Acc Ch-7 Average Due Date Sa
-
Upload
shivasrinivas -
Category
Documents
-
view
217 -
download
0
Transcript of Acc Ch-7 Average Due Date Sa
-
8/19/2019 Acc Ch-7 Average Due Date Sa
1/15
7Average Due Date
Unit 1: Average Due Date
Question 1
A promissory note executed by Mr. X is due on 12.8.2007. What is the maturity date of the
promissory note including grace days? (2 Marks, May, 2007) (PCC)
Answer
Where the promissory note is due (including grace days) on public holiday, the preceding day
shall be the due date. Hence, the due date is 14.8.2007.
Question 2
Mr. A advanced ` 30,000 to Mr. B on 1.4.2008. The amount is repayable in 6 equal monthly
instalments commencing from 1.5.2008. Compute the average due date for the loan.
(2 Marks, May, 2008) (PCC)
Answer
Average due date =sinstalmentof .No
repaymenttolendingof datethefrommonthsof Sumloanof Date +
= 1.4.2008 +6
)654321( +++++
= 1.4.2008 + 3.5 months = 16th July 2008
Question 3
R had the following bills receivable and bills payable against S. Calculate average due datewhen the payment can be made or received without any loss or gain of interest to either party.
Bills Receivable Bills Payable
Date of the Bill Amount ( ̀ ) Tenure inmonths
Date of bill Amount ( ̀ ) Tenure inmonths
1.6.08 9,000 3 29.5.08 6,000 2
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
2/15
Average Due Date 7.2
5.6.08 7,500 3 3.6.08 9,000 3
9.6.08 10,000 1 10.6.08 10,000 2
12.6.08 8,000 2 13.6.08 7,000 2
20.6.08 12,000 3 27.6.08 11,000 1
Holiday intervening in the period 15 th August, 2008, 16 th August, 2008, and 6 th September, 2008.
(4 Marks, November, 2008) (PCC)
Answer
Calculation of Average Due Date (taking base date as 12th July, 2008)
Date Due dateincluding days
of grace
Amount ( ̀ ) No. of Daysfrom July 12
Products ( ̀ ) Remarks
1.6.08 4.9.08 9,000 54 4,86,000 Bills Receivable
5.6.08 8.9.08 7,500 58 4,35,000
9.6.08 12.7.08 10,000 0 0
12.6.08 14.8.08 8,000 33 2,64,000
20.6.08 23.9.08 12,000 73 8,76,000
46,500 20,61,000
29.5.08 1.8.08 6,000 20 1,20,000 Bills Payable
3.6.08 5.9.08 9,000 55 4,95,000
10.6.08 13.8.08 10,000 32 3,20,00013.6.08 14.8.08 7,000 33 2,31,000
27.6.08 30.7.08 11,000 18 1,98,000
43,000 13,64,000
Difference of Products = ` 20,61,000 – ` 13,64,000 = ` 6,97,000
Difference of Amount = ` 46,500 – ` 43,000 = ` 3,500
Average Due Date =Base Date +
Amount of
oductsof
Difference
Pr Difference
=July 12 +
500,3
000,97,6
= July 12 + 199.14 or 199 days= 27th January, 2009
Note:
(i) B/R of 12.6.08 Due date changed due to holidays
(ii) B/P of 3.6.08 Due date changed due to holidays
(iii) B/P of 13.6.08 Due date changed due to holidays
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
3/15
7.3 Accounting
Question 4
Harish has the following bills due on different dates. It was agreed to settle the total amount
due by a single cheque payment. Find the date of the cheque.
(i) ` 5,000 due on 5.3.2009
(ii) ` 7,000 due on 7.4.2009
(iii) ` 6,000 due on 17.7.2009
(iv) ` 8,000 due on 14.9.2009 (4 Marks, November, 2009) (PCC)
Answer
Calculation of number of days from the base dateDue date Amount ( ̀ ) No. of days from 5.3.09 Product
5.3.2009 5,000 0 0
7.4.2009 7,000 33 2,31,000
17.7.2009 6,000 134 8,04,000
14.9.2009 8,000 193 15,44,000
26,000 25,79,000
Average due date = Base date +Sumof Product
Sumof Amount
= 5.3.2009 +26,000
25,79,000 = 99 days
The date of the cheque will be 99 days from the base date i.e.12.6.2009. So on
12th June, 2009, all bills will be settled by a single cheque payment.
Question 5
A trader allows his customers, credi t for one week only beyond which he charges interest @
12% per annum. Anil, a customer buys goods as follows:
Date of Sale/Purchase Amount ( ̀ )
January 2, 2009 6,000January 28, 2009 5,500
February 17, 2009 7,000
March 3, 2009 4,700
Anil sett les his account on 31st March, 2009. Calculate the amount of interest payable by Anil
using average due date method. (8 Marks, November, 2009) (IPCC)
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
4/15
Average Due Date 7.4
Answer
Let us assume 9th January, 2009 to be the base date:
Date of Sale Due date ofpayment
Amount (̀)
No. of days from 9th January, 2009
Product
Jan. 2 Jan. 9 6,000 0 0
Jan. 28 Feb. 4 5,500 26 1,43,000
Feb. 17 Feb. 24 7,000 46 3,22,000
March 3 March 10 4,700 60 2,82,000
23,200 7,47,000
Average Due date = Base date +amountof Sum
oductPr of Sum
= 9th January, 2009 +200,23
000,47,7
= 9th January 2009 + 32 days
i.e. 32 days from 9th January, 2009 = 10th February, 2009
Thus, average due date = 10th February, 2009
No. of days from 10th February, 2009 to 31st March, 2009 = 49 days.
Interest payable by Anil on ` 23,200 for 49 days @ 12% per annum
= ` 23,20049 12
× = 373.74365 100
× `
Question 6
Swaminathan owed to Subramanium the following sums :
` 5,000 on 20 th January, 2009
` 8,000 on 3rd March, 2009
` 6,000 on 5 th April, 2009
` 11,000 on 30 th April, 2009
Ascertain the average due date. (2 Marks, May, 2010) (IPCC)
Answer
Calculation of average due date taking 20 th January as the base date
Due Date Amount `
No. of days from 20 th January
Product
20th January 5,000 0 0
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
5/15
7.5 Accounting
3rd March 8,000 42 3,36,000
5th April 6,000 75 4,50,000
30th April 11,000 100 11,00,000
30,000 18,86,000
Average due date = 20th January + AmountTotal
ProductTotal
= 20th January +30,000
18,86,000
= 20th January, 2009 + 63 days (approx)
= 24th March, 2009
Question 7
From the following details find out the average due date:
Date of Bill Amount ( ̀ ) Usance of Bill
29th January, 2009 5,000 1 month
20 th March, 2009 4,000 2 months
12 th July, 2009 7,000 1 month
10 th August, 2009 6,000 2 months
(4 Marks, November, 2010) (IPCC)Answer
Calculation of Average Due Date
(Taking 3rd March, 2009 as base date)
Date of bill 2009 Term Due date
2009
Amount No. of days
from the basedate i.e. 3rd
March,2009
Product
( ̀ ) ( ̀ ) ( ̀ )
29th
January 1 month 3rd
March 5,000 0 020th March 2 months 23rd May 4,000 81 3,24,000
12th July 1month 14th Aug. 7,000 164 11,48,000
10th August 2 months 13th Oct. 6,000 224 13,44,000
22,000 28,16,000
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
6/15
Average Due Date 7.6
Average due date = Base date + Days equal toSum of Products
Sum of Amounts
= 3rd March, 2009 +28,16,000
22,000
= 3rd March, 2009 + 128 days
= 9th July, 2009
Working Note:
1. Bill dated 29th January, 2009 has the maturity period of one month, but there is nocorresponding date in February, 2009. Therefore, the last day of the month i.e. 28th
February, 2009 shall be deemed maturity date and due date would be 3rd March, 2009(after adding 3 days of grace).
2. Bill dated 12th July, 2009 has the maturity period of one month, due date (after adding 3days of grace) falls on 15th August, 2009. 15th August being public holiday, due date
would be preceding date i.e. 14th August, 2009.
Question 8
A and B are partners in a firm and share prof its and losses equally. A has withdrawn thefollowing sum during the half year ending 30 th June 2010:
Date Amount
`January 15 5,000
February 10 4,000
Apri l 5 8,000
May 20 10,000
June 18 9,000
Interest on drawings is charged @ 10% per annum. Find out the average due date and
calculate the interest on drawings to be charged on 30 th June 2010.
(4 Marks, May, 2011) (IPCC)
Answer
Calculation of Average due date
(Base Date 15th Jan, 2010)
Date Amount
`
No. of days Product
`
January 15 5,000 0 0
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
7/15
7.7 Accounting
February 10 4,000 26 1,04,000
April 5 8,000 80 6,40,000
May 20 10,000 125 12,50,000
June 18 9,000 154 13,86,000
36,000 33,80,000
Average due date = Base date +Total product
daysTotal amount
×
= 15th Jan +33,80,000
36,000 days
= 15th Jan + 94 days (approx.)
= 19th April, 2010
Number of days from 19th April, 2010 to 30th June, 2010 = 72 days
Interest on drawings from 19th April to 30th June @10%:
= ` 36,00072 10
365 100× ×
= ` 710
Hence, interest on drawings ` 710 will be charged from A on 30th June, 2010.
Question 9
Mr. Black accepted the following bills drawn by Mr. White:
Date of Bill Period Amount ( ̀ )
09-03-2010 4 months 4,000
16-03-2010 3 months 5,000
07-04-2010 5 months 6,000
18-05-2010 3 months 5,000
He wants to pay all the bills on a single date. Interest chargeable is @ 18% p.a. and
Mr. Black wants to save ` 150 on account of interest payment. Find out the date on which hehas to effect the payment to save∗ interest of ` 150. Base date to be taken shall be the
earliest due date. (8 Marks, November, 2011) (IPCC)
∗The word ‘save’ should be read as ‘earn’ for better understanding of the requirement of the question.
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
8/15
Average Due Date 7.8
Answer
Calculation of Average Due Date taking base date as 19.06.2010
Date of Bill Period Maturitydate
No. of days from thebase date
Amount
( ̀ )
Products
09.03.2010 4 months 12.07.2010 23 4,000 92,000
16.03.2010 3 months 19.06.2010 0 5,000 0
07.04.2010 5 months 10.09.2010 83 6,000 4,98,000
18.05.2010 3 months 21.08.2010 63 5,000 3,15,000
20,000 9,05,000
Average due date = Base date + Total of productTotal of amount
= 19.06.2010 +9,05,000
20,000= 45 days (approx.)
= 3rd August, 2010.
Computation of date of payment to earn interest of 150
Interest per day = [` 20,000 x (18/100)]/365 days
= ` 3,600/365 = ` 10 per day (approx.)
To earn interest of ` 150, the payment should be made 15 days (` 150 / ` 10 per day) earlier
to the due date. Accordingly, the date of payment would be:
Date of payment to earn interest of ` 150 = 3rd August, 2010 –15 days
= 19th July, 2010.
Question 10
M/s Stairs & Co. draw upon M/s Marble & Co. several bills of exchange due for payment on
different dates as under :
Date of Bill Amount( ̀ ) Tenure of Bill
12 th May 44,000 3 months
10 th June 45,000 4 months
1st July 14,000 1 month
19th July 17,000 2 months
Find out the average due date on which payment may be made in one single amount by M/sMarble & Co. to M/s Stairs & Co. 15th August, Independence Day, is national holiday and
22nd September declared emergency holiday, due to death of a national leader.
(4 Marks, May 2012) (IPCC)
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
9/15
7.9 Accounting
Answer
Calculation of Average Due Date
(Taking 4th August as the base date)
Date of bill Term Due date Amount
`
No. of days fromthe base date i.e.
4th August
Product
12th May 3 months 14th August 44,000 10 4,40,000
10th June 4 months 13th October 45,000 70 31,50,000
1st July 1 month 4th August 14,000 0 0
19th July 2 months 23th September 17,000 50 8,50,000
1,20,000 44,40,000
Average due date=Base date+ Days equal toTotal of products
Total amount
= 4th August +44,40,000
1,20,000
= 4th August +37 days = 10th September
Question 11
T owes to K the following amounts:` 7,000 due on 15 th March, 2012
` 12,000 due on 5 th April, 2012
` 30,000 due on 25 th April, 2012
` 20,000 due on 11 June, 2012
He desires to make the full payment on 30 th June, 2012 along with interest @ 10% per annum
from the average due date. Find out the average due date and the amount of interest. Amount
of interest may be rounded off to the nearest rupee. (4 Marks, November 2012) (IPCC)
Answer
Calculation of Average Due Date taking 15th March, 2012 as the base date
Due date Amount No. of days from the basedate i.e. 15 th March, 2012
Product
`
15th March, 2012 7,000 0 0
5th April, 2012 12,000 21 2,52,000
25th April, 2012 30,000 41 12,30,000
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
10/15
Average Due Date 7.10
11th June 2012 20,000 88 17,60,000
69,000 32,42,000
Average due date = Base date + Days equal toamountTotal
productsof Total
= 15th March, 2012 +32,42,000
69,000
= 15th March, 2012 + 47 days (approx.) =1st May, 2012
Interest amount: Interest can be calculated on ` 69,000 from 1st May, 2012 to 30th June,
2012 at 10% p.a. i.e. interest on ` 69,000 for 60 days at 10%p.a. =` 69,000 x 10/100 x 60/366
= ` 1,131 (approx.)
Question 12
The following transactions took place between Thick and Thin. They desire to settle their
account on average due date.
Purchases by Thick from Thin (
)
9th July, 2013 7,200
14th August, 2013 12,200
Sales by Thick to Thin (
)
15th July, 2013 18,000
31st August, 2013 16,500
Calculate Average Due Date and the amount to be paid or received by Thick.
(4 Marks, November 2013) (IPCC)
Answer
Calculation of Average Due Date
Computation of products for Thick’s payments
(Taking 9.7.13 as base date)
Due Date Amount No. of days from base date to due date Product
` `
9.7.13 7,200 0 0
14.8.13 12,200 36 4,39,200
19,400 4,39,200
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
11/15
7.11 Accounting
Computation of products for Thin’s payments (Base date = 9.7.13)
Due Date Amount No. of days from base date to duedate
Product
` `
15.7.13 18,000 6 1,08,000
31.8.13 16,500 53 8,74,500
34,500 9,82,500
Excess of Thin’s products over Thick [9,82,500-4,39,200] 5,43,300
Excess of Thin’s amounts over Thick [34,500-19,400] 15,100
Number of days from base date to date of settlement is =15,100
5,43,300= 36 days (approx.)
Hence, the date of settlement of the balance amount is 36 days after 9th July, i.e. 14th August.
Thus, on 14th August, 2013, Thin has to pay ` 15,100 to Thick.
Question 13
Define Average Due Date. List out the various instances when Average Due Date can be
used. (4 Mark, IPCC May, 2014)
Answer
In business enterprises, a large number of receipts and payments by and from a single party mayoccur at different points of time. To simplify the calculation of interest involved for such
transactions, the idea of average due date has been developed. Average Due Date is a break-evendate on which the net amount payable can be settled without causing loss of interest either to the
borrower or the lender.
Few instances where average due date can be used:
(i) Calculation of interest on drawings made by the proprietors or partners of a business firm
at several points of time.
(ii) Settlement of accounts between a principal and an agent.
(iii) Settlement of contra accounts, that is, A and B sell goods to each other on different
dates.Question 14
Kishanlal has made the following sales to Babulal. He allows a credit period of 10 days
beyond which he charges interest @ 12% per annum.
Date of Sales Amount ( ̀ )
26.05.14 12,000
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
12/15
Average Due Date 7.12
18.07.14 18,000
02.08.14 16,500
28.08.14 9,500
09.09.14 15,500
17.09.14 13,500
Babulal wants to settle his accounts on 30-9-2014. Calculate the interest payable by him using Average Due Date (ADD). If Babulal wants to save interest of ` 588, how many days before
30.9.2014 does he have to make payment? Also find the payment date in this case.
(4 Marks, IPCC November, 2015)
Answer
Calculation of Average Due date (Taking 05th June as the base date)
Date Due Date Amount
`
No. of days fromBase date
Product
`
26.05.2014 05.06.2014 12,000 0 0
18.07.2014 28.07.2014 18,000 53 9,54,000
02.08.2014 12.08.2014 16,500 68 11,22,000
280.8.2014 07.09.2014 9,500 94 8,93,000
09.09.2014 19.09.2014 15,500 106 16,43,00017.09.2014 27.09.2014 13,500 114 15,39,000
85,000 61,51,000
Average due date = 5.6.14 +61,51,000
85,000= 5.6.14 + 72 days (app.) = 16.08.2014
Interest if settlement is done on 30.9.14
85,000 x 12% x365
45 =` 1,258 (approx.)
If Babulal wants to save interest of ` 588, then he has to make the payment following days
before 30.09.2014:
= 588/1258 X 45 days (16.08.2014 to 30.09.2014) = 21 days earlier
Payment date, in the above case, will be 09.09.2014.
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
13/15
7.13 Accounting
Unit 2: Account Current
Question 1
What is meant by ‘Red-Ink interest’ in an Account Current? (2 Marks) (November, 2007) (PCC)
Answer
In an Account Current, interest is calculated on the amount of a bill from the date oftransaction to the closing date of the period concerned. In case the due date of the bill falls
after the closing date of the account, then no interest is allowed for that period. However, it iscustomarily followed that interest from the date of closing to the due date is written in red ink
in the appropriate side of the Account Current. This interest is called Red-Ink Interest. This
Red-Ink interest is treated as negative interest.
Question 2
What is Account current? (2 Marks, May, 2008) (PCC)
Answer
Account current is a running statement of transactions between parties, maintained in the form
of a ledger account, for a given period of time and includes interest allowed or charged onvarious items. It is prepared when transactions regularly take place between two parties. An
account current has two parties – one who renders the account and the other to whom the
account is rendered.
Question 3
Roshan has a current account with partnership firm. It has debit balance of ` 75,000 as on01-07-2012. He has further deposited the following amounts:
Date Amount ( )
14-07-2012 1,38,000
18-08-2012 22,000
He withdrew the following amounts :
Date Amount (
)
29-07-2012 97,00009-09-2012 11,000
Show Roshan's A/c in the ledger of the firm. Interest is to be calculated at 10% on debitbalance and 8% on credit balance. You are required to prepare current account as on 30th
September, 2012. (4 Marks, November 2013) (IPCC)
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
14/15
Average Due Date 7.14
Answer
Roshan’s Current Account with Partnership firm (as on 30.9.2012)
Date Particulars Dr
( ̀ )
Cr
( ̀ )
Balance
( ̀ )
Dr.orCr.
Days Dr Product
( ̀ )
CrProduct
( ̀ )
01.07.12 To Bal b/d 75,000 75,000 Dr. 13 9,75,000
14.07.12 By Cash A/c 1,38,000 63,000 Cr. 15 9,45,000
29.07.12 To Self 97,000 34,000 Dr. 20 6,80,000
18.08.12 By Cash A/c 22,000 12,000 Dr. 22 2,64,000
09.09.12 To Self 11,000 23,000 Dr. 22 5,06,00030.09.12 To Interest A/c 457 23,457 Dr.
30.09.12 By Bal. c/d 23,457
1,83,457 1,83,457 24,25,000 9,45,000
Interest Calculation:
On ` 24,25,000x 10% x 1/365 = ` 664
On ` 9,45,000 x 8% x 1/365 = (` 207)
Net interest to be debited = (` 457)
Note: The above current account has been prepared by means of product of balances method.
Question 4
From the following particulars prepare a current account ∗ , as sent by Mr. Ram to Mr. Siva as
on 31st October 2014 by means of product method charging interest @ 5% p.a.
2014 Particulars `
1st July Balance due from Siva 750
15 th August Sold goods to Siva 1250
20 th August Goods returned by Siva 200
22 nd Sep Siva paid by cheque 800
15 th
Oct Received cash from Siva 500(4 Marks, IPCC November, 2014)
∗ ‘Current Account’ to be read as ‘Account Current’
© The Institute of Chartered Accountants of India
-
8/19/2019 Acc Ch-7 Average Due Date Sa
15/15
7.15 Accounting
Answer
Siva in Account Current with Ram as on 31st Oct, 2014
Dr. Cr.
` Days Product( ̀ )
` Days Product( ̀ )
01.07.14 To Bal. b/d 750 123 92,250 20.08.14 By SalesReturns
200 72 14,400
15.8.14 To Sales 1,250 77 96,250 22.09.14 By Bank 800 39 31,200
31.10.14 To Interest 18.48 15.10.14 By Cash 500 16 8,000
By Balance
of Products
1,34,900
_____ ______ 31.10.14 By Bal. c/d 518.48 ______
2018.48 1,88,500 2018.48 1,88,500
Interest =` 1,34,900 x365
1
100
5× =` 18.48