Aboriginal Cultural Heritage Management Plan · Plan (ACHMP) for the inclusion in the Mandalong...

67
rpsgroup.com.au REPORT Aboriginal Cultural Heritage Management Plan For Mandalong LW25-31 Extraction Plan Prepared by: RPS AUSTRALIA EAST PTY LTD Ground Floor, 241 Denison Street Broadmeadow, NSW 2292 Australia PO Box 428, Hamilton NSW 2303 Prepared for: CENTENNIAL COAL MANDALONG PTY LTD 12 Kerry Anderson Drive Mandalong NSW 2264 T: +61 2 4940 4200 T: +61 2 4973 0943 E: [email protected] E: [email protected] W: Author: Tessa Boer-Mah Reviewed: Darrell Rigby Approved: Darrell Rigby No.: 139123 Version: Final Date: 20/8/2018

Transcript of Aboriginal Cultural Heritage Management Plan · Plan (ACHMP) for the inclusion in the Mandalong...

  • rpsgroup.com.au

    REPORT

    Aboriginal Cultural Heritage Management Plan

    For Mandalong LW25-31 Extraction Plan

    Prepared by: RPS AUSTRALIA EAST PTY LTD

    Ground Floor, 241 Denison Street

    Broadmeadow, NSW 2292

    Australia

    PO Box 428, Hamilton NSW 2303

    Prepared for: CENTENNIAL COAL MANDALONG PTY LTD

    12 Kerry Anderson Drive

    Mandalong NSW 2264

    T: +61 2 4940 4200 T: +61 2 4973 0943

    E: [email protected] E: [email protected]

    W:

    Author: Tessa Boer-Mah

    Reviewed: Darrell Rigby

    Approved: Darrell Rigby

    No.: 139123

    Version: Final

    Date: 20/8/2018

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page ii

    REPORT

    Document Status

    Version Purpose of Document Authored by Reviewed by Review Date

    2. Client Draft Tessa Boer-Mah /Dragomir Garbov

    Tessa Boer-Mah 25/5/2018

    Final Final Tessa Boer-Mah /Dragomir Garbov

    Tessa Boer-Mah 8/6/2018

    Approval for issue

    Name Signature Date

    Darrell Rigby 20/8/2018

    This report was prepared by [RPS Australia East Pty Ltd (‘RPS’)] within the terms of its engagement and in direct response to a scope

    of services. This report is strictly limited to the purpose and the facts and matters stated in it and does not apply directly or indirectly and

    must not be used for any other application, purpose, use or matter. In preparing the report, RPS may have relied upon information

    provided to it at the time by other parties. RPS accepts no responsibility as to the accuracy or completeness of information provided by

    those parties at the time of preparing the report. The report does not take into account any changes in information that may have

    occurred since the publication of the report. If the information relied upon is subsequently determined to be false, inaccurate or

    incomplete then it is possible that the observations and conclusions expressed in the report may have changed. RPS does not warrant

    the contents of this report and shall not assume any responsibility or liability for loss whatsoever to any third party caused by, related to

    or arising out of any use or reliance on the report howsoever. No part of this report, its attachments or appendices may be reproduced

    by any process without the written consent of RPS. All enquiries should be directed to RPS.

    Final with Consultation Final Tessa Boer-Mah /Dragomir Garbov

    Tessa Boer-Mah 20/8/2018

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page iii

    REPORT

    Contents EXECUTIVE SUMMARY .................................................................................................................................... 6

    1 INTRODUCTION ................................................................................................................................. 7

    1.1 Background ....................................................................................................................................... 7

    1.2 Study Area ......................................................................................................................................... 7

    1.3 Purpose .............................................................................................................................................. 7

    1.4 Scope .................................................................................................................................................. 8

    1.5 Authorship ......................................................................................................................................... 8

    2 REGULATORY REQUIREMENTS ................................................................................................... 10

    3 RELEVANT FEATURES, SIGNIFICANCE, SUBSIDENCE PREDICTIONS AND IMPACTS ......... 13

    3.1 Aboriginal Cultural Heritage Sites ................................................................................................. 13

    3.2 Significance Assessment ............................................................................................................... 16

    3.3 Aboriginal Cultural Significance .................................................................................................... 16

    3.3.1 Method of Assessing Cultural Significance ....................................................................................... 16

    3.3.2 Structure of the Cultural Significance Assessment Table ................................................................. 17

    3.3.3 Outcome of the Cultural Mapping Workshop .................................................................................... 17

    3.3.4 Scientific (Archaeological) Significance Criteria ................................................................................ 18

    3.3.5 Assessment of Archaeological Significance ..................................................................................... 19

    4 SUBSIDENCE PREDICTIONS AND IMPACTS ............................................................................... 20

    4.1 Review of Potential Subsidence Impacts and Environmental Consequences ......................... 20

    4.2 Updated subsidence predictions ................................................................................................... 22

    4.3 Summary .......................................................................................................................................... 22

    5 PERFORMANCE MEASURES ......................................................................................................... 24

    5.1 Performance Indicators .................................................................................................................. 25

    6 MONITORING PROGRAM ............................................................................................................... 26

    6.1 Monitoring Protocols for Structurally Sensitive Sites (Grinding Grooves & Rockshelters) ... 26

    6.2 Monitoring Protocols for Artefact Scatters/Isolated Finds/Open Quarries ............................... 27

    6.3 Monitoring Protocols for Scarred Trees/Carved Trees ............................................................... 28

    7 ADAPTIVE MANAGEMENT ............................................................................................................. 30

    7.1 Centennial Coal Management Framework .................................................................................... 30

    7.2 Adaptive Management Strategy for Mandalong Mine ................................................................. 30

    7.3 Remediation / Rehabilitation of Potential Impacts ...................................................................... 31

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page iv

    REPORT

    8 CONTINGENCY PLAN ..................................................................................................................... 32

    9 REPORTING AND NOTIFICATIONS ............................................................................................... 33

    10 CONTINUAL REVIEW AND IMPROVEMENT ................................................................................. 35

    11 CONCLUSION .................................................................................................................................. 36

    12 REFERENCE LIST ........................................................................................................................... 37

    13 ACRONYMS AND UNITS ................................................................................................................. 38

    Tables Table 1 Key Conditions of Development Consent SSD-5144 .......................................................................... 10

    Table 2 Key Heritage Sites in Extraction Plan Area (GDA94, Zone 56) .......................................................... 13

    Table 3 Cultural Significance Criteria (developed from the Burra Charter with Input by ATOAC and ADTOAC) ..................................................................................................................................................... 17

    Table 4 Cultural Significance Assessment Ranking Table ............................................................................... 17

    Table 5 Cultural Significance Assessment of site types ................................................................................... 18

    Table 6 Archaeological Significance Criteria .................................................................................................... 18

    Table 7 Scientific Assessment Rating by Site Type and Characteristics ......................................................... 19

    Table 8 Predicted Subsidence Effects at Aboriginal Heritage Sites Prepared for the EIS ............................... 20

    Table 9 Impact Potential Criteria for Aboriginal Heritage Sites (EIS) ............................................................... 21

    Table 10 Predicted Level of Impact on Aboriginal Sites ................................................................................... 21

    Table 11 Updated Subsidence Predictions (Ditton 2018) ................................................................................ 22

    Table 12 SSD 5144 Performance Measures for Aboriginal Cultural Heritage ................................................. 24

    Table 13 Approved and predicted Impact or Environmental Consequences ................................................... 24

    Table 14 Reporting and Notification Requirements .......................................................................................... 33

    Table 9 Consultation comments and outcomes ............................................................................................... 51

    Figures Figure 1 Project Area .......................................................................................................................................... 9

    Figure 2 Extraction Plan Area LW25-31 ........................................................................................................... 12

    Figure 3 Heritage Sites in Extraction Plan Area ............................................................................................... 15

    Figure 4 Project Area and subsidence predictions ........................................................................................... 23

    Appendices Appendix 1 Trigger Action Response Plan (TARP)

    Appendix 2 Legislative Requirements

    Appendix 3 AHIMS Searches

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page v

    REPORT

    Appendix 4 Consultation

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 6

    REPORT

    Executive Summary

    RPS has been engaged by Centennial Coal Pty Ltd to provide an Aboriginal Cultural Heritage Management

    Plan (ACHMP) for the inclusion in the Mandalong Mine Extraction Plan for second workings in Longwalls 25

    to 31. The Extraction Plan Area (EP Area) is defined in detail in Section 1.2, Figure 1 and 2 of the ACHMP.

    Development consent SSD_5144 for the Mandalong Southern Extension Project (MSEP) was approved in

    October 2015. This Aboriginal Cultural Heritage Management Plan (ACHMP) has been developed in

    accordance with Condition 6 (l), Schedule 4 of SSD_5144 and the Guidelines for the Preparation of

    Extraction Plans (DP&E and DRE, 2015). As there are no non-Aboriginal Heritage items within the EP Area,

    this management Plan addresses only Aboriginal heritage sites/items within the EP Area as described

    further below. This report is intended to fulfil all relevant statutory and regulatory requirements, the statement

    of commitments and recommendations in the EIS (SLR 2013). This report is also compliant with the

    procedures and protocols from the overarching Northern Region Aboriginal Cultural Heritage Management

    Plan (RPS 2016).

    Eleven (11) Aboriginal heritage sites/items are located inside the EP Area. These eleven Aboriginal heritage

    sites/items are located within the mine workings area and thus may be impacted by subsidence.

    Overall, it is assessed that 2 of the 11 sites (18.18% of known sites) are ‘possibly’ to be impacted by surface

    cracking and erosion damage. The remaining 9 sites have been assessed as to be ‘unlikely’ or ‘very unlikely’

    to be impacted; or in one case – to be subject to ‘negligible’ impact.

    In order to address the subsidence predictions the Northern Region Aboriginal Cultural Heritage

    Management Plan outlines three monitoring phases: Phase 1, Phase 2 and Phase 3. Phase 1 baseline

    recording to be undertaken on all archaeological sites prior to site undermining. Phase 2 monitoring will be

    required on all archaeological sites on the EP Area. Phase 3 is to be undertaken approximately 8 months

    after the mining activity has finished. Phase 3a may be required in cases where final subsidence is not

    achieved until after a number of longwall extractions have taken place

    In the event of unpredicted impacts or deviation in the mine conditions from normality, site personnel will

    follow the corrective actions outlined in the Trigger Action Response Plan (TARP).

    Whilst not expected, should any previously unidentified Aboriginal heritage sites/items be encountered,

    Mandalong Mine will follow procedures outlined in Section 11 of the Northern Region Aboriginal Cultural

    Heritage Management Plan.

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 7

    REPORT

    1 Introduction

    RPS was commissioned by Centennial Mandalong Pty Ltd (Centennial Mandalong) to prepare an Aboriginal

    Cultural Heritage Management Plan to support an Extraction Plan for the extraction of Mandalong Mine

    Longwalls 25 to 31.

    1.1 Background

    Mandalong Mine is an existing underground longwall coal mining operation producing thermal coal that is

    supplied to domestic and export markets. It is located approximately 35 kilometres south-west of Newcastle

    near Morisset in New South Wales Figure 1. Mandalong Mine is 100 percent owned and operated by

    Centennial Mandalong Pty. Limited (Centennial Mandalong), a subsidiary of Centennial Coal Company

    Limited. Centennial Coal Company Limited is a wholly owned subsidiary of Banpu Public Company Limited.

    Mandalong Mine operates under Development Consent SSD-5144 which was granted on 12 October 2015

    by the NSW Planning Assessment Commission under Part 4, Division 4.1 of the NSW Environmental

    Planning and Assessment Act 1979 (EP&A Act) (NSW Government 1979), and provided for extension of the

    mining area with a production limit of 6.5 million tonnes per annum of thermal coal from the West Wallarah

    and Wallarah-Great Northern Seams.

    The currently approved Mandalong Mine comprises the underground workings and surface infrastructure of

    the following:

    The Mandalong Mine Access Site, encompassing underground workings and associated surface

    infrastructure near Morisset.

    Delivery of run-of-mine coal from the underground workings to the Cooranbong Entry Site. The

    Cooranbong Entry Site coal handling and processing facilities are approved under the Northern Coal

    Logistic Project (SSD-5145).

    Delivery of run-of-mine coal from the underground workings to the Delta Entry Site, located near Wyee at

    the Vales Point Rail Unloader Facility. The coal handling facility is approved under DA35-2-2004.

    Mandalong South Surface Site (MSSS), which is yet to be constructed, encompassing ventilation shafts,

    ventilation fans and underground delivery boreholes located approximately 6 kilometres south-west of the

    Mandalong Mine Access Site.

    Centennial Mandalong has prepared an Extraction Plan to address the requirements of Schedule 4,

    Condition 6 of SSD-5144 and has been prepared in accordance with the Guidelines for the Preparation of

    Extraction Plans (NSW Department of Planning and Environment 2015).

    1.2 Study Area

    The Study Area for this Heritage Management Plan encompasses the 26.5 degree angle of draw around the

    secondary extraction areas of Longwalls 25 to 31 as shown on Figure 2.

    1.3 Purpose

    This ACHMP was prepared to support an Extraction Plan for the extraction of coal from the Mandalong Mine

    Longwalls 25 to 31. This Heritage Management Plan has been designed to identify the monitoring and

    measures for heritage sites within the Study Area that are required to be implemented to demonstrate that

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 8

    REPORT

    the relevant performance measures are achieved. Mitigation and management measures have been

    proposed where relevant.

    1.4 Scope

    This Management Plan:

    • Addresses specific requirements set by Condition 6 in Schedule 4 of SSD_5144, and related

    regulatory requirements in accordance with Condition 2 and 4 of Schedule 6 as outlined in Section

    4.

    • Addresses the monitoring and management of potential subsidence-related impacts to Aboriginal

    cultural heritage resulting from mine development within the EP Area at Mandalong Mine.

    1.5 Authorship

    RPS Heritage Manager Tessa Boer-Mah prepared this Aboriginal Cultural Heritage Management Plan with

    input from RPS Newcastle Senior Heritage Consultant Dragomir Garbov. RPS Heritage Technical Director

    Darrell Rigby has reviewed and approved this document.

    .

  • Halekulani

    ManneringPark

    Morisset

    Rathmines

    San Remo

    SummerlandPoint

    AWABASTATEFOREST

    OLNEYSTATEFOREST

    HEATON STATE FORESTLegend

    Development consentboundaryExtraction Plan Area LW25-31_26.5 AODState forest

    Path: S:\Centennial\All Jobs\139123 Mandalong\10 - Drafting\Arcgis Map Documents\Arch\HMP Figures\139123 Figure 1 Locality HMPA A4 20180503.mxd

    PR 137770DATUM: GDA94PROJECTION: MGA Zone 56FIGURE 1: LOCALITY PLAN

    RPS AUSTRALIA EAST PTY LTD (ABN 44 140 292 762)241 DENISON STREET BROADMEADOW PO BOX 428 HAMILTON NSW 2303T: 02 4940 4200 F: 02 4961 6794 www.rpsgroup.com.au

    0 1 2 3 4 5 kmSCALE AT A4 SIZE

    Date: 3/05/2018Technician: Natalie.Wood

    Data Sources:RPS, ClientLand and Property 2015

    CLIENT: CENTENNIAL COAL

    LOCATION:

    PURPOSE: JOB NO.:

    LW25 TO 31MANDALONGHERITAGE

    1:100,000

    IMPORTANT NOTE 1. This plan was p repared fo r the sole pu rposes of the client for the specific purpose of producing a photographic overlay plan.This p lan is s trictly limited to the Purpose and does not apply directlyor indirectly and will not be u sed for any other application, purpose,use or matter. The plan is presented without the assumption of a duty of care to any other person (o ther than the Client) ("Third Party") and may not be rel ied on by T hird Party. 2. RPS Australia East Pty Ltd will not be liable (in negligence or otherwise) for any direct or indirect loss, damage, liability or claimaris ing ou t of or incidental to:a. a Th ird Party publishing, using or relying on the plan;b. RPS Australia East Pty Ltd rely ing on information provided to it bythe Client or a Third Party where the information is incorrect,incomplete, inaccurate, out-of-date or unreasonable;c. any inaccu racies or other faults with information or data sourced from a Third Party;d. RPS Australia East Pty Ltd rely ing on surface indicators that are incorrect or inaccurate;e. the Client o r any T hird Party not verifying information in this plan where recommended by RPS Australia East Pty Ltd;f. lodgment o f this plan with any local authority against the recommendation of RPS Aus tralia East Pty Ltd;g. th e accuracy, reliabili ty, suitab ility or completeness of any app rox imations o r est imates made or referred to by RPS AustraliaEas t Pty Ltd in this plan.3. Without limiting paragraph 1 or 2 above, this plan may not be copied, distributed, o r reproduced by any p rocess unless this note is clearlydisplayed on the plan.4. The aerial photography used in this plan has not been rectified. This image has been overlaid as a best fi t on the boundaries shownand posi tion is approximate only.

    NEW_A4_Portrait 2017 Rev: A Produced:NWReviewed: NW Date: 15/08/2017

    Cessnock

    Gosford

    Newcastle

    Sydney

    Wyong

    Location

    kN

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 10

    REPORT

    2 Regulatory Requirements

    Centennial Mandalong’s operations are conducted in accordance with applicable State and Commonwealth

    environmental, planning, mining, safety, and natural resource legislation. Centennial Mandalong maintains a

    register of relevant environmental legislative and regulatory requirements in a compliance database.

    The Mandalong Southern Extension Project (MSEP) was granted Development Consent SSD_5144 on the

    12th of October 2015. The consent provides the conditional planning approval framework for mining activities

    to be addressed within an Extraction Plan and supporting management plans required by Condition 6 in

    Schedule 4, as detailed in Table 1. Performance measures relevant to this management plan (as described

    in Condition 2 in Schedule 6 of SSD_5144) are detailed separately in Table 1.

    Table 1 Key Conditions of Development Consent SSD-5144

    Condition Requirement Section Addressed

    Schedule 4

    Condition 6

    (Extraction plan)

    The Applicant shall prepare and Extraction Plan for all second workings on site to the satisfaction of the Secretary. Each Extraction Plan must:

    l) include a Heritage Management Plan, which has been prepared in consultation with OEH and Registered Aboriginal Parties to manage the potential environmental consequences of the proposed second workings on both Aboriginal and non-Aboriginal heritage items and reflects the

    requirements of condition 22 Schedule 3;

    This document

    o) Trigger Action Response Plans addressing all features in Tables 6 and 7, which contain:

    • Appropriate triggers to warn of the development of an increasing risk of

    exceedance of any performance measure;

    • Specific actions to respond to high risk exceedance of any performance

    measure to ensure that the measure is not exceeded;

    • An assessment of the remediation measures that may be required if

    exceedances occur and the capacity to implement the measures.

    Appendix A

    p) Include a Contingency Plan that expressively provides for:

    • The adaptive management where monitoring indicates that there has been an exceedance of any performance measure in Tables 6 and 7, or where any such exceedance appears likely; and

    • An assessment of the remediation measures that may be required if exceedances occur and the capacity to implement the measures.

    Section 8

    Condition 9

    Schedule 4

    (Grinding Groove Trial Mitigation)

    Prior to the extraction of Longwall 25, the Applicant must undertake trial mitigation works at grinding groove sites RPS DF04 and RPS PS11, in consultation with Forestry Corporation of NSW, OEH and Registered Aboriginal Parties, and to the satisfaction of the Secretary.

    Section 7.3

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 11

    REPORT

    Condition Requirement Section Addressed

    Condition 10

    Schedule 4

    (Grinding Groove

    Trial Mitigation)

    The Applicant must:

    (a) Monitor the effectiveness of the trial mitigation works during and following the extraction of Longwall 25;

    (b) Provide a report on the monitoring to the Secretary, OEH and Registered Aboriginal Parties; and

    (c) Use the report to inform the impact avoidance, management and mitigation

    strategies in future Extraction Plans covering other grinding groove sites,

    To the satisfaction of the Secretary.

    Section 7.3

    Schedule 6

    Condition 2

    (Management Plan Requirements)

    The Applicant must ensure that the management plans required under this consent are prepared in accordance with the relative guidelines, and include:

    a) Detailed baseline data;

    b) A description of:

    • The relevant statutory requirements (including any relevant approval, Licence or lease conditions);

    • Any relevant limits or performance measures/criteria; and

    • The specific performance indicators that are proposed to be used to judge the performance of, or guide the implementation of , the

    development or any management measures;

    Section 2; Section 5; Appendix B

    c) A description of the measures that would be implemented to comply with the relevant statutory requirements, limits, or performance

    measures/criteria;

    Section 5

    d) A program to monitor and report on the:

    • Impacts and environmental performance of the development; and

    • The effectiveness of any management measures;

    Section 6

    e) A contingency plan to manage any unpredicted impacts and their consequences and to ensure that ongoing impacts reduce o levels below

    relevant impact assessment criteria as quickly as possible;

    Section 8

    f) A program to investigate and implement ways to improve the environmental performance of the development over time;

    Section 10

    g) A protocol for managing and reporting any:

    • Incidents;

    • Complaints;

    • Non-compliances with statutory requirements; and;

    • Exceedances of the impact assessment criteria and/or

    performance criteria; and;

    Section 9

    h) A protocol for periodic review of the plan. Section 10

    The relevant Acts and regulations protecting and managing cultural heritage in New South Wales are

    detailed within the Centennial Coal - Northern Region Aboriginal Cultural Heritage Management Plan

    (ACHMP) (RPS 2016) and summarised in Appendix 2.

  • OLNEY STATEFOREST LONGWALL 25

    LONGWALL 31

    LONGWALL 30

    LONGWALL 29

    LONGWALL 28

    LONGWALL 27

    LONGWALL 26

    BYRONS GULLY

    MORANS C

    REEK

    BINALONG WAY

    CHAPMAN ROAD

    MANDAL

    ONG

    ROAD

    YAMBO FOREST ROAD

    CURTIS ROAD

    LITTLE VALLEY ROAD

    REYNOLDS ROAD

    174

    120

    98

    78

    6254

    3836

    140126

    144136

    134122

    114106

    150140

    120

    84

    184162 1

    72

    130126108

    96 82

    48

    60 50

    726452 5446

    96 64

    88

    78146

    122

    214186

    9084

    7864

    190170

    174 160

    8680

    10296

    32282624

    86

    80

    144142

    42

    40

    170168

    128

    112110108

    100

    9692

    88

    84

    76

    74

    70

    66

    58

    56

    50

    132

    118

    116

    114

    106

    104

    102

    100

    98

    96

    178

    134

    132

    116

    114

    106

    104

    62

    124

    232

    198

    172

    102

    100

    76

    72

    70

    66

    62

    54

    52

    98

    86

    98104

    82

    80

    74

    90

    108

    92

    92

    88

    90

    72

    34

    32

    182

    180

    174

    166

    9492

    88

    82

    32

    30

    28

    24216 212

    210202

    208204

    200196

    190

    186

    182176

    180

    174

    174

    166

    164

    158

    156

    158154

    154

    150

    152 148

    146

    136

    128

    132

    130

    126

    120124

    120

    124

    118

    116

    116

    112

    112

    108

    110

    110

    104102

    10682

    98

    94

    92

    96

    92

    94

    88

    90

    86

    86

    80

    80

    80

    7874 78

    7676

    72

    68 64

    60

    56

    58

    48

    44

    4642

    36

    32

    30

    26

    28

    28

    24

    LegendDevelopment consentboundaryExtraction Plan Area LW25-31_26.5 AODState forestCadastreProposed Longwalls2m ContoursDrainageRoadsTracks

    Path: S:\Centennial\All Jobs\139123 Mandalong\10 - Drafting\Arcgis Map Documents\Arch\HMP Figures\139123 Figure 2 LW25-31 HMP B A4 20180510.mxd

    PR 139123DATUM: GDA94PROJECTION: MGA Zone 56FIGURE 2: PROPOSED LONGWALL 25 TO 31 EXTRACTION AREA

    RPS AUSTRALIA EAST PTY LTD (ABN 44 140 292 762)241 DENISON STREET BROADMEADOW PO BOX 428 HAMILTON NSW 2303T: 02 4940 4200 F: 02 4961 6794 www.rpsgroup.com.au

    0 100 200 300 400 500 mSCALE AT A4 SIZE

    Date: 10/05/2018Technician: Natalie.Wood

    Data Sources:RPS, ClientLand and Property 2015

    CLIENT: CENTENNIAL COAL

    LOCATION:

    PURPOSE: JOB NO.:

    LW 25 TO 31MANDALONGHERITAGE

    1:14,000

    IMPORTANT NOTE 1. This plan was p repared fo r the sole pu rposes of the client for thespecific purpose of producing a photographic overlay plan.This p lan is s trictly limited to the Purpose and does not apply directlyor indirectly and will not b e u sed for any other application, purpose,use or matter. The plan is presented without the assumption of a duty ofcare to any other person (o ther than th e Client) ("Third Party") and may not be rel ied on by T hird Party. 2. RPS Australia East Pty Ltd will not be liable (in negligenceor otherwise) for any direct or indirect loss, damage, liability or claimaris ing ou t of or incidental to:a. a Th ird Party publishing, using or relying on the plan;b. RPS Australia East Pty Ltd rely ing on information provided to it bythe Client or a Third Party where the information is incorrect,incomplete, inaccurate, out-of-date or unreasonable;c. any inaccu racies or other faults with information ordata sourced from a Third Party;d. RPS Australia East Pty Ltd rely ing on surface indicators that are incorrect or inaccurate;e. the Client o r any T hird Party not v erifying information inthis plan where recommended by RPS Australia East Pty Ltd;f. lodgment o f this plan with any local authority against therecommendation of RPS Aus tralia East Pty Ltd;g. th e accuracy, reliabili ty, suitab ility or completeness of any app rox imations o r est imates made or referred to by RPS AustraliaEas t Pty Ltd in this plan.3. Without limiting paragraph 1 or 2 above, this plan may not be copied,distributed, o r reproduced by any p rocess unless this note is clearlydisplayed on the plan.4. The aerial photo graph y used in this plan has not been rectified.This image has been overlaid as a best fi t on the boundaries shownand posi tion is approximate only.

    NEW_A4_Portrait 2017 Rev: A Produced:NWReviewed: NW Date: 15/08/2017

    kN

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 13

    REPORT

    3 Relevant features, significance, subsidence predictions and impacts

    This section outlines the Aboriginal heritage sites/items in the EP Area.

    3.1 Aboriginal Cultural Heritage Sites

    Eleven (11) Aboriginal sites were identified within the Extraction Plan Area. The sites fall within four site

    categories: Grinding Grooves, Artefact Scatters, Culturally Modified (Scarred) Trees and Stone

    Arrangements (Table 2; Figure 3). The majority of these sites were identified as part of the Heritage Impact

    Assessment for the Mandalong Southern Extension Project (RPS 2013).

    Table 2 Key Heritage Sites in Extraction Plan Area (GDA94, Zone 56)

    AHIMS RPS Site Name Type Easting Northing

    45-3-1223 Moran's Creek Artefact Scatter 352004 6329190

    45-3-3469 RPS MAND STH AH03 Grinding Groove 352661 6330027

    45-3-3490 RPS MAND STH CYL07 Grinding Groove 351021 6330514

    45-3-3501 RPS DF03 Grinding Groove 350522 6330289

    45-3-3502 RPS DF04 Grinding Groove 350470 6330285

    45-3-3506 RPS MAND STH PS11 Grinding Groove 350536 6330234

    45-3-3536 RPS MAND STH TBM29 Artefact Scatter 351914 6329290

    45-3-3539 RPS MAND STH TBM31 Grinding Groove 352259 6329874

    45-3-3540 RPS MAND STH TBM32 Stone Arrangement 352295 6329929

    45-3-3541 RPS MAND STH TBM33 Modified Tree (Carved or Scarred) 352284 6329914

    45-3-3542 RPS MAND STH TBM34 Grinding Groove 352084 6329803

    To provide a coherent approach to the analysis the sites are grouped by site type and site characteristics

    (such as numbers of artefacts or numbers of grinding grooves). Those site types, together with a description

    are as follows:

    Grinding Grooves

    Grinding grooves are elongated narrow depressions in soft rocks (particularly sedimentary), generally

    associated with watercourses, that are created by the shaping and sharpening of ground-edge implements.

    To produce a sharp edge the axe blank (or re-worked axe) was honed on a natural stone surface near a

    source of water. The water was required for lubricating the grinding process. Axe grinding grooves can be

    identified by features such as a narrow short groove, with greatest depth near the groove centre. The

    grooves also display a patina developed through friction between stone surfaces. Generally a series of

    grooves are found as a result of the repetitive process.

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 14

    REPORT

    Artefact scatters

    Artefact scatters reflect accidental loss or intentional discard of stone artefacts, when numerous artefacts are

    found it could reflect a campsite, a raw material procurement site or a quarry. There were nine artefact

    scatters comprising 8% of the identified site types, this is in contrast to the majority of sites recorded in NSW,

    with artefacts being the most common site type.

    Culturally Modified (Scarred) Trees

    Culturally modified trees include scarred and carved trees. Scarred trees are caused by the removal of bark

    for use in manufacturing canoes, containers, shields or shelters. Notches were also carved in trees to permit

    easier climbing. Scarred trees are only likely to be present on mature trees remaining from original

    vegetation. Carved trees, the easiest to identify, are caused by the removal of bark to create a working

    surface on which engravings are incised. Carved trees were used as markers for ceremonial and symbolic

    purposes, including burials. Although carved trees were relatively common in NSW in the early 20th century,

    vegetation removal has rendered this site type extremely rare. Modified trees, where bark was removed for

    often domestic use are less easily identified. Criteria for identifying modified trees include: the age of the

    tree; type of tree (the bark of many trees is not suitable, also introduced species would be unlikely subjects);

    axe marks (with the need to determine the type of axe - stone or steel – though Aborigines after settlement

    did use steel); shape of the scar (natural or humanly scarred); height of the scar above the ground

    (reasonable working height with consideration given to subsequent growth).

    Stone Arrangements

    Stone arrangements include lines, circles, mounds, or other patterns of stone arranged by Aboriginal people.

    These may be associated with bora grounds, ceremonial sites, mythological or sacred sites. Stone

    arrangements are more likely to occur on hill tops and ridge crests that contain stone outcrops or surface

    stone, where impact from recent land use practices has been minimal.

  • !(

    #*

    !(

    !(

    !(!(!(

    !(

    !(

    #*

    !(

    &:

    &:

    &:

    OLNEY STATEFORESTLONGWALL 2

    5

    LONGWALL 31

    LONGWALL 30

    LONGWALL 29

    LONGWALL 28

    LONGWALL 27

    LONGWALL 26

    BYRONS GULLY

    MORANSCREEK

    45-3-122345-3-3536

    45-3-3469

    45-3-3490

    45-3-350145-3-350245-3-3506

    45-3-353945-3-354045-3-3541

    45-3-3542BINALONG WAY

    MANDALO

    NG ROAD

    YAMBO FOREST ROAD

    CHAPMAN ROAD

    CURTIS ROAD

    LITTLE VALLEY ROAD

    REYNOLDS ROAD

    230210200

    150120

    100

    140110

    90 8070

    50

    180160130

    1601501401

    30120

    8070

    110100

    60

    180170

    150 140 130 120

    110

    140 120 100 90 80 70 60

    110

    50

    908070120 110

    5040

    90

    80

    190

    170

    60

    90

    100

    40

    100

    170110

    110

    110

    110100

    30

    2020LegendDevelopment consentboundary

    Extraction Plan Area LW25-31_26.5 AOD

    State forest

    Proposed Longwalls

    10m Contours

    Drainage

    Roads

    Tracks

    AHIMS!( Artefact Scatter

    !( Grinding Groove

    #*

    Isolated Find

    #*

    Scarred Tree

    !( Stone Arrangement

    Ground Truthed 45-3-3502

    &: Ground Truthed 45-3-3506

    Path: S:\Centennial\All Jobs\139123 Mandalong\10 - Drafting\Arcgis Map Documents\Arch\HMP Figures\139123 Figure 3 AHIMS HMP C A4 20180607.mxd

    PR 139123DATUM: GDA94

    PROJECTION: MGA Zone 56FIGURE 3: PROPOSED LONGWALL 25 - 31 WITH AHIMS

    RPS AUSTRALIA EAST PTY LTD (ABN 44 140 292 762)

    241 DENISON STREET BROADMEADOW PO BOX 428 HAMILTON NSW 2303

    T: 02 4940 4200 F: 02 4961 6794 www.rpsgroup.com.au

    0 100 200 300 400 500 m

    SCALE AT A4 SIZE

    Date: 7/06/2018Technician: Natalie.Wood

    Data Sources:

    RPS, Client

    Land and Property 2015

    CLIENT: CENTENNIAL COAL

    LOCATION:

    PURPOSE:

    JOB NO.:

    LW 25 TO 31MANDALONGHERITAGE

    1:15,000

    IMPORTANT NOTE 1. This plan was p repared fo r the sole pu rposes of the client for the

    specific purpose of producing a photographic overlay plan.This p lan is s trictly limited to the Purpose and does not apply directly

    or indirectly and will not be u sed for any other application, purpose,

    use or matter. The plan is presented without the assumption of a duty of care to any other person (o ther than the Client) ("Third Party") and

    may not be rel ied on by T hird Party.

    2. RPS Australia East Pty Ltd will not be liable (in negligence or otherwise) for any direct or indirect loss, damage, liability or claim

    aris ing ou t of or incidental to:

    a. a Th ird Party publishing, using or relying on the plan;b. RPS Australia East Pty Ltd rely ing on information provided to it by

    the Client or a Third Party where the information is incorrect,incomplete, inaccurate, out-of-date or unreasonable;

    c. any inaccu racies or other faults with information or

    data sourced from a Third Party;d. RPS Australia East Pty Ltd rely ing on surface indicators

    that are incorrect or inaccurate;e. the Client o r any T hird Party not verifying information in

    this plan where recommended by RPS Australia East Pty Ltd;

    f. lodgment o f this plan with any local authority against the recommendation of RPS Aus tralia East Pty Ltd;

    g. th e accuracy, reliabili ty, suitab ility or completeness of any app rox imations o r est imates made or referred to by RPS Australia

    Eas t Pty Ltd in this plan.

    3. Without limiting paragraph 1 or 2 above, this plan may not be copied,

    distributed, o r reproduced by any p rocess unless this note is clearlydisplayed on the plan.

    4. The aerial photography used in this plan has not been rectified.

    This image has been overlaid as a best fi t on the boundaries shown

    and posi tion is approximate only.

    NEW_A4_Portrait 2017 Rev: A Produced:NWReviewed: NW Date: 15/08/2017

    kN

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 16

    REPORT

    3.2 Significance Assessment

    In order to develop appropriate heritage management outcomes, it is necessary for Aboriginal sites or areas

    of archaeological sensitivity to undergo significance assessment. Aboriginal heritage can be significant for

    cultural and/or scientific reasons. Aboriginal people are the best placed to assess cultural significance and

    are therefore consulted in the Aboriginal heritage management process. Within the local Aboriginal

    community, input on cultural significance may be obtained from Traditional Descendants / Owners or

    Aboriginal / Indigenous people. The following extract from Ask First, produced by the Australian Heritage

    Commission (2002:4), is used to define those representatives.

    Traditional Owners are those people who, through membership in a descent group or clan, have

    responsibility for caring for particular country and are authorised to speak for country and its heritage.

    Authorisation to speak for country and heritage may be as a senior Traditional Owner, an elder, or, in more

    recent times, as a registered Native Title claimant.

    Other Indigenous people with interests are those who, through their personal or family history of involvement

    with a particular place, have an interest in its heritage values. Such places could include, but are not limited

    to, mission stations, places of Indigenous protest, and areas of land where people worked. Sometimes these

    people are described as custodians, but this can mean different things in different areas of Australia. In some

    areas custodians are responsible for looking after places and sometimes the stories and ceremonies linked

    to these places. In other areas custodians are Indigenous people who look after a place on behalf of others.

    Scientific significance is assessed according to the scientific criteria outlined in OEH heritage guidelines.

    3.3 Aboriginal Cultural Significance

    Archaeological field investigations are an effective way of determining the location of Aboriginal sites in the

    landscape. However, the cultural significance of the sites and landscape can only be assessed by the

    cultural knowledge holders, as they draw on knowledge from their ancestors and their own experiences.

    Understanding the cultural significance of the landscape is an integral part of undertaking a cultural heritage

    impact assessment in the Southern Extension Area.

    All Registered Aboriginal Parties were invited to participate in cultural significance assessment workshops

    conducted on 26, 27 and 30 April 2012. The intention was to ensure the Aboriginal Parties were given the

    opportunity to discuss the significance of the sites as a group. The workshop also provided an opportunity for

    this significance to be relayed to Centennial and RPS.

    3.3.1 Method of Assessing Cultural Significance

    Cultural significance is assessed according to the principals outlined in the Burra Charter (Australia ICOMOS

    1999) and the Guide to Investigating, Assessing and Reporting on Aboriginal Cultural Heritage in NSW (OEH

    2011). In the Burra Charter (1999:12), cultural significance means the aesthetic, historic, scientific or social

    value for past, present or future generations. Under NSW NPWS Heritage Guidelines (OEH 2011: 9), the

    assessment of value and significance must consider the aesthetic, historic, social and scientific value that

    the heritage item possesses. The representatives of ATOAC and ADTAOC, for the cultural significance

    workshop, adopted some of criteria from the Burra Charter and the OEH guidelines (2011) in addition to their

    own culturally determined criteria (Table 3).

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 17

    REPORT

    Table 3 Cultural Significance Criteria (developed from the Burra Charter with Input by ATOAC and ADTOAC)

    Criteria Description

    Social: Ceremonial/Spiritual/Dreaming Connection

    This criterion refers to any ceremonial, spiritual or dreaming connection that the site may have to the Traditional Owner Group/s. This criterion also considers its past teaching potential.

    Rarity This criterion refers to how rare the site is in reference to location, site type, site integrity on a local and regional scale. Rarity is also assessed on its archaeological potential.

    Inter-relatedness This criterion refers to whether the site is believed to be related or associated to another site in the landscape.

    Historic and Teaching Potential

    This criterion refers to any potential future and/or present use for educational purposes in the teaching of culture and history.

    Aesthetic This criterion refers to the sites aesthetic qualities. Please note that the notion of visual appeal is a subjective concept.

    Outlook Outlook refers to whether the site has an extensive outlook over ADTOAC and ATOAC country and/or if the area of the site has an attractive perspective to the Traditional Owners.

    3.3.2 Structure of the Cultural Significance Assessment Table

    At the commencement of the workshops, the Aboriginal Parties decided that the cultural significance ranking

    would be gained through group consensus. The participants then assessed each site on the criteria provided

    in Table 4 giving 1 to 5 points according to the level of cultural significance. The cumulative score then

    provided a ranking for each site. Table 4 details the potential point/s given per site and the cumulative

    potential score.

    Table 4 Cultural Significance Assessment Ranking Table

    Ranking System Points allotted Cumulative Points

    High Cultural Significance 1 Point 1 to 6 Points

    High to Very High Cultural Significance 2 Points 7 to 13 Points

    Very High Cultural Significance 3 Points 14 to 20 Points

    Very High to Extremely High Cultural Significance 4 Points 21 to 27 Points

    Extremely High Cultural Significance 5 Points 28 to 30 Points

    3.3.3 Outcome of the Cultural Mapping Workshop

    The cultural mapping workshop resulted in the assignment of a cultural significance assessment. Table 5

    provides an overall indication of the cultural significance ranking by site type.

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 18

    REPORT

    Table 5 Cultural Significance Assessment of site types

    Site type Ranking range

    Grinding grooves 19-30

    Rockshelter 23-30

    Rockshelters with art 30

    Rockshelter with PAD 26-30

    Artefact scatter 19-30

    Isolated artefact 19-30

    Stone arrangement 30

    Culturally modified tree 26-30

    Water source 27

    All site types assessed by the group, apart from the Water Source, were considered to have sites ranked at

    30 points, Extremely High Cultural Significance.

    3.3.4 Scientific (Archaeological) Significance Criteria

    The following significance assessment refers only to those Aboriginal cultural heritage sites within the Study

    Area.

    Archaeological significance, also referred to as scientific significance, is determined by assessing an

    Aboriginal heritage site or area according to archaeological criteria. The assessment of archaeological

    significance is used to develop appropriate heritage management and impact mitigation strategies. Criteria

    for archaeological significance have been developed in accordance with the principals of the ICOMOS Burra

    Charter (Australia ICOMOS 2013). The following archaeological significance criteria have been used: rarity,

    representativeness, integrity, connectedness, complexity, and research potential and are defined in Table 6.

    Table 6 Archaeological Significance Criteria

    Criteria Description

    Rarity This criterion compares the frequency of the identified site types with others previously recorded in the local or regional landscape.

    Representativeness

    All sites are representative of a site type, however some sites may be in better condition or demonstrate more clearly a particular site type. Representativeness is based on the understanding of extant sites in the local or regional landscape and the purpose of this criterion is to ensure a representative sample of sites is conserved for future generations.

    Integrity

    This refers to site intactness. A site with contextual integrity can provide information relating to chronology, social systems, tool technology, site formation processes, habitation, and frequency of use, as well as other occupation indicators. Moderate to high levels of disturbance will generally result in low integrity.

    Educational Potential This criterion is used to identify whether a site has the potential for education and learning about Aboriginal culture.

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 19

    REPORT

    Research Potential This criterion is used to identify whether a site has the potential to contribute new information to the interpretation of Aboriginal occupation in the area.

    The archaeological significance criteria are usually assessed on two scales: local and regional. In

    exceptional circumstances State significance may also be identified. Archaeological significance criteria are

    assessed in three levels and a score assigned: low (score = 1), moderate (score = 2), and high (score = 3).

    A combination of these scores then enables an overall significance ranking of the site to be determined:

    Low significance 5-7;

    Moderate significance 8-12; and

    High significance 13-15

    3.3.5 Assessment of Archaeological Significance

    The archaeological significance of the identified Aboriginal site types within the EP Area has been assessed

    and is summarised in Table 7.

    Table 7 Scientific Assessment Rating by Site Type and Characteristics

    Site Type S

    co

    pe

    of

    Assessm

    en

    t

    Rese

    arc

    h

    Po

    ten

    tial

    Rarity

    Rep

    resen

    tativ

    en

    ess

    Inte

    grity

    Ed

    uca

    tiona

    l

    Po

    ten

    tial

    Lo

    cal

    sig

    nific

    ance

    Reg

    iona

    l

    sig

    nific

    ance

    Sta

    te

    Sig

    nific

    an

    ce

    *

    Artefact Scatter

    (10 -14 artefacts)

    Local 2 3 3 1 3 High Low N/A

    Regional 1 1 1 1 1

    Artefact Scatter

    (5 -10 artefacts)

    Local 1 2 2 1 2 Moderate Low N/A

    Regional 1 1 1 1 1

    Artefact Scatter

    (2 - 4 artefacts)

    Local 1 1 2 1 1 Low Low N/A

    Regional 1 1 1 1 1

    Culturally modified trees

    Local 3 3 3 3 3 High Moderate N/A

    Regional 2 2 3 2 3

    Grinding groove cluster (small 1-5)

    Local 2 2 2 3 2 Moderate Moderate N/A

    Regional 2 2 2 3 3

    Grinding groove cluster

    (large 6-31)

    Local 3 2 3 3 3 High Moderate N/A

    Regional 2 2 2 3 3

    Stone arrangements

    Local 2 3 3 2 3

    High High Nil Regional 2 3 3 2 3

    State 1 1 1 1 1

    *State significance was only assessed for sites with high regional significance

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 20

    REPORT

    4 Subsidence Predictions and Impacts

    Eleven Aboriginal cultural heritage sites were identified in the Project Area (Table 8). The effect of

    subsidence on Aboriginal sites depends on the physical characteristics of the Aboriginal sites and on the

    level of subsidence including tilts, tensile strains and vertical subsidence.

    The subsidence predictions in the EIS were prepared by Ditton Geotechnical Services (2013) and an

    updated subsidence assessment was undertaken as part of the Extraction Plan Ditton Geotechnical Services

    (2018).

    The EIS subsidence predictions including, tilt and horizontal strains for each Aboriginal site are presented in

    Table 8.

    Table 8 Predicted Subsidence Effects at Aboriginal Heritage Sites Prepared for the EIS

    Site # Site Name Site Type Final Subsidence (m)

    Tilt (mm/m)

    Horizontal strain (mm/m)

    45-3-1223 Moran's Creek Open Camp Site -0.96 2.8 -4.1

    45-3-3469 RPS MAND STH AH03 Grinding Groove -0.01 0.4 0.4

    45-3-3490 RPS MAND STH CYL07 Grinding Groove -0.03 1.4 1.3

    45-3-3501 RPS DF03 Grinding Groove -0.82 8.3 -3.0

    45-3-3502 RPS DF04 Grinding Groove -0.77 8.5 -2.4

    45-3-3506 RPS MAND STH PS11 Grinding Groove -0.95 4.1 -4.1

    45-3-3536 RPS MAND STH TBM29 Artefact Scatter -0.63 7.5 4.6

    45-3-3539 RPS MAND STH TBM31 Grinding Groove -0.91 5.9 -3.2

    45-3-3540 RPS MAND STH TBM32 Stone Arrangement -0.93 3.1 -2.5

    45-3-3541 RPS MAND STH TBM33 Scarred Tree -0.95 1.5 -3.1

    45-3-3542 RPS MAND STH TBM34 Grinding Groove -0.74 9.4 1.9

    4.1 Review of Potential Subsidence Impacts and Environmental Consequences

    The likelihood of damage occurring at the sites has been assessed based on the following impact parameter

    criteria (Table 9) by Ditton Geotechnical Services (2013). The criteria consider the theoretical cracking limits

    of rock of 0.3 to 0.5 mm/m and the ‘system’ slackness or strain ‘absorbing’ properties of a jointed and

    weathered rock mass during subsidence deformation. The lack of measured observed impact (i.e. surface

    cracking) due to measured strains of up to 2 to 3 mm/m above the Mandalong Mine is an example of the

    difference between theoretical and in-situ rock mass cracking behaviour (Ditton Geotechnical Services

    2013).

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 21

    REPORT

    Table 9 Impact Potential Criteria for Aboriginal Heritage Sites (EIS)

    Cracking Damage Potential - Indicative Probabilities of Occurrence

    Predicted 'smooth profile' Horizontal Strain (mm/m)

    Tensile Compressive

    Very Unlikely (5

    Erosion Damage Potential - Indicative Probabilities of Occurrence Predicted Surface Gradient Change or Tilt

    Increase

    Very Unlikely (30 mm/m)

    Source: Ditton Geotechnical Services 2013

    The subsidence report prepared for the EIS assessed the ‘Cracking Damage Potential’ is considered the

    primary damage potential indicator and the ‘Erosion Damage Potential’ is an additional secondary criterion

    that is relevant to features exposed to concentrated water flows along creeks or sites that have been

    damaged by cracking. Therefore, for the cases where cracking is deemed ‘possible’ or ‘likely’ at a site, the

    potential for erosion damage will also be considered ‘possible’ or ‘likely’ (Ditton Geotechnical Services

    2013).The predicted level of impact on Aboriginal sites as assessed for the EIS is detailed in the table below

    for the sites currently subject to this Extraction Plan.

    Table 10 Predicted Level of Impact on Aboriginal Sites

    Site # Site Name Site Type Impact

    45-3-1223 Moran's Creek Open Camp Site Possible

    45-3-3469 RPS MAND STH AH03 Grinding Groove V. Unlikely

    45-3-3490 RPS MAND STH CYL07 Grinding Groove V. Unlikely

    45-3-3501 RPS DF03 Grinding Groove Possible

    45-3-3502 RPS DF04 Grinding Groove Unlikely

    45-3-3506 RPS MAND STH PS11 Grinding Groove Possible

    45-3-3536 RPS MAND STH TBM29 Artefact Scatter Likely

    45-3-3539 RPS MAND STH TBM31 Grinding Groove Possible

    45-3-3540 RPS MAND STH TBM32 Stone Arrangement Negligible

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 22

    REPORT

    Site # Site Name Site Type Impact

    45-3-3541 RPS MAND STH TBM33 Scarred Tree Possible

    45-3-3542 RPS MAND STH TBM34 Grinding Groove Possible

    4.2 Updated subsidence predictions

    Centennial Mandalong has reduced the lengths of Longwalls 25 to 31 which has mitigated potential impacts

    to Aboriginal sites due to subsidence. As a result subsidence predictions for eleven Aboriginal sites have

    been revised (Table 11).

    Table 11 Updated Subsidence Predictions (Ditton 2018)

    Site # Site Name LW Subsidence (m)

    Horizontal

    Strain

    (mm/m)

    Tilt (mm/m) Cracking Damage Potential / Erosion

    45-3-1223 Moran's Creek 31 -0.62 0.2 (4) 13.5 Possible/Possible

    45-3-3469 RPS AH03 27 0.000 0.2 0.3 Very Unlikely/Very Unlikely

    45-3-3490 RPS CYL07 25 -0.08 1.6 2.2 Unlikely/Very Unlikely

    45-3-3501 RPS DF03 25 -0.07 1.2 3.3 Unlikely/Unlikely

    45-3-3502 RPS DF04 25 -0.01 0.4 0.9 Very Unlikely/Very Unlikely

    45-3-3506 RPS PS11 25 -0.09 1.3 3.9 Unlikely/Unlikely

    45-3-3536 RPS TBM29 30 -0.64 4.2 9.6 Possible/Possible

    45-3-3539 RPS TBM31 28 -0.87 -3.2 (3) 7.2 Unlikely/Unlikely

    45-3-3540 RPS TBM32 28 -0.88 -1.7 (3) 4.2 Unlikely/Unlikely

    45-3-3541 RPS TBM33 28 -0.91 -2.4 (3) 3.6 Unlikely/Unlikely

    45-3-3542 RPS TBM34 28 -0.72 2(3) 8.5 Unlikely/Unlikely

    4.3 Summary

    The results in Table 11 indicate the following potential impacts to the Aboriginal Heritage Sites due to the proposed longwalls:

    • One open camp site and one artefact scatter may be ‘possibly’ impacted.

    Overall, it is assessed that 2 of the 11 sites (18.18% of known sites) are “possibly” to be impacted by surface

    cracking and erosion damage.

  • !(

    #*

    !(

    !(

    !(!(!(

    !(

    !(

    #*

    !(

    &:

    &:

    &:

    OLNEY STATEFOREST

    4 3

    LONGWALL 25

    LONGWALL 31

    LONGWALL 30

    LONGWALL 29

    LONGWALL 28

    LONGWALL 27

    LONGWALL 26

    B YRONS GULLY

    MORANSCREEK

    45-3-122345-3-3536

    45-3-3469

    45-3-3490

    45-3-350145-3-350245-3-3506

    45-3-353945-3-354045-3-3541

    45-3-3542

    MANDAL

    ONG

    ROAD CHAPMAN ROAD

    BINALONG WAY

    CURTIS ROAD

    LITTLE VALLEY ROAD

    REYNOLDS ROAD

    LegendDevelopment consentboundary

    Extraction Plan Area LW25-

    31_26.5 AOD

    State forest

    Drainage

    Proposed Longwalls

    Roads

    Tracks

    AHIMS!( Artefact Scatter

    !( Grinding Groove

    #*

    Isolated Find

    #*

    Scarred Tree

    !( Stone Arrangement

    Ground Truthed 45-3-3502

    &: Ground Truthed 45-3-3506

    Subsidence Contours -Elevation-1.3

    -1.2

    -1.1

    -1

    -0.9

    -0.8

    -0.7

    -0.6

    -0.5

    -0.4

    -0.3

    -0.2

    -0.1

    -0.02

    Path: S:\Centennial\All Jobs\139123 Mandalong\10 - Drafting\Arcgis Map Documents\Arch\HMP Figures\139123 Figure 4 Subsidence HMP C A4 20180607.mxd

    PR 139123DATUM: GDA94

    PROJECTION: MGA Zone 56FIGURE 4: PROJECT AREA AND SUBSIDENCE PREDICTIONS

    RPS AUSTRALIA EAST PTY LTD (ABN 44 140 292 762)

    241 DENISON STREET BROADMEADOW PO BOX 428 HAMILTON NSW 2303

    T: 02 4940 4200 F: 02 4961 6794 www.rpsgroup.com.au

    0 100 200 300 400 500 m

    SCALE AT A4 SIZE

    Date: 7/06/2018Technician: Natalie.Wood

    Data Sources:

    RPS, Client

    Land and Property 2015

    CLIENT: CENTENNIAL COAL

    LOCATION:

    PURPOSE:

    JOB NO.:

    LW 25 TO 31MANDALONGHERITAGE

    1:15,000

    IMPORTANT NOTE 1. This plan was p repared fo r the sole pu rposes of the client for the

    specific purpose of producing a photographic overlay plan.This p lan is s trictly limited to the Purpose and does not apply directly

    or indirectly and will not be u sed for any other application, purpose,

    use or matter. The plan is presented without the assumption of a duty of care to any other person (o ther than the Client) ("Third Party") and

    may not be rel ied on by T hird Party.

    2. RPS Australia East Pty Ltd will not be liable (in negligence or otherwise) for any direct or indirect loss, damage, liability or claim

    aris ing ou t of or incidental to:

    a. a Th ird Party publishing, using or relying on the plan;b. RPS Australia East Pty Ltd rely ing on information provided to it by

    the Client or a Third Party where the information is incorrect,incomplete, inaccurate, out-of-date or unreasonable;

    c. any inaccu racies or other faults with information or

    data sourced from a Third Party;d. RPS Australia East Pty Ltd rely ing on surface indicators

    that are incorrect or inaccurate;e. the Client o r any T hird Party not verifying information in

    this plan where recommended by RPS Australia East Pty Ltd;

    f. lodgment o f this plan with any local authority against the recommendation of RPS Aus tralia East Pty Ltd;

    g. th e accuracy, reliabili ty, suitab ility or completeness of any app rox imations o r est imates made or referred to by RPS Australia

    Eas t Pty Ltd in this plan.

    3. Without limiting paragraph 1 or 2 above, this plan may not be copied,

    distributed, o r reproduced by any p rocess unless this note is clearlydisplayed on the plan.

    4. The aerial photography used in this plan has not been rectified.

    This image has been overlaid as a best fi t on the boundaries shown

    and posi tion is approximate only.

    NEW_A4_Portrait 2017 Rev: A Produced:NWReviewed: NW Date: 15/08/2017

    kN

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 24

    REPORT

    5 Performance measures

    Performance measures for Aboriginal Cultural heritage sites are provided for in Table 6 of Schedule 4 of the

    SSD 5144 conditions of consent and summarized in Table 12 below.

    Table 12 SSD 5144 Performance Measures for Aboriginal Cultural Heritage

    Sites Performance Measures

    Stone Arrangement RPS TBM 32 Negligible subsidence impacts or environmental consequences

    All other Aboriginal sites/items at the site No subsidence impact or environmental consequence greater than the predicted in the documents listed in Condition 2(b) of Schedule 2.

    Table 13 compares the predicted impact with the impacts predicted in the EIS.

    Table 13 Approved and predicted Impact or Environmental Consequences

    Site # Site Name Approved Level of Impact Predicted Level of Impact (EIS)

    45-3-1223 Moran's Creek No greater than predicted Possible

    45-3-3469 RPS MAND STH AH03 No greater than predicted V. Unlikely

    45-3-3490 RPS MAND STH CYL07 No greater than predicted V. Unlikely

    45-3-3501 RPS DF03 No greater than predicted Possible

    45-3-3502 RPS DF04 No greater than predicted Unlikely

    45-3-3506 RPS MAND STH PS11 No greater than predicted Possible

    45-3-3536 RPS MAND STH TBM29 No greater than predicted Likely

    45-3-3539 RPS MAND STH TBM31 No greater than predicted Possible

    45-3-3540 RPS MAND STH TBM32 Negligible Negligible

    45-3-3541 RPS MAND STH TBM33 No greater than predicted Possible

    45-3-3542 RPS MAND STH TBM34 No greater than predicted Possible

    “Negligible” is defined as per the SSD-5144 as “small and unimportant, such as not to be worth

    considering” (SSD-5144, Page 4). For the purpose of this Aboriginal Cultural Heritage Management Plan,

    negligible as referred to in this section is defined as:

    In the longer term being small and insignificant and causing little or no impact. Short term impacts may be

    greater than negligible but if they are of limited duration they may be negligible when considered over the

    longer term.

    Based on the predicted subsidence impacts (Ditton 2018), it is considered the performance measures for the

    eleven Aboriginal heritage sites within the Extraction Plan Area will be achieved. A monitoring program will

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 25

    REPORT

    be implemented to confirm if impacts remain within predictions and identify any management or mitigation

    measures as required.

    5.1 Performance Indicators

    To establish compliance with the performance measures outlined in Section 5.1, Centennial Mandalong has

    developed a TARP to work with the existing monitoring program established by the Northern Region

    Aboriginal Cultural Heritage Management Plan. Centennial’s approach to the monitoring program is

    presented in Section 5 and the TARP in Section 6 and Appendix 1.

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 26

    REPORT

    6 Monitoring program

    The aim of the monitoring program is to identify whether there is a risk of harm to Aboriginal sites as a result

    of mining activities and to identify appropriate mitigation strategies, if required. This monitoring program has

    been developed in accordance with the principles of due diligence as defined by the NP&W Regulation 2009.

    While the broad principles of the Due Diligence Code of Practice for the protection of Aboriginal Objects in

    NSW (DECCW 2010) and the NSW Minerals Industry Due Diligence Code of Practice for the Protection of

    Aboriginal Objects (Minerals Council 2010) have been adopted; additional (and more specific heritage)

    management protocols have been developed to manage the complexities of mining activities, the nature of

    the Aboriginal sites present and the assessment of harm.

    The monitoring program needs to record the condition of the site before mining (baseline survey and

    baseline check) and the condition of the site after mining (post mining initial condition and post mining

    secondary condition check) and thus has been separated into three phases.

    Phase 1: Baseline recording (prior to site being undermined)

    Phase 2: Post mining initial condition (immediately after undermining)

    Phase 3: Post mining secondary condition (approximately 8 months after undermining)

    Phase 3a: (Longwall Mining) - In instances where final subsidence is not achieved until after a number

    of longwall extractions have taken place, then additional inspections by a qualified cultural heritage

    consultant may be required to assess any risks to Aboriginal sites.

    Phase 1, the baseline survey aims to record the condition of the site before mining (for example, has a

    scarred tree tilted prior to mining as result of tree growth or natural cracking of a rockshelter site due to

    weathering processes). Phase 2, the post mining initial condition check is to establish whether there has

    been any change to site and if change has occurred whether it is from the effects of subsidence. The

    purpose of Phase 3 - the post mining secondary condition check - is to identify whether there has been any

    change to the site in the period since mining and to make an assessment on whether the ground surface

    conditions have stabilised. If ground surface conditions have stabilised, then further monitoring should not be

    required.

    Note: Access to Aboriginal sites to undertake monitoring is subject to landowner approval. If landowner

    approval is not obtained, no access can be granted to carry out the monitoring activities. In order to ensure

    that sites which require monitoring are appropriately undertaken, monitoring protocols have been provided

    below. Representatives of the registered Aboriginal Parties should be invited to participate in all three

    phases of the monitoring process for Aboriginal sites.

    The following monitoring protocols are relevant to the EP Area LW 25 – 31:

    6.1 Monitoring Protocols for Structurally Sensitive Sites (Grinding Grooves & Rockshelters)

    Once a grinding groove or rockshelter site has been assessed to be at risk of harm and it is not feasible for

    Centennial to modify the mining footprint to eliminate the risk, then irrespective of whether the risk is related

    to surface facilities and/or ground surface subsidence, the following protocol must be adopted.

    Phase 1: In order to manage rockshelter/grinding groove site, a baseline recording must be undertaken

    before the commencement of mining. This baseline recording must include the following:

    Detailed archaeological recording,

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 27

    REPORT

    Archival-quality photos; and

    The designation of survey control points for monitoring.

    The heritage consultant will be responsible for undertaking the detailed recording and taking photographs of

    the site and observations of the rock morphology (surface) should be recorded. The archival-quality

    photographs should be taken in accordance with OEH and Heritage Branch guidelines. A 3D terrestrial scan

    of the rockshelter/grinding groove site(s) may also be considered if appropriate.

    A minimum of six (6) control points should be nominated on the rockshelter/grinding groove site(s). The

    recording of control points must be undertaken by a suitably qualified surveyor (appointed by Centennial or

    heritage consultant) in consultation with the heritage consultant using a total station or better equipment if

    available. The purpose of the control points is to provide points of reference on the rockshelter/grinding

    groove in order to later monitor the effects of subsidence. The location of these control points should

    preferably be tied to known surveyed points outside the zone of influence and/or other permanent points

    such as electricity transmission towers.

    Measures to reduce potential adverse impacts to sites at high risk as a result of mining activities to be

    considered in consultation with the Aboriginal parties.

    Phase 2: Within a reasonable timeframe after the completion of undermining, the condition of the site must

    be reinspected and the condition of the site compared to the last documented results. Again, observations of

    the rock morphology (surface) should also be recorded, particularly if there is widening of existing cracks

    and/or development of new cracks. Signs of sheet erosion or exfoliation must also be recorded and archived.

    This data must be compared to recorded information in Phase 1.

    If the site is assessed to be at a greater risk of harm as a result of mining activities, Centennial’s

    Environmental Team must notify and inform OEH (Enviroline: 131 555) that there is a potential for harm to

    the site and follow the advice given by OEH

    Phase 3: The post mining secondary check must be undertaken approximately 8 months after the mining

    activity was finished. A final check of the six (6) control point measurements must be undertaken and

    compared to previous results. If there are no changes to the rock surface morphology, widening of existing

    cracks or signs of sheet erosion/surface exfoliation, then no further monitoring is required.

    If there is a discrepancy from the baseline recording and determined to be as a result of subsidence,

    Centennial must contact a suitably qualified cultural heritage consultant to assess the potential risk of harm

    to the site. The appropriate mitigation measures provided by the inspecting heritage consultant must be

    followed and implemented accordingly.

    Phase 3a: (Longwall Mining) - In instances where final subsidence is not achieved until after a number of

    longwall extractions have taken place, then additional inspections by a qualified cultural heritage consultant

    may be required to assess any further risks to Aboriginal sites.

    6.2 Monitoring Protocols for Artefact Scatters/Isolated Finds/Open Quarries

    Once an open site has been assessed to be at risk of harm and it is not feasible for Centennial to modify the

    mining footprint to eliminate the risk, then irrespective of whether the risk is related to surface facilities and/or

    ground surface subsidence the following protocol must be adopted.

    Phase 1: Immediately before the commencement of mining activity, a baseline check of the sites condition

    must be undertaken. The purpose of this exercise is to document the condition of the site immediately before

    mining related activities take place and gauge whether there are impacts to the site related to natural

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 28

    REPORT

    processes rather than mining activities. Monitoring of the site should be undertaken using the following

    documentation methods:

    Digital photography (scaled as appropriate);

    Field notes to record the current condition and status of the site;

    GPS (using differential, preferably) to locate and confirm site location; and

    Produce a site plan using baseline and offsets (tape measure), or GPS plotted polygons, as appropriate

    During the due diligence inspection and baseline recording, the location of the site must be verified using a

    GPS and the site dimensions and content must be confirmed. Photos of the site need to be taken so that the

    overall condition can be documented.

    If the site is determined by the archaeologist and representatives of the Aboriginal Parties to be at an

    inappropriate risk of harm, consideration should be given to salvage the artefacts with the aim of returning

    the objects to their original location after the completion of mining. This process would be subject to a

    Section 90 application approval by OEH.

    Phase 2: Within a reasonable timeframe after the completion of undermining, the condition of the site must

    be reinspected and the condition of the site compared to the last documented results. If the level of harm to

    the site becomes evident immediately post-mining, Centennial must endeavour to protect the site from

    further harm for example, by using non-invasive barrier fencing to prevent erosion. The Centennial

    Environmental Team must notify and inform OEH (Enviroline: 131 555) if that there is a potential for harm to

    the site and follow the advice given by OEH.

    Phase 3: The post mining secondary check must be undertaken approximately 8 months after the mining

    activity has finished. The inspection is required to make an assessment on whether the ground surface

    conditions have stabilised. If ground conditions have stabilised and no changes to site condition is observed,

    then no further monitoring should be required. If noticeable amounts of erosion or disturbance is identified,

    Centennial’s Environmental Team must also notify and inform OEH (Enviroline: 131 555) that there is a

    potential for harm to the site and follow the advice given by OEH.

    Phase 3a: (Longwall Mining) - In instances where final subsidence is not achieved until after a number of

    longwall extractions have taken place, then additional inspections by a qualified cultural heritage consultant

    may be required to assess any further risks to Aboriginal sites.

    6.3 Monitoring Protocols for Scarred Trees/Carved Trees

    Once a scarred/carved tree site has been assessed to be at risk of harm and it is not feasible for Centennial

    to modify the mining footprint to eliminate the risk, then irrespective of whether the risk is related to surface

    facilities and/or ground surface subsidence, the following protocol must be adopted.

    Phase 1: A baseline recording of the site's condition must be ascertained and tabulated for future monitoring

    purposes. The baseline assessment will involve recording the position and tilt of the tree prior to sub-surface

    mining. The baseline recording requires the following measurements to be recorded:

    Level of the tree (base);

    V-notch (top) tilt measurement (as an easting and northing location);

    V-notch (top) level;

    V-notch (bottom) tilt measurement (as an easting and northing location);

    V-notch (bottom) level; and

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 29

    REPORT

    Degree of tilt.

    Phase 2: The tilt and condition of the scarred/carved tree must be re-assessed immediately post mining.

    During the monitoring, if it is identified that the tilt of the tree exceeds 10° from the baseline recording,

    Centennial must endeavour to protect the tree from further tilting by erecting a non-invasive framework which

    may be in the form of bracing or other exterior supports. In this instance, Centennial’s Environmental Team

    must also inform and notify OEH (Enviroline: 131 555) that there is a potential for harm to the site. An AHIP

    may be required to be obtained prior to attempting to protect the site.

    Phase 3: The post mining secondary check must be undertaken approximately 8 months after the mining

    activity has finished. The inspection is required to make an assessment on whether the ground surface

    conditions have stabilised. If ground conditions have stabilised and no changes to sites condition is

    observed, then no further monitoring should be required.

    If it is identified that the tilt of the tree exceeds 10° from the baseline recording, Centennial must endeavour

    to protect the tree from further tilting by erecting a non-invasive framework to prevent further tilt to the tree

    where possible. Centennial’s Environmental Team must also inform and notify OEH (Enviroline: 131 555)

    that there is a potential for harm to the site and follow the advice given by OEH.

    Phase 3a: (Longwall Mining) - In instances where final subsidence is not achieved until after a number of

    longwall extractions have taken place, then additional inspections by a qualified cultural heritage consultant

    may be required to assess any further risks to Aboriginal sites.

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 30

    REPORT

    7 Adaptive management

    7.1 Centennial Coal Management Framework

    An Adaptive Management Framework provides for flexible decision making, adjusted to consider

    uncertainties as management outcomes are understood.

    Through feedback to the management process, the management procedures are changed in steps until

    monitoring shows that the desired outcome is obtained. The monitoring program has been developed so that

    there is statistical confidence in the outcome.

    In adaptive management, the goal to be achieved is set, so there is no uncertainty as to the outcome, and

    conditions requiring adaptive management do not lack certainty, but rather they establish a regime which

    would permit changes, within defined parameters, to the way the outcome is achieved.

    The Centennial Coal Adaptive Management Framework is a process of ongoing testing, learning, monitoring

    and managing and relies on:

    Description of the environmental value and its role in the landscape, including aspects of an operation

    that may result in a significant impact to the environmental value (not all aspects of a project will generate

    impacts;

    A model of the environmental response to certain management actions/decisions, supported by the

    description of the environment;

    Mechanisms to test the model;

    Engagement with relevant stakeholders in the description of the environment and development of models,

    model outcomes and management actions/decisions;

    Identification of clear management objectives for each environmental value (including heritage);

    – Monitoring the system using best available technologies and multiple lines of evidence to:

    – Evaluate progress against objectives;

    – Determine the status of the system;

    – Increase our understanding of the system; and

    – Refine the modelling where applicable.

    7.2 Adaptive Management Strategy for Mandalong Mine

    As the most effective form of management on the risk hierarchy, Mandalong Mine has gone through an

    extensive mine design process specifically to eliminate risks and avoid potential impacts to surface features.

    Progressive implementation and monitoring of mining within the approved mining zones during the mine

    schedule affords further opportunity and flexibility for adaptive management if required.

    The adaptive management approach at Mandalong Mine involves monitoring and evaluation against

    performance measures and associated indicators in Trigger Action Response Plans (TARP) established for

    the extraction plan and supporting management plans (refer Section 7 and Appendix 1). Where

    performance indicators indicate increasing levels of risk (conditions green, amber then red being exceeded),

    escalating adaptive management measures are engaged in accordance with the TARP. The process has

    been successfully implemented in existing Extraction Plan areas at Mandalong Mine and has been updated

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 31

    REPORT

    to reflect EIS commitments and consent requirements for the Mandalong Southern Extension Project,

    including specific performance measures.

    In accordance with Condition 8 (Adaptive Management) in Schedule 6 of SSD_5144, where any exceedance

    of applicable criteria and/or performance measures has occurred, Centennial will at the earliest opportunity:

    a. Take all reasonable and feasible steps to ensure that the exceedance ceases and does not reoccur

    b. Consider all reasonable and feasible options for remediation (where relevant) and submit a report to

    the Department describing those options and any preferred remediation measures or other course of

    action; and

    c. Implement remediation measures as directed by the Secretary, to the satisfaction of the Secretary.

    Adaptive management measures would follow failure/root cause analysis where appropriate (including

    review of any observed impacts in EP Areas for potential mining induced causes and would be undertaken in

    consultation with relevant stakeholders, and involve review of this management plan.

    7.3 Remediation / Rehabilitation of Potential Impacts

    Mandalong Mine will undertake trial mitigation works at grinding groove sites RPS DF04 and RPS PS11 in

    accordance with Condition 9, Schedule 6 of SSD_5144, monitor the effectiveness of the trial mitigation and

    report on the monitoring in accordance with Condition 10, Schedule 6 of SSD_5144. The initial phase of the

    mitigation works has been undertaken (RPS 2018).

    Due to the minimal subsidence effects expected for the remaining Aboriginal archaeological sites, the need

    to implement remediation/rehabilitation measures for potential impacts are considered unlikely. However, in

    the event that remediation is required, Mandalong Mine will undertake remediation in accordance with:

    Conditions 8a)-c) in Schedule 6 of SSD_5144 (refer details in Section 6.2 above), noting in particular the

    requirement to submit a report to DP&E describing remediation options and any preferred remediation

    measures or other course of action;

    Any relevant actions prescribed in the Trigger Action Response Plan (TARP) developed for relevant plans

    of management;

    The current Mining Operations Plan and Rehabilitation Management Plan;

    Sections 7 and 8 of the Northern Region Aboriginal Cultural Heritage Management Plan; and

    In consultation with key stakeholders including any affected land holders and relevant government

    agencies.

    A Response Strategy will be adopted if a significant impact to Aboriginal sites is detected as a result of

    mining activities within the Extraction Plan area.

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 32

    REPORT

    8 Contingency plan

    A Trigger Action Response Plan (TARP) has been developed using the performance indicators for

    management of heritage (Appendix 1). The TARP applies only to the EP Area for Longwall 25 - 31.

    The contingency plan where a performance indicator has been exceeded is outlined in the TARP. A trigger

    will result in additional investigations to determine if the exceedance is related to non-mining-factors or is a

    consequence of mining activity. The response to these exceedances will follow the TARP. Management/

    corrective actions can be implemented where required to remedy these non-conformities and report

    accordingly.

  • 139123 | Aboriginal Cultural Heritage Management Plan | For Mandalong LW25-31 Extraction Plan | 20/8/2018

    Page 33

    REPORT

    9 Reporting and notifications

    Reporting is undertaken in accordance with the requirements of specific requirements of relevant approvals

    and licences including SSD_5144 and generally in accordance with the Guidelines for the Preparation of

    Extraction Plans ‘EP Guidelines’ (NSW Department of Planning and Environment 2015).

    Centennial Mandalong will submit the following reports as detailed in Table 14 during the second workings

    as relevant to management of heritage.

    Table 14 Reporting and Notification Requirements

    Report Triggers Requirements

    Incident1, Reporting Any incident1 relating to heritage in accordance with consent condition 10 (Schedule 6), or as triggered by the TARP.

    Secretary of DP&E, Lake Macquarie City Counci