AAAC Meeting: October 12, 2005 ALMA Update: October 2004-October 2005 Bob Dickman ALMA Staff...
-
Upload
nicholas-hood -
Category
Documents
-
view
212 -
download
0
Transcript of AAAC Meeting: October 12, 2005 ALMA Update: October 2004-October 2005 Bob Dickman ALMA Staff...
AA
AC
Me
eti
ng
: O
cto
be
r 12
, 20
05 ALMA Update:
October 2004-October 2005
Bob DickmanALMA Staff Associate
Division of Astronomical Sciences
AA
AC
Me
eti
ng
: O
cto
be
r 12
, 20
05
Events Reviewed
• Antenna procurement
• Rebaselining
• Cost Review
• Near Future
AA
AC
Me
eti
ng
: O
cto
be
r 12
, 20
05 Rebaselining
• Fall 2004: Rebaselining begins March 2002 project baseline antedates formal project
agreements and Japanese participation
• September 2005: “Final” re-baseline cost estimate (JAO) Assumptions
Common antenna type, ESO maintains procurement schedule, and 50-element array starting point
Increase in cost: Antennas Other areas
List of possible changes/descopes/scrubs NSF working hard to buttress overruns: descopes,
considering deferrable work, additional partnerships
• November 2005 goal: New Project Baseline (Scope, Cost and Schedule) in place
AA
AC
Me
eti
ng
: O
cto
be
r 12
, 20
05 Rebaselining: Cost Escalation Sources
• Antennas Delay for coordinated procurement Commodity price increases: oil, steel, nickel
• Site Booming Chilean economy Dollar/peso exchange rates
• Management Joint ALMA Office, including Project Management &
Control System (PMCS) Costs of partnership
• Systems Engineering and Integration Complexity of project
• Other (e.g., missing scope, etc.)
AA
AC
Me
eti
ng
: O
cto
be
r 12
, 20
05 Cost Review
• Lehman-style cost review
• Review requested by ALMA Board Report will be passed on to NSF and ESO Council
• 4 days: October 13-16, 2005
• Detailed assessment of Cost Schedule Management Initial assessment of integrating Japan Enhanced ALMA;
early operations; operations
• Panel: Chair: Steve Beckwith Vice-Chair: Thijs de Graauw 20-member panel
7 members each nominated by NA and ESO 4 members nominated by Japan 2 members nominated by Chile
• Report timed to fit needs of ALMA Board, NSF
AA
AC
Me
eti
ng
: O
cto
be
r 12
, 20
05 Antenna Procurement: I
• Parallel procurement required by different legal regimes and practices of partners
• Each partner provides half the total number of antennas
• Highly coordinated, based on purchase of two prototypes
• Goal is manufacture of a single design
• Start: December 2003. Bumps in the road: Prototype performance:
Late questions about (mainly) one prototype arose Summer-Fall 2004
Extended testing program given to JAO; settled in early 2005 (both prototypes are excellent)
Coordinated procurement broke down in June 2005 with the interruption of the ESO procurement
AA
AC
Me
eti
ng
: O
cto
be
r 12
, 20
05 Antenna Procurement: II
• In June 2005, ALMA Board urged NSF/AUI/NRAO to proceed with a unilateral NA procurement
• This approach was supported by ESO Council
• NRAO signed antenna contract July 11, 2005
• Significantly higher costs than even 1 year earlier: Commodity cost increases Assume all NRE (recoverable) Loss of quantity discount (recoverable)
AA
AC
Me
eti
ng
: O
cto
be
r 12
, 20
05 Antenna Procurement: III
• ESO making rapid progress on procurement
NSF action has accelerated process On schedule to complete by end of October ESO Council endorsed a 50-element array
• Both prototype designs still in the running in Europe
AA
AC
Me
eti
ng
: O
cto
be
r 12
, 20
05
Immediate Future: Milestones
• ALMA Cost review: October 13-16
• ALMA Board acts on ESO antenna choice: November 1
• NSF-USG decision process to select and authorize new baseline: October 2005 - March 2006
• New Baseline put in place
AA
AC
Me
eti
ng
: O
cto
be
r 12
, 20
05
Challenges
• Operations Costs
• U.S. Cost increase Non-Defense
discretionary budgetary climate