Accomplishments Referral scanning process has been built and testing is underway
description
Transcript of Accomplishments Referral scanning process has been built and testing is underway
Accomplishments Referral scanning process has been built and testing is underway
Scanners have been installed and tested with the referral scanning facility
All the dates on this project have slipped due to significant extension to project scope and changes to technical architecture
Key Issues & Risks
1. Agreement to rationalise templates for each unit for all clinical units
2. Availability of GP surgery email addresses for emailing discharge summaries
3. Delivery of functionality to automatically populate clinical teams details
4. Lack of single referral management process to ensure that referrals are captured on arrival
5. Issues with adding historic documents if not appropriately filed and named
6. Setting up Clinical Documentation library on SharePoint with advance search facility
7. To redesign the Clinical Documentation Library Interface (Phase 2)
Upcoming Activities Develop e-learning training material – this is an ongoing task
Both scanning and SharePoint testing to be completed by 29/01/10
User acceptance testing and trail run of training materials
Arrange pilot user training for week beginning 11/03/10
Organise demonstrations to the wider user population to get feedback and engagement
Mitigating Actions
1.The project team is working with the clinical units taking part in the pilot
2.Commissioning team are liaising with the commissioners
3.In discussion with supplier to implement the functionality. Due to its complexity the delivery dates have been slipping.
4.It has been agreed with the Director of Operations that this process will only take place in Centralised Bookings
5.Units will have to rename files to meet the file naming requirements to enable them to be processed
6.To be delivered by the supplier on 22/01/10. This date has slipped previously due to technical issues encountered.
7.Discussed with supplier and awaiting for a delivery date
Key Milestones
Server Development and configuration
30/06/09COMPLETE
Agreeing templates for pilot units 19/06/09COMPLETE
Xanadutec end to end system implementation
13/08/09COMPLETE
CIMS end to end implementation 13/08/09COMPLETE
PHASE 1
Authorisation process 30/09/09COMPLETE
Populating Clinicians demographics
Awaiting date from Suppliers
Adding historic documents for the 3 pilot units
22/03/10
Completion of testing 29/01/10
Final software and hardware configuration
24/02/10
Deliver training ( for 3 units) 11/03/10 - 19/03/10
Pilot go live with 3 units 29/03/10
Go live for remaining units (one unit at a time)
19/04/09
PHASE 2
Scanning of referrals process 05/02/2009
Clinical Documentation Library (CDL) Highlight Report 15/01/10 Appendix A
Accomplishments
IM & T policies have been published on the RNOHWeb Policy and procedure
Working search facility
Metadata to be identified in all policies has been submitted for approval
Roll out plan for Trust wide policies.
Key Issues
1. Publishing Trust wide policies and procedures
2. Confirmation of the commencement of the workflow development
Upcoming Activities
Publish trust wide polices as per the roll out plan
Incorporate all policies into the Corporate Document Library
Phase 2
Further development of the module to provide full workflow to support our requirement
Mitigating Actions
1.Roll out plan has been devised by HR department
2.This has been discussed with the developer and are awaiting for a delivery date.
Key Milestones
Corporate Document Library Project as at 15/01/10
Training for Administration Users
COMPLETED
Integrate IM&T Policies 13/11/09COMPLETED
Search facility COMPLETED
Go live IM&T Pilot 16/11/09COMPLETED
Go live (Please see separate rollout plan from Jackie Stephens – Agenda item 11, attachment J)
February to August 2010
PHASE 2Completion of Workflow Development including version control, notification of policy expiry, integration with Outlook
June 2010
Accomplishments
Real time Patient feedback went live on 1/12/2009
Nursing department are using tablet PC’s to capture real time patient feedback. No further issues have been identified
Key Issues
1. None
Upcoming Activities
Phase 2
To complete the integration of SharePoint with Data Warehouse to produce consolidated reports on the feedback received.
Mitigating Actions
1. None
Key Milestones
Real Time Patient Feedback Project as at 15/01/10
Proof of concept 21/08/09COMPLETE
Demonstration to stakeholders
21/08/09COMPLETE
Finalised form factor 21/08/09COMPLETE
Approve Design 30/10/09COMPLETED
Confirm Data Items 30/10/09COMPLETED
Create web application 08/11/09COMPLETED
Design survey 13/11/09COMPLETED
Create reports 20/11/09COMPLETED
Testing 27/11/09COMPLETED
Deliver training 04/12/09COMPLETED
Go live 07/12/09COMPLETED
Phase2 Integration with Data warehouse
31/03/2010
Accomplishments We have completed 3 Implementation Pushes (Including Slope Wards, SCIC, PNI, Theatres, Plaster
Theatre, SDU, SCIC, PNI Paediatric Unit, Metabolic Unit, Coxen/ADU, DOG, IM&T) – we have rolled out to a total of 270 PCs. Feedback has been largely positive.
Key Issues & Risks
1. Patient information sharing across systems will not work if the patient does not have a NHS number booked in the Trust systems. This presents a clinical risk as users may view the wrong patient details in a particular system.
2. Users have requested that the hospital number is displayed on peoples’ PCs and not the NHS number
3. Some Clinicians have requested some changes to ICE to enhance patient context sharing
Upcoming Activities Completion of Implementation Pushes 4, 5 & 6
Completion of Single Sign on and Context Management functionality for RadCentre. This will enable us to complete the Push 6 roll out for Imaging
Completion of RNOH 1+1 Operations Manual and handover to relevant application owners and IT Support
Debrief and lessons learnt to be completed with the Supplier.
Mitigating Actions
1. The team is currently working to provide a solution which will ensure that when searching for patients with no NHS numbers in one system, subsequent applications will yield no results and force the user to repeat the patient search
2. The project team is working with the supplier to provide a solution
3. The project team is working with the supplier to provide a solution
Project Schedule and Preparation Activities
15/05/09COMPLETE
Application Bridge Development Environment Established
18/05/09COMPLETE
Design Complete 22/05/09COMPLETE
Application Bridge Development Complete
24/07/09COMPLETE
Roll out strategy/planning Complete
14/08/09COMPLETE
Testing Complete - Trust acceptance of functionality
19/10/09(SLIPPED)
Pilot Phase 1 4/09/09COMPLETE
Bridgeworks Training 24/09/09COMPLETE
Pilot Phase 2 30/10/09COMPLETE
Push 1 2/11/09COMPLETE
Push 2 13/11/09COMPLETE
Push 3 (Slope) 12/12/10COMPLETE
Push 4 (BTU &remaining Wards) 22/01/10
Push 5 (Bolsover Street & Outpatients Clinic Rooms)
5/02/10
Push 6 (Imaging & Therapies) Feb 2010
Key Milestones
Single Sign On and Context Management Highlight Report as at 15/01/10RNOH 1+1
RNOH INSIGHT Status Update as at 15/01/10
AccomplishmentsData Warehouse
PAS load validation - a number of additional data issues have now been identified and require further investigation by the supplier and the Trust. The sign off date has slipped to February.
RadCentre data model is being constructed in the Data Warehouse and Data transfer into the Datawarehouse has started and we will look to validate the data during the course of January and February
Automated Data Cleansing of Inpatient Episodes missing referrals completed.
Insight Reporting
Completed work on Data Warehouse sourced Phase 1 Reports that are solely reliant on PAS data (based on the requirements raised by the work streams) .
Agreed with Finance on phase 2 PLC data flows.
Key Issues & Risks
1. The PAS Data transfer sign off date has slipped again to February given the number of data issues identified, that require investigation by both the Trust and supplier
2. Given the absence of referral information in RadCentre, we are currently not able to RIS patient exam information to the referral information in PAS
Upcoming ActivitiesData Warehouse Completion of Data cleansing effort and validation of PAS load and automated update process – Sign off of PAS Data
transfer in the Data warehouse Analysis of RadCentre Data and completion Imaging data transfer into the Data warehouse Initiate discussions regarding population of therapies data into the Data warehouse (Phase 2).
Insight Reporting Present Data warehouse sourced Phase 1 reports for review by the relevant workstream leads Conduct a design review of Insight to ensure that the reporting tool meets the information needs of the intended
audience. Complete Insight reports for the 18 Week Recovery Board
Mitigating Actions
Key Milestones – Phase 1
Linking with QlikTech (for PAS data in DW) 19/08/09 COMPLETE
Completion of PAS Data Transfer Feb 2010(SLIPPED)
Completion of RadCentre Data Transfer Feb 2010
Workstreams to deliver Requirements 30/06/09COMPLETE
Completion of 18 Weeks Reporting Solution
1/07/09COMPLETE
Completion of the Prosthesis Reporting Solution
24/07/09COMPLETE
Completion of Daily Discharge Monitoring Report
28/07/09COMPLETE
Completion of New to Follow up ratio 11/08/09COMPLETE
Completion of Coded/Uncoded Lists Report
21/08/09COMPLETE
Phase 1 Business Intelligence Reports
Completion of Operational Workstream Reporting Solution
May 2010
Completion of PBR Clinical Coding Reporting Solution
June 2010
Completion of Clinician Workstream Reporting Solution
June 2010
Completion of Executive Information Workstream Solution
July 2010
Completion of Data Quality Workstream Reporting Solution
July 2010
Development of Phase1 reports and Business Intelligence Output
July 2010
1. The project team is working with the supplier to resolve these issues as a matter of urgency
2. The supplier is currently analysing RIS and PAS data to find another way to link them
Accomplishments
Interim wireless point installed to allow testing to take place
Further software updates have been made to the system following testing
Equipment requirements have now been agreed and can be purchased
The Tablets have been tested and they meet the user requirements
The Interface to PAS has been completed
Example demographic data load database delivered
Email and Faxing directly from the system using NHS mail has been tested and is working successfully.
Key Issues
1. IT skills in the department
2. Implementation of significant changes to working practices
3. Design of comprehensive test scripts
4. Development and listing of business continuity requirements and perational plan
Upcoming Activities
Final scenarios and test scripts to be completed
Testing to continue on the interim version of application including further interface testing
Delivery of further updates to the application following user acceptance testing
The live wireless points to be installed
Business Continuity Plan and Operational Plan to be completed
Mitigating Actions
1.Preliminary IT skills training delivered
2.Maintaining engagement of key staff
3.These are being delivered by the key users
4.This will become a critical service for delivering patient care and will be totally dependent upon the system
Key Milestones
Apr 20, 2023 6
Orthotics Paper Lite Project as at 15/01/2010
Delivery of Completed Application
30/10/09
Application Testing Feb 2010(SLIPPED)
Install Wireless and Network Points
COMPLETED
Interface to PAS COMPLETED
Deliver training 01/12/09
Pilot Go live Feb 2010SLIPPED 8w
Go Live Mar 2010SLIPPED 8w
Post Implementation Issues and Support
Mar 2010 onwards
Accomplishments
Discharge Letter Completed in readiness for the process to run within iCS PAS although there may now be some further updates required following discussion with the Users
A solution has been found for the Drugs database but discussion is now centred around how to update the system on a regular basis
Agreement has been reached with the Users as to the population of diagnosis and procedure codes
Key Issues
1. Finalising Discharge Letter template to work within PAS
2. Embedding of process changes in areas and with personnel where Discharge Summaries are to be completed
3. Some changes may be required for Go Live
Upcoming Activities
Work with the PAS supplier to get the Drug Database uploaded with a process to update this regularly
Set up standard phrases as appropriate
Obtain Clinical Sign off to the process
Establish Training Plan
Deliver Training
Mitigating Actions
1.Further minor changes required
2.Discussions with key stakeholders are taking place with a view to implementing this process
3.Raise the changes with PAS Supplier with a view to prioritising early development
Key Milestones
Apr 20, 2023 7
PAS Discharge Summary Project as at 15/01/2010
Application and Process Testing COMPLETED
Training for Pilot Users MARCH 2010SLIPPED 12w
Pilot Go Live March 2010SLIPPED 12w
Go live APRIL 2010SLIPPED 12w