A3 Report Out Kitting Project June 1, 2009

6
Exercise Lean LLC Prepared by John Petak 864.363.0984 Implementation/Action Plan A3 Project Summary Background / Business Case : Initial Condition : Project Leader: John F. Petak Team Members: Mike Campbell, Laura Carden Frederick Cosby Project Name : Trust Technologies , Inc. Warehouse Kitting Project Indicators/Measurables : Future Condition : Trust Technologies currently supplies Woodward FST 4 parts on daily pull system. We would like to delivery in 7 kits 37 part references from on site warehouse to include 5 other supplies to Woodard FST. This would generate savings for Woodard FST on floor space, inventory reduction, manpower utilization, potential freight costs. C urrentState Future State Target Target Savings A ctual Savings % Change Floor Space 200 sq ft 350 sq ft 3.4% People 2 2 2.0 Freight TBD TBD Inventory 12 units 12 units - Jan Feb M arch April M ay June July A ug S ept O ct N ov D ec 1. J.P etak 4 hrs G reen 2. J.P etak,F C osby 2 hrs G reen 3. J.P etak .5 hrs G reen 4. J.P etak 2 hrs 5. J.P etak 2 hrs G reen 6. J.P etak 2 hrs G reen 7. J.P etak 4 hrs G reen 8. J.P etak,C M anley 9. J.P etak,C M anley 10. J.P etak,C M anley 11. J.P etak,C M anley 12. J.P etak,C M anley 13. J.P etak,C M anley 14. J.P etak,C M anley 15. J.P etak 16. J.P etak 17 J.P etak 18 J.P etak 19 J.P etak 20 RFQ P rinter& S cannerforhandling paperw ork J.P etak,R S tudart 21 Total - $ 0 0 TotalS tatus Prepared by: Planned StartDate A ctual StartDate Status: E xercise Lean LLC -John P etak Finish Date Finish Date G reenTargetA chieved C oncept,D esign,P rocure,Test,V alidate,S tartP roduction M ilestone Com pleted M ilestones Y ellow Targetin Jeopardy Duration Period Duration Period Red TargetM issed No P roject S ingle A ctions E xplanation ofC urrent S tatus O n tim e delivery Actual R esults($) O thertargets: M easurable Targets: W alk W oodw ard FS T value stream s S tatus O w ner C oncept.define 7 kits forflow lanes footprint Im plementation Expense ($) B uild w orksheetP FE P V alue stream m ap currentstate 4 Trustparts VSM W oodw ard FS T com ponents C onceptdesign kitforS w ozzle 601P 065-01 Tim e S chedule 2009 C oncept,design kitforA ssem bly -A ssy S w irlerA dpate 601P 054-01 C reatfuture state V S M forkiting proposes C oncept,design kitforS hroud -W eld assy IFC 601P 554-01 Target R esults ($) C oncept,design kitforA ssem bly-W eld P rem ix Tip Tub 601P 058-01 C onceptdesign kitforFlange 520P 451-01,02 TrustTechnologies,Inc -G reenville,S C K itting C om ponents -W FST & Trust Trustto W ooodw ard FS T John F. P etak W e currently supply 4 parts to W oodw ard FST on daily basis.They are Flange 520P451-01,02;S wozzle 601P065-01,; Fuel Tip A sem bly 520P 464-01 thru 12;Fuel Tip Assem bly 520P 750-01 and w e w ould like to expand this to central "pick" w arehouse system which w ould include 33 partreferences from W FST and 4 from TrustTechnologies,Inc. B usiness U nit/Facility: V alue S tream : V alue S tream Loop: V alue S tream O wner: C onceptdesign kitforFuelTip A ssem bly 520P 464-01 thru 12 C onceptdesign kitforFuelTip A ssem bly 520P 750 -01 RFQ forfoam inserts for7 kits /C arts C oncept,design layoutforkiting C oncept,design kitforR ing-B razing 506P 399-65 C oncept,design kitforA ssem bly-W eld O uterB ellow s 601P 055-01 C oncept,design kitforA ssem bly 601P 056-01 C oncept,design kitforA ssem bly -W eld D iffTip Tube 601P 057-01 0 0 0 0 0 1 1 1 1 1 1 previous year Feb A pril June A ug O ct D ec P rojectM etric

description

 

Transcript of A3 Report Out Kitting Project June 1, 2009

Page 1: A3 Report Out Kitting Project June 1, 2009

Exercise Lean LLCPrepared by John Petak864.363.0984

Implementation/Action Plan

A3 Project Summary

Background / Business Case:

Initial Condition:

Project Leader: John F. Petak

Team Members: Mike Campbell, Laura CardenFrederick Cosby

Project Name: Trust Technologies , Inc. Warehouse Kitting Project

Indicators/Measurables:Future Condition:

Trust Technologies currently supplies Woodward FST 4 parts on daily pull system. We would like to delivery in 7 kits 37 part references from on site warehouse to include 5 other supplies to Woodard FST. This would generate savings for Woodard FST on floor space, inventory reduction, manpower utilization, potential freight costs.

Current State Future State Target Target Savings

Actual Savings

% Change

Floor Space 200 sq ft 350 sq ft 3.4%

People 2 2 2.0 Freight TBD TBD

Inventory 12 units 12 units

-

Jan Feb March April May June July Aug Sept Oct Nov Dec

1. J. Petak 4 hrs Green

2. J. Petak, F Cosby 2 hrs Green

3. J. Petak .5 hrs Green

4. J.Petak 2 hrs

5. J.Petak 2 hrs Green

6. J. Petak 2 hrs Green

7. J.Petak 4 hrs Green

8. J.Petak, C Manley

9. J.Petak, C Manley

10. J.Petak, C Manley

11. J.Petak, C Manley

12. J.Petak, C Manley

13. J.Petak, C Manley

14. J.Petak, C Manley

15. J. Petak

16. J. Petak

17 J.Petak

18 J. Petak

19 J. Petak

20 RFQ Printer & Scanner for handling paper work J.Petak, R Studart

21

Total -$ 0 0 Total Status

Prepared by: Planned Start Date Actual Start Date Status:

Exercise Lean LLC - John Petak Finish Date Finish Date GreenTarget Achieved

Concept, Design, Procure, Test , Validate, Start Production Milestone Completed MilestonesYellow Target in Jeopardy

Duration Period Duration Period Red Target Missed

No Project Single Actions

Explanation of Current Status

On time delivery

Actual Results($)

Other targets:Measurable Targets:

Walk Woodward FST value streams

StatusOwner

Concept. define 7 kits for flow lanes footprint

Implementation Expense ($)

Build worksheet PFEP

Value stream map current state 4 Trust parts

VSM Woodward FST components

Concept design kit for Swozzle 601P065-01

Time Schedule 2009

Concept, design kit for Assembly - Assy Swirler Adpate 601P054-01

Creat future state VSM for kiting proposes

Concept, design kit for Shroud - Weld assy IFC 601P554-01

Target Results ($)

Concept, design kit for Assembly- Weld Premix Tip Tub 601P058-01

Concept design kit for Flange 520P451-01,02

Trust Technologies, Inc - Greenville, SCKitting Components - WFST & TrustTrust to Wooodward FSTJohn F. Petak

We currently supply 4 parts to Woodward FST on daily basis. They are Flange 520P451- 01,02; Swozzle 601P065-01, ; Fuel Tip Asembly 520P464-01 thru 12; Fuel Tip Assembly 520P750-01 and we would like to expand this to central "pick" warehouse system which would include 33 part references from WFST and 4 from Trust Technologies,Inc.

Business Unit/Facility:Value Stream:Value Stream Loop:Value Stream Owner:

Concept design kit for Fuel Tip Assembly 520P464-01 thru 12

Concept design kit for Fuel Tip Assembly 520P750 - 01

RFQ for foam inserts for 7 kits / Carts

Concept, design layout for kiting

Concept, design kit for Ring- Brazing 506P399-65

Concept, design kit for Assembly- Weld Outer Bellows 601P055-01

Concept, design kit for Assembly 601P056-01

Concept, design kit for Assembly - Weld Diff Tip Tube 601P057-01

00000111111

previous year

Feb April June Aug Oct Dec

Project Metric

Page 2: A3 Report Out Kitting Project June 1, 2009

Exercise Lean LLCPrepared by John Petak864.363.0984

Storage LocationParts @ CleanParts @ Process Parts @ Pick

Point of Use Dock Door

601P054601P055601P056601P057601P058

601P054601P055601P056601P057601P058

601P054601P055601P056601P057601P058

601P054601P055601P056601P057601P058

Supervisor

Warehouse

Shipping &

receiving

Production

Planner

EPE DailyPeople 2OHI 12Floor Sp 48sq ft

EPE DailyPeople 2OHI 12Floor Sp 6 sq ft

EPE DailyPeople 2OHI 12Floor Sp 45 sq ft

EPE DailyPeople 2OHI 12Floor Sp 0

Picker Picker

Work orders 601P057

Move to kitting area

Direct Ship

castings

Direct Ship all

Components

Current State Woodward FST

June 1, 2009

Current State – Woodward FST

Page 3: A3 Report Out Kitting Project June 1, 2009

Exercise Lean LLCPrepared by John Petak864.363.0984

Woodward FST

Current State – Trust Technologies, IncWoodward FST

Woodard FST

Accurate Brazing

EMJ

Aerodyne

520P451-01,02

540”

630”36

Daily

520750-01

25’

Daily36

6 hrs

520P464-01,12

2,215”

0

Daily

36

601P065

Daily

368 hrs

2,688”

Forecast 6-8 wks

E mails, phone calls

E mails, phone calls

Fork Truck

540 sec 2,215 sec 25 min 2,688 sec

3 days 1 day 2 days 3 days

VSM – Kitting Project

Current State Map

Daily

520P451,01,02

630”

540’

36

Daily

Page 4: A3 Report Out Kitting Project June 1, 2009

Exercise Lean LLCPrepared by John Petak864.363.0984

36parts /day

601P054-01

36parts /day

601P052-01

36parts /day

601P056-01

36parts /day

601P055-01

36parts /day

601P554-01

36parts /day

601P057-01

36parts /day

601P058-01

520P452-01

601P062-01

520P464-01

601P061-01

601P060-01

520P459-01

116E4680P001

601P065-01

601P053-01

601P064-01

#1KIT

#7KIT

#6KIT

#5KIT

#4KIT

#2KIT

#3KIT

601P063-01

520P581-01

601P059-01

520P464-01

520P750-01

520P578-01

520P578-02

520P577-01

520P580-01

520P579-01

520P451-01

506P405-87

506P406-26

506P408-26

506P407-97

506P409-51

506P406-40

506P399-65

506P400-03

520P467-01

520P468-01

520P862-88

522P014-01

Phone CallsPrinter/ScannerE-mails

Phone CallsE-businessE-mails Woodward

Trust

Future State – Trust Technologies, Inc.

Fork Truck Deliverydaily milk runs

Meetings

Meetings

Kitting Associate

Target = Pull & pick 1 kit every 1.5 hrs

Page 5: A3 Report Out Kitting Project June 1, 2009

Exercise Lean LLCPrepared by John Petak864.363.0984

Page 6: A3 Report Out Kitting Project June 1, 2009

Exercise Lean LLCPrepared by John Petak864.363.0984