Abbreviated Remedial Resettlement Action Plan...
Transcript of Abbreviated Remedial Resettlement Action Plan...
1
Abbreviated Remedial Resettlement Action Plan (ARRAP)
Governmental Complex in
Ramtha Municipality
Municipal Services and Social Resilience Project (MSSRP)
This documents is prepared based on The Project
Resettlement Policy Framework (RPF) December 26, 2013 in line with
OP 4.12 - Involuntary Resettlement OP 4.12, Annex A - Involuntary Resettlement Instruments
Prepared by:
Project Management Unit
February,2019
2
Contents Abbreviations .......................................................................................................................... 3
1.0 Executive Summary ............................................................................................................ 4
1.1 Methodology .............................................................................................. 5
2.0 Introduction and Project Description .................................................................................... 7
2.1 The sub-Project of Governmental Complex in Ramtha Municipality ...................................... 9
2.2 Land Ownership ............................................................................................................13
2.3 Subproject Site analysis ..................................................................................................15
3.0 Kiosk Ownership History ....................................................................................................17
4.0 Project Affected Persons PAPs ............................................................................................23
4.1 Project Affected Households (PAHs) ................................................................................24
4.2 Census Survey ...............................................................................................................24
4.3 Valuation of Assets ........................................................................................................26
4.4 The valuation of kiosk assets during the operation period of Mr. Omar Dardour ...................27
5.0 Resettlement Assistance ......................................................................27
5.1 The compensation packages and resettlement assistance of the current occupants ..............27
5.2 Compensation package of the owner of the original kiosk, Mr. Omar Dardour ......................29
5.3 Summary of Compensation Packages ...............................................................................30
5.4 The compatibility with the external valuation report ................. Error! Bookmark not defined.
Other Benefits of the Compensation Package: ........................................................................30
6.0 Consultations with displaced people about acceptable alternatives ........................................30
7.0 Institutional responsibility for implementation .....................................................................38
8.0 Procedures for grievance redress ........................................................................................41
9.0 Arrangements for monitoring and implementation ...............................................................42
10.0 Timetable and budget ......................................................................................................46
List of Figures .........................................................................................................................47
List of Tables ..........................................................................................................................48
3
Abbreviations
MSSRP Municipal Services and Social Resilience Project ARRAP Abbreviated Remedial Resettlement Action Plan BP Bank Procedures CVDB Cities and Village Development Bank ESMF Environmental and Social Management Framework ESIA Environmental and Social Impact Assessment GRM Grievance Redress Mechanism IR/LA Involuntary Resettlement / Land Acquisition LAL Land acquisition Law MOMA Ministry of Municipal Affairs OP Operational Policy PAPs Project Affected Persons PMU Project Management Unit PM Participating Municipality RAP Resettlement Action Plan RPF Resettlement Policy Framework TOR Terms of Reference PAH Project Affected Household
4
1.0 Executive Summary
This Abbreviated Remedial Resettlement Action Plan (A-RRAP) is conducted for the
Municipal Services and Social Resilience Project, Ramtha municipality sub-project in order to
fulfill the requirements of the Resettlement Policy Framework (RPF) of the MSSRP and the
objectives of world Bank’s (WB) Involuntary Resettlement Policy (OP 4.12) as The overall
objectives of the ARAP are as follows:
1. Involuntary resettlement should be avoided where feasible, or minimized, exploring
all viable alternative project designs.
2. Where it is not feasible to avoid resettlement, resettlement activities should be
conceived and executed as sustainable development programs, providing sufficient
investment resources to enable the persons displaced by the project to share in
project benefits. Displaced persons should be meaningfully consulted and should
have opportunities to participate in planning and implementing resettlement
programs.
3. Displaced persons should be assisted in their efforts to improve their livelihoods and
standards of living or at least to restore them, in real terms, to pre-displacement
levels or to levels prevailing prior to the beginning of project implementation,
whichever is higher.
4.
This Abbreviated Remedial Resettlement Action Plan (ARRAP) is prepared to address the issue
of demolishing one kiosk for the purpose of building a governmental complex in Ramtha
municipality. The complex is partially funded by the MSSRP project FY2018. Five PAPs were
identified as direct affected people from the sub-project implementation. Their households
are also explored for further socioeconomic studies. In-kind and cash compensations are
provided. The total cash compensation is (8,830) JOD. PAPs are also compensated for
transition period allowance and assets transport allowance for two relocations. PAPs are
encouraged to apply to the available job vacancies that the governmental complex will
provide during the construction phase. MSSRP Resettlement Action Plans (RAPs) are
prerequisites for implementation of subproject activities causing economic or physical
displacement. ARAPs may be prepared in the case of less than 200 people are affected, and
there is no physical displacement. IN all cases, the RPF and OP 4.12 requires compensation
measures to be provided before displacement occurs. These measures include provision of
compensation and other assistance required for relocation - prior to displacement as well as
preparation and provision of resettlement sites with adequate facilities. Taking of land and
related assets or denial of access to assets (e.g., resettlement sites, new homes, related
infrastructure, public services, and moving allowances) may take place only after
compensation has been paid to Project Affected Persons (PAPs).
As described in the project RPF, Project Affected Persons (PAPs) are defined as people
who are directly affected socially and economically by Bank financed projects. The direct
social and economic impacts include but are not limited to: a) relocation or loss of shelter, b)
5
loss of assets or access to assets, c) loss of income sources or means of livelihood, whether or
not the affected persons must move to another location, and d) the involuntary restriction or
access to legally designated parks and protected areas that results in adverse impacts on the
livelihood of the affected displaced persons and communities.
This Remedial ARAP has been prepared to address economic displacement impacts
for 5 PAPs as a result of the Ramtha municipality sub-project, the Governmental Complex.
PAPs lost their assets -a demolished kiosk- resulting in loss of income sources and
means of livelihood before compensation has been paid. CVDB highlighted the importance of
conducting a Remedial Resettlement Action Plan (RRAP) before the demolition during the
early site visits. However, the municipality was not aware that the demolition of kiosk before
compensation has been paid would trigger the World Bank’s Operational Policy 4.12. For such
reason, the sub-project was considered non-compliant and a Remedial ARRAP on a
retroactive basis was prepared. According to Jordanian laws, the removal of the kiosk does
not require compensation. This ARRAP provides supplemental measures over and above
Jordanian Law to meet the requirements of the RPF and the grant agreement under MSSRP.
This ARRAP identifies all PAPs, provides an overview of their profile and assesses their
socioeconomic conditions. It also highlights the consultations and compensation measures
proposed, and establish a clear grievance mechanism and the basis for conclusions.
1.1 Methodology
Since the compensation relies on the valuation of assets, a private valuator, who is
certified by the Jordanian Land and Survey Department (LSD), was hired. His report was also
verified by an engineering Consultation Company. The report evaluated the following:
1- The total replacement cost including labor of the kiosk as delivered to the current
occupants on March, 2017. This was done based on the information provided by
the owner of the kiosk. The valuator also contacted the original owner of the kiosk
to identify some missing data.
2- The total replacement cost including labor of the current kiosk. This was done
based on many photos taken before the demolition by CVDB safeguards specialist.
The valuator also considered all information and discussions provided by the
current occupants.
3- Some collected information given by PAPs was also Cross-checked in the
evaluation report, which is found in Annex 2.
6
PMU also conducted several site visits to collect information from PAPs and PM. These site visits are listed in Table 1.
Table 1: PMU site visits
# Date Stakeholders:
PMU, PM, WB, AP(s), CVDB
Specialists: community outreach/ safeguards/
Proc.,etc. Visit Reasons Visit Outputs
1 12th of Augest,2018
PMU, CVDB • The Deputy Project manager
• Procurement specialist
• Feasibility Study Specialist
• The feasibility study
• The overall sub-project circumstances
• Identifying the presence of the kiosk
• The feasibility study.
2 13th of September,2018
PMU, CVDB • Safeguards specialist
• Feasibility Study Specialist
Safeguards non-compliance of demolishing the kiosk.
Urgent actions: Violation removal request presented by the PM on 16th of Sep.,2018
3 2ndof October,2018
PMU, CVDB • Safeguards specialist
• PMU Site engineer
Meeting with design office and field visit to the site
Modifications of the design
4 24th of October,2018
PMU, PM, WB, CVDB
• The Deputy Project manager
• Safeguards specialists
• Community Outreach specialist
• WB Representatives
Discuss the RPF violation with the Mayor
7
2.0 Introduction and Project Description
The objective of the Municipal Services and Social Resilience Project (MSSRP) is to
Support Jordanian municipalities affected by the influx of Syrian refugees in delivering
services and employment opportunities for Jordanians and Syrians. The project (MSSRP)
builds on a successful first phase – Emergency Services and Social Resilience Project (ESSRP)
and will help further achieve the original ESSRP Development Objective, while also supporting
the Government’s commitment towards ‘turning the Syrian crisis into a development
opportunity’ and ‘rebuilding Jordanian host communities’. It aims to mitigate drivers of social
tensions caused by the local impact of the influx of Syrian refugees at the municipal level
through strengthening the processes of municipal service delivery.
Project Components: The proposed second AF will maintain the parent project’s two
main components: (i) Municipal Grants; and (ii) Institutional Support and Project
Management.
Component 1: Municipal Grants (estimated US$27 million)
Municipal grants will be provided annually for a total of 21 municipalities. While the focus under the parent ESSRP was on the provision of timely delivery of services as an emergency response, the proposed second AF will place higher emphasis on sustainability, responsiveness, and efficiency of services in a way that promotes longer-term resilience1 and mitigates risks to social cohesion at local levels. This will be achieved by: (i) focusing on more inclusive community consultations to ensure that investments better reflect Jordanian and Syrian women’s and men’s needs and priorities; (ii) emphasizing that investments made through sub-projects are aligned with municipal strategic planning over the medium-term; (iii) ensuring predictability of funding to allow for better planning that takes into account the cost of operating and maintaining procured assets and longer-term sustainability and resilience needs; and, (iv) encouraging municipalities to use labor-intensive techniques for public works to support the generation of jobs for Jordanians and Syrian refugees. Component 2 – Institutional Support and Project Management (Estimated Amount US$3.0
million)
Activities under this component will include: (i) institutional strengthening with Specialists’ support, (ii) capacity building and trainings, and (iii) technical assistance. Under institutional strengthening, local specialists will be hired, to support and strengthen the oversight and monitoring capacity of the PMU and CVDB while providing implementation support to PMs. The 26 PMs will also benefit from customized technical assistance and training to improve the quality and efficiency of their services, focusing on the following key aspects: (i) improved strategic, financial planning, investment/project planning, and safeguards focus, (ii) improved
8
accountability vis-à-vis the communities through the use of citizen outreach and citizen engagement tools with focus on gender-streamlining, (iii) targeting youth and females through inclusive practices and projects in order to strengthen social cohesion between Syrians and Jordanians. Finally, this Component will finance contracts with other organizations for supporting implementation, including contracts with experts in labor-based works investments. An Innovation Fund (IF) will be introduced under Component 1. This mechanism will incentivize municipalities to compete through competitive proposals for funding of investments. The IF will finance demand-driven projects that may be multi-year and may involve inter-municipality collaboration. The objective of the Innovation Funds is: to promote innovation, cross-municipality learning and partnerships to ensure the achievement of specific outcomes related to (i) generating employment opportunities for Jordanians and Syrians; and (ii) providing improved socio-economic services to communities, with focus on females, youth, and other marginalized groups.
The project is financed through donor contributions to a new Multi Donor Trust Fund
– the Municipal Services and Social Resilience Trust Fund: Government of the Netherlands ($6
million), the United Kingdom (DFID) ($13 million), Government of Canada ($12 million) and
USAID ($3 million) - for the equivalent of US$ 30 million .The Project will aim to achieve a
number of results set out in the Project Appraisal Document.
The implementing agency for the project is Ministry of Municipal Affairs (MOMA)
supported by the Cities and Villages Development Bank (CVDB). A Project Steering Committee
(SC) provides overall strategic direction and oversight to the Project. A Project Management
Unit (PMU) housed in MOMA coordinates and manages overall project implementation.
Executing Agencies (EAs) are the participating municipalities.
9
2.1 The sub-Project of Governmental Complex in Ramtha Municipality
The allocated funds were 14 million assigned for twenty-one municipalities under the
Municipal Sub-grants (MG) Component of the MSSRP. Ramtha municipality’s allocation was
667,000 JOD for the FY 2018. Public consultations were held to set PM priority and strategic
plans as shown in Figure 1. The need of governmental complex came as the first priority,
through conducting several community sessions with the citizens of Ramtha, including men,
women, youth, people with disabilities and Syrians.
The total sub-project cost will approximately reach 2.3 M (JOD). PM Budget of 2018,
2019, and 2020 will finance a total of 1.65 M (JOD) as shown in figure 2, where the remaining
667,000 (JOD) is planned to be financed by MSSRP MGof FY 2018. The Sub-Project Budget is
shown in Table 1 .
Figure 1: Public consultations result in Ramtha municipality
10
Figure 2: letter of allocation for the subproject budget
Table1: The Sub-Project Budget
Funding source Amount (JOD) Number
MSSRP FY2018 668,000 1
PM Budget FY2018 325, 750 2
PM Budget FY2019 662,500 3
PM Budget FY2020 662,500 4
2,318,750 Total
The compound consists of 7 floors as shown in Figure 5. The area of each floor is 1250
m2. The basement floor is designed to be a multipurpose hall. The hall was designed for
meetings, concerts, or events. It will be the first one in Ramtha city. Other floors will be rented
to different governmental agencies (e.g. Department of Land and Survey, Directorate of
Labor, Health Directorate)
11
Figure 3: Front Perspective of The Complex
The governmental agencies will be gathered in one building to serve the city of
Ramtha, not only the population of the municipality. Ramtha city consists of two
municipalities as shown in figure 4, these two municipalities are participating in the MSSRP.
1- Ramtha municipality:
a. Alramtha
b. Albouydah
2- Sahel Horan municipality
a. Alturah
b. Alshajarah
c. Emrauah
d. Thunaibah
Figure 4: The City of Ramtha
12
Figure 5: PM letter sent to governmental agencies and their responses
The governmental complex will be a one stage project. The entire building will be
constructed in one bidding contract. During the construction activities, the subproject is
expected to 1) boost local spending into the local economy, 2) create job opportunities for
local residents and 3) generate employment for local unskilled and semi-skilled workers.
Construction activities and associated negative impacts were presented during the
community consultation session held in Ramtha Municipality on 13th of January, 2019, for the
purpose of conducting an ESIA for the same sub-project. The ESIA will cover the sub-project
objectives, environmental and social impacts, analysis of sub-project alternatives,
environmental and social management plan and the mitigation measures of implementing
the sub-project. At the operational stage, the complex will 1) improve the landscape with
green spaces 2) minimize the cost and effort since the existing Governmental agencies are
spread in different locations around the city and 3) minimize the traffic congestions. The
economic feasibility outcomes are summarized in the ESIA document The complex will be
socially feasible helping government to effectively deliver services to local community,
Jordanians and Syrian refugees. According to the feasibility study, there are eight
governmental entities that are willing to rent offices in the governmental complex with a total
amount of income that will reach 251,650 JDs (almost 366,000$) per year. The municipality,
which is currently renting a building on the main street of Ramtha, will be able to use this rent
in other aspects and useful ways to delivering more services to the community, once the
complex is finished and the municipality starts using its own offices.
13
2.2 Land Ownership
The land is owned by the Hashemite kingdom of Jordan Treasury / Ministry of
Municipal Affairs shown in figure 9. The land is assigned to build a governmental complex in
Ramtha municipality as described in the title deed. However, such ownership needs to be
reassigned every year. Figure 6 shows a letter from CVDB requesting the PM to clarify the
ownership status of the land. MoMA sent a formal letter to the land and survey department
(LSD) to reassign the land. Figure 7 shows the response of the LSD describing that the land is
already assigned to build a governmental complex in Ramtha municipality since 2011, and the
decision was validated again in January, 2019, as the letter indicates.
Figure 9: the title deed of the land
14
Figure 6: correspondences to reassign the subproject land
15
Figure 7: The Assignment Letter by the department of land and survey
2.3Sub-project Site analysis
The subproject land is almost located in the middle of Ramtha city with 80 m along
the main street of Alsakhrat Almusharifa as shown in Figure 8. The availability of public
transportation raises the strategic importance of the proposed land, which is the most
appropriate land for constructing such a complex. The municipality owns other lands but is
far away from the center of the city. This specific site was chosen years ago, since 2011, in
order to minimize resettlement to the extent possible compared to other sites People would
only need one transportation to get there minimizing the cost and effort. The existing
Governmental agencies are spread in different locations around the city in which traffic jam
could be a serious problem. In addition, most of the city population works in public sector
agencies. Gathering such population in one place could achieve the social feasibility of the
16
proposed subproject. The location of the proposed land is also near very important
governmental buildings such as schools, healthcare center and Public Park. The coordinate of
the land (32.55905815, 36.00076154) could be used to observe clearer information about
neighboring land properties. Such importance makes the subproject socially feasible. Other
important information is listed in Figure 4 and Table 2.
Figure 8: the locationof the proposed landusing the Department of Land And Survey website
Table 1: Sub-Project Land Basic Information
Parameter Value
Governorate Irbid governorate
City Al Ramtha
Land number 161
Neighborhood 29
Total Area(m2) 6,186.00
Near the Location 1. Comprehensive health center. 2. Musab bin Omair Secondary School for Boys. 3. Ramtha Health Directorate. 4. IbnHazm Elementary School. 5. Public Park.
On Main Street Yes, AlsakhratAlmusharifaSt.
17
3.0 Kiosk Ownership History
The subject of this A-RAP is limited to 50 m2 kiosk situated on the proposed project
land of 6000 m2as shown in Figure 11. There were three owners/operators of the kiosk since
it was first erected on the site in 2011 and the structure underwent several reconstructions.
Such changes are shown in Figures 10,11 and 12. The kiosk was located on the main street at
the corner of the land to be used for building the governmental complex. Figure 12 shows
some photos of the kiosk taken on October, 2018.
A) B)
Figure 10: Google earth photo in A) 2009 for the land B) the first appearance of the in 9/2012 with area less than 40 m
Figure 11: Google earth photo shows the kiosk in 2/2017 with area 50 m2
18
Figure 12: The kiosk, Kazem cafe.
The development of the kiosk started on 2010 when the PM rented out a piece of land
with total area of 24 m2 to Mr. Jamal Abdel Aziz (52 years old) on 29th of June, 2010. The
contract gave the right to build a Ramadan tent during the holy month. The goal of this tent
was selling locally grown fruit and vegetables. The contract is shown in figure 13a.The rental
agreement states that the tenant has to pay a nominal annual amount of 100 (JOD). On 23th
of February, 2016Mr. Jamal sold the tent to Mr. Omar AlDardour as shown in figure 14. No
rental payments have been received by the PM since then.
19
Figure 13: The rental agreements between PM and Mr. Jamal Abdel Aziz
20
Figure 14: The Selling Agreement between Mr. Jamal Abdel Aziz and Mr. Omar Al Dardour
After that, Mr. Omar AlDardour used part of the land and rebuilt the skeleton of the
kiosk. The following summarizes Mr. Omar AlDardour activities:
1- Mr. Omar AlDardour bought the kiosk from Mr. Jamal Abdel Azizfor3,000 JOD.
2- The kiosk is made of wooden walls, steel tubes, and steel sheet ceiling.
3- Mr. Omar AlDardour expanded the kiosk by 16 m2 using same materials with total
cost of 1,000 JOD.
4- Mr. Omar AlDardour did not sign any agreement/contract with the PM.
5- Mr. Omar AlDardour did not pay any monthly rent to the PM.
6- Mr. Omar AlDardour rented the kiosk to Mr. Ahmad Abdul-Aziz on March, 2017
with 125 JOD per month as shown in figure 13b.
7- Mr. Omar AlDardour is the owner of the “original kiosk”.
21
Figure 15: the rental agreements between Mr. Omar and Mr. Ahmed
Since March, 2017, Mr. Ahmad Abdul-Aziz launched internal partnership with his
brother Mr. KhalidAbdul-Azizto operate the kiosk as a part time job sharing the profit equally
with other two full-time operators. The full-time operators are Mr. Khalid Abdul-Aziz’s sons:
Mr. Ali and Mr. Khazim. These 4 operators are referred to here as the “current occupants“
who did major modifications to the kiosk. These modifications are listed in the following
sections.
22
Figure 14: Kiosk Ownership History
PM sent a formal letter of evacuation to the current occupants on 16thof September,
2018as shown in figure 16.a.PM demolished the kiosk on 26th of September,2018. The
current occupants had a 10 days period to evacuate the kiosk and move their assets, which
they indicated was sufficient.
23
Figure 16: Evacuation removal request presented by the PM
4.0 Project Affected Persons PAPs
Project affected persons are shown in Table 2 and further illustrated in figure
18. From the discussion above, it is noted that the operation of the kiosk may not be in
conformity with the original leasing conditions.
Table 2: PAPs
# PAPs Name
1 The current owner of the kiosk.
Mr. Omar Dardour.
2 The current occupants.
Mr. Ahmad Abdul-Aziz, Mr. KhalidAbdul-Aziz, Mr. Ali KhalidAbdul-Aziz, and Mr. Khazim Khalid Abdul-Aziz.
Total 5
24
Figure 18: PAPs
4.1 Project Affected Households(PAHs)
Project Affected Households (PAHs) are shown in figure 19. There are 4 households
with a total of 19 persons involved. Detailed information can be found in the Census survey
of PAPs in Annex 2, as the PMU conducted socio-economic surveys for each PAP.As described
by the RPF, each person receiving compensation will have a dossier containing:
• Individual bio-data information,
• Number of people s/he claims as household dependents,
• Level of income and of production through an inventory of material assets and
improvements in land, and debts.
4.2 Census Survey
A census survey of each of the 5 PAPs and their households which is found in Annex 2
also covers the requirement of OP 4.12:
• In Selecting the current occupants of the affected area to establish a basis for
the design of the resettlement program and to exclude subsequent inflows of
people from eligibility for compensation and resettlement assistance;
• Draw the standard characteristics of displaced households, including a
description of production systems, labor, and household organization; and
baseline information on livelihoods (including, as relevant, production levels
25
and income derived from both formal and informal economic activities) and
standards of living (including health status) of the displaced population;
• Describe the magnitude of the expected loss in total or partial of assets, and
the extent of displacement, physical or economic.
According to the census surveys of the five PAPs:
1. PAP Khalid (male) has a total household of seven personnel: wife and two daughters, three
male boys and his elderly mother who is 77 years old. He owns a house in Ramtha and works
as a driver in the Ministry of Agriculture, with a total salary of $645 per month. He also owns
two pieces of land in Ramtha area. PAP Ali and PAP Kazim –Khalid’s sons- lost their source of
income due to the demolition of the kiosk. PAP Ali is married and has two daughters, while
PAP Kazim is still engaged.
2. PAP Ahmad (male), Khalid’s brother, is married and has no children. He owns a house and
a piece of land in Ramtha area, but also lost his source of income due to the demolition of the
kiosk.
3. PAP Omar (male) has a total household of six personnel: wife and two daughters, three
male boys who have no jobs. Omar was an English teacher but currently retired with a total
retirement salary of $707 per month. He owns a house and used to take a monthly rent from
PAP Ahmad with a total amount of $177 per month. He bought the kiosk from its previous
owner with a total amount of $4,238. PAP Omar acknowledged the fact that the land is owned
by the municipality, and he did not pay any rent for the municipality whatsoever.
Detailed survey census of all PAPs, are found in Annex 2, as well as the consent papers and
their signed approvals to disclose the ARRAP with all relevant information stated in the
document.
26
Figure 19: Project Affected Household (PAH)
4.3. Cutoff date
The cut-off date is required to prevent opportunistic influx/rush migration into the
chosen land areas. Cut-off date can be set as the date when the census of affected persons
was first conducted. The date of conducting the first Census Survey was on 6th of November,
2018, and so is considered as the Cut-off date. Mr. Jamal Abdel Aziz was excluded since he
sold the kiosk on 23th of February; 2016 and was no longer impacted by the sub-project
implementation.
4.4Valuation of Assets
As described by the RPF documents of the MSSRP project, Replacement values will be
based on the methodology described earlier, as the private evaluator prepared a detailed
report on evaluation of the demolished kiosk according to a number of photos taken by the
CVDB team during former visits. This methodology includes, also:
1- Drawings of individual's house[structures] and all its related structures and
support services.
2- Average replacement costs of different types of household buildings and
structures based on information on the quantity and type of materials used for
construction (e.g. bricks, rafters, bundles of straw, doors etc.).
3- Prices of these items collected in different local markets and as provided by the
Ministry of Public Works and Housing.
4- Costs for transportation and delivery of these items to acquire/replace land or
building site.
5- Estimates of construction of new buildings including labor required.
27
The result of the valuator report is summarized in the following table, and it matches
the estimate of the current occupants as shown in the evaluation report Annex 2.
Table 8: Evaluation of destroyed assets provided by the external valuator.
# Assets Cost estimate provided by external valuator JOD
Finish
ing co
st
1 Security glass door 600
2 Signage of the kiosk 270
3 Washbasin and Marble 200
4 External and internal lighting 300
5 false ceiling 400
6 Total 1,770
7 Replacement cost including labor 3000
8 Total replacement cost including labor
4,770
4.4 The valuation of kiosk assets during the operation period of Mr. Omar Dardour
The kiosk was rented by M. Omar Dard or to the current occupants in March 2017.
Valuation of the kiosk as delivered to the current occupants on that date is listed in table 9.
The private valuator called Mr. Omar AlDardour to determine the full replacement cost of
the kiosk at time of rental.
Table 10: valuation of the original kiosk as delivered to current occupants on March, 2017
Assets
1 Steel door The rep
lacemen
t cost in
clud
ing
labo
r pro
vided
by th
e externa
l
valu
ato
r JOD
2,0
00
JO
D
2 wooden walls
3 Plastering and painting
4 Tiles
5 steel sheet ceiling and tubes
6 Two aluminum windows with its protecting steel
nets
7 External and internal lighting
5.0 Resettlement Assistance
5.1 The compensation packages and resettlement assistance of the current occupants
According to the project RPF, the current occupants are considered as:
28
1- Owners of non-Permanent buildings: Entitled to in-kind compensation or cash
compensation at full replacement cost including labor and relocation expenses,
prior to displacement. 2- They are facing “loss of income sources or means of livelihood”. Whether or not
the affected persons must move to another location, it requires that PAPs should
be assisted in their efforts to improve their livelihoods and standards of living or
at least to restore them, in real terms, to pre-displacement levels or to levels
prevailing prior to the beginning of project implementation, whichever is higher.
Suggested ways of compensation include:
a. Compensation for land and reconstruction structure/buildings and
facilities.
b. Compensation for loss in production.
c. Provision for continuance of employment of workers affected from
relocation during the transition period through provision of temporary
premises, or compensation for lost wages.
It is important to highlight the following information:
1- Transition period allowance is considered from the day of kiosk demolition to the
expected date of ARAP implementation, which is calculated to be 6 months. This is
considered sufficient time for PAPs to n find another job.
2- Provision of transport allowance will be provided, both retroactively for transport of
moveable assets before demolition, and at the time when the current occupants can
relocate to the new kiosk location.
3- PAPs will be offered the opportunity for preference in employment opportunities for
the sub project (loader driver, security guard and construction workers). Creating job
opportunities is one of the major goals of the MSSRP project in which local
communities and Syrian refugees are benefiting from 5% of the sub-project budget as
direct employment.
4- The PM and the PMU were open to discuss different options of compensation
suggested during conducting this A-RAP.5- After approving the suggested
compensation Packages, PMU ensures that:
a- The valuation report was provided to PAPs to review the report and submit
grievances if unsatisfied. The report served as a basis for negotiations with PAPs.
b- PAPs also were given the option of hiring a certified valuator of their choice if
they decide to contest a valuation, but none of them requested that.
29
The suggested compensation package of the current occupants is listed in table 11.
Table 11: Entitlement matrix of the current occupants (tenants)
# Item Period Amount JOD
Total JOD
Type of compensation
1 Compensation for lost assets and
livelihood
In kind compensation through provision of new kiosk in
complex, with initial occupancy fee waived.2
2 Transition period allowance for loss
of business income from old kiosk
6 months 10003 6,000 Cash payment
2 assets transport allowance for two
relocations
80 80 Cash payment
4 Additional Measures Of Employment
Employment opportunities for PAPs during construction of
complex.
Total 6,080
5.2 Compensation package of the owner of the original kiosk, Mr. Omar Dardour
According to the project RPF, Mr. Omar Dardour occupants are considered as
1- Owner of non-Permanent buildings: Entitled to in-kind compensation or cash
compensation at full replacement cost including labor and relocation expenses,
prior to displacement.
Mr. Omar AlDardour will be given the following compensation listed in Table 12.
Table 12: Compensation package of the owner of the original kiosk Mr. Omar Dardour.
# Item Period Amount JOD
Total JOD
Type of compensation
1 Transition period
allowance for loss of rental
income
6 months 1254 750 Cash payment
2
3Estimate of monthly income from kiosk provided by PAPs 4Monthly rent as per rental agreement
30
2 Compensation for lost assets
2,000 2,000 Cash payment
3 Additional Measures Of Employment
Employment opportunities for PAPs during construction of
complex.
Total 2,750
5.3 Summary of Compensation Packages
Table 13: Summary of Compensation Packages for all PAPs
# PAPs Name Total Cash Compensation
JOD
Additional Measures Of Employment
Resettlements
1 The current occupants.
Mr. Ahmad Abdul-Aziz, Mr. Khalid Abdul-Aziz, Mr. Ali, and Mr. Khazim.
6,080 Yes Yes
2 The owner of the original
kiosk.
Mr. Omar Dardour. 2,750 Yes No
Total 8,830
Other Benefits of the Compensation Package include:
1- Providing legal employment opportunities to the current occupants during and
after the construction of the sub-project.
2- The current occupants will have social security insurance during their work with
the contractors of the sub-project.
3- At the end of the construction activities, AP(s) will be able to register the kiosk as
a legal place of earning money. The kiosk will be rented to the current occupants
without initial occupancy fee.
6.0 Consultations with displaced people about acceptable alternatives
1- The alternatives considered to avoid or minimize resettlement:
Key points highlighted by the PM:
1- The governmental complex was given priority number one in the community
consultations conducted earlier which raises the importance of the sub-project.
31
2- PM does not have any other suitable land, since the land chosen was already
assigned to build a governmental complex in Ramtha.
3- The design of the governmental complex was already completed.
Prior to the demolition, the current occupants were not satisfied with the solution of
demolishing the kiosk without cash compensation for the lost assets mentioned so far, but
then agreed with the solution of compensation of a new kiosk in the governmental complex.
An internal agreement was signed between the current occupants and the PM, after
demolition took place. This agreement is shown in figure 21. PMU was not a part of this
agreement.
32
Figure 21: Agreement between PM and current occupants to rent a kiosk in the governmental complex without a vacancy payment which is waved
33
Table 16: communications and consultations with PAPs
# Date Stakeholders: PMU, PM, WB, AP(s), CVDB
Reasons outputs
1 16th of September, 2018
PM, and the current occupants
letter of evacuation the current occupants evacuate the kiosk
2 26th of September, 2018.
PM, and The current occupants
Demolition of the kiosk
3 23rd of Dec.,2018
PM, the current occupants
Commitment types that PM could give to the current occupants.
A commitment letter in which the PM agreed to give the current occupants new kiosk without vacancy cost .
4 6th of Nov.,2018
PMU, CVDB, the current occupants
Held an Interview with the current occupants.
The Social and economic studies for Khalid family. Discuss and identify compensation options with the PAPs.
5 13th of January, 2019
PMU, CVDB, the current occupants.
Completion of any missing information.
The Social and economic studies for Khalid family.
34
Discuss and identify compensation options with the PAPs described in the previous sections.
6 20th of January, 2019
PMU, Mr. Omar Dard our
Completion of any missing information.
The Social and economic studies for Omar family. Discuss and identify compensation options with the PAPs described in the previous sections.
Table 17: Summary of the main outputs of the surveys and interviews with the PAPs
Outcomes Time and Date Meetings with PAPs
- Assess his social and economic conditions, And prepare a report about the case, with all relevant official documents.
6/11/2018 Tuesday
Interview with Mr. Khaled
-Determine Affected Households(PAHs) of the PAPs. -Current occupants selected Mr. Khalid Abdul-Azizas a representative to act and negotiate on their behalf. -Since March, 2017, Mr. Ahmad Abdul-Aziz launched internal partnership with his brother Mr. Khalid Abdul-Aziz to operate the kiosk as a part time job sharing the profit equally with the other two full-time operators; Mr. Ali and Mr. Kazim. - PM demolished the kiosk on 26th of September, 2018. The current occupants had a 10 days period to evacuate the kiosk and move their assets.
13/1/2019 Sunday
Interview with Mr. Khaled, Ali, Kazem, Ahmed
35
- Mr. Khazim Abdul-Aziz told the team that the process of moving the assets needed just one day using one pickup. - Removal of the kiosk did affect the monthly income of the current occupants as they had no other source of income, except for Mr. Khalid Abdul-Aziz. - The net profit of the kiosk was equally divided between the current occupants. - Evaluation of the original kiosk as delivered to current occupants on March, 2017 and improvements that have been added to the building.
- Mr. Omar AlDardour is the owner of the original kiosk. -Mr. Omar AlDardour was aware that the land was owned by the PM, and proceeded to on-lease it to another person. - Mr. Omar AlDardour bought the kiosk from Mr. Jamal Abdel Azizfor3,000 JOD. - Mr. Omar AlDardour expanded the kiosk by 16 m2 using same materials with total cost of 1,000 JOD. - Mr. Omar AlDardourdid not sign any agreement/contract with the PM. - Mr. Omar AlDardour did not pay any monthly rent to the PM.
20/1/2019, Sunday
24/1/2019 Thursday
Mr. Omar Dardour did not allow the PMU member to meet him personally. Information given by Mr. Omar Dardour was collected through a phone call.
36
- Mr. Omar AlDardour rented the kiosk to Mr. Ahmad Abdul-Azizon March, 2017 with an amount of 125 JOD per month.
Consultation with PAPs took place in the municipality building on February 4th, 2019. The purpose of conducting the ARAAP document was briefly
explained to them, compensation packages were discussed with them as well and then approved and signed. Also, the Independent Evaluation
Report was explained to each PAP. They also read all the information stated in their socioeconomic surveys and signed it for approval. It was
explained to them that their names and the names of their household will be disclosed publically on WB official site, and they signed for approval
regarding this issue. No concerns were raised by the PAPs. PAP Khalid provided a written document stating that he represents PAPs: Ahmad, Ali
and Kazim.
Minutes of Meeting with the PAPs and their approval on all relevant documents are found in Annex 2.
37
Figure 22: Meeting with PAPs, and approval of main parts of ARAAP
38
7.0Institutional responsibility for implementation
This section describes the institutional arrangements for the implementation of the A-RAP.
The small scale and relatively simple nature of the displacement action does not warrant many special
institutional arrangements that may be required in larger sub-projects. Thus, this sub-project will rely
on mechanisms and institutions that are already in place. These are presented below in table 17. The
ARAP work plan is illustrated in Table 18.
Table 18: Institutional responsibility
# Institutions Responsibility
1 PMU, MoMA. preparing and submitting the A-RAP for the WB, which is a remedial plan as the kiosk was already demolished, in our case
2 WB provides technical support and advice as appropriate to enhance the PMU capacity and experience. The ARAP requires clearance by the WB.
3 MoMA, as the implementing agency
disclosing this A-RAP on WB official website, translate into Arabic and made available to the PAPs
4 MoMA, PMU 1- Ensuring the overall implementation of the A-RAP in a satisfactory manner that would satisfy the WB Guidelines.
2- ensuring financial arrangements
3- Post monitoring and reporting on the overall implementation.
4- Liaising with different institutions and stakeholders who have roles in the implementation of the proposed A-RAP.
5 Ramtha Municipality
1- implementing the suggested compensation and resettlement assistance
2- providing the necessary commitment letter in which PM gives
• The current occupants a new kiosk without initial vacancy cost
• The current occupant’s employment opportunities when construction of the sub-project starts
• The cash compensation to all PAPs suggested earlier from the Municipality allocation of FY2018.
39
Table 19: ARAP Work Plan, Expected by End of February, 2019
No. Task description Responsibility start date End date Status Outputs and taken actions
1 Submitting revised copy of the Abbreviated Remedial Resettlement Action Plan to WB Social Safeguards Specialists
PMU October,2018
24, January,2019
In progress
1- Approved compensation scheme. 2- Adequate Census survey.
2 Meeting of displaced persons PAPs.
PMU,PAPs 1, February,2019
4, February,2019
Done 1- Describe the compensation scheme to PAPs.
2- Sign the valuation of assets by PAPs. 3- Complete any missing data. 4- Describe the procedures for grievance
redress to PAPs.
3 Submission of written Grievances, (if any)
PM, PAPs 5, February,2019
7, February,2019
Planned 1- Valuation report, if PAPs hired another one.
5 Project design modifications
PM, PMU and the design office.
11, February,2019
15, February,2019
Planned 1- Verified design documents taking into account the valuator report, in case PM agrees.
6 Issuing the compensation packages
PMU, PAPs, PM
11, February,2019
15, February,2019
Planned • Issuing the cash compensation packages
No. Task description
Responsibility
start date End date Status Outputs and taken actions
8 hiring the current occupants: filling out subproject vacancies
PMU,PM, AP(s).
As sub-project gets started.
planned
40
10 The resettlement of AP(s): giving the new kiosk (The physical relocation).
PM By the end of sub-project construction.
planned Relocation to the new kiosk site.
11 Monitoring and Evaluation
PMU, and MOMA.
1, January,2018
31, December,2019
planned 1- Grievances redress mechanisms.
12 Sub-project Construction Commencement Date
PM and Contractor
May, 2019 May, 2020 planned Sub-project finished and kiosk handed to current occupant PAPs
41
8.0 Procedures for Grievance Redress Mechanisms
To ensure that all PAPs have a safe, reliable, and accountable means for their
grievances to be heard, a specific arrangement is suggested as it is a confined situation in our
case; the kiosk demolition and the appropriate way of compensation of the land and the
assets: A Grievance Committee shall be formed. Members include:
1- MSSRP Project Manager or Deputy
2- Safeguards specialist in CVDB
3- Community Outreach specialist/PMU
4- Representative from Local Development Unit in Ramtha Municipality
5- Representative chosen by PAPs
This GC will be responsible for the following tasks:
- The Committee will receive and register the complaints.
- The Committee will respond to the complainant with a rational justification describing
the process by which the complaint was considered and explain the reasons behind
any decision taken by the Committee.
- The Committee will meet periodically and as required to review the received
complaints.
- The Committee will consider each complaint on a case-by-case basis to determine
whether the case constitutes a valid complaint, if so, the Committee is required to find
a fair and just solution to the claim.
- Decisions will be made by consensus, and properly documented.
- There is already a GRM established for the MSSRP Project. In Ramtha case, it could be
through using different tools such as Ramtha Municipality official website, face book
page, GRM log and direct calls to the mayor and municipal staff and engineers. Those
channels could be used by the PAPs as well, and also through informing the PMU of
any grievances, directly.
42
9.0 Arrangements for monitoring and implementation
The main objective of the monitoring exercise is to enable PMU and other stakeholders
to follow up on the progress of the process and make sure that everything is on track in terms
of deliverable on the required time. Additionally, the monitoring seeks to identify perceptions
and levels of satisfaction of those affected of the activity. Main inputs, output and outcomes
are presented in the following table as the list of deliverables. However, the process is
obviously created to try to find a satisfying solution to the issue. Therefore, the main outcome
is to achieve satisfaction of those affected by the process.
Two forms of monitoring are required:
- Internal monitoring that will be undertaken by both PMU in MoMA and CVDB, and
Ramtha Municipality. This monitoring will ensure that the A-RAP is being implemented
in a proper and satisfactory way to all stakeholders including the PAPs and get their
feedback on the A-RAP implementation.
- WB Monitoring through supervision missions to review the progress of the A-RAP and
reference their findings in Aide memoires.
When preparing a monitoring plan, it needs to be taken into consideration that everyone
involved in the process of the actual activity to be involved in the monitoring plan as well. This
will be specifically in terms of collecting information required for each indicator. These parties
include, but not limited to the following:
1. PMU staff
2. Mayor
3. Relevant municipality staff
4. M&E
There are two main levels of indicators included in this monitoring exercise :
1. Process level indicators: are those that are represented as deliverable of the
activity .
2. Outcome level indicators: are those indicators identified in the table below.
These indicators will allow decision makers and stakeholders of the activity to find out
whether the process followed has resulted in a satisfying outcome or not. Also it will provide
lessons learned to improve the process in similar future situations. The monitoring work plan
will be based on the compensation and resettlement work plan in terms of process level
indicators. However, the outcome monitoring should start immediately after the
compensation and resettlement activities are completed to capture the highest possible level
of reactions and perceptions around it, while relevant people are still remembering the
process followed.
43
The monitoring plan will track the progress of the implementation plan step by step and ask
questions on the methodologies used and whether or not planned activities were
completed. This is to make sure that relevant stakeholders have sufficient information in
order to help evaluating the process as well as the outcome.
The below table shows the monitoring indicators that will be used to measure the identified
outcome and track the process followed. It is important to note that the table includes the
indicators that will be measured by multiple methodologies/questions using different forms
of collecting data as follows:
1. Extracting information from the PMU/PM records. There will be specific tool for this.
2. Key informant interview with PMU and PMs. There will be specific tool for this.
3. Key informant interview with affected people. There will be specific tool for this.
44
Table 20: monitoring indicators
Indicator Unit of measurement
Frequency Responsibility
Data Source
number of affected people disaggregated by sex
Number Semi-Annually PMU, PM PMU records/interview with PMs and PMU staff
Zone of impact of the demolishing the kiosk
text Semi-Annually PMU, PM PMU records/interview with PMs and PMU staff
size of financial losses disaggregated by sex
Number Semi-Annually PMU, PM PMU records/interview with PMs and PMU staff
Prepare socioeconomic studies including valuation of compensation
yes/No and text
once PMU PMU records/interview relevant PMU staff
Type and design of resettlement plan text once PMU PMU records/interview relevant PMU staff
number of agencies responsible for resettlement activities
Number once PMU PMU records/interview relevant PMU staff
conduct the agreed compensation plan
yes/No and text
PMU, PM PMU records/interview with PMs and PMU staff
zone of impact of the resettlement plan
text once PMU, PM PMU records/interview relevant PMU staff
number of people benefiting from the resettlement plan disaggregated by sex
Number once PMU, PM PMU records/interview relevant PMU staff
45
Table 20: monitoring indicators cont.
Indicator Unit of measurement
Frequency Responsibility Data Source
extent to which affected people are satisfied with the process
scale one week after the process completion
PMU, PM
KI interview with all affected people discussing the levels of satisfactions and very important to take it further and discuss reasons of dissatisfaction and other solution methodologies could have been taken into consideration
extent to which affected people are satisfied with the outcome of the process
scale one week after the process completion
PMU, PM
KI interview with all affected people discussing the levels of satisfactions and very important to take it further and discuss reasons of dissatisfaction and other solution that could have been taken into consideration
extent to which municipality is satisfied with the process
scale one week after the process completion
PMU, PM KI interview with relevant people at the municipality to see their take on the process followed and its outcome
extent to which other stakeholders are satisfied about the process and outcome
scale one week after the process completion
PMU, PM interview with relevant stakeholders
Zone of impact according to affected people
text one week after the process completion
PMU, PM KI interview with affected people
the magnitude of the affected loss according to affected people
text one week after the process completion
PMU, PM KI interview with affected people
preferred resettlement alternatives according to affected population
text one week after the process completion
PMU, PM KI interview with affected people
46
10.0 Timetable and budget
Table 21 summarizes the A-RAP Components cost estimation. The sub-components of
direct compensation are only valid, if the AP(s) don’t take the employment opportunity or not
eligible to sub-project employment vacancies. As discussed so far, the PM assigned one of the
10 kiosks to the AP(s) as discussed in the Institutional responsibility section. The PM will not
take any initial vacancy cost form the AP(s). However, AP(s) need to sign up yearly-based
contract in which the monthly rent will be charged.
Table 21: A-RAP Components cost estimates
A-RAP Components
A-RAP Subcomponents
The Subcomponents
Cost (JOD) Sources of Funds
Time for Expenditures/
Assignment
Compensation
Cash compensation
3,955 Component - 1: Municipal Grant
of Ramtha municipality of FY
2018.
Immediately
Employment Opportunity
Null Embedded within The subproject
budget
As subproject launches
Resettlement Program
Free Kiosk5 Null Immediately
5The initial cost will be null; however monthly rent will be charged.
47
List of Figures
Figure 1: Public consultations result in Ramtha municipality ........................................................................................................................................ 8
Figure 2: letter of allocation the subproject budget .................................................................................................................................................... 9
Figure 3: Front Perspective of The Complex .............................................................................................................................................................. 10
Figure 4: The City of Ramtha ................................................................................................................................................................................... 10
Figure 5: PM letter sent to governmental agencies and theirresponses ........................................................................................................................ 11
Figure 6: correspondences to reassign the subproject land......................................................................................................................................... 12
Figure 7: The Assignment Letter by the department of land and survey ....................................................................................................................... 13
Figure 8: the locationof the proposed land using the Department of Land And Survey website ...................................................................................... 14
Figure 9: the title deed of the land........................................................................................................................................................................... 14
Figure 10: Google earth photo in A) 2009 for the land B) the first appearance of the in 9/2012 with area less than 40 m .................................................. 16
Figure 11: Google earth photo shows the kiosk in 2/2017 with area 50 m2 .................................................................................................................. 16
Figure 12: The kiosk, Kazem cafe. ............................................................................................................................................................................ 16
Figure 12: the rental agreements between a) PM and Mr. Jamal Abdel Aziz b) Mr. Omar and Mr. Ahmed ....................................................................... 17
Figure 13: Kiosk Ownership History.......................................................................................................................................................................... 18
Figure 19: the monthly salary of the operator Khalid for the past 3 years ..................................................................................................................... 19
Figure 15: Violation removal request presented by the PM ........................................................................................................................................ 19
Figure 14: meetings held between PAPs and PMU ..................................................................................................................................................... 20
Figure 15: PAPs ..................................................................................................................................................................................................... 21
Figure 16: Project Affected Household (PAHs) ........................................................................................................................................................... 22
Figure 20: The final copy of the design documents of the complex: subproject site layout ............................................................................................. 29
Figure 21: A commitment letter .............................................................................................................................................................................. 32
Figure 22: Meeting with PAPS and approval of main parts of ARAAP ........................................................................................................................... 35
48
List of Tables
Table 1: Sub-Project Land Basic Information ............................................................................................................................................................. 15
Table 2: PAPs ........................................................................................................................................................................................................ 20
Table 3: the area of the kiosk .................................................................................................................................................................................. 23
Table 4: some basic information about the kiosk ....................................................................................................................................................... 23
Table 5: Sold or consumed items ............................................................................................................................................................................. 23
Table 6: list of saved equipment .............................................................................................................................................................................. 23
Table 7: valuation of destroyed assets provided by the current occupants. .................................................................................................................. 24
Table 8: valuation of destroyed assets provided by the external valuator. .................................................................................................................... 24
Table 9: Valuation information of the kiosk on March, 2017 ....................................................................................................................................... 25
Table 10: valuation of the original kiosk as delivered to current occupants on March, 2017 ........................................................................................... 25
Table 11: Compensation package of the current occupants ........................................................................................................................................ 26
Table 12: Compensation packages of the owner of the original kiosk Mr. Omar Dardour. .............................................................................................. 28
Table 13: Summary of Compensation Packages for all PAPs ........................................................................................................................................ 28
Table 14: Benefits gained from the resettlement (the new kiosk in the governmental complex) ..................................................................................... 30
Table 15: PMU site visit .......................................................................................................................................................................................... 33
Table 16: communications and consultations with PAPs............................................................................................................................................. 34
Table 17: survey outputs and interviews with PAPs ................................................................................................................................................... 34
Table 18: Institutional responsibility ........................................................................................................................................................................ 35
Table 19: ARAP Work Plan ...................................................................................................................................................................................... 36
Table 20: monitoring indicators ............................................................................................................................................................................... 41
Table 21: monitoring indicators cont. ....................................................................................................................................................................... 42
Table 21: A-RAP Components cost estimates ............................................................................................................................................................ 43
49
Annexes
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74