A Stochastic Programming Approach to Natural Gas Portfolio and Transpofrt Optimisation BSc

download A Stochastic Programming Approach to Natural Gas Portfolio and Transpofrt Optimisation BSc

of 83

description

Stochastic Programming

Transcript of A Stochastic Programming Approach to Natural Gas Portfolio and Transpofrt Optimisation BSc

  • 1

    A Stochastic Programming Approach to Natural Gas Portfolio and

    Transport Optimization

    Ketty Hua

    A thesis submitted in partial fulfillment

    of the requirements for the degree of

    BACHELOR OF APPLIED SCIENCE

    Supervisor: Roy H. Kwon

    Department of Mechanical and Industrial Engineering

    University of Toronto

    March 2008

  • 2

    Abstract

    The purpose of this Thesis is to develop and compared linear programming models that will balance

    and optimize a natural gas portfolio and transport problem. We have developed and compared

    models using three approaches: deterministic, stochastic minimizing the expected cost, and

    stochastic minimizing the Conditional Value-at-Risk. The Stochastic models implemented are based

    on a two-stage stochastic model with integer recourse. Numerical examples using stylized data are

    shown to illustrate the differences in the optimal decisions determined from the models.

  • 3

    Acknowledgements

    This thesis is supervised by Professor R.H. Kwon who provided me with guidance in research and

    enlightenment through discussions.

  • 4

    Table of Contents

    Abstract ................................................................................................................................................................................ 2

    Acknowledgements ............................................................................................................................................................. 3

    List of Figures ...................................................................................................................................................................... 5

    List of Tables ....................................................................................................................................................................... 6

    CHAPTER 1 - INTRODUCTION ................................................................................................................................ 8

    1.1 Natural Gas Market in North America ................................................................................................................ 8

    1.2 Financial and Operations Risk Management ....................................................................................................... 9

    1.3 Natural Gas Network and Portfolio ................................................................................................................... 11

    1.4 Risk Measure Tools and Methodology ............................................................................................................... 14

    1.4.1 Value-at-risk .................................................................................................................................................... 14

    1.4.2 Conditional Value-at-risk (CVaR)................................................................................................................ 15

    1.5 CVaR Minimization ............................................................................................................................................... 16

    1.6 Stochastic Programming ....................................................................................................................................... 17

    1.7 CVaR Minimization Approach in Stochastic Programming ........................................................................... 19

    CHAPTER 2 PROBLEM FORMULATION ......................................................................................................... 20

    2.1 Deterministic Approach ....................................................................................................................................... 20

    2.2 Stochastic Approach Minimizing Expected Cost ......................................................................................... 28

    2.3 Stochastic Approach Minimizing CVaR ......................................................................................................... 32

    CHAPTER 3 COMPUTATIONAL RESULTS ..................................................................................................... 34

    3.1 Deterministic Approach ....................................................................................................................................... 35

    3.2 Expected Cost Approach ..................................................................................................................................... 43

    3.2.1 Deterministic demand ................................................................................................................................... 43

    3.2.2 Stochastic demand ........................................................................................................................................ 54

    3.3 CVaR Approach ..................................................................................................................................................... 64

    Conclusion ......................................................................................................................................................................... 76

    APPENDIX : REFERENCES ...................................................................................................................................... 77

    OPL format for Deterministic Model ........................................................................................................................... 78

    OPL Format for Stochastic Model with minimizing Expected Cost ....................................................................... 80

    OPL format for stochastic model with minimizing CVaR ........................................................................................ 82

  • 5

    List of Figures

    Figure 1 Source: NYMEX, Impact of events on Natural Gas Prices ........................................................................ 9

    Figure 2 Source: Petroleum Encyclopedia, Oil and Gas Journal, Schematic Diagram of North American

    Market Hubs ...................................................................................................................................................................... 11

    Figure 3 Source: US Energy Policy, Schematic Diagram of North American Producing Basins ........................ 11

    Figure 4 Source: CAPP, North American Transport Pipeline Network ................................................................. 12

    Figure 5 Schematic diagram of the Flow of gas between locations within a gas network .................................... 20

    Figure 6 Portfolio loss distribution of the Expected Cost Approach and CVaR Approach ................................ 65

  • 6

    List of Tables

    Table 1 Fixed and variable volume market forwards .................................................................................................. 34

    Table 2 Storage capacity limits, unit costs, injection/withdrawal rate...................................................................... 34

    Table 3 Production costs and limits from Sources/Supplies..................................................................................... 35

    Table 4 Demand requirement for each of the time period in MMBtu .................................................................... 37

    Table 5 Spot market prices at each of the time period in $/MMBtu ....................................................................... 37

    Table 6 Capacity Acquisition Strategy for Deterministic Approach, all units are stated in MMBtu, unless

    otherwise indicated ........................................................................................................................................................... 38

    Table 7 Overall Cost of the System using the Deterministic Approach, all units are stated in MMBtu unless

    otherwise indicated ........................................................................................................................................................... 39

    Table 8 Spot Market Trading Profits from Deterministic Approach, all units are stated in MMbtu unless

    otherwise indicated ........................................................................................................................................................... 41

    Table 9 Cost to Meet Demand from Deterministic Approach, all units are stated in MMbtu unless otherwise

    indicated ............................................................................................................................................................................. 42

    Table 10 Spot market prices in the three scenarios considered ................................................................................ 43

    Table 11 Cost to Meet Demand for the Three Scenarios Considered Using Stochastic - Minimizing Expected

    Cost Approach .................................................................................................................................................................. 44

    Table 12 Capacity Acquisition Strategy for Stochastic Expected Cost Approach (Deterministic Demand), all

    units are stated in MMBtu, unless otherwise indicated ............................................................................................... 45

    Table 13 Overall System Cost for Stochastic Expected Cost Approach (Deterministic Demand), all units are

    stated in MMBtu, unless otherwise indicated ............................................................................................................... 47

    Table 14 Spot Market Transaction for Stochastic Expected Cost Approach (Deterministic Demand), all units

    are stated in MMBtu, unless otherwise indicated ........................................................................................................ 50

    Table 15 Cost to Meet Demand Stochastic Expected Cost Approach (Deterministic Demand), all units are

    stated in MMBtu, unless otherwise indicated ............................................................................................................... 53

  • 7

    Table 16 Stochastic Demand Values ............................................................................................................................. 54

    Table 17 Capacity Acquisition Strategy for Stochastic Expected Cost Approach (Stochastic Demand), all units

    are stated in MMBtu, unless otherwise indicated ........................................................................................................ 55

    Table 18 Overall System Cost for Stochastic Expected Cost Approach (Stochastic Demand), all units are

    stated in MMBtu, unless otherwise indicated ............................................................................................................... 57

    Table 19 Total Profit from Spot Market Trading Transactions for Stochastic Expected Cost Approach

    (Stochastic Demand), all units are stated in MMBtu, unless otherwise indicated .................................................. 60

    Table 20 Total Cost to Meet Demand for Stochastic Expected Cost Approach (Stochastic Demand), all units

    are stated in MMBtu, unless otherwise indicated ........................................................................................................ 63

    Table 21 VaR and CVaR with various beta values for UB for forward type= 10.................................................. 65

    Table 22 VaR, CVaR, Maximum number of forwards purchased with respect to varying UB for forward type

    .............................................................................................................................................................................................. 65

    Table 23 Expected loss and standard deviation with the expected cost and CVaR approaches ......................... 66

    Table 24 Capacity Acquisition Strategy for Stochastic Minimizing CVaR Approach with =0.99, all units are

    stated in MMBtu, unless otherwise indicated ............................................................................................................... 67

    Table 25 Overall System Cost for Stochastic Minimizing CVaR Approach with =0.99, all units are stated in

    MMBtu, unless otherwise indicated ............................................................................................................................... 69

    Table 26 Total Profit from Spot Market Transactions for Stochastic Minimizing CVaR Approach with

    =0.99, all units are stated in MMBtu, unless otherwise indicated ........................................................................... 72

    Table 27 Total Cost to meet demand for Stochastic Minimizing CVaR Approach with =0.99, all units are

    stated in MMBtu, unless otherwise indicated ............................................................................................................... 75

  • 8

    CHAPTER 1 - INTRODUCTION

    1.1 Natural Gas Market in North America

    The countries in North America recognize the important role of a competitive natural gas market on

    the economic, environmental and social welfare. In the U.S., there has been long belief in

    competitive markets, based on private ownership of energy capital and resources, to ensure the

    optimal supplies and consumption of natural gas.[2] In Canada, deregulation of the natural gas

    industry began in 1984, mainly aimed for a more open market, allowing market prices to be

    determined by supply and demand forces. Some of the significant structural changes in policy

    included 1) The option for consumers to purchase from a supplier other than their Local Utility,

    such as from a Marketer or a Producer; 2) Opening up pipeline capacities to third parties; and 3)

    Lifting the 30-year reserve-to-production ratio policy, freeing up large quantities of gas in storages

    for export opportunities. [1] Although many restrictions were removed, today, items such as

    transport and storage fees, transmission and other areas where the market does not adequately serve

    its policy objectives are still regulated or controlled by regulators such as the National Energy Board

    (NEB). The deregulation of the natural gas market allowed new participants to compete and enabled

    them with access to pipelines distribution capacities.

    With more new participants in a deregulated and integrated North American market, there is a need

    for new natural gas transaction and risk management system solutions to manage the growing price

    risks from a more dynamic environment.

  • 9

    1.2 Financial and Operations Risk Management

    A participant in the Natural Gas market with a gas portfolio faces the challenges of managing both

    financial and operational risks to meet various demand levels mean while optimizing their

    profitability. Natural Gas prices are heavily correlated to oil prices and greatly influenced by weather

    conditions. [1] As a result, fluctuations in oil prices driven by market supply and demand, and

    geopolitical events around the globe greatly impact the market prices. In addition, further

    uncertainties are introduced from unpredictable and uncontrollable weather conditions (Figure 1)

    Since natural gas is typically used in space heating, in colder winters, the consumption of the

    commodity is substantially higher than average. The increase in demand during these periods creates

    the demand shock effect in which spot market prices become highly volatile, thus making

    financial and operational planning difficult.

    Market instruments, such as forward contracts, are available to allow market participants to mitigate

    the risks of price volatility. A forward contract can be purchased from a seller for delivery of a

    specified quantity of natural gas at a pre-agreed location, time and price in the future for a price at

    Figure 1 Source: NYMEX, Impact of events on Natural Gas Prices

  • 10

    the time when the contract is engaged. 1By entering a forward contract, gas price will be locked to

    hedge against future uncertainties in the spot market. We will also consider the addition of another

    instrument known as the swing option, which allows the flexibility of the contract holder to

    receive volumes of natural gas within a predefined range at pre-agreed time periods. The swing

    option will facilitate risk management and give the purchaser of the contract the volume flexibility to

    vary their demand levels of the forward in the future.

    Another type of contract is called a Swap contract. Similar to a forward contract, the swap locks in

    the value of the commodity at a pre-agreed price. In a swap contract, the seller of the swap agrees

    to pay the buyer for the increase in price of the underlying commodity above an agreed-upon value

    (the price of the swap) at the time when the swap expires, and the buyer agrees to pay the seller for

    any decreases below the agreed-upon value. [3] Thus, the seller of a swap is protected against any

    decreases in the price of the commodity, and a buyer is protected against any price increases. In this

    thesis, we develop an optimization model that can be used by the seller of the swap contract to

    minimize the cost for meeting demand. The swing options are also considered, in which the buying

    of the contract can withdrawal a range of volume of gas during a time period.

    It is of an interest to the seller of the contract to determine the optimal forward contract acquisition

    strategies to minimize the overall network cost to meet demand.

    1 A forward contract differs from a future contract in that physically delivery is intended for the former, and not in

    the latter. [1]

  • 11

    1.3 Natural Gas Network and Portfolio

    A Natural Gas Network consists of producing basins, storage areas, demand locations, hubs and

    pipelines connecting them. In the portfolio problem, we will assume the provider of the case study

    has its own sources of supply. Examples of such sourcing locations which contribute to the North

    American natural gas supply are: the Western Canadian Sedimentary Basin (WCSB) in Alberta; the

    Mid-continent in the central and mid-western U.S.; and the Gulf of Mexico region (Figure 3).

    Natural Gas is extracted, produced and distributed from the basins to the markets and Local

    Distribution Companies (LDCs), and eventually to the residential and commercial end-users.

    The pricing and trading of the gas occur at market hubs. Hubs update both spot and future gas

    prices on a daily basis, which serve as benchmark prices for trading transactions.2 Major hub

    locations in North America are: AECO in Canada, and the Henry Hub in Louisiana U.S (Figure 2).

    2 Units of price is stated in $/Bcf

    Figure 2 Source: Petroleum Encyclopedia, Oil and Gas Journal,

    Schematic Diagram of North American Market Hubs

    Figure 3 Source: US Energy Policy, Schematic Diagram of North

    American Producing Basins

    Natural Gas Basins

    in North America

    North American

    Market Centers and

  • Each hub sets the referencing price independently; therefore there are variations

    The variation in prices is related to the cost of transport, as well as the supply and demand

    conditions in the region. High volatility of prices on the market translates to potential arbitrage

    opportunities in time, in which gas can be purchased for a lower price a

    at a higher price in the future. Potential arbitrage opportunities also exist in

    market prices of gas are set independently at these hubs, there are variations in prices between

    locations. In such situation, profits can be made by purchasing gas at a lower price from one

    location, transported to sell for a high price at another. In addition to physical trading, electronic

    trading is also available. For the purpose of this analysis, only physical tradin

    Connecting the producing basin, the end

    the transport pipelines. Major pipeline systems in North America are the Trans

    Canada and the PG&E Gas transm

    the maximum flow of natural gas over a specified period of time for which

    Figure 4 Source: CAPP, North American Transport Pipeline Network

    12

    Each hub sets the referencing price independently; therefore there are variations between locations.

    ion in prices is related to the cost of transport, as well as the supply and demand

    High volatility of prices on the market translates to potential arbitrage

    , in which gas can be purchased for a lower price at the present, stored and sold

    at a higher price in the future. Potential arbitrage opportunities also exist in location. Since the spot

    market prices of gas are set independently at these hubs, there are variations in prices between

    uation, profits can be made by purchasing gas at a lower price from one

    location, transported to sell for a high price at another. In addition to physical trading, electronic

    trading is also available. For the purpose of this analysis, only physical trading will be considered.

    the end-users (LDCs) natural gas markets, and storage facilities

    Major pipeline systems in North America are the Trans-Canada Pipelines in

    PG&E Gas transmission Northwest in the U.S. (Figure 4). The capacity represents

    the maximum flow of natural gas over a specified period of time for which a pipeline system or

    Source: CAPP, North American Transport Pipeline Network

    North American Transport

    Pipeline Network

    between locations.

    ion in prices is related to the cost of transport, as well as the supply and demand

    High volatility of prices on the market translates to potential arbitrage

    t the present, stored and sold

    . Since the spot

    market prices of gas are set independently at these hubs, there are variations in prices between

    uation, profits can be made by purchasing gas at a lower price from one

    location, transported to sell for a high price at another. In addition to physical trading, electronic

    g will be considered.

    LDCs) natural gas markets, and storage facilities are

    Canada Pipelines in

    The capacity represents

    a pipeline system or

  • 13

    portion thereof is designed or contracted, not limited by existing service conditions. [9] For market

    participants, pipeline capacity contracts can be acquired through auctions for long term periods of

    typically 10 years or less. These capacities give rights to the contract holders to transport volumes of

    gas along a fixed pipeline path between locations. A procurement strategy for capacity acquisition

    must be developed to optimize the usage and reduce the overall system cost for distribution.

    As the demand for natural gas is significantly higher in the winter months, excess production from

    the summer is typically injected into storages and withdrawn during peak demands. For market

    participants, storages can be used as a tool for risk management. Gas can be purchased during the

    summer time when prices are relatively lower for storage and used for delivery in the winter when

    market prices are higher and more volatile. Some limitations do exist for storage injection and

    withdrawals as the cost, volume and time required to transport in and out of these area are

    constrained.

    As the complexity of the gas network increases, managing market risks to meet demands under

    various uncertainties become non-trivial. To optimize portfolio performance, a strategy for resource

    acquisition and dispatch must be developed in addition to purchasing of forward contracts.

  • 14

    1.4 Risk Measure Tools and Methodology

    1.4.1 Value-at-risk

    Value-at-Risk (VaR) is a tool for measuring risks by determining the maximum decrease in the value

    (loss) of the portfolio (in monetary value) given a confidence level x 100% over a specified period

    of time. The loss, represented by (, ), is a function of the decision vector and the random vector . The loss can take either a positive value or a negative one. In the latter case, the negative loss would describe a gain. For each decision , (, ) takes on some random value having a distribution brought about by the set of uncertain parameters, . We will assume the vector follows a probability distribution denoted by (). The cumulative probability of the loss (, ) not exceeding a threshold value then takes on the form [4]

    (x, ) = ()(,) . Where is the VaR values of the loss associated with the decision vector at a given probability level in (0, 1). [4]

    (x) = min | (x, ) } Because the loss function of a portfolio is not normally distributed, but rather heavy-tailed. By

    minimizing the value-at-risk, a set of optimal decisions is selected that does not favour large losses.

    There exist undesirable mathematical probabilities associated with VaR in the application of

    optimization such as the non-subadditivity and non-convexity properties. [4] In the case of sub-

    additivity, the VaR associated with a combination of portfolios can be greater than the sum of the

  • 15

    risks of the individual portfolios. That is ( + !) > + (!) . This is undesirable because portfolio diversification should reduce risk. The non-convexity property makes optimization

    difficult when calculated using scenarios because the VaR as a function of can exhibit multiple local extrema.

    1.4.2 Conditional Value-at-risk (CVaR)

    Due to implications with using VaR in optimization, Conditional Value-at-Risk (CVaR), with better

    mathematical properties is preferred and used in this thesis. The value of CVaR is by definition

    greater than the value of VaR at a given confidence level . Thus, a low CVaR will also yield a low

    VaR value.[4][5]

    It is shown in [4][6] that the CVaR is defined by

    (x) = (1 )&' (, )()(,)() . Thus CVaR represents the conditional expectation of the loss associated with vector x in the case

    which the loss exceeds VaR or (x).

  • 16

    1.5 CVaR Minimization

    To utilize CVaR (x) defined by (x) = (1 )&' ( (, )()(,)() in an optimization problem, a single function is developed to characterize (x) and (x). The simplified function becomes[4]

    F(x, ) = + (1 )&' ( (, )()(,) . It was shown in [4] that the F(x, ) is related to CVaR or (x) by the formula

    (x) = min

    F(x, ) = F(x, (x, )). F(x, ) is convex and continuously differentiable, thus CVaR can be easily determined by minimizing the function numerically. Furthermore, the VaR or , for which F(x, ) depend on, does not need to be calculated independently in order to derive (x). Instead VaR can be obtained as a by product.

    F(x, ) can be approximated from a set of sample data ',+,, . that belongs to a probability space ().

    F/(x, ) = + (q(1 ))1 123x, yk6 7q

    k=1+

    Although F/(x, ) is not differentiable with respect to , however, it still can be minimized through various methods, including linear programming. It was shown in [6] that the linear programming

    representation of the problem takes on the form:

  • 17

    min

    F/(x, ) = + (q(1 ))1 1 z9qk=1 Subjected to the following constraints:

    9 z9 3x, yk6 z9 0.

    1.6 Stochastic Programming

    Stochastic programming is a method for modeling optimization problems by taking into

    consideration of the uncertainty of the problem data. Unlike in a deterministic model (Simple Linear

    Programming model), in which the optimal solution is obtained by assuming the input parameters

    are accurate; in a stochastic model, the optimal solution is obtained by applying random variations to

    these input parameters to project the optimal decision that would be prepare for various

    uncertainties. The optimal set of decisions will be one which maximizes the expected value of the

    objective function for all possible outcomes. If a deterministic approach is adopted, in the case

    where the projected data is inaccurate, the original set of optimal decisions obtained from this

    approach would limit opportunities and yield undesired results.

    The two-stage Stochastic Linear Programming model with integer recourse model is widely used

    within Stochastic Programming. In the first-stage of the model, a set of decisions defined by linear

    constraints are made. After a random event occurs, affecting the outcome of the first-stage decision,

    a recourse action is taken in the second stage to enable corrections to the solution altered by the

  • 18

    random event. The optimal solution will be obtained by choosing both the first-stage decisions and

    the second-stage recourse decisions that will maximize the expected outcome.

    The general two-stage stochastic model with recourse takes on the form [7]

    ?@A + BCD(, E)| = F, 0G where D(, E(H)) = IA |J = (H) L, 0}. Vector represents the first-stage decisions. The second-stage decisions or the corrective actions denoted by are determined for each scenario described by some random vector E(H), where H an element which determines the nature of the random event with some probability value of occurring. E(H) is formed from a combination of elements in IA , L, A, representing the objective function for the second-stage decisions, the resulting values of the first-stage decisions, and the sum of the values from the first-

    stage and second-stage decisions, respectively. For our gas portfolio problem, only the Amatrix is considered random.

    In our two-stage model, the first stage determines the volume of pipeline capacity contracts to

    engage in and the number of forwards to purchase for each of the planning time periods. The

    second stage decisions give the amount of gas to withdraw/inject from storage facilities, the amount

    of gas to purchase/sell on the spot markets, and finally the transport of gas from storage, source and

    the spot market to meet demand requirements, for each of the planning time periods. Discrete

    scenarios are generated by considering the uncertainty of demands and gas spot prices. We will

    employ stylized probabilities for the input parameters.

    Arbitrage opportunity are also considered in the model, and occurs when there is a price mismatch

    between either the forward prices and the spot market price, or two spot market prices at separate

    locations, for a specific time. The number of forwards which can be purchased will be bounded by a

  • 19

    limit defined by the user to avoid unrealistic situations where large quantities of forwards are

    purchased in case of an attractive arbitrage opportunity.

    1.7 CVaR Minimization Approach in Stochastic Programming

    Combining the approximation function of Conditional Value-at-Risk in section 1.5 and the general

    two-stage stochastic programming model in Section 1.6, the two-stage stochastic model minimizing

    the CVaR with discrete probabilities for (H) is defined in [6] as minM,N,O,P DQRPS (T, ) = + (1 )&' 1 UVTV

    .VW'

    Subjected to the constraints

    JV = L TV @A + IAV TV 0, V. The problem will determine the VaR, CVaR, the first stage decisions , and the second stage recourse decisions . The CVaR minimization approach in two-stage stochastic programs has been previously applied to

    Replication of Electricity Custom Contract problem in [6].

  • CHAPTER 2 PROBLEM FORMULATION

    2.1 Deterministic Approach

    We will propose a deterministic linear programming m

    Deterministic models for the application of gas portfolio and transport have been

    in [10]. The strategy is to determine the

    demand while optimizing total revenue of the portfolio. The strategy would consist of acquisition of

    pipeline capacities, purchasing of mark

    storages, buying from the spot market

    Figure 5 Schematic diagram of the Flow of gas between locations within a gas network

    We will assume that the market participant owns

    natural gas and |X| storage spaces for storing gas.at || locations at time period Y for interest for the analysis. Assuming

    fixed, therefore this revenue stream

    We will also consider |Z[| different market forwards available each time periods in the future. The two types of forwards considered, fixed and variable volume

    20

    EM FORMULATION

    Approach

    propose a deterministic linear programming model for our portfolio optimization problem.

    Deterministic models for the application of gas portfolio and transport have been previously

    determine the resource acquisition and dispatch volumes required to meet

    revenue of the portfolio. The strategy would consist of acquisition of

    pipeline capacities, purchasing of market forwards, generation from producing basins, utilization of

    storages, buying from the spot market, at each of the future time periods.

    Schematic diagram of the Flow of gas between locations within a gas network

    assume that the market participant owns |\| producing basins, or sources that storage spaces for storing gas. ]^_ volumes of gas must be delivered for demand

    for Y = 1, L`, where L` denotes the number of time periods ofAssuming the price charged on a unit of gas used to fulfill the demands is

    this revenue stream will be omitted in the objective function.

    different market forwards available to deliver specific volumes of gas at

    The two types of forwards considered, fixed and variable volume

    odel for our portfolio optimization problem.

    previously studied

    volumes required to meet

    revenue of the portfolio. The strategy would consist of acquisition of

    et forwards, generation from producing basins, utilization of

    Schematic diagram of the Flow of gas between locations within a gas network

    asins, or sources that can supply

    volumes of gas must be delivered for demand

    denotes the number of time periods of

    price charged on a unit of gas used to fulfill the demands is

    ver specific volumes of gas at

    The two types of forwards considered, fixed and variable volume

  • 21

    forwards are denoted as abcMd^ = 1, eZ[bcMd^e and afPgcPhid = eZ[bcMd^e + 1, , |Z[| , respectively. Where eZ[bcMd^e represented the number of fixed volume forwards and eZ[fPgcPhide represents the number of variable volume contracts. A forward can be purchased at price `[fj_ at Hub , for 1, , lm}. The forward will deliver |[fj_| volume of natural gas during time period Y. In addition to the forward contracts, spot market purchases can also be made at each hubs for the

    price of `nj_ . per unit of gas. Finally, pipeline capacities must be acquired at a volume of oPh for pipeline (, F) for the duration of analysis. The cost per unit of capacity will assumed to be CCab.

    The following parameters and decision variables are used in the deterministic model.

    Parameters

    t Time period Y 0, , L`} (a,b) Pipeline between locations a and b. (, F) 1, , Z} h, g Hub location 1, , lm}, p 1, , lm} i Storage location = 1, , qm} v Set of market forwards, fixed and variable volume a 1, , Z[} e Source location \ 1, , Bm} d Demand location 1, , ]m} CSI Unit cost for gas injection from storage

    CSW Unit cost for gas withdrawal from storage

    SR Maximum rate of storage injection or withdrawal

  • 22

    CE Unit cost for gas extraction from source

    CC Unit cost of capacity for pipeline

    SUB Maximum allowable storage volume of storage

    PUB Maximum allowable pipeline volume which can be purchased for pipeline

    EUB Maximum allowable extraction volume for source

    LBvt Minimum allowable volume of Forwardvht that can be drawn at time t

    UBvt Maximum allowable volume of Forwardvht that can be drawn at time t

    PMht Price of gas on the spot market at Hubh at time t

    PFvth Price of gas forward associated with Forwardvht at Hubh at time t

    Ddt Gas demand at location d at time t

    MBS Minimum benchmark strategy

    Decision variable

    STit Volume in Storageit at time t

    RMTht Volume that sold at Hubh at time t

    BMTht Volume that purchased at Hubh at time t

    VFvht Volume that will be delivered by Forwardvht at Hubh for time t

    ETet Volume extracted from Sourceet at time t

    FDvhdt Amount of Forwardvht used to meet demand at location d, at time t

    FMvhgt Amount of Forwardvht used to sell at Hubg at time Y FSvhit Amount of Forwardvht used to put in Storageit at time t

    SDidt Amount of Storageit used to meet demand at location d, at time t

    SMiht Amount of Storageit used to sell at Hubh at time t

    EDedt Amount of Sourceet used to meet demand at location d, at time t

  • 23

    EMeht Amount of Sourceet used to sell at Hubh at time t

    ESeit Amount of Sourceet used to put in Storagei at time t

    BMDhdt Amount of gas purchased on the spot market at Hubh for demand at location d, at time t

    BMShit Amount of gas purchased in the spot market at Hubh for Storagei, at time t

    BMMhgt Amount of gas purchased in the spot market at Hubh for Hubg, at time t

    FLabt Amount of flow through in pipeline (a,b) at time t

    Cab Amount of capacity bought for pipeline (, F) NFPvht Number of Forwardvht purchased at Hubh, at time t

    The objective function minimizes the overall system costs, which includes cost associated with

    pipeline capacity acquisition, buying in the spot market, cost of producing at sources, cost of market

    forwards, cost of storage injection and withdrawals, subtracted by revenues from selling on the spot

    market.

    n=> r 1 @s@=Y @tXYXuPv wcwdv + 1 1 txyx @tXYXbzg{Pg^v_c|d + 1 1 (s}x@X=>p @tXYX x\a\>}\X)j~hv_c|d+ 1 1 (=>\@Y=t> @tXYX + y=Yxy @tXYX)_zgPudv_c|d + 1 1 Xt}x@\ X}ss @tXYXvz~gdv_c|d

    Where:

    1 = 1 oo(oPh)(P,h)

    1 1 = 1 1 1 `[fj_[fj_

    fW'

    jW'A

    _W'

  • 24

    1 1 ( ) = 1 1 `x=@\(`}xtxxF=Yxp\ + `}xtx]\ + `}xtxqYtxp\j~hv_c|d qtxt\@Y=t>([txyxtxqYtxp\ + qt}x@\txqYtxp\v_zgPudv_c|d+ `}xtxqYtxp\) + otXYtqYtxp\(qYtxp\tx]\ + qtxt

  • 25

    _c qLc_' = 1 1 [qfjc_ jW'

    RfW' + 1 Bqdc_

    dW' + 1 !nqjc_

    jW' 1 q]c^_

    ^W' + 1 qncj_

    jW' + qLc_

    Storage limits

    Amount stored at a particular storage is less than or equal to the maximum capacity at the storage

    _c qLc_ q! Amount withdrawn from storage during time t is less than or equal to the amount in storage at the

    beginning of time t _c 1 q]c^_^W' + 1 qncj_

    jW' qLc_

    The rate at which volume is injected or withdrawn from a particular storage is bounded by the

    maximum rate SR

    _c 1 q]c^_^W' + 1 qncj_

    jW' q _c 1 1 [qfjc_

    jW'R

    fW' + 1 Bqdc_

    dW' + 1 !nqjc_

    jW' q

    Spot market purchase balance

    Amount of gas purchased at a spot market is equal to the sum of the total volume used to satisfy

    demand requirements, for delivery to storage, and for location arbitrage strategy

    _j !nL j_ = 1 !n]j^_^W' + 1 !nqjc_

    cW' + 1 !nnuj_

    uW'

    Spot market sell balance

    Amount of gas purchased at a spot market is equal to the sum of the total volume delivered from

    forwards, production, storage, and location arbitrage strategy

    _j nL j_ = 1 qncj_cW' 1 Bndj_

    dW' + 1 1 [nfuj_

    fW'

    uW' + 1 !nnuj_

    uW'

  • 26

    Forward balance

    Total forward is equal to the amounts put in storage, used for demand, and sold on the spot market.

    _jf [ fj_ = 1 [nfju_uW' + 1 [qfjc_

    cW' + 1 []fj ^ _

    ^W'

    Forward limits

    The volume delivered by a particular forward is bounded by the maximum number and minimum

    number of forwards which can be purchased

    _fj m! f_ 1 Z[ f`ju_uW' [fj_ !f_ 1 Z[ f`ju_

    uW'

    Source balance

    The total amount delivered from production is equal to the sum of the amount sold on the spot

    market, delivered to storage, and used to satisfy demand

    _d BL d_ = 1 Bndj_jW' + 1 Bqdc_

    vW' + 1 B]d^_

    ^W'

    Source limits

    The total amount drawn from a source is less than the maximum production capacity

    _d BLd_ B! Capacity

    Amount flown through the pipeline is less than the amount of capacity bought

    _(P,h)[mPh_ oPh Amount of capacity bought is less than or equal to the maximum capacity which can be acquired for

    the pipeline

    _(P,h) oPh `! Demand Balance

  • 27

    The demand requirement is satisfied from volumes delivered by forwards, spot purchases,

    production and storages

    _^ ]^_ = 1 1 []fj ^ _ fW'

    jW' + 1 q]c^_

    cW' + 1 B]d^_

    dW' + 1 !n]j^_

    jW'

    Minimum Benchmark Strategy

    The minimum benchmark strategy can be a set of contracts which can be obtained conveniently on

    the market to satisfy demand requirements. Establishing a minimum benchmark strategy will

    eliminate undesired decisions in which the cost to meet demand from the optimal solution exceed

    the minimum benchmark strategy. 1 1 1 1 `[fj_[]fj^_fW'

    jW' + oqJ 1 q]c^_

    cW' + oB 1 B]d^_

    dW'

    A_W' + 1 `nj_!n]j^_

    jW'

    ^W' n!q

  • 28

    2.2 Stochastic Approach Minimizing Expected Cost

    In the stochastic approach with the objective function of minimizing the expected system cost, we

    introduce a set of scenario dependent parameters. We will assume the spot market prices and

    demands are uncertain. The uncertainty is factored in by representing possible outcomes in discrete

    scenarios; each scenario is given a probability of occurrence. The second stage decisions or the

    recourse actions will differ for each scenario to determine the optimal solution when a particular

    scenario occurs.

    Scenario independent parameters

    t Time period Y 0, , L`} s Scenario X 1, , Lq} (a,b) Pipeline between locations a and b. (, F) 1, , Z} h, g Hub location 1, , lm}, p 1, , lm} i Storage location = 1, , qm} v Set of market forwards, fixed and variable volume a 1, , Z[} e Source location \ 1, , Bm} d Demand location 1, , ]m} CSI Unit cost for gas injection from storage

    CSW Unit cost for gas withdrawal from storage

    SR Maximum rate of storage injection or withdrawal

    CE Unit cost for gas extraction from source

    CC Unit cost of capacity for pipeline

    SUB Maximum allowable storage volume of storage

  • 29

    PUB Maximum allowable pipeline volume which can be purchased for pipeline

    EUB Maximum allowable extraction volume for source

    LBvt Minimum allowable volume of Forwardvht that can be drawn at time t

    UBvt Maximum allowable volume of Forwardvht that can be drawn at time t

    PFvth Price of gas forward associated with Forwardvht at Hubh at time t

    MBS Minimum benchmark strategy

    Scenario dependent parameters

    PMhts Price of gas on the spot market at Hubh at time t, in scenario s

    Probs Probability of occurrence associated with scenario s

    Ddts Gas demand at location d at time t, scenario s

    Scenario independent decision variable

    VFvht Volume that will be delivered by Forwardvht at Hubh for time t,

    Cab Amount of capacity bought for pipeline (, F) Decision variable

    STits Volume in Storageit at time t, scenario s

    RMThts Volume that sold at Hubh at time t, scenario s

    BMThts Volume that purchased at Hubh at time t, scenario s

    ETets Volume extracted from Sourceet at time t, scenario s

    FDvhdts Amount of Forwardvht used to meet demand at location d, at time t, scenario s

    FMvhgts Amount of Forwardvht used to sell at Hubg at time t, scenario s

    FSvhits Amount of Forwardvht used to put in Storageit at time t, scenario s

    SDidts Amount of Storageit used to meet demand at location d, at time t, scenario s

    SMihts Amount of Storageit used to sell at Hubh at time t, scenario s

  • 30

    EDedts Amount of Sourceet used to meet demand at location d, at time t, scenario s

    EMehts Amount of Sourceet used to sell at Hubh at time t, scenario s

    ESeits Amount of Sourceet used to put in Storagei at time t, scenario s

    BMDhdts Amount of gas purchased on the spot market at Hubh for demand at location d, at time t, scenario s

    BMShits Amount of gas purchased in the spot market at Hubh for Storagei, at time t, scenario s

    BMMhgts Amount of gas purchased in the spot market at Hubh for Hubg, at time t, scenario s

    FLabts Amount of flow through in pipeline (a,b) at time t, scenario s

    NFPvhts Number of Forwardvht purchased at Hubh, at time t, scenario s

    n=> r 1 oo(oPh)(P,h) + 1 1 1 `[fj_[fj_

    fW'

    jW'A

    _W'+ 1 `nj_v 1 !nnju_vuW' + 1 !n]j^_v

    ^W'

    + 1 !nqjc_vcW' 1 [nfuj_v

    uW' 1 Bndj_vdW' 1 qncj_v

    cW'

    1 !nnuj_vuW'

    jW'+ 1 oq 1 1 [qfjc_v

    jW'

    fW'+ 1 Bqdc_vdW' + 1 !nqjc_v

    jW'

    + oqJ 1 q]c^_v^W' + 1 qncj_v

    jW'cW'

    + 1 oB 1 B]d^_v^W' + 1 Bndj_v

    jW'+ 1 Bqdc_vcW'

    dW'

    _W+ 1 `xtFvAvW' 1 1 `nj_v 1 !nnju_v

    uW'

    + 1 !n]j^_v^W' + 1 !nqjc_v

    cW' 1 [nfuj_vuW' 1 Bndj_v

    dW'

    1 qncj_vcW'

    jW'A

    _W' 1 !nnuj_vuW' + 1 1 oq 1 1 [qfjc_v

    jW'

    fW'

    + 1 Bqdc_vdW' + 1 !nqjc_v

    jW' + oqJ 1 q]c^_v^W' + 1 qncj_v

    jW'

    cW'A

    _W'+ 1 1 oB 1 B]d^_v^W' + 1 Bndj_v

    jW'

    + 1 Bqdc_vcW'

    dW'A

    _W'

    Subject to the following constraints

    v_c qLc_'v = 1 1 [qfjc_vjjW'R

    fW' + 1 Bqdc_v

    dW' + 1 !nqjc_v

    jjW' 1 q]c^_v

    ^W' + 1 qncj_v

    jW' + qLc_v v_c qLc_v q! v_c 1 q]c^_v^W' + 1 qncj_v

    jW' qLc_v

  • 31

    v_c 1 q]c^_v^W' + 1 qncj_v

    jW' q v_c 1 1 [qfjc_vjjW'

    RfW' + 1 Bqdc_v

    dW' + 1 !nqjc_v

    jjW' q

    v_j !nL j_v = 1 !n]j^_v^W' + 1 !nqjc_v

    cW' + 1 !nnuj_v

    uW'

    v_j nL j_v = 1 qncj_vcW' 1 Bndj_v

    dW' + 1 1 [nfuj_v

    fW'

    uW' + 1 !nnuj_v

    uW'

    v_jf [ fj_ = 1 [nfju_vuW' + 1 [qfjc_v

    cW' + 1 []fj^_v

    ^W'

    _fj m!jf_ 1 Z[ f`ju_uW' [fj_ !f_ 1 Z[ f`ju_

    uW'

    v_d BL d_v = 1 Bndj_vjW' + 1 Bqdc_v

    vW' + 1 B]d^_v

    ^W'

    v_d BLd_v B! v_(P,h)[mPh_v oPh v_(P,h) oPh `! v_^ ]^_ = 1 1 []fj^_vfW'

    jjW' + 1 q]c^_v

    cW' + 1 B]d^_v

    dW' + 1 !n]j^_v

    jW'

    1 `xtFvAvW' 1 1 1 1 `[fj_[]fj^_v

    fW'

    jW' + oqJ 1 q]c^_v

    cW' + oB 1 B]d^_v

    dW'A

    _W' + 1 `nj_v!n]j^_v

    jW'

    ^W' n!q

  • 32

    2.3 Stochastic Approach Minimizing CVaR

    In this section, we formulate a new two-stage stochastic model that will allows us to reduce greater

    risk for the portfolio by minimizing the expected loss with the risk measure Conditional Value-at-

    Risk. With the newly defined objective function discussed in section 1.7 and the set of constraints

    developed in section 2.2 the new linear programming problem becomes:

    n=> + 11 1 sxtFvmtvA

    vW'

    Subject to the following constraints

    v_c qLc_'v = 1 1 [qfjc_vjjW'R

    fW' + 1 Bqdc_v

    dW' + 1 !nqjc_v

    jjW' 1 q]c^_v

    ^W' + 1 qncj_v

    jW' + qLc_v v_c qLc_v q! v_c 1 q]c^_v^W' + 1 qncj_v

    jW' qLc_v

    v_c 1 q]c^_v^W' + 1 qncj_v

    jW' q v_c 1 1 [qfjc_vjjW'

    RfW' + 1 Bqdc_v

    dW' + 1 !nqjc_v

    jjW' q

    v_j !nL j_v = 1 !n]j^_v^W' + 1 !nqjc_v

    cW' + 1 !nnuj_v

    uW'

    v_j nL j_v = 1 qncj_vcW' 1 Bndj_v

    dW' + 1 1 [nfuj_v

    fW'

    uW' + 1 !nnuj_v

    uW'

    v_jf [ fj_ = 1 [nfju_vuW' + 1 [qfjc_v

    cW' + 1 []fj^_v

    ^W'

    _fj m!jf_ 1 Z[ f`ju_uW' [fj_ !f_ 1 Z[ f`ju_

    uW'

  • 33

    v_d BL d_v = 1 Bndj_vjW' + 1 Bqdc_v

    vW' + 1 B]d^_v

    ^W' v_d BLd_v B! v_(P,h)[mPh_v oPh v_(P,h) oPh `! v_^ ]^_ = 1 1 []fj^_vfW'

    jjW' + 1 q]c^_v

    cW' + 1 B]d^_v

    dW' + 1 !n]j^_v

    jW'

    1 `xtFvAvW' 1 1 1 1 `[fj_[]fj^_v

    fW'

    jW' + oqJ 1 q]c^_v

    cW' + oB 1 B]d^_v

    dW'A

    _W' + 1 `nj_v!n]j^_v

    jW'

    ^W' n!q

    v mtv 1 oo(oPh)(P,h) + 1 1 1 `[fj_[fj_

    fW'

    jW'A

    _W'+ 1 1 `nj_v 1 !nnju_vuW' + 1 !n]j^_v

    ^W' + 1 !nqjc_v

    cW' 1 [nfuj_v

    uW' 1 Bndj_v

    dW'

    jW'

    A_W

    1 qncj_vcW' 1 !nnuj_v

    uW' + 1 1 oq 1 1 [qfjc_v

    jW'

    fW' + 1 Bqdc_v

    dW' + 1 !nqjc_v

    jW'

    cW'A

    _W+ oqJ 1 q]c^_v^W' + 1 qncj_v

    jW' + 1 1 oB 1 B]d^_v

    ^W' + 1 Bndj_v

    jW' + 1 Bqdc_v

    cW'

    dW'

    A_W

  • 34

    CHAPTER 3 COMPUTATIONAL RESULTS

    Numerical examples are provided for different cases using the deterministic, stochastic - minimizing

    expected cost, and stochastic minimizing CVaR approaches as discussed in the previous chapter.

    We will conduct our analysis for four time periods or a total of four months. The natural gas

    network will be composed of three separate storage areas with maximum storage capacities, injection

    and withdrawal rates and unit costs listed in (Table 2); two supply or source locations with their

    respective production limits presented in (Table 3). Finally, the pipeline capacities will be limited to a

    maximum of 10,000,000 MMBtu available for purchase in contract with an average unit cost of

    $0.86/MMBtu per capacity purchased for each pipeline. There also exist six different market

    forward types available for delivery at different time periods as listed in (Table 1). Forwards can be

    delivered to any of the market hubs for redistribution and we set the maximum number of forwards

    which can be purchased of each type for delivery at each hub to 10 units (ie. 10 forwards/forward

    type/delivery hub).

    Forward Type

    ($/MMBtu) Upperbound (MMBtu)

    Lowerbound (MMBtu) Time 1 Time 2 Time 3

    F1fixed 7.50 8.40 10.40 5000 5000

    F2fixed 7.40 8.70 8.90 8500 8500

    F3fixed 7.30 8.50 8.40 7300 7300

    F1variable 7.80 8.90 8.60 7400 7000

    F2variable 7.90 9.10 9.40 3200 3000

    F3variable 8.00 8.10 6.70 6500 5000

    Table 1 Fixed and variable volume market forwards

    Location Maximum Storage

    Capacities

    Injection/Withdrawal Rates (MMBtu/Time

    Period)

    Unit Cost of Injection/Withdrawal

    ($/Mmbtu)

    Storage 1 1000000 10000 0.05

    Storage 2 1000000 10000 0.05

    Storage 3 1000000 10000 0.05

    Table 2 Storage capacity limits, unit costs, injection/withdrawal rate

  • 35

    Location Time 0 Time 1 Time 2 Time 3

    Production Limits (MMBtu)

    Source 1 10000 10000 10000 10000

    Source2 15000 15000 15000 15000

    Unit cost of Production ($/MMBtu)

    Source 1 5.50 5.50 5.50 5.50

    Source2 5.50 5.50 5.50 5.50

    Table 3 Production costs and limits from Sources/Supplies

    3.1 Deterministic Approach

    We will consider five separate locations where demand must be met in the volumes listed in( Table

    4). We will assume that the spot market prices of natural gas at each of the hubs at each time period

    will take on the values listed in (Table 5).

    It is determined that the minimum cost benchmark to meet demands between time periods 1 to 3

    contains 3 F3 variable (5000 MMBtu), 1 F3 variable (6100 MMBtu), 3 F3 fixed forwards for time 1;

    3 F1fixed, 9 F3 variable (6500 MMBtu), 1 F3 variable (6000 MMBtu) forwards for time 2; and 9 F3

    Variable (6500 MMBtu), 1 F3 Variable (5900 MMBtu), 2 F3 fixed, 1 F2 variable (3000 MMBtu)

    forwards for time 3. The total cost of the minimum bench mark is $1,514,440.

    Assuming all demands and Spot Market prices will follow the values as predicted, the optimal

    strategy to the deterministic problem is shown in Table 6, Table 7,Table 8 and Table 9. The overall

    system cost takes on a negative value, meaning arbitrage opportunities are taken. That is when in

    excess of meeting the demand requirement; natural gas is also sold on the spot market to generate

    revenue. The optimal strategy involves purchasing the maximum number of forwards with a

    relatively large price difference between the forward price and spot market price; purchasing on the

    spot market at the hub which has the lowest price for selling at the hub location with the highest

  • 36

    price during the time period; and producing at the maximum capacity at all two sources. The

    delivery of the forwards are generally set at the hub locations where they are sold on the spot market

    to reduce/eliminate pipeline acquisition costs. For example, during time period 2, 10 forwards of F1

    fixed are delivered to both hubs 1 and 3 for spot market selling without redistribution. This results

    in a revenue generation of $0.03 per unit and $0.14 per unit for hubs 1 and 3, respectively without

    additional transportation cost considerations. The maximum volume purchased on the spot market

    for arbitrage opportunity in location is dictated by the maximum pipeline capacity. For example,

    during time period 1, a total of 20,000,000 MMBtu of gas is purchased at hub 2 for the unit price of

    $4.26 to sell at Hubs 1 and 3 at 10,000,000 MMBtu each for a price difference of $3.19. A spot

    market location arbitrage strategy is also dependent on the relative pipeline acquisition costs and the

    availability of the capacity in the case when a more favorable opportunity also exists (such as in the

    case for time period 3, when forwards F3 fixed and F3 variable are favored over the Hub 3 spot

    market price for selling at Hub 1). Both sources are set to produce at their maximum capacities as

    the cost of production is considerably lower than spot and forwards prices. As the storage

    withdrawal and injection rates are restricted, the optimal strategy also includes selling on the spot

    market from the reserves during time periods 0 (Now) and 3 when the spot prices are the highest,

    and storing gas from purchases off of the spot market during time period 1 when the market price is

    the lowest. Demand requirements are satisfied by a combination of volumes from spot market

    purchases and forwards, determined by the lower cost strategy out of the two options. Using

    volumes from storages are not favored as the withdrawal rate is highly limited.

    The calculated total cost to meet demand for time periods 1, 2, and 3 is $1,375,650 compared to our

    minimum benchmark strategy of $1,514,440. This results in a total saving of $138,790.00 using the

    deterministic model. This saving value can be used as a benchmark for setting price strategies on the

    gas volumes delivered to the demand customers.

  • 37

    Location (MMBtu)

    Time 1 Time 2 Time 3

    Demand 1 9600 12000 16000

    Demand 2 6400 14000 15000

    Demand 3 8000 17000 16500

    Demand 4 6500 18000 15500

    Demand 5 7500 18500 19000

    Table 4 Demand requirement for each of the time period in MMBtu

    Location ($/MMBtu)

    Time 0 Time 1 Time 2 Time 3

    Spot Price Hub1 9.00 7.45 8.43 9.45

    Spot Price Hub2 9.10 4.26 8.34 7.64

    Spot Price Hub3 8.90 7.45 8.54 8.45

    Table 5 Spot market prices at each of the time period in $/MMBtu

  • 38

    Capacity Acquisition Strategy

    Destination Locations

    Storage 1 Storage 2 Storage 3 Hub 1 Hub 2 Hub 3 Demand 1 Demand2 Demand 3 Demand 4 Demand 5 D

    e

    p

    a

    r

    t

    u

    r

    e

    L

    o

    c

    a

    t

    i

    o

    n

    s

    Storage 1 0 0 0 10000 0 0 0 0 0 0 0

    Storage 2 0 0 0 10000 0 0 0 0 0 0 0

    Storage 3 0 0 0 10000 0 0 0 0 0 0 0

    Hub 1 0 0 0 0 0 0 0 0 0 0 0

    Hub 2 10000 10000 10000 10000000 0 10000000 16000 15000 17000 18000 19000

    Hub 3 0 0 0 10000000 0 0 0 0 0 0 0

    Source 1 0 0 0 10000 0 0 0 0 0 0 0

    Source 2 0 0 0 15000 0 0 0 0 0 0 0

    Total Capacity Acquired 30170000

    Total Cost of Capacity $ 25,946,200.00

    Table 6 Capacity Acquisition Strategy for Deterministic Approach, all units are stated in MMBtu, unless otherwise indicated

  • 39

    Spot Price ($/MMBtu)

    Total Purchased on

    the Spot Market

    Total Sold on Spot Market

    F1 fixed

    F2 fixed

    F3 fixed

    F4 variable

    F5 variable

    F6 variable

    Total in Storage Total Production

    from Source (MMBtu)

    Total Cost ($) Total Revenue

    ($) Net Cost ($)

    Time 0

    Hub 1 $9.00 0 10040000 Storage 1 5000 Source 1 10000 55,000.00 90,360,000.00 -90,305,000.00 Hub 2 $9.10 0 0 Storage 2 5000 Source 2 15000 82,500.00 0.00 82,500.00 Hub 3 $8.90 10000000 0 Storage 3 5000 89,000,000.00 0.00 89,000,000.00

    Time 1

    Hub 1 $7.45 0 10256000 0 85000 73000 0 0 0 Storage 1 0 Source 1 10000 1,217,150.00 76,407,200.00 -75,190,050.00 Hub 2 $4.26 20068000 0 0 0 0 0 0 0 Storage 2 0 Source 2 15000 85,572,430.00 0.00 85,572,430.00 Hub 3 $7.45 0 10085000 0 85000 73000 0 0 0 Storage 3 0 1,162,150.00 75,133,250.00 -73,971,100.00

    Time 2

    Hub 1 $8.43 0 10140000 5000

    0 0 0 0 0 65000 Storage 1 10000 Source 1 10000 1,002,000.00 85,480,200.00 -84,478,200.00 Hub 2 $8.34 20018500 4000 0 0 0 0 0 65000 Storage 2 10000 Source 2 15000 167,563,790.00 33,360.00 167,530,430.00

    Hub 3 $8.54 0 10188000 5000

    0 0 73000 0 0 65000 Storage 3 10000 1,567,500.00 87,005,520.00 -85,438,020.00

    Time 3

    Hub 1 $9.45 0 20384000 0 85000 73000 74000 32000 65000 Storage 1 10000 Source 1 10000 2,797,900.00 192,628,800.00 -189,831,400.00 Hub 2 $7.64 20017000 0 0 0 0 0 0 65000 Storage 2 10000 Source 2 15000 153,448,380.00 0.00 153,447,880.00 Hub 3 $8.45 9862000 10000000 0 0 73000 0 0 65000 Storage 3 10000 84,383,100.00 84,500,000.00 -117,400.00

    Total System Cost (Revenue) -103,696,430.00

    Table 7 Overall Cost of the System using the Deterministic Approach, all units are stated in MMBtu unless otherwise indicated

  • 40

    Spot Market Profits

    Spot Market Hub Location for Selling

    Spot Price ($/MMBtu)

    Spot Purchase for Arbitrage

    F1 fixed F2 fixed F3 fixed F4

    variable F5

    variable F6

    variable

    Total Storage for Spot Market

    Selling

    Total Production towards Spot Market

    Selling Net Profit ($)

    Time 0

    Hub 1 Hub 1 9.00 0 Storage 1 5000 Source 1 10000

    Hub 2 9.10 0

    Storage 2 5000 Source 2 15000

    Hub 3 8.90 10000000 Storage 3 5000

    1000000

    134250

    87500 1,221,750.00

    Hub 2 Hub 1 9.00 0

    Storage 1 0 Source 1 0

    Hub 2 9.10 0

    Storage 2 0 Source 2 0

    Hub 3 8.90 0 Storage 3 0

    0

    0

    0 0.00

    Hub 3 Hub 1 9.00 0

    Storage 1 0 Source 1 0

    Hub 2 9.10 0

    Storage 2 0 Source 2 0

    Hub 3 8.90 0 Storage 3 0 0 0 0 0.00

    Time 1

    Hub 1 Hub 1 7.45 0 0 85000 73000 0 0 0 Storage 1 0 Source 1 10000

    Hub 2 4.26 10000000 0 0 0 0 0 0 Storage 2 0 Source 2 15000

    Hub 3 7.45 0 0 0 73000 0 0 0 Storage 3 0 31900000 0 4250 21900 0 0 0 0 48750 31,974,900.00

    Hub 2 Hub 1 7.45 0 0 0 0 0 0 0 Storage 1 0 Source 1 0

    Hub 2 4.26 0 0 0 0 0 0 0 Storage 2 0 Source 2 0

    Hub 3 7.45 0 0 0 0 0 0 0 Storage 3 0

    0 0 0 0 0 0 0 0 0 0.00

    Hub 3 Hub 1 7.45 0 0 0 0 0 0 0 Storage 1 0 Source 1 0

    Hub 2 4.26 10000000 0 0 0 0 0 0 Storage 2 0 Source 2 0

    Hub 3 7.45 0 0 85000 0 0 0 0 Storage 3 0

    31900000 0 4250 0 0 0 0 0 0 31,904,250.00

    Time 2 Hub 1 Hub 1 8.43 0 50000 0 0 0 0 65000 Storage 1 0 Source 1 10000

    Hub 2 8.34 10000000 0 0 0 0 0 0 Storage 2 0 Source 2 15000

    Hub 3 8.54 0 0 0 0 0 0 0 Storage 3 0 900000 1500 0 0 0 0 21450 0 73250 996,200.00

    Hub 2 Hub 1 8.43 0 0 0 0 0 0 0 Storage 1 0 Source 1 0

    Hub 2 8.34 0 0 0 0 0 0 4000 Storage 2 0 Source 2 0

    Hub 3 8.54 0 0 0 0 0 0 0 Storage 3 0 0 0 0 0 0 0 960 0 0 960.00

    Hub 3 Hub 1 8.43 0 0 0 0 0 0 0 Storage 1 0 Source 1 0

    Hub 2 8.34 10000000 0 0 0 0 0 0 Storage 2 0 Source 2 0

    Hub 3 8.54 50000 0 73000 0 0 65000 Storage 3 0

    2000000 7000 0 2920 0 0 28600 0 0 2,038,520.00

    Time 3 Hub 1 Hub 1 9.45 0 85000 73000 74000 32000 65000 Storage 1 10000 Source 1 10000

    Hub 2 7.64 10000000 0 0 0 0 0 0 Storage 2 10000 Source 2 15000

    Hub 3 8.45 9862000 0 0 73000 0 0 65000 Storage 3 10000

    27962000 0 46750 153300 62900 1600 357500 282000 98750 28,964,800.00

  • 41

    Hub 2 Hub 1 9.45 0 0 0 0 0 0 0 Storage 1 0 Source 1 0

    Hub 2 7.64 0 0 0 0 0 0 0 Storage 2 0 Source 2 0

    Hub 3 8.45 0 0 0 0 0 0 0 Storage 3 0

    0 0 0 0 0 0 0 0 0 0.00

    Hub 3 Hub 1 9.45 0 0 0 0 0 0 0 Storage 1 0 Source 1 0

    Hub 2 7.64 10000000 0 0 0 0 0 0 Storage 2 0 Source 2 0

    Hub 3 8.45 0 0 0 0 0 0 0 Storage 3 0

    8100000 0 0 0 0 0 0 0 0 8,100,000.00

    Total Net Profit 105,201,380.00

    Table 8 Spot Market Trading Profits from Deterministic Approach, all units are stated in MMbtu unless otherwise indicated

  • 42

    Cost to Meet Demand

    Time Period Demand Location

    Spot Price ($/MMBtu)

    Spot Purchase

    for Demand

    F1fixed F2

    fixed F3

    fixed F4

    variable F5

    variable F6

    variable Cost to Meet Demand ($)

    Time 1 Demand 1 Hub 1 7.45 0 0 0 0 0 0 0 0.00

    Hub 2 4.26 9600 0 0 0 0 0 0 40,896.00

    Hub 3 7.45 0 0 0 0 0 0 0 0.00 40,896.00 Demand 2 Hub 1 7.45 0 0 0 0 0 0 0 0.00

    Hub 2 4.26 6400 0 0 0 0 0 0 27,264.00

    Hub 3 7.45 0 0 0 0 0 0 0 0.00 27,264.00 Demand 3 Hub 1 7.45 0 0 0 0 0 0 0 0.00

    Hub 2 4.26 8000 0 0 0 0 0 0 34,080.00

    Hub 3 7.45 0 0 0 0 0 0 0 0.00 34,080.00 Demand 4 Hub 1 7.45 0 0 0 0 0 0 0 0.00

    Hub 2 4.26 6500 0 0 0 0 0 0 27,690.00

    Hub 3 7.45 0 0 0 0 0 0 0 0.00 27,690.00 Demand 5 Hub 1 7.45 0 0 0 0 0 0 0 0.00

    Hub 2 4.26 7500 0 0 0 0 0 0 31,950.00

    Hub 3 7.45 0 0 0 0 0 0 0 0.00 31,950.00 Total Cost to Meet Demand During Time 1 161,880.00 Time 2 Demand 1 Hub 1 8.43 0 0 0 0 0 0 0 0.00

    Hub 2 8.34 0 0 0 0 0 0 12000 97,200.00

    Hub 3 8.54 0 0 0 0 0 0 0 0.00 97,200.00 Demand 2 Hub 1 8.43 0 0 0 0 0 0 0 0.00

    Hub 2 8.34 0 0 0 0 0 0 14000 113,400.00

    Hub 3 8.54 0 0 0 0 0 0 0 0.00 113,400.00 Demand 3 Hub 1 8.43 0 0 0 0 0 0 0 0.00

    Hub 2 8.34 0 0 0 0 0 0 17000 137,700.00

    Hub 3 8.54 0 0 0 0 0 0 0 0.00 137,700.00 Demand 4 Hub 1 8.43 0 0 0 0 0 0 0 0.00

    Hub 2 8.34 0 0 0 0 0 0 18000 145,800.00

    Hub 3 8.54 0 0 0 0 0 0 0 0.00 145,800.00 Demand 5 Hub 1 8.43 0 0 0 0 0 0 0 0.00

    Hub 2 8.34 18500 0 0 0 0 0 0 154,290.00

    Hub 3 8.54 0 0 0 0 0 0 0 0.00 154,290.00 Total Cost to Meet Demand During Time 2 648,390.00 Time 3 Demand 1 Hub 1 9.45 0 0 0 0 0 0 0 0.00

    Hub 2 7.64 1500 0 0 0 0 0 14500 108,610.00

    Hub 3 8.45 0 0 0 0 0 0 0 0.00 108,610.00 Demand 2 Hub 1 9.45 0 0 0 0 0 0 0 0.00

    Hub 2 7.64 0 0 0 0 0 0 15000 100,500.00

    Hub 3 8.45 0 0 0 0 0 0 0 0.00 100,500.00 Demand 3 Hub 1 9.45 0 0 0 0 0 0 0 0.00

    Hub 2 7.64 0 0 0 0 0 0 16500 110,550.00

    Hub 3 8.45 0 0 0 0 0 0 0 0.00 110,550.00 Demand 4 Hub 1 9.45 0 0 0 0 0 0 0 0.00

    Hub 2 7.64 15500 0 0 0 0 0 0 118,420.00

    Hub 3 8.45 0 0 0 0 0 0 0 0.00 118,420.00 Demand 5 Hub 1 9.45 0 0 0 0 0 0 0 0.00

    Hub 2 7.64 0 0 0 0 0 0 19000 127,300.00

    Hub 3 8.45 0 0 0 0 0 0 0 0.00 127,300.00 Total Cost to Meet Demand During Time 2 565,380.00

    The Total Cost to Meet Demand 1,375,650.00 Table 9 Cost to Meet Demand from Deterministic Approach, all units are stated in MMbtu unless otherwise indicated

  • 43

    3.2 Expected Cost Approach

    We now consider the case which uncertainty exists with the spot market prices at each of the time

    periods. We will assume that the spot market prices are stochastic and take on the values as listed in

    Table 10. with the probabilities of occurrence at 35%, 45% and 20% for scenarios 1, 2, and 3,

    respectively.

    Scenario Probability Location ($/MMBtu)

    Time 1 Time 2 Time 3

    Scenario 1 0.35 Spot Price Hub1 7.45 8.43 9.45

    Spot Price Hub2 4.26 8.34 7.64

    Spot Price Hub3 7.45 8.54 8.45

    Scenario 2 0.45 Spot Price Hub1 9 9.1 11.32

    Spot Price Hub2 6 9 8.95

    Spot Price Hub3 8.5 8.9 8.95

    Scenario 3 0.2 Spot Price Hub1 7 8.2 9.11

    Spot Price Hub2 5 8.2 7.5

    Spot Price Hub3 7 8.4 8.21

    Table 10 Spot market prices in the three scenarios considered

    3.2.1 Deterministic demand

    As the demand requirements; forward options; cost of the minimum benchmark; storage,

    production and capacity prices and limitations remain the same as the deterministic model, the

    optimal replication strategy is shown in Table 12, Table 13, Table 14, and Table 15. The spot market

    prices for scenario 1 are the same as the conditions used in the deterministic model. Scenarios 2 and

    3, presents the cases for which the spot price are expected to be relatively higher and lower,

    respectively. Under scenario 2, when the spot prices are relatively higher for all time periods, it is

    favorable to purchase more forwards to sell on the spot market. Purchasing more forwards would

    produce undesirable outcomes for some instances in scenarios 3 (For example, Time 1, spot markets

    1 and 3), when the spot market prices drop below the original prices of the forwards. However,

    since the optimal strategy is based on the expected value, therefore, because of a higher probability

    of occurrence for scenarios 1 and 2, the overall strategy would remain as taking advantage of the

    arbitrage opportunity by purchasing more forwards. If each scenario is calculated independently

    using the deterministic model, the volumes of forwards purchased to sell on the spot market would

    wholly depend on the relative prices of the two. With the stochastic approach, a strategy which

    optimizes the expected results is determined. Such strategy would reduce the risks of uncertainty by

    taking into consideration of different possible outcomes. The uncertainty of the prices does not

  • 44

    negatively impact the type of strategies associated with location arbitrage, and selling on the spot

    market from both production and storages, because recourse decisions are determined for each time

    period under each scenario to take into consideration of the negative effects of undesired outcomes.

    However the magnitude of the arbitrage opportunity is affected by the uncertainty of prices.

    Similar to the deterministic model, in the stochastic approach, demand requirements are satisfied by

    a combination of volumes from spot market purchases and forwards, determined by the lower cost

    strategy out of the two options. In scenario 2, when the spot market prices are high, more demand

    volumes are met through forward contracts. While in scenario 3, more demand volumes are met

    through spot market purchases.

    The expected cost to meet demand is $1,447,077.00, with an expected savings of $67,363.00. With

    the uncertainty of the spot market prices factored in our model, the cost to meet demand for each

    scenario is still less than the minimum benchmark cost. All decisions determined by the stochastic

    model would heavily rely on correct scenarios and expected values used.

    Scenario Total Cost to Meet Demand

    Minimum Benchmark Cost

    1 $1,429,270.00 $1,514,440.00

    2 $1,472,650.00 $1,514,440.00

    3 $1,420,700.00 $1,514,440.00

    Table 11 Cost to Meet Demand for the Three Scenarios Considered Using Stochastic - Minimizing Expected Cost Approach

  • 45

    Capacity Acquisition Strategy

    Destination Locations

    Storage 1 Storage 2 Storage 3 Hub 1 Hub 2 Hub 3 Demand 1 Demand2 Demand 3 Demand 4 Demand 5

    D

    e

    p

    a

    r

    t

    u

    r

    e

    L

    o

    c

    a

    t

    i

    o

    n

    s

    Storage 1 0 0 0 10000 0 0 0 0 0 0 0

    Storage 2 0 0 0 10000 0 0 0 0 0 0 0

    Storage 3 0 0 0 10000 0 0 0 0 0 0 0

    Hub 1 0 0 0 0 0 0 0 0 0 0 0

    Hub 2 10000 10000 10000 10000000 0 10000000 16000 15000 17000 18000 19000

    Hub 3 0 0 0 10000000 0 0 0 0 0 0 0

    Source 1 0 0 0 10000 0 0 0 0 0 0 0

    Source 2 0 0 0 15000 0 0 0 0 0 0 0

    Total Capacity Acquired 30170000

    Total Cost of Capacity $ 25,946,200.00 Table 12 Capacity Acquisition Strategy for Stochastic Expected Cost Approach (Deterministic Demand), all units are stated in MMBtu, unless otherwise indicated

  • 46

    Scenario Spot Price ($/MMBtu)

    Total Purchased

    on the Spot

    Market

    Total Sold on Spot

    Market

    F1 fixed

    F2 fixed

    F3 fixed

    F4 variable

    F5 variable

    F6 variable

    Total in Storage Total

    Production from Source

    Total Cost ($)

    Total Revenue

    ($) Net Cost ($)

    Time 0

    Hub 1 9.00 0 10040000 Storage 1 5000 Source 1 10000 55000 90360000 -90,305,000.00 Hub 2 9.10 0 0 Storage 2 5000 Source 2 15000 82500 0 82,500.00 Hub 3 8.90 10000000 0 Storage 3 5000 89000000 0 89,000,000.00

    System Cost During Time 0 (Now) -1,222,500.00 Time 1

    Scenario 1 (0.35)

    Hub 1 7.45 0 10478000 50000 85000 73000 74000 32000 65000 Storage 1 0 Source 1 10000 2,942,150.00 78061100 -75,118,950.00 Hub 2 4.26 20068000 0 0 0 0 0 0 0 Storage 2 0 Source 2 15000 85,572,430.00 0 85,572,430.00 Hub 3 7.45 0 10208000 50000 85000 73000 74000 0 0 Storage 3 0 2,114,350.00 76049600 -73,935,250.00

    -63,481,770.00

    Scenario 2 (0.45)

    Hub 1 9.00 0 20404000 50000 85000 73000 74000 32000 65000 Storage 1 0 Source 1 10000 2,942,150.00 183636000 -180,693,850.00 Hub 2 6.00 20068000 0 0 0 0 0 0 0 Storage 2 0 Source 2 15000 120,490,750.00 0 120,490,750.00 Hub 3 8.50 9926000 10208000 50000 85000 73000 74000 0 0 Storage 3 0 86,485,350.00 86768000 -282,650.00

    -60,485,750.00

    Scenario 3 (0.20)

    Hub 1 7.00 0 10528000 50000 85000 73000 74000 32000 65000 Storage 1 0 Source 1 10000 2,942,150.00 73696000 -70,753,850.00 Hub 2 5.00 20068000 0 0 0 0 0 0 0 Storage 2 0 Source 2 15000 100,422,750.00 0 100,422,750.00 Hub 3 7.00 0 10158000 50000 85000 73000 74000 0 0 Storage 3 0 2,114,350.00 71106000 -68,991,650.00

    -39,322,750.00 System Cost DuringTime 1 -57,301,757.00

    Time 2

    Scenario 1 (0.35)

    Hub 1 8.43 0 10213000 50000 0 73000 0 0 65000 Storage 1 10000 Source 1 10000 1,622,500.00 86095590 -84,473,090.00 Hub 2 8.34 20035000 143500 50000 0 73000 0 0 65000 Storage 2 10000 Source 2 15000 168,741,900.00 1196790 167,545,110.00 Hub 3 8.54 0 10188000 50000 0 73000 0 0 65000 Storage 3 10000 1,567,500.00 87005520 -85,438,020.00

    -2,366,000.00

    Scenario 2 (0.45)

    Hub 1 9.10 0 20223000 50000 0 73000 0 0 65000 Storage 1 10000 Source 1 10000 1,622,500.00 184029300 -182,406,800.00 Hub 2 9.00 10024500 123000 50000 0 73000 0 0 65000 Storage 2 10000 Source 2 15000 91,870,500.00 1107000 90,763,500.00 Hub 3 8.90 9950000 138000 50000 0 73000 0 0 65000 Storage 3 10000 90,122,500.00 1228200 88,894,300.00

    -2,749,000.00

    Scenario 3 (0.20)

    Hub 1 8.20 0 213000 50000 0 73000 0 0 65000 Storage 1 10000 Source 1 10000 1,622,500.00 1746600 -124,100.00 Hub 2 8.20 10047500 156000 50000 0 73000 0 0 65000 Storage 2 10000 Source 2 15000 84,039,500.00 1279200 82,760,300.00 Hub 3 8.40 0 10188000 50000 0 73000 0 0 65000 Storage 3 10000 1,567,500.00 85579200 -84,011,700.00

    -1,375,500.00 System Cost DuringTime 2 -2,340,250.00

    Time 3

    Scenario 1 (0.35)

    Hub 1 9.45 0 20384000 0 85000 73000 74000 32000 65000 Storage 1 10000 Source 1 10000 2,797,900.00 192628800 -189,830,900.00 Hub 2 7.64 20066000 49000 0 0 0 0 0 65000 Storage 2 10000 Source 2 15000 153,822,740.00 374360 153,448,380.00 Hub 3 8.45 9926000 10138000 0 0 73000 74000 0 65000 Storage 3 10000 85,560,300.00 85666100 -105,800.00

    -36,488,320.00

    Scenario 2 (0.45)

    Hub 1 11.32 0 20384000 0 85000 73000 74000 32000 65000 Storage 1 10000 Source 1 10000 2,797,900.00 230746880 -227,948,980.00 Hub 2 8.95 10017000 0 0 0 0 0 0 65000 Storage 2 10000 Source 2 15000 90,170,650.00 0 90,170,650.00 Hub 3 8.95 10000000 212000 0 0 73000 74000 0 65000 Storage 3 10000 91,186,600.00 1897400 89,289,200.00

    -48,489,130.00

    Scenario 3 (0.20)

    Hub 1 9.11 0 20384000 0 85000 73000 74000 32000 65000 Storage 1 10000 Source 1 10000 2,797,900.00 185698240 -182,900,340.00 Hub 2 7.50 20035500 18500 0 0 0 0 0 65000 Storage 2 10000 Source 2 15000 150,784,750.00 138750 150,646,000.00

  • 47

    Hub 3 8.21 9853000 10065000 0 0 73000 74000 0 65000 Storage 3 10000 82,578,730.00 82633650 -54,920.00 -32,309,260.00

    System Cost During Time 3 -41,052,872.50

    Total System Cost -101,917,379.50 Table 13 Overall System Cost for Stochastic Expected Cost Approach (Deterministic Demand), all units are stated in MMBtu, unless otherwise indicated

  • 48

    Spot Market Profits

    Time Period

    Scenario

    Spot Market Hub

    Location for Selling

    Spot Price ($/MMBtu)

    Spot Purchase

    for Arbitrage

    F1 fixed

    F2 fixed

    F3 fixed

    F4 variable

    F5 variable

    F6 variable

    Total Storage for Spot Market Selling

    Total Production towards Spot Market

    Selling Net Profit ($)

    Time 0

    Hub 1 Hub 1 9.00 Storage 1 5000 Source 1 10000

    Hub 2 9.10

    Storage 2 5000 Source 2 15000

    Hub 3 8.90 10000000 Storage 3 5000

    1000000 134250 87500 1221750

    Hub 2 Hub 1 9.00

    Storage 1

    Source 1

    Hub 2 9.10

    Storage 2

    Source 2

    Hub 3 8.90

    Storage 3

    0 0 0 0.00

    Hub 3 Hub 1 9.00

    Storage 1

    Source 1

    Hub 2 9.10

    Storage 2

    Source 2

    Hub 3 8.90 Storage 3

    0

    0

    0 0.00

    Time 1

    Scenario 1 (0.35)

    Hub 1 Hub 1 7.45

    50000 85000 73000 74000 32000 65000 Storage 1

    Source 1 10000

    Hub 2 4.26 10000000 Storage 2

    Source 2 15000

    Hub 3 7.45

    74000 Storage 3

    31900000 -2500 4250 10950 -51800 -14400 -35750 0 48750 31,859,500.00

    Hub 2 Hub 1 7.45

    Storage 1

    Source 1

    Hub 2 4.26

    Storage 2

    Source 2

    Hub 3 7.45

    Storage 3

    0 0 0 0 0 0 0 0 0 0.00

    Hub 3 Hub 1 7.45

    Storage 1

    Source 1

    Hub 2 4.26 10000000 Storage 2

    Source 2

    Hub 3 7.45 50000 85000 73000

    Storage 3

    31900000 -2500 4250 10950 0 0 0 0 0 31,912,700.00

    Scenario 2 (0.45)

    Hub 1 Hub 1 9.00 50000 85000 73000 74000 32000 65000 Storage 1

    Source 1 10000

    Hub 2 6.00 10000000 Storage 2

    Source 2 15000

    Hub 3 8.50 9926000

    74000 Storage 3

    34963000 75000 136000 124100 177600 35200 65000 0 87500 35,663,400.00

    Hub 2 Hub 1 9.00

    Storage 1

    Source 1

    Hub 2 6.00

    Storage 2

    Source 2

    Hub 3 8.50

    Storage 3

    0 0 0 0 0 0 0 0 0 0.00

    Hub 3 Hub 1 9.00

    Storage 1

    Source 1

    Hub 2 6.00 10000000 Storage 2

    Source 2

    Hub 3 8.50 50000 85000 73000

    Storage 3

    25000000 50000 93500 87600 0 0 0 0 0 25,231,100.00

    Scenario 3 (0.20)

    Hub 1 Hub 1 7.00 50000 85000 73000 74000 32000 65000 Storage 1

    Source 1 10000

    Hub 2 5.00 10000000 Storage 2

    Source 2 15000

    Hub 3 7.00

    50000

    74000 Storage 3

    20000000 -50000 -34000 -21900 -118400 -28800 -65000 0 37500 19,719,400.00

    Hub 2 Hub 1 7.00

    Storage 1

    Source 1

    Hub 2 5.00 Storage 2

    Source 2

  • 49

    Hub 3 7.00

    Storage 3

    0 0 0 0 0 0 0 0 0 0.00

    Hub 3 Hub 1 7.00

    Storage 1

    Source 1

    Hub 2 5.00 10000000 Storage 2

    Source 2

    Hub 3 7.00

    85000 73000

    Storage 3

    20000000 0 -34000 -21900 0 0 0

    0

    0 19,944,100.00

    Time 2

    Scenario 1 (0.35)

    Hub 1 Hub 1 8.43 50000 73000 65000 Storage 1

    Source 1 10000

    Hub 2 8.34 10000000

    Storage 2

    Source 2 15000

    Hub 3 8.54

    Storage 3

    900000 1500 0 -5110 0 0 21450 0 73250 991,090.00

    Hub 2 Hub 1 8.43

    Storage 1

    Source 1

    Hub 2 8.34

    38000 73000 32500 Storage 2

    Source 2

    Hub 3 8.54

    Storage 3

    0 -2280 0 -11680 0 0 7800 0 0 -6,160.00

    Hub 3 Hub 1 8.43

    Storage 1

    Source 1

    Hub 2 8.34 10000000

    Storage 2

    Source 2

    Hub 3 8.54 50000 73000 65000 Storage 3

    2000000 7000 0 2920 0 0 28600 0 0 2,038,520.00

    Scenario 2 (0.45)

    Hub 1 Hub 1 9.10 50000 73000 65000 Storage 1

    Source 1 10000

    Hub 2 9.00 10000000 Storage 2

    Source 2 15000

    Hub 3 8.90 9950000 50000 0 Storage 3 10000

    2990000 70000 0 43800 0 0 65000 90500 90000 3,349,300.00

    Hub 2 Hub 1 9.10

    Storage 1

    Source 1

    Hub 2 9.00 50000 73000

    Storage 2

    Source 2

    Hub 3 8.90

    Storage 3

    0 30000 0 36500 0 0 0 0 0 66,500.00

    Hub 3 Hub 1 9.10

    Storage 1

    Source 1

    Hub 2 9.00

    Storage 2

    Source 2

    Hub 3 8.90

    73000 65000 Storage 3

    0 0 0 29200 0 0 52000 0 0 81,200.00

    Scenario 3 (0.20)

    Hub 1 Hub 1 8.20 50000 73000 65000 Storage 1

    Source 1 10000

    Hub 2 8.20

    Storage 2

    Source 2 15000

    Hub 3 8.40

    Storage 3

    0 -10000 0 -21900 0 0 6500 0 67500 42,100.00

    Hub 2 Hub 1 8.20

    Storage 1

    Source 1

    Hub 2 8.20

    36000 73000 47000 Storage 2

    Source 2

    Hub 3 8.40

    Storage 3

    0 -7200 0 -21900 0 0 4700 0 0 -24,400.00

    Hub 3 Hub 1 8.20

    Storage 1

    Source 1

    Hub 2 8.20 10000000

    Storage 2

    Source 2

    Hub 3 8.40 50000 73000 65000 Storage 3

    2000000 0 0 -7300 0 0 19500

    0

    0 2,012,200.00

    Time 3

    Scenario 1 (0.35)

    Hub 1 Hub 1 9.45 85000 73000 74000 32000 65000 Storage 1 10000 Source 1 10000

    Hub 2 7.64 10000000 Storage 2 10000 Source 2 15000

    Hub 3 8.45 9926000 74000

    Storage 3 10000

    28026000 0 46750 76650 125800 1600 178750 282000 98750 28,836,300.00

    Hub 2 Hub 1 9.45

    Storage 1

    Source 1

    Hub 2 7.64 49000 Storage 2

    Source 2

    Hub 3 8.45

    Storage 3

  • 50

    0 0 0 0 0 0 46060 0 0 46,060.00

    Hub 3 Hub 1 9.45

    Storage 1

    Source 1

    Hub 2 7.64 10000000

    Storage 2

    Source 2

    Hub 3 8.45 73000

    65000 Storage 3

    8100000 0 0 3650 0 0 113750 0 0 8,217,400.00

    Scenario 2 (0.45)

    Hub 1 Hub 1 11.32 85000 73000 74000 32000 65000 Storage 1 10000 Source 1 10000

    Hub 2 8.95 10000000

    Storage 2 10000 Source 2 15000

    Hub 3 8.95 10000000

    Storage 3 10000

    47400000 0 205700 213160 201280 61440 300300 338100 145500 48,865,480.00

    Hub 2 Hub 1 11.32

    Storage 1

    Source 1

    Hub 2 8.95

    Storage 2

    Source 2

    Hub 3 8.95

    Storage 3

    0 0 0 0 0 0 0 0 0 0.00

    Hub 3 Hub 1 11.32

    Storage 1

    Source 1

    Hub 2 8.95

    Storage 2

    Source 2

    Hub 3 8.95 73000 74000 65000 Storage 3

    0 0 0 40150 25900 0 146250 0 0 212,300.00

    Scenario 3 (0.20)

    Hub 1 Hub 1 9.11 85000 73000 74000 32000 65000 Storage 1 10000 Source 1 10000

    Hub 2 7.50 10000000 Storage 2 10000 Source 2 15000

    Hub 3 8.21 9853000 73000 74000

    Storage 3 10000

    24967700 0 17850 103660 75480 -9280 156650 271800 90250 25,674,110.00

    Hub 2 Hub 1 9.11

    Storage 1

    Source 1

    Hub 2 7.50

    18500 Storage 2

    Source 2

    Hub 3 8.21

    Storage 3

    0 0 0 0 0 0 14800 0 0 14,800.00

    Hub 3 Hub 1 9.11

    Storage 1

    Source 1

    Hub 2 7.50 10000000 Storage 2

    Source 2

    Hub 3 8.21

    65000 Storage 3

    7100000 0 0 0 0 0 98150 0 0 7,198,150.00

    Total Profit from Selling on the Spot Market 103,562,411.50 Table 14 Spot Market Transaction for Stochastic Expected Cost Approach (Deterministic Demand), all units are stated in MMBtu, unless otherwise indicated

  • 51

    Cost to meet Demand

    Time Period

    Scenario Demand Location

    Spot Price ($/MMBtu)

    Spot Purchase

    for Demand

    F1fixed F2

    fixed F3

    fixed F4

    variable F5

    variable F6

    variable Cost to Meet Demand ($)

    Time 1

    Scenario 1

    Demand 1 Hub 1 7.45 0 0.00

    Hub 2 4.26 9600 40,896.00

    Hub 3 7.45 0 0.00

    40,896.00

    Demand 2 Hub 1 7.45 0 0.00

    Hub 2 4.26 6400 27,264.00

    Hub 3 7.45 0 0.00

    27,264.00

    Demand 3 Hub 1 7.45 0 0.00

    Hub 2 4.26 8000 34,080.00

    Hub 3 7.45 0 0.00

    34,080.00

    Demand 4 Hub 1 7.45 0 0.00

    Hub 2 4.26 6500 27,690.00

    Hub 3 7.45 0 0.00

    27,690.00

    Demand 5 Hub 1 7.45 0 0.00

    Hub 2 4.26 7500 31,950.00

    Hub 3 7.45 0 0.00

    31,950.00

    Total Cost to Meet Demand during Time 1 in Scenario 1 161,880.00

    Scenario 2

    Demand 1 Hub 1 9.00 0.00

    Hub 2 6.00 9600 57,600.00

    Hub 3 8.50 0.00

    57,600.00

    Demand 2 Hub 1 9.00 0.00

    Hub 2 6.00 6400 38,400.00

    Hub 3 8.50 0.00

    38,400.00

    Demand 3 Hub 1 9.00 0.00

    Hub 2 6.00 8000 48,000.00

    Hub 3 8.50 0.00

    48,000.00

    Demand 4 Hub 1 9.00 0.00

    Hub 2 6.00 6500 39,000.00

    Hub 3 8.50 0.00

    39,000.00

    Demand 5 Hub 1 9.00 0.00

    Hub 2 6.00 7500 45,000.00

    Hub 3 8.50 0.00

    45,000.00

    Total Cost to Meet Demand during ime 1 in Scenario 2 228,000.00

    Scenario 3

    Demand 1 Hub 1 7.00 0.00

    Hub 2 5.00 9600 48,000.00

    Hub 3 7.00 0.00

    48,000.00

    Demand 2 Hub 1 7.00 0.00

    Hub 2 5.00 6400 32,000.00

    Hub 3 7.00 0.00

    32,000.00

    Demand 3 Hub 1 7.00 0.00

    Hub 2 5.00 8000 40,000.00

    Hub 3 7.00 0.00

    40,000.00

    Demand 4 Hub 1 7.00 0.00

    Hub 2 5.00 6500 32,500.00

    Hub 3 7.00 0.00

    32,500.00

    Demand 5 Hub 1 7.00 0.00

    Hub 2 5.00 7500 37,500.00

    Hub 3 7.00 0.00

    37,500.00

    Total Cost to Meet Demand duringTime 1 in Scenario 3 190,000.00

  • 52

    Total Expected Cost to Meet Demand at Time 1 197,258.00

    Time 2

    Scenario 1

    Demand 1 Hub 1 8.43 0.00

    Hub 2 8.34 12000

    100,800.00

    Hub 3 8.54

    0.00 100,800.00 Demand 2 Hub 1 8.43

    0.00

    Hub 2 8.34

    14000 113,400.00

    Hub 3 8.54

    0.00

    113,400.00 Demand 3 H