.jpg)
Does USPAP require a definition of the rights
being appraised?Std Rule 1-2(e)
Identify the characteristics of the property that are relevant to the type and definition of value and intended use of the appraisal, including:
(ii) The real property interest to be valued
![Page 5: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/5.jpg)
SCOPE OF WORK RULE
DISCLOSURE OBLIGATIONS
The report must contain sufficient information to allow intended users
to understand the scope of work performed.
![Page 6: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/6.jpg)
CONCLUSION
Easements, i.e. the partial interests or rights being acquired, must be clearly stated and understood to
produce a credible report.
![Page 7: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/7.jpg)
EASEMENTS
Physical Characteristics
•Surface
•Subsurface
•Above Surface
Duration
•Permanent
•Temporary
![Page 8: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/8.jpg)
TYPICAL R/W EASEMENTS
•Construction (usually temporary)
•Drainage (permanent and/or temporary)
•Utility (usually permanent)
•Slope (permanent or temporary)
•Sidewalk (usually permanent)
![Page 9: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/9.jpg)
DEFINING the EASEMENTS(rights being acquired)
![Page 10: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/10.jpg)
Temporary Construction Easement - “Provides work area for the temporary use of land outside normal right of way that is necessary for construction of the project. The use of this land will be for a specified time period and the purpose of the TCE must be clearly shown on the plans. Permanent grading changes are not normally performed on areas acquired as TCE.” - as defined by the West Virginia Department of Transportation – Division of Highways – Design Directive (DD-301 Right of Way Plans) - dated April 1, 2004.
![Page 11: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/11.jpg)
In this case the purpose of the TCE is not clearly shown on the ROW plans as required by the WV DOT. For this appraisal, the purpose of the TCE is to tie the grade of the proposed ROW to the existing grade at the subject property. The TCE will allow for construction and for maneuvering of equipment for the duration of the TCE. The rights being acquired by the WVDOT are for the full use and enjoyment of the property for the duration of the temporary easement - the rights remaining to the fee owner consist of the right to cross the property for reasonable access purposes so long as the use of the easement is not impeded.
![Page 12: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/12.jpg)
Permanent Drainage Easement (PDE) – “Said Permanent Drainage easement in perpetuity is for the installation and maintenance of drainage facilities, and for all purposes for which the DEPARTMENT is authorized by law to subject same. The Department and its agents or assigns shall have the right to construct and maintain in a proper manner in, upon and through said premises a drainage facility with all necessary pipes, poles and appurtenances, together with the right at all times to enter said premises for the purpose of inspecting said drainage facility and making all necessary repairs and alterations thereon; together with the right to cut away and keep clear of said drainage facility all trees and other obstructions that may in any way endanger or interfere with the proper maintenance and operation of the same with the right at all times of ingress, egress and regress. It is understood and agreed that the Department shall have the right to construct and maintain the cut and/or fill slopes in the above-described permanent drainage easement area(s). It is further understood and agreed that Permanent Drainage shall be used by the Department for additional working area during the above described project.” - as defined by the North Carolina Department of Transportation form FRM7-N, Titled “Drainage Easement”
![Page 13: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/13.jpg)
In this case, the purpose of the PDE is not clearly shown on the ROW plans. For this appraisal, it is assumed that the purpose of the PDE is to facilitate drainage. The PDE will allow for construction of drainage improvements and for maneuvering of equipment within the easement into perpetuity. In our opinion, the rights being acquired by the NCDOT are for the full use and enjoyment of the property for drainage purposes - the rights remaining to the fee owner consist of the right to use the property for density calculation and land use matters and the liability of continuing to pay real property taxes, however the owner cannot physically use the property in any manner other than crossing over it as long drainage flow is not impeded in any way.
![Page 14: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/14.jpg)
The City of Charlotte has not provided a definition for a sidewalk and utility easement. As a result we have defined it as follows: A taking which provides an area for the construction and maintaining of a sidewalk and public utilities. It is permanent in nature and grants the City of Charlotte the rights for the full use and enjoyment of the property for maintaining the sidewalk and any utilities installed. The rights remaining to the fee owner consist of the right to cross the property for access purposes so long as the use of the easement is not impeded.
SIDEWALK AND UTILITY EASEMENT
![Page 15: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/15.jpg)
The City of Charlottev.
Anthony R. Combs, et. al.
![Page 16: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/16.jpg)
The City Appraiser:“…that he had not appraised the
entire property before and after the TCE, based on his experience the TCE’s do not adversely affect the
remainder of the property.”
![Page 17: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/17.jpg)
Property Owners Appraiser:“…believing that the TCE had a
material impact on the entirety of the Combs’ property, not just the 330 square feet subject to the TCE…”
![Page 18: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/18.jpg)
“As for the Combs’ property, although it was acknowledged that certain improvements
had been damaged, …his valuation did not include any assessment of whether the remainder of the Combs’ property was
affected in any other respect by the temporary taking.
![Page 19: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/19.jpg)
“… because (the appraiser) based his valuation of the TCE on his experience that
such temporary takings do not affect the remainder of the condemnee’s property
rather than an actual assessment that the Combs’ property outside the TCE was
affected, his method of proof lacked sufficient reliability.”
![Page 20: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/20.jpg)
![Page 21: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/21.jpg)
![Page 22: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/22.jpg)
![Page 23: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/23.jpg)
RECENT ISSUES
![Page 24: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/24.jpg)
![Page 25: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/25.jpg)
![Page 26: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/26.jpg)
![Page 27: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/27.jpg)
TERM of the TCE
•States (DOT) requesting the term of the temporary easement not be stated in the appraisal report
•Does this violate USPAP?
•Implement the JER (Law or Regulation?)
![Page 28: Acquisition of partial interest](https://reader033.fdocuments.us/reader033/viewer/2022061517/56813aea550346895da3507b/html5/thumbnails/28.jpg)
DESIGN/BUILD?