Project Progress – 31th Oct 2013
STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 31.10.13
1.10th Floor Slab : Completed2.11th Floor Slab : Flat No 1 & 2,4 & 5 flat Bar Bending work In Progress 3rd flat Columns work In Progress
STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 31.10.13
1.10th Floor Slab : Completed2.11th Floor Slab : Flat No 1 & 2 slab Planning Today,4 & 5 Shuttering work in progress,3rd flat Columns Steel
Work In Progress
STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 31.10.13
1.8th Floor Slab : Flat No 01 Slab Completed ,Flat No 02 Planning Today
STATUS REPORT OF MY HOME ABHRA Tower-”D” As On 31.10.13
1.10th Floor Slab : Completed2.11th Floor Slab : Flat No 1 and 2 Completed,4 and 5 flat Bar Bending Work Progress,3rd Flat Columns work In
Progress
STATUS REPORT OF MY HOME ABHRA Tower-”E” As On 31.10.13
1.10th Floor Slab : Completed2.11th Floor Slab : Flat No 1 & 2 Slab Completed ,4 & 5 flats Slab Planning Today ,3rd Flat Slab bar
Bending Completed