ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if...

49
ACBO 2016 Leveraging State Funding with Integrated Planning PRESENTERS Ann-Marie Gabel VP Administrative Services, Long Beach City College Melanie Siddiqi VP Administrative Affairs, Chaffey College Eric Mittlestead Associate Vice Chancellor for Facilities, Kern CCD Deborah Shepley Director, Higher Education, Gensler 1

Transcript of ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if...

Page 1: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

ACBO 2016Leveraging State Funding

with Integrated PlanningPRESENTERS

Ann-Marie GabelVP Administrative Services,

Long Beach City College

Melanie SiddiqiVP Administrative Affairs,

Chaffey College

Eric MittlesteadAssociate Vice Chancellor

for Facilities, Kern CCD

Deborah ShepleyDirector, Higher Education,

Gensler

1

Page 2: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Outline

1. Integrated Planning

• What?

• Why?

• Where?

• How?

2. Case Studies

• Chaffey College

• Long Beach City College

3. Summary of Key Strategies

4. Q+A

2

Page 3: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

IntegratedPlanning

3

Page 4: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

What?

DEFINITION

Integrated planning (IP) is the process whereby all

planning and resource allocation activities throughout

every level of the organization are effectively linked

and coordinated, and driven by the institution’s vision,

mission, and academic priorities.

SCUP, Society for College and

University Planning

4

Page 5: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Grab your cell phone!

To Join the Poll:

1. Send a text:

Number: 22333

Message: acbo

2. Receive a confirmation

* Poll is anonymous

acbo

5

Page 6: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

6

Page 7: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

7

Page 8: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

8

Page 9: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

9

Page 10: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Facilities Planning

Educational Planning

State Capital Outlay Planning

Local Bond Planning

Where?

10

Page 11: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Facilities Planning

Educational Planning

Local Bond Planning

Where?

DATA

Project

End

State Capital Outlay Planning

DATAIntegrated Planning

11

Page 12: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

How?

DATA

• Key Elements

o Enrollment and WSCH Forecasts

o Space Inventory Data

o Facilities Condition Index

o Capacity Load Ratios

12

Page 13: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

DATA

Enrollment + WSCH Forecasts

13

Page 14: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

DATA

Space Inventory

14

Page 15: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Eligible for state funding

DATA

Capacity Load Ratios

15

Page 16: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Space Type 2015 2020 2025

Lecture 137 % 133 % 128 %

Lab 75 % 79 % 75 %

Office 112 % 105 % 98 %

Library 71 % 60 % 56 %

Instr. Media 35 % 54 % 53 %

DATA

Capacity Load Ratios

16

Page 17: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

• Report to the State Chancellor’s

Office due annually on July 1

• Updated each year to include:

o Enrollment Data (Fall)

o Project List

o Initial Project Proposal (IPPs)

• Serves as the basis for

consideration of state funding

for projects

Five-Year Construction Plan

17

Page 18: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

• Category A Safety related

• Category B Instructional Growth

• Category C Instructional Modernization

• Category D Theaters, Gymnasiums, CDC's and M&O

• Category E Non-Instructional Growth

• Category F Non-Instructional Modernization

Categories of Projects

18

Page 19: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

IPP FPPFacility Planning

Unit reviews &

selects most

viable projects

to proceed to

FPP phase

Projects not

selected return

to IPP phase

FPU reviews

and scores

FPPs &

projects are

selected

for funding

July 2015 July 2016 July 2018

Prelim Design

Prelims

* If waiting

for State-

wide bond

INITIAL

PROJECT

PROPOSAL

FINAL

PROJECT

PROPOSALBudget is

Signed

and Funds

are Released

(if available)*

IPP

IPP

FPP

Key:

IPP – Initial Project Proposal

FPP – Final Project Proposal

FPU – Facility Planning UnitFunding Cycles

Page 20: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Five-Year Construction Plan

MAINTENANCE BUILDING

CAMPUS POLICE

SHOPS RENOVATION

ALLIED HEALTH

CTE BUILDING

CAMPUS X - INSTRUCTIONAL BUILDING

CAMPUS CENTER RENOVATION

CHILD DEVELOPMENT CENTER

KINESIOLOGY COMPLEX

INTERDISCIPLINARY COMPLEX

20

Page 21: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

DESCRIPTION- Project name

- Project Category

- Occupancy Date

- Brief description

SCORE- Rubric based on project

category

- Maximum score of 200

SPACE ANALYSIS- Space added

- Space removed

- Capacity loads – start

and end of project

Initial Project Proposal (IPP)

21

Page 22: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

EXAMPLE

Initial Project Proposal (IPP)

22

Page 23: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Case Study 1Chaffey College

23

Page 24: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

24

Chaffey College

Page 25: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Rancho Cucamonga

198 acres

46 buildings

586,048 gross square feet

18,249 headcount

Fontana

8 acres

3 buildings

50,731 gross square feet

3,954 headcount

Chino

100 acres

5 buildings

120,473 gross square feet

3,976 headcount

Single College District with three sites:

25

Page 26: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

26

Page 27: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Facilities Planning

Educational Planning

Local Bond Planning

State Capital Outlay Planning

Levels of Integration

27

Page 28: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Institutional Goal 1: Chaffey College will provide quality learning experiences that promote

holistic student development and support success and completion in a timely manner.

Institutional Goal 2: Chaffey College will create, maintain, and support innovative and effective

learning environments that engage students toward success and completion.

Institutional Goal 3: Chaffey College will provide an effective organizational structure and

workforce through strategic hiring practices in which all employees are given the encouragement

and resources needed to achieve excellence.

Institutional Goal 4: Chaffey College will support the needs of the communities through

meaningful external relations, workforce development, outreach, partnerships, and linkages.

Institutional Goal 5: Chaffey College will decrease the achievement gap.

Institutional Goal 6: Chaffey College will responsibly manage financial, physical, technological,

and environmental resources through effective planning, decision-making, and implementation.

InstitutionalGOALS

28

Page 29: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

PlanningPRINCIPALS

• Maximize Functional Space

• Eliminate Non-functional Space

• Improve Efficiency/Utilization Of Facilities

• Right-size The Campus To Address Program Needs

• Improve The Campus Identity

• Position The District To Maximize Funding

• Simplify Implementation

29

Page 30: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Rancho Cucamonga

Fontana

Chino

Approved IPPs

30

Page 31: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

CHINO CAMPUS

Instructional Building 1 FPP 31

Page 32: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Update w better imageFPP Element

• Program• Diagrams• Score

32

Page 33: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

33

Case Study 2Long Beach City College

Page 34: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Facilities Planning

Educational Planning

State Capital Outlay Planning

Local Bond Planning

Levels of Integration

34

Page 35: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

35

Page 36: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Long Beach CCD –Case Study

2041 Facilities Master Plan

Considerations

• Programmatic Need

• Timing

• Swing Space

• State Funding

• Local Funding

36

Page 37: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Single College District with two sites:

Liberal Arts Campus

120 acres

35 buildings

1,294,379 gross square feet

15,004 FTES

Pacific Coast Campus

30 acres

19 buildings

319,007 gross square feet

4,073 FTES

37

Page 38: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Liberal Arts Campus

38

Page 39: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Pacific Coast Campus

39

Page 40: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

31 to 60 months…

Project Phases

40

Page 41: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Legend? Notes?

Project List

41

Page 42: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Project List

42

Page 43: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Project List

43

Page 44: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

FPP

44

Page 45: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

FPP

45

Page 46: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Estimated Cash Flow

46

Page 47: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Key Strategies

47

Page 48: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Key Strategies

Timelines

• Coordinate planning timelines

• Maximize opportunities for linking efforts

Data

• Collect data to serve multiple efforts

• Use data to inform planning discussions

IPPs and FPPs

• Strategize, prioritize and be selective

• Engage key stakeholders

Funding Plans

• Develop realistic project budgets

• Escalate based on realistic timelines

• Include a contingency

Communication

• Broaden communication to build wide-spread support

48

Page 49: ACBO 2016 Fall/10-25 Opt1 2pm...FINAL PROJECT PROPOSAL Budget is Signed and Funds are Released (if available)* IPP IPP FPP Key: IPP –Initial Project Proposal FPP –Final Project

Leveraging State Funding with Integrated Planning

Questions?PRESENTERS

Ann-Marie GabelVP Administrative Services

Long Beach City College

[email protected]

Melanie SiddiqiVP Administrative Affairs

Chaffey College

[email protected]

Eric MittlesteadAssociate Vice Chancellor for Facilities, Kern

CCD

[email protected]

Deborah ShepleyDirector, Higher Education

Gensler

Deborah_Shepley@gensler