A/47/12 (Sept. 22 to Oct 1, 2009) – slide 1 The WIPO New Conference Hall Project Documents A/47/12...
-
Upload
noah-eustace-owens -
Category
Documents
-
view
213 -
download
0
Transcript of A/47/12 (Sept. 22 to Oct 1, 2009) – slide 1 The WIPO New Conference Hall Project Documents A/47/12...
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 1
The WIPO New Conference Hall Project
Documents A/47/12 and WO/PBC/14/10Behnisch Architekten brochure
Updated model of the WIPO buildings complexModel for the proposed New Hall
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 2
Long-standing need for meeting facilities for WIPO
Issue raised by the Secretariat since the 1990s
► 1998Member States approved the launching of studiesfor a new building and a new conference hall
► 2002Member States approved proposalsfor a new building, a new conference halland additional parking reserved for delegates
The Secretariat continues to watch trends
► Evolution of membership to treaties► New treaties► Evolution of attendance to meetings► Evolution in the working environment for international meetings
(See WO/PBC/14/10, Part III, Annex I, Tables I-1, 2, 3)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 3
WIPO activities: looking ahead
More than 100 years
► Late 19th century: Paris and Berne Conventions► 2nd half of 20th century: normative and registration activities► 21st century: IP and global issues
The new WIPO Strategic Goals
► WIPO as the leading intergovernmental forum for addressingintersections between IP and global public policy issues
► Effective trusted communication at all levels
Resulting in a new working environmentnot limited to plenary sessions
► More multilateral discussions► More bilateral discussions► More interactions and interdependence between various Unions
(See WO/PBC/14/10, Part III)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 4
The New Conference Hall Project “Phase One”
December 2008Approval by Member States of "Phase One"
Phase One: from December 2008 to September 2009
► To be prepared by the Architect and the specialists:
► Complete architectural and technical project[high-level description in Architect brochure]
► Complete dossier ready for subsequent submission toGeneva Authorities as full application for building permit
► To be prepared by the Secretariat:
► Detailed proposal and budget estimate for "Phase Two"[document WO/PBC/14/10]
(See WO/PBC/14/10, Part II)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 5
Project “Phase Two”
September 2009
► Examination of the detailed Project► Recommendation by the PBC
► Decision by the Assemblies
From October 2009 onwards: Phase Two
► If the Project is approved by the Assemblies:Execution of the Project by the Secretariat
► October 2009 to October 2010: tender process► start of construction in January 2011► completion of construction in December 2012
(See WO/PBC/14/10, Part II and Annex III)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 6
WIPO needs for large- and medium-size meetings
THREE issues
the required combination of rooms
for the required number of days
during the required period
(See WO/PBC/14/10, §12)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 7
Minimum needs for the Assemblies
ONE LARGE meeting room (800+ seats)
At least 12 BREAKOUT ROOMS for Delegates
7 for Countries Groups (some with interpretation)1 for Groups Coordinators4 for bilateral meetings
At least 12 OFFICES for Assemblies Chairs and Secretariat
2 individual offices for Chairs of Assemblies (General Assembly, etc.) 10 individual or shared offices for WIPO Secretariat
(for a minimum of 15 staff)
All the above for9 to 10 consecutive days
(+ 3 to 4 days for setting up and removal,if meeting held off-site)
(See WO/PBC/14/10, Annex I, Table I-5)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 8
Minimum needs for a representative set of medium-size meetings(Standing Committees, IGC, CDIP, PBC, etc.)
ONE medium-size meeting room (300+ seats)
At least 12 BREAKOUT ROOMS for Delegates
7 for Countries Groups (some with interpretation)1 for Groups Coordinators4 for bilateral meetings
At least 7 OFFICES for Committee Chair and Secretariat
1 individual office for Chair of Committee6 individual or shared offices for WIPO Secretariat
(for a minimum of 10 staff)
All the above for2 to 5 consecutive days for each meeting
(+ 2 to 3 days for setting up and removal,if meeting held off-site)
(See WO/PBC/14/10, Annex I, Tables I-5, 6)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 9
Average YEARLY needs for a representative set of medium-size meetings
Average number of delegates per sessionCurrently 200 to 350+
Horizon 5 years 300 to 400+Horizon 10 years 400 to 500+
Standing CommitteesCopyright (SCCR)
IT (SCIT)Patents (SCP)Trademarks (SCT)
CDIPPBCInternational Authorities____________________________TOTAL
[* Based on 10-year data]
Number ofsessions*
2222221
________13
sessions
Number ofdays*
101010101052
________57
days
(See WO/PBC/14/10, Part III, §12)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 10
Average YEARLY needs for large AND medium-size meetings
Number of Numbersessions of days
Assemblies 1 10Medium-size meetings 13 57______________________________________ _____ _____
TOTAL 14 67 sessions days
MONTHLY AVERAGE=
more than ONE meetingmore than 5 DAYS
[~ 7 days per MONTH, when discounting Aug., mid-Dec. to end Jan.]
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 11
Is the CICG an acceptable alternative ?
► For the WIPO Assemblies► In the 6-year period from 2008 to 2013► Reservations made up to 5 years in advance
CICG availability confirmed for all days, all rooms and during requested period
ONLY FOR 2010 and 2013fully positive alternative only in 33% of cases
Other years in the same period► 1 year no availability (2009)► 1 year still on waiting list (2012)► 2 years availability for less than number of days required (2008, 2011*)
[* 2011: ITU asked if WIPO could vacate the CICG. UNOG can offer either only one large room and 2 breakout rooms on the required dates, or it can offer the required rooms but only if the dates are changed to the period during the ITU TELECOM (no hotels available within
acceptable distance), which would not be feasible for WIPO.]
(See WO/PBC/14/10, Part IV, §23)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 12
Is the UNOG an acceptable alternative ? (1)
In the last 10 YEARS, WIPO has NOT been able to obtain:
► the required combination of rooms► for the required number of days
► during the required periods
From time to time,WIPO could have obtained one large or medium-size meeting room, but:
► either ONLY a few breakout rooms -- however always less than 7 Some Countries Groups would have had to hold their breakoutsessions at UNOG and the other Groups at WIPO
► either ONLY for some days of the sessions
► or on different dates (more availabilities at UNOG in August, and from mid-December to end January)
(See WO/PBC/14/10, Part IV, §22)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 13
Is the UNOG an acceptable alternative ? (2)
UNOG gives priority to
► its own meetings► the UN Programs meetings ► the UN Commissions meetings► meetings called by the UN New York
UNOG considers only in December of each year for the coming yearrequests from other Organizations, such as WIPO
UNOG does not offer to Delegates coming from the capitals the same flexibility as offered by WIPO for registration
► after the deadline specified in the invitation circular► or easily and promptly on arrival, regardless of the day of arrival
during the meeting
[This is the case of 20% of Delegates coming to WIPO meetings]
(See WO/PBC/14/10, Part IV, §22)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 14
WIPO Member States agenda and work programs
► The Secretariat should have sufficient flexibilityin offering WIPO Member States
► options for holding their various types of meetingsAssemblies, Standing Committees, Working Groups, etc.
► in accordance with their respective agenda and priorities► within a timeframe that fits within their decision-making processes
► WIPO Member States when deciding on their own meetings should not continue to be negatively impacted
► by the limited availabilities at WIPO and elsewhere in Geneva ► by the meetings schedules of the UN and other UN Organizations ► by the holding of other types of international meetings in Geneva
(See WO/PBC/14/10, §20)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 15
Project description: the Conference Hall per se
► 900 seats (871 + 29)
► 9 interpretation booths and one technical booth
► Foyer for 1000 persons
► Facilities for Delegatesloungedocument counterInternet deskscloakrooms
► Other related facilitiespress roominterpreters meeting roometc.
with access toreserved delegates parking
in underground currentlyunder construction
(See Architect brochure andWO/PBC/14/10, Part V)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 16
Project description: the related AB Building modifications
AB mezzanine: additional meeting (breakout) rooms ► 2 rooms (each with 24 seats, 3 interpretation booths)► 1 room (with 20 seats)► 3 rooms (each with 15 seats)
AB lobby enlargement► several additional small lounge areas for delegates► relocation of the Visitors’ Center
AB forecourt and access► re-sizing entrance area: security clearance and registration desk► relocating access ramp to AB Building underground parking
(including for parking reserved for Delegates)
AB underground► improvement of existing facilities
(in particular to replace facilities in rented premises)
(See Architect brochure andWO/PBC/14/10, Part V)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 17
Increasing the number and range of larger meeting rooms
900
765
341325
27086
New Hall
Room B Room A
ByJan 2013
(9 languages)(6 languages)(3 languages)
The New Hall would not be dividable. Two meetings could not be held concurrently in the Hall. The Hall could however easily be used in more than one configuration.
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 18 [Languages: (2) (3)]
24 24 20 15 15 15(3) (3)
14 24 36 37 (2) (2) (3)
24 24
New byJan 2013
No longeravailable from
Jan 2011
AB BUILDING
13th floor======================================
=Mezzanine
Rentedbuildings
38 31 40 20 20(2)
New Building
Replaced inJan 2011 by
14
Increasing the number and range of (breakout) meeting rooms
From 9 to ….....15 rooms2009 2013
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 19
Other specific features of the Project
► UN H-MOSS compliance
► ACCESSIBILITY facilitatedin particular, for physically-impaired and visually- impaired persons
► ENVIRONMENTALLY-friendly construction
► Could be used by (and rented to) EXTERNAL PARTIES► possibility integrated in the architectural design from the start► therefore available for non-WIPO-related meetings
for WIPO Member Statesfor other IP stakeholdersfor other entities, organizations, parties
(See WO/PBC/14/10, §§ 13, 14, 38, 59, 60)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 20
Total estimated cost of the Project (Phase One and Phase Two)
Construction costs, honoraria, fees CHFNew Hall per se 55,300,000Modifications to AB Building/new building + 8,900,000
____________= 64,200,000
Amount for Phase Oneapproved in December 2008, to be deducted - 4,200,000
Provision for Miscellaneousand Unforeseen (6%) + 4,000,000
SUB-TOTAL = 60,000,000
REMAINING TOTALsubject to recommendation and decision = 64,000,000
(See WO/PBC/14/10, Part VII)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 21
Proposed financing
Total construction cost, honoraria, fees (CHF) 60,000,000Provision for Miscellaneous and Unforeseen 4,000,000
AMOUNT remaining to be financed 64,000,000
PROPOSED FINANCING 64,000,000
Appropriation from WIPO Reserves 24,000,000Extension of existing commercial loan 40,000,000
EFFECT on regular budget(as from biennium 2012-2013) 1,600,000
Interest on commercial loan 1,300,000Administrative fees and charges 300,000
(See WO/PBC/14/10, Part VII)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 22
Project management structure
To be based on existing management structure for ongoing construction
► Construction Committee► Internal Project Monitoring Team
► Architect and other engineers► Pilot
► Project Charter► Risk Registers (Pilot and WIPO)
► Selection Board ► additional new mandate (selection of future General Contractor) ► updated composition
to be based on 2009 Assemblies newly elected officersto replace 2005 officers
(See WO/PBC/14/10, Part VI)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 23
Project control and audit
To be based on existing specific control and audit for ongoing construction
► External Auditor
► WIPO Audit Committee
► Internal Auditor
► Legal advice fromthe Institute for Swiss and International Construction Law
(University of Fribourg)
(See WO/PBC/14/10, Part VI)
A/47/12 (Sept. 22 to Oct 1, 2009) – slide 24
Thank you for your attention.