Abbey Renovation Update

14
Abbey Renovation Update

Transcript of Abbey Renovation Update

Page 1: Abbey Renovation Update

Abbey Renovation Update

Page 2: Abbey Renovation Update

#1 Permits

• Architectural, structural, electrical, plumbing etc. Submitted & accepted

• Fire alarm drawing and permit application submitted & accepted

• Low voltage drawing and permit application submitted & accepted

• HVAC permit application submitted & accepted

• All requested information has been provided and we now finally have a permit

Page 3: Abbey Renovation Update

#2 Demo/Masonry

Window openings are done CMU openings at door frames into suites are done Complete brick at door frames in stairwell Power wash building exterior All complete except for following items: Set steel beams at baths 207 and 208 Parapet wall at south end staircase leaning due to water

damage

Page 4: Abbey Renovation Update

#3 Asbestos Abatement

• Removed plaster insulation at pipe fittings

• 9x9 floor tiles at closet

• Found additional ACM behind walls which were removed

Page 5: Abbey Renovation Update

#4 Millwork

• Wardrobes are built and in finishing process

• Window unit fabrication started approximately 1/25/18. Fabrication is three weeks (2/12 ish)

• TV cabinet fabrication will start after window units and will be another three weeks (2/26 ish). Then second floor bookcases, and then laundry room.

• Fine line recommends the two shelves at the bottom of the cabinet be staggered so the areas at the back can be utilized

• Fine line have been notified to modify the millwork in the novice master/assistant novice masters rooms

• Anticipated completion would be 4/1/18 or later

Page 6: Abbey Renovation Update

#5 Plumbing

• Rough plumbing for laundry room and baths 207/208 continuing.

• All bathroom rough is complete

• Currently working on corridor baseboard heat lines

• Hot Water Baseboard:

• Existing baseboard in the corridor had to be removed to install new entry frames

• Window baseboard heaters were removed and new HVAC units will take care of both heating/cooling

Page 7: Abbey Renovation Update

HVAC

• To start work week of 1/2/18

• Ductwork is in progress

• Refrigerant piping is in progress

• HVAC rough to be complete by 2/05

• Roof layout complete.

• Duct penetrations complete

• Curbs on roof.

Page 8: Abbey Renovation Update

#8 & 9 Carpentry/Doors, Frames, and Hardware

• Scheduled to start framing 12/27 or 12/28.

• Arches between bedroom/living rooms have been eliminated. Openings to be square

• In progress with framing

• Soffit on hold pending room A/C unit install

• Gypsum/spackle to start immediately after rough inspections received

• Doors and hardware are ready. Need heating system to be in operation and constant building temperatures required before doors can be delivered.

Page 9: Abbey Renovation Update

Windows

• Installation complete

Page 10: Abbey Renovation Update

#11,12 & 13

• Ceramic Tile:

• All material is available and waiting for gypsum/spackle prior to installation

• Wood Flooring/Carpet:

• All material is available

• Constant temperatures required before material can be delivered

• Electric:

• Rough electric 90% complete. Inspection ready early next week

• New panels to be installed/scheduled for delivery of 2/05/18

Page 11: Abbey Renovation Update

• Laundry Room:

• Final architectural and MEP layout and room elevation sketches are done.

• Mechanical roughing in progress

• Appliance cut sheets provided and roughing is in progress

Page 12: Abbey Renovation Update

• Emergency Call System to Nurses Station:

• To be added in each room

• Finishes:

• Paint colors have been selected

• West side Entrance/Road:

• Widen roadway to allow emergency vehicle access

• Grade area to have storm water flow away from building

• Change proposals to write:

• Demo and steel headers in two bathrooms

• Light gage framing at wet wall only in five bathrooms

• Adding rigid insulation to wardrobe exterior wall (material only)

• Insulation at all exterior walls

• Light gage framing at window wall (material only)

• Electric heaters in five (5) bathrooms

• Supply and install two doors with full glass at laundry room

• Additional twelve (12) recessed lights for bedrooms and baths

• Novice master and assistant novice masters bathrooms to be modified to include shower/faucet and toilet.

Page 13: Abbey Renovation Update

#16 West side Entrance/Road

• Widen roadway to allow emergency vehicle access

• Grade area to have storm water flow away from building

Page 14: Abbey Renovation Update

Happy New Year as we slide closer towards success. Thank you