Acid Roundtable 2013 Scottsdale - H2SO4h2so4.com.br/downloads/RoundTable-EUA-2013/Outotec... ·...
Transcript of Acid Roundtable 2013 Scottsdale - H2SO4h2so4.com.br/downloads/RoundTable-EUA-2013/Outotec... ·...
Acid Roundtable 2013 Scottsdale
A double- track road: acid plant size (The Mouse and the Elephant)
Peter Ernst, Head of Sulphuric Acid Departement
The Mouse and the Elephant?
?
?
The Mouse and the Elephant!
5000 t/d
250 t/d
...when it comes to plant size, it needs to be considered: § Economics § Design
§ Process § Mechanical
§ Supply & Construction § Fabrication § Construction § Logistic
§ Operation & Commissioning § Example: 250 tpd „skid“ plant vs 5,000 tpd „Mega“ plant
...from small to large
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1971
19
72
1973
19
74
1975
19
76
1977
19
78
1979
19
80
1981
19
82
1983
19
84
1985
19
86
1987
19
88
1989
19
90
1991
19
92
1993
19
94
1995
19
96
1997
19
98
1999
20
00
2001
20
02
2003
20
04
2005
20
06
2007
20
08
2009
20
10
Capacity (Tpd Mh)
Incitec Pivot (WMCF)
Vale (Goro Nickel)
(Chart based on OUTOTEC reference list; S and met. Gas based)
3 x 5,000 tpd Ma‘aden Complex
Development of plant sizes
Economical impact
0
20
40
60
80
100
120
140
160
180
200
0 0.5 1 1.5 2 2.5 3
Cos
t [%
]
Plant Size
Economical impact
250 tpd (tailored) 5,000 tpd
Standarization vs Customization
Capex vs
Operational flexibility/availability
250 tpd (standard, skid)
5,000 tpd
Eng.
Supply
Constr.
Eng.
Supply
Constr.
Eng.
Supply
Constr.
§ Process Design § Optimization of process conditions, e.g.
SO2-content
§ Optimization of process conditions of equipment/plant sections
§ Mechanical Design § Size limitations for certain equipment due
to mechanical limitations § Different behaviour of process equipment
§ Gas and liquid distribution challenges
§ Flow dynamics differ with increased sizes
Design
Impact of SO2 concentration
Supply & Construction § Fabrication
§ Degree of pre-fabrication limited by size/weights
§ Lead times for material
§ Structural integriy decrease while fabrication tolerances increase
§ Transportation § Allowable dimensions re port facilities, land
transportation
§ Construction § Availability and quality of constr. equipment and
manpower
§ Infrastructure (e.g. camp accomodation, sufficient local fabrication areas, work-shops)
Evaluation of pre-fabrication vs site fabrication
Operation & Commissioning
§ Large plants offer different concepts for equipment/units
§ Usually different production buffer concepts (day
vs week) § Larger distances (....in case of troubles)
§ Lager sizes show different plant behaviour § Learning Tools, eg. dynamic training simulator
Learning Tools
§ Dynamic Plant Simulator § Basic Operator training
§ Familiarize with „new“ plant
§ Appropriate reactions to process upsets
§ Facilitate commissioning
Commissioning Experience
1500
2000
2500
3000
3500
4000
4500
5000
0 5 10 15 20 25 30 35 40
t/d
Days
Plant 1
Commissioning Experience
1500
2000
2500
3000
3500
4000
4500
5000
0 10 20 30 40 50 60
t/d
Days
Plant 1 Plant 2
Commissioning Experience
1500
2000
2500
3000
3500
4000
4500
5000
0 10 20 30 40 50 60 70
t/d
Days
Plant 1 Plant 2 Plant 3
Example – Plant Concept
Size/Type 250 tpd/skid plant 3 x 5,000 tpd Eng./ Standard pre-design (red. of cost ) Customized/tailored Clients request Partly considered/low flexibility Incorporated/high flexibility Fabrication Prefabricated Site fabrication/prefabricated
(Technology center) (global sourcing) Transport/ Standard container Highly complicated logistics Construction Minimized (red. local resorces) Maximized (all local res. needed) Maintenance Standarized components/ Highly customized equipment
sub-systems
Example – Plant Concept
Drying and absorption Section
Converter Section
Drying and absorption Section
Converter Section
S-melting/ Filtration
S-melting/ Filtration
Example – Plot plan
120m
90m
Example – Plot plan
120m
90m 31m
20m
Above ground S-melter
- Capacity: 80 t/h at maximum - Heating coils removable - Easy access for maintenance and cleaning of tank - Integrated pre-coating
compartment
Sulphur filter and storage - Main „leaf-type“ filter - Additional polishing filter - Day storage tank
Sulphur melting and Filtration Neither large nor small plants have „special“ requirements
Example – Combustion Concept
Drying Tower
Combustion Furnace & Waste Heat Boiler
Small sized plants follow „conventional“ plant design Specific features for large sized plants: § Combustion Concept:
§ Sulphur will be combusted at 18 vol.-% SO2 and ≈1.600 °C
§ SO2 gases will be cooled in water tube boiler (WHB)
§ Additional air will be mixed to SO2 gas after WHB to achieve required O2/SO2 ratio
Example – Combustion Concept Specific features for large sized plants: § Boiler Concept:
§ ~1700 °C gas temperature § > 3500 mtpd § References in power plants
(up to 2000 °C) § All sizes can be realized with single
boiler § Superheater or economizer
elements applies to boiler concept (e.g. temperature control by pre- superheater)
§ Cold bypass possible
§ Burner system: § Luro II burner
§ Spinning cup design,
§ Capacity: up to 35 t/h per burner
§ Operating range: 15 – 110 %
§ Efficient operation (no steam leaks etc)
Example – Absorption Section
Specific features for large sized plants: • Tower design according to „conventional“ plants:
• Bricklined towers • Conservative Packing (>3.5 m) • Standard distributor • Common acid system, sea water coolers
• Maximum tower diameter limited by flow patterns and mechanical limitations; larger capacities would require different design.
Example – Absorption Section
Specific features for small sized plants: • Tower design limited by „container“ dimensions:
• Venturi Absorber design • Seperate casing for Candle filters (could serve as
pump tank) • Material of construction: SS310 / SX • Common acid system • Acid cooler options: anodic protected s&t or SX cooler
Example – Converter Section
Specific features for large sized plants: § Converter fully welded stainless steel design from 304H, 321H
§ Outside diameter of converter of 17 m
§ Integration of internal heat exchangers (up to three internal heat exchanger) into converter
§ First pass preferred on top
§ Radial gas distribution for 1st and 4th pass
Example – Converter Section
Specific features for small sized plants: § Converter dimension limited by container size
§ Fully welded stainless steel design from 304H, 321H
§ Two beds per converter bullet with integrated boiler elements, (SH – Bed III – Re-Heat –
Bed IV – ECO)
§ All accesses to bullets standarized
Re-Heat Exch.
Bed 2
FAT
A standard plant solution will save delivery time and capex cost - Impact on Capex is significant for smaller plants, - Pre-fabrication of complete plant units reduces site activites and ensures good workmanship
For large (mega plants) process customization is critical for capex and opex optimization
- Opportunities for specific developments of known plant sections - „Economies of scale“ vs „operational availability/flexibility“
Conclusion