A REPORT TO ICON DUNFAIR LIMITED A GEOTECHNICAL INVESTIGATION … · 2018-02-07 · a report to...
Transcript of A REPORT TO ICON DUNFAIR LIMITED A GEOTECHNICAL INVESTIGATION … · 2018-02-07 · a report to...
A REPORT TO ICON DUNFAIR LIMITED
A GEOTECHNICAL INVESTIGATION
PROPOSED RESIDENTIAL DEVELOPMENT
2024 AND 2026 ALTONA ROAD AND 200 FINCH AVENUE
CITY OF PICKERING
REFERENCE NO. 1701-S023
MARCH 2017
DISTRIBUTION 3 Copies - Icon Dunfair Limited 1 Copy - Soil Engineers Ltd. (Oshawa) 1 Copy - Soil Engineers Ltd. (Toronto)
Reference No. 1701-S023 ii
TABLE OF CONTENTS
1.0 INTRODUCTION ................................................................................... 1
2.0 SITE AND PROJECT DESCRIPTION .................................................. 2
3.0 FIELD WORK ........................................................................................ 3
4.0 SUBSURFACE CONDITIONS .............................................................. 4
4.1 Topsoil ............................................................................................ 4 4.2 Earth Fill ......................................................................................... 5 4.3 Sandy Silt Till ................................................................................. 5 4.4 Sand ............................................................................................... 7 4.5 Silty Clay ........................................................................................ 8 4.6 Compaction Characteristics of the Revealed Soils ........................ 9
5.0 GROUNDWATER CONDITIONS ........................................................ 12 6.0 DISCUSSION AND RECOMMENDATIONS ...................................... 14
6.1 Foundations .................................................................................... 16 6.2 Engineered Fill ............................................................................... 19 6.3 Basement and Slab-On-Grade ........................................................ 22 6.4 Underground Services .................................................................... 23 6.5 Backfilling in Trenches and Excavated Areas ............................... 24 6.6 Sidewalk, Interlocking Stone Pavement and Landscaping ............ 26 6.7 Pavement Design ............................................................................ 27 6.8 Soil Parameters ............................................................................... 29 6.9 Excavation ...................................................................................... 29
7.0 LIMITATIONS OF REPORT ................................................................. 31
Reference No. 1701-S023 iii
TABLES
Table 1 - Estimated Water Content for Compaction ........................................ 10
Table 2- Groundwater Levels ........................................................................... 12
Table 3 - Founding Levels ................................................................................ 17
Table 4 - Pavement Design ............................................................................... 27
Table 5 - Soil Parameters .................................................................................. 29
Table 6 - Classification of Soils for Excavation ............................................... 30
DIAGRAM
Diagram 1- Frost Protection Measures (Foundations) ..................................... 19
ENCLOSURES Borehole Logs ...................................................................... Figures 1 to 9 Grain Size Distribution Graphs ........................................... Figures 10 and 11 Borehole Location Plan ....................................................... Drawing No. 1 Subsurface Profile ................................................................ Drawing No. 2
Reference No. 1701-S023 1
1.0 INTRODUCTION
In accordance with written authorization dated January 3, 2017, from
Mr. Stephen Brown of Icon Dunfair Limited, a geotechnical investigation was carried
out at 2024 and 2026 Altona Road and 200 Finch Avenue, in the City of Pickering,
for a Proposed Residential Development.
The purpose of the investigation was to reveal the subsurface conditions and to
determine the engineering properties of the disclosed soils for the design and
construction of the proposed project.
The geotechnical findings and resulting recommendations are presented in this
Report.
Reference No. 1701-S023 2
2.0 SITE AND PROJECT DESCRIPTION
The City of Pickering is situated on Iroquois (glacial lake) plain where, in places, the
glacial till stratigraphy has been partly eroded by the water action of the glacial lake
and filled with lacustrine sands, silts, clays and reworked till.
The site, approximately 2.19 hectares (5.4 acres) in area, is located at the northwest
quadrant of Altona Road and Finch Avenue in the City of Pickering. At the time of
investigation, the site is mostly covered with trees and vegetation, with existing
residences at the northeast and southwest portions. Near the west boundary of the
property, there is an existing scrap yard. The existing site gradient is relatively flat,
with a slight drop towards the southwest.
We understand that the site will be developed into a residential subdivision,
consisting of semi-detached houses and townhouse blocks. The new development
will be provided with municipal services, paved access roadway and parking spaces,
meeting urban standards.
Reference No. 1701-S023 3
3.0 FIELD WORK
The field work, consisting of 9 boreholes was performed on February 3, 2017 at the
locations shown on the Borehole Location Plan, Drawing No. 1. Borehole 1,
terminated at a depth of 0.6 m from the ground surface, was conducted for surface
soil sampling and limited for environmental assessment. Boreholes 6 and 7 were
terminated at a depth of 4.7 m due to refusal to augering on probable boulder. The
remaining boreholes were extended to depths of 6.3 to 6.7 m from grade.
Upon completion of drilling and soil sampling, four (4) monitoring wells were
installed one each in selected boreholes for Environmental Site Assessment.
The holes were advanced at intervals to the sampling depths by a track-mounted,
continuous-flight power-auger machine equipped for soil sampling. Standard
Penetration Tests, using the procedures described on the enclosed “List of
Abbreviations and Terms”, were performed at the sampling depths. The test results
are recorded as the Standard Penetration Resistance (or ‘N’ values) of the subsoil.
The relative density of the granular strata and the consistency of the cohesive strata
are inferred from the ‘N’ values. Split-spoon samples were recovered for soil
classification and laboratory testing.
The field work was supervised and the findings were recorded by a Geotechnical
Technician.
The elevation at each of the borehole locations was determined using Trimble 6000
GeoXH Global Navigation Satellite System survey equipment, which has an accuracy
of 10 cm.
Reference No. 1701-S023 4
4.0 SUBSURFACE CONDITIONS
Detailed descriptions of the encountered subsurface conditions are presented on the
Borehole Logs, comprising Figures 1 to 9, inclusive. The revealed stratigraphy is
plotted on the Subsurface Profile, Drawing No. 2, and the engineering properties of
the disclosed soils are discussed herein.
The investigation has revealed that beneath a topsoil veneer and a layer of earth fill,
the site is underlain by sandy silt till with occasional sand and silty clay layers.
4.1 Topsoil (Boreholes 1, 2, 3, 6, 7, 8 and 9)
The revealed topsoil thickness ranges between 25 cm and 60 cm. It is dark brown in
colour, indicating that it contains appreciable amounts of roots and humus. This
material is unstable and compressible under loads; therefore, the topsoil is considered
to be void of engineering value. Due to the humus content, the topsoil will generate
an offensive odour and may produce volatile gases under anaerobic conditions.
Therefore, the topsoil must not be buried below any structures or deeper than 1.2 m
below the exterior finished grade so it will not have an adverse impact on the
environmental well-being of the developed area.
Borehole 1, drilled for environmental assessment, was terminated at a depth of 0.6 m
from the prevailing ground surface.
Since the topsoil is considered void of engineering value, it can only be used for
general landscaping or landscape contouring purposes.
Reference No. 1701-S023 5
4.2 Earth Fill (All Boreholes)
The earth fill, consisting of silty sand with silty clay, gravel, occasional topsoil and
organics, was contacted. The earth fill in Boreholes 4 and 5 was found to contain
debris of wood, plastic and a mixture of topsoil. The earth fill extends to depths of
0.7 to 1.4 m below the prevailing ground surface.
The natural water content values of the earth fill range from 12% to 20%, with a
median of 14%, indicating that the earth fill is in a moist to wet condition.
The obtained ‘N’ values range from 1 to 22 blows per 30 cm of penetration,
indicating the relative density of the earth fill was non-uniform.
In using the earth fill for structural backfill, it must be subexcavated, inspected, sorted
free of debris, concentrated topsoil inclusions and deleterious materials, if any, and
properly recompacted in layers.
One must be aware that the samples retrieved from boreholes 10 cm in diameter may
not be truly representative of the geotechnical and environmental quality of the fill,
and do not indicate whether the topsoil beneath the earth fill was completely stripped.
This should be further assessed by laboratory testing and/or test pits.
4.3 Sandy Silt Till (All Boreholes)
The sandy silt till stratum was contacted at depths of 0.8 to 2.9 m below the
prevailing ground surface. It consists of a random mixture of soils; the particle sizes
range from clay to gravel, with the silt fraction exerting the dominant influence on its
soil properties. It structure is heterogeneous, showing a glacial deposit.
Reference No. 1701-S023 6
The obtained ‘N’ values range from 10 to over 50, with a median of 29 blows per
30 cm of penetration, indicating that the relative density of the sandy silt till is
compact to very dense, being generally compact.
The natural water content was determined and the results are plotted on the borehole
logs. These values range from 5% to 16%, with a median of 10%, indicating that the
silt till is in a damp to very moist condition, being generally moist.
Grain size analyses were performed on 3 representative samples; the results are
plotted on Figure 10.
Based on the above findings, the engineering properties of the silt till relating to the
project are given below:
• High frost susceptibility and soil-adfreezing potential.
• Low water erodibility.
• Moderately low permeability, with an estimated coefficient of permeability of
10-6 cm/sec, an average percolation rate of 60 min/cm, and runoff coefficients
of:
Slope
0% - 2% 0.15
2% - 6% 0.20
6% + 0.28
• A frictional soil, its shear strength is primarily derived from internal friction
and is augmented by cementation. Therefore, its strength is primarily soil
density dependent.
• In steep cuts, the till will be stable; however, under prolonged exposure,
localized sheet collapse will occur, particularly in the zone where wet sand and
silt layers are prevalent.
Reference No. 1701-S023 7
• A poor pavement-supportive material with an estimated CBR value of 5%.
• Moderate corrosivity to buried metal, with an estimated electrical resistivity of
4000 to 4500 ohm·cm.
4.4 Sand (Boreholes 4, 5, 8 and 9)
The sand deposit was contacted below the earth fill. It is fine grained or fine to
medium, with silt and occasional gravel.
The obtained ‘N’ values range from 11 to 31 blows per 30 cm of penetration,
indicating that the relative density of the sand deposit is compact to dense.
The natural water content was determined and the results are plotted on the borehole
logs. These values range from 7% to 21%, with a median of 17%, indicating that the
sand is in a damp to wet condition, being generally wet or saturated.
A grain size analysis was performed on 1 representative sample; the result is plotted
on Figure 11.
Based on the above findings, the deduced engineering properties pertaining to the
project are given below:
• Moderate frost susceptibility and low soil-adfreezing potential.
• High water erodibility.
• Pervious, with an estimated coefficient of permeability of 10-3 cm/sec, an
average percolation rate of 10 min/cm, and runoff coefficients of:
Reference No. 1701-S023 8
Slope
0% - 2% 0.04
2% - 6% 0.09
6% + 0.13
• A frictional soil, the shear strength is primarily derived from internal friction;
therefore, the strength is density dependent. Due to the dilatancy, the shear
strength of the wet sand is susceptible to impact disturbance; i.e., the
disturbance will induce a build-up of pore pressure within the soil mantle,
resulting in soil dilation and a reduction of shear strength.
• The sand will slough if it is wet and run with water seepage and the bottom
will boil under a piezometric head of 0.4 m.
• Fair pavement-supportive material, with an estimated CBR value of 8%.
• Moderately low corrosivity to buried metal, with an estimated electrical
resistivity of 6000 ohm·cm.
4.5 Silty Clay (Boreholes 4 and 5)
The silty clay was contacted underlying the sand deposit. It contains occasional
seams of silty sand.
The obtained ‘N’ values are 7 and 13 blows per 30 cm of penetration, indicating the
consistency of the clay is firm to stiff.
The natural water content was determined at 19% and 21%, indicating a very moist
condition.
The deduced engineering properties pertaining to the project are given below:
• High frost susceptibility and soil-adfreezing potential.
Reference No. 1701-S023 9
• The laminated silty sand layers are water erodible.
• Low permeability, with an estimated coefficient of permeability of 10-7 cm/sec,
an average percolation rate of more than 80 min/cm, and runoff coefficients of:
Slope
0% - 2% 0.15
2% - 6% 0.20
6% + 0.28
• A cohesive-frictional soil, its shear strength is derived from consistency and
augmented by the internal friction of the silt. Its shear strength is moisture
dependent, due to the dilatancy of the silt, the overall shear strength of the silty
clay is susceptible to impact disturbance; i.e., the disturbance will induce a
build-up of pore pressure within the soil mantle, resulting in soil dilation and a
reduction of shear strength.
• In steep cuts, the weathered clay with high moisture will slough readily and a
cut face in the sound clay may collapse as the wet silt slowly sloughs.
• A very poor pavement-supportive material, with an estimated CBR value of
3% or less.
• Moderately high to moderate corrosivity to buried metal, with an estimated
electrical resistivity of 3000 to 4000 ohm⋅cm.
4.6 Compaction Characteristics of the Revealed Soils
The obtainable degree of compaction is primarily dependent on the soil moisture and,
to a lesser extent, on the type of compactor used and the effort applied.
As a general guide, the typical water content values of the revealed soils for Standard
Proctor compaction are presented in Table 1.
Reference No. 1701-S023 10
Table 1 - Estimated Water Content for Compaction
Soil Type Determined Natural Water Content (%)
Water Content (%) for Standard Proctor Compaction
100% (optimum) Range for 95% or +
Existing Earth Fill 12 to 20 (median 14) 12 8 to 15
Sandy Silt Till 5 to 16 (median 10) 13 8 to 16
Sand 7 to 21 (median 17) 10 6 to 13
Silty Clay 19 and 21 17 13 to 21
The above values show that most of the on-site material is suitable for 95% or +
Standard Proctor compaction. However, part of the earth fill and the saturated sand
are too wet and will require aeration prior to structural compaction. Aeration can be
achieved by spreading them thinly on the ground in the dry, warm weather or the
saturated sand can be stockpiled to drain the excess water prior to structural
compaction.
The till and clay should be compacted using a heavy-weight, kneading-type roller.
The sand can be compacted by a smooth roller with or without vibration, depending
on the water content of the soils being compacted. The lifts for compaction should be
limited to 20 cm, or to a suitable thickness as assessed by test strips performed by the
equipment which will be used at the time of construction.
One should be aware that with considerable effort, a 90%± Standard Proctor
compaction of the wet silty sand is achievable. Further densification is prevented by
the pore pressure induced by the compactive effort; however, large random voids will
have been expelled and, with time, the pore pressure will dissipate and the percentage
Reference No. 1701-S023 11
of compaction will increase. There are many cases on record where after a few
months of rest, the density of the compacted mantle had increased to over 95% of its
maximum Standard Proctor dry density.
When compacting the till or clay on the dry side of the optimum, the compactive
energy will frequently bridge over the chunks in the soil and be transmitted laterally
into the soil mantle. Therefore, the lifts of this soil must be limited to 20 cm or less
(before compaction). It is difficult to monitor the lifts of backfill placed in deep
trenches; therefore, it is preferable that the compaction of backfill at depths over
1.0 m below the road subgrade be carried out on the wet side of the optimum. This
would allow wider latitude of lift thickness.
If the compaction of the soils is carried out with the water content within the range
for 95% Standard Proctor dry density but on the wet side of the optimum, the surface
of the compacted soil mantle will roll under the dynamic compactive load. This is
unsuitable for pavement construction since each component of the pavement structure
is to be placed under dynamic conditions which will induce the rolling action of the
subgrade surface and cause structural failure of the new pavement. The slab-on-
grade, foundations for buildings and utilities will be placed on a subgrade which will
not be subjected to impact loads. Therefore, the structurally compacted soil mantle
with the water content on the wet side or dry side of the optimum will provide an
adequate subgrade for the construction.
The presence of boulders in the till will prevent transmission of the compactive
energy into the underlying material to be compacted. If an appreciable amount of
boulders over 15 cm in size mixed with the material, it must either be sorted or must
not be used for structural backfill and/or construction of engineered fill.
Reference No. 1701-S023 12
5.0 GROUNDWATER CONDITIONS
The boreholes and monitoring wells were checked for the presence of groundwater
and the occurrence of cave-in upon their completion and on February 10, 2017. The
levels are plotted on the Borehole Logs and listed in Table 2.
Table 2- Groundwater Levels
BH No. Ground El.
(m)
Borehole Depth
(m)
Well Installed
Depth (m)
Measured Groundwater/
Cave-in* Level On Completion
Groundwater Level on
February 10, 2017
Depth (m)
El. (m)
Depth (m)
El. (m)
2 139.4 6.3 - 1.8 137.6 - -
3 139.4 6.6 - 1.2/1.5* 138.2/137.9* - -
4 139.9 6.7 5.2 3.7/4.0* 136.2/135.9* 2.7 137.2
5 139.0 6.7 5.5 3.7/4.0* 135.3/135.0* 1.3 137.7
6 138.9 4.7 - 0.9* 138.0* - -
7 138.6 4.7 3.7 0.8 137.8 0.2 138.4
8 138.5 6.3 - 0.9/1.2* 137.6/137.3* - -
9 138.1 6.6 4.0 1.2/1.4* 136.9/136.7* 0.9 137.2
Groundwater and/or cave-in of boreholes were recorded at depths of 0.8 to 4.0 m
below the prevailing ground surface, upon completion of drilling. On February 10,
2017, the stabilized groundwater level was recorded at depths of 0.2 to 2.7 m from
the ground surface, or El. 138.4 to 137.2 m in the monitoring wells.
The detected groundwater is likely due to infiltrated precipitation trapped in the earth
fill or in the sand and silt layers rendering perched groundwater above the strata of
low permeable clay or till. It is expected to fluctuate with the seasons.
Reference No. 1701-S023 13
In excavation, the groundwater yield from the clay and till, due to their low
permeability, is expected to be small and limited, while the yield from the saturated
sand is expected to be moderate to appreciable and likely persistent. The water can
be collected to a sump and removed by conventional pumping.
Reference No. 1701-S023 14
6.0 DISCUSSION AND RECOMMENDATIONS
The investigation has disclosed that beneath a topsoil veneer, 25 to 60 cm in
thickness, and a layer of earth fill, extending to depths of 0.7 to 1.4 m, the site is
underlain by compact to very dense sandy silt till with occasional compact to dense
sand and firm to stiff silty clay layers.
Groundwater and/or cave-in of boreholes were recorded at depths of 0.8 to 4.0 m
below the prevailing ground surface upon completion of drilling. Stabilized
groundwater levels in the monitoring wells were recorded at depths of 0.2 to 2.7 m
from the ground surface, or El. 138.4 to 137.2 m on February 10, 2017. The detected
groundwater is likely due to infiltrated precipitation trapped in the earth fill or in the
sand layers rendering perched groundwater above the strata of low permeable clay or
till. It is expected to fluctuate with the seasons.
We understand that the existing structures will be demolished and the site will be
regraded for the development of a residential subdivision. The geotechnical findings
which warrant special consideration are presented below:
1. The topsoil is void of engineering value, unsuitable for engineering
applications. Due to its humus content, the topsoil will generate an offensive
odour and may produce volatile gases under anaerobic conditions. For the
environmental as well as the geotechnical well-being of the future
development, the topsoil should not be buried below any structures or deeper
than 1.2 m below the external finished grade.
2. Due to the unknown history of the earth fill, and the presence of topsoil and
other deleterious materials, the fill is unsuitable for supporting any structure
sensitive to movement. In using the fill for structural backfill, or in pavement
or slab-on-grade construction, it should be subexcavated, inspected, sorted free
Reference No. 1701-S023 15
of debris, concentrated topsoil inclusions and any deleterious materials, and
properly recompacted in layers. If it is impractical to sort the debris, topsoil
and other deleterious material from the fill, the fill must be wasted.
3. The sound natural soil below the topsoil and earth fill is suitable for normal
spread and strip footing construction for the proposed houses and townhouse
blocks.
4. The footing subgrade must be inspected by either a geotechnical engineer, or a
geotechnical technician under the supervision of a geotechnical engineer, or by
a building inspector who has geotechnical experience, to ensure that its
condition is compatible with the design of the foundation.
5. Where cut and fill is necessary for site grading, substantial savings can be
realized by placing the fill in an engineered manner suitable for foundation,
underground services and access roadway construction. This must, however,
be properly planned and implemented during the site grading stage.
6. In the west portion of the site where saturated sand is present, the basement
structure should be constructed above the saturation level unless the
submerged portion is waterproofed, otherwise, dewatering from the foundation
subdrains will be required. The stabilized groundwater level will be specified
in the hydrogeological assessment report.
7. The subgrade for the underground services should consist of properly
compacted inorganic earth fill or sound natural soil. A Class ‘B’ bedding is
recommended for the underground services construction. The bedding
material should consist of compacted 20-mm Crusher-Run Limestone, or
equivalent. In areas where the subgrade is saturated, a Class ‘A’ bedding
should be considered.
8. Curb subdrains will be required for road construction.
9. Excavation should be carried out in accordance with Ontario Regulation
213/91.
Reference No. 1701-S023 16
10. The till contains occasional cobbles and boulders. Boulders over 15 cm in size
must not be used for structural backfill and/or construction of engineered fill.
Excavation into the till containing boulders will require extra effort and the use
of a heavy-duty backhoe.
The recommendations appropriate for the project described in Section 2.0 are
presented herein. One must be aware that the subsurface conditions may vary
between boreholes. Should this become apparent during construction, a geotechnical
engineer must be consulted to determine whether the following recommendations
require revision.
6.1 Foundations
Based on the borehole findings, normal spread and strip footings of the proposed
structures must be placed below the earth fill and onto the sound, natural soil. As a
general guide, the recommended soil pressures for use in the design of conventional
footings, together with the corresponding suitable founding levels, are presented in
Table 3.
Reference No. 1701-S023 17
Table 3 - Founding Levels
Borehole No.
Recommended Maximum Allowable Soil Pressure (SLS)/ Factored Ultimate Soil Bearing Pressure (ULS) and
Suitable Founding Level
100 kPa (SLS) 160 kPa (ULS)
200 kPa (SLS) 320 kPa (ULS)
400 kPa (SLS) 640 kPa (ULS)
Depth (m) El. (m) Depth (m) El. (m) Depth (m)
El. (m)
2 - - 1.4 or + 138.0 or - 2.4 or + 137.0 or -
3 - - 1.4 or + 138.0 or - 2.4 or + 137.0 or -
4 1.6 or + 138.3 or - 4.8 or + 135.1 or - - -
5 1.0 or + 138.0 or - 2.4 or + 136.6 or - - -
6 1.2 or + 137.7 or - - - 2.4 or + 136.5 or -
7 - - 1.0 or + 137.6 or - 2.4 or + 136.2 or -
8 - - 1.0 or + 137.5 or - 3.2 or + 135.3 or -
9 1.0 or + 137.1 or - 3.2 or + 134.9 or - - -
Where cut and fill is required for site grading, it is generally more practical and
economical to place an engineered fill suitable for a Maximum Allowable Soil
Pressure (SLS) of 100 kPa for normal footing construction. The requirements and
procedures for engineered fill construction are discussed in Section 6.2.
The recommended soil pressure (SLS) incorporates a safety factor of 3. The total and
differential settlements of the footings are estimated to be 25 mm and 15 mm,
respectively.
Reference No. 1701-S023 18
The footings must meet the requirements specified in the latest version of the Ontario
Building Code. As a guide, the structure should be designed to resist an earthquake
force using Site Classification ‘D’ (stiff soil).
In the west portion of the site, where a saturated sand stratum is present, the basement
structure should be constructed above the saturated level unless the submerged
portion is waterproofed, otherwise, permanent dewatering from the foundation
subdrains will be required. The subdrains will consist of perimeter drains and under-
floor drains, connecting into sump pits where water can be removed by gravity or
pumping. All the subdrains should be encased in a fabric-filter to protect them
against blockage by silting.
If groundwater is encountered in the footing excavation, or the subgrade is found to
be wet, the subgrade should be protected by a concrete mud-slab placed immediately
after exposure. This will prevent construction disturbance and costly rectification.
Due to the presence of earth fill, the footing subgrade must be inspected by either a
geotechnical engineer, or by a geotechnical technician under the supervision of a
geotechnical engineer, or a building inspector who has geotechnical experience, to
assess its suitability for bearing the designed foundations.
Foundations exposed to weathering or in unheated areas should be protected against
frost action by a minimum of 1.2 of earth cover.
The on site soils are high in soil-adfreezing potential. If they are used for the
foundation backfill, the foundation walls should be constructed in concrete and
shielded by a polyethylene slip-membrane for protection against soil adfreezing. The
recommended measures are schematically illustrated below in Diagram 1.
Reference No. 1701-S023 19
Diagram 1- Frost Protection Measures (Foundations)
Vapour Barrier
Slip-Membrane (Closed End Up)Folded Heavy Polyethylene
Covered with 19-mm Clear StoneSubdrain Encased in Fabric Filter
1.2m
Floor Subdrain
(Subject to
Conditions)Groundwater
The membrane will allow vertical movement of the heaving soil (due to frost)
without imposing structural distress on the foundations. The external grading should
be such that runoff is directed away from the foundation.
6.2 Engineered Fill
It is generally more economical to place engineered fill for normal footing,
underground services and pavement construction. The engineering requirements for
a certifiable fill for pavement construction, municipal services, slab-on-grade, and
footings designed with a Maximum Allowable Soil Pressure (SLS) of 100 kPa and a
Factored Ultimate Soil Bearing Pressure (ULS) of 160 kPa are presented below:
1. All of the topsoil, earth fill and organics must be removed and the subgrade
must be inspected and proof-rolled prior to any fill placement. The weathered
soils must be subexcavated, sorted and recompacted and the subgrade must be
inspected and proof-rolled prior to any fill placement.
2. Inorganic soils must be used, and they must be uniformly compacted in lifts
20 cm thick to 98% or + of their maximum Standard Proctor dry density up to
1.4 m
Reference No. 1701-S023 20
the proposed finished grade and/or slab-on-grade subgrade. The soil moisture
must be properly controlled on the wet side of the optimum.
3. If imported fill is to be used, the hauler is responsible for its environmental
quality and must provide a document to certify that the material is free of
hazardous contaminants.
4. If the residential units’ foundations are to be built soon after the fill placement,
the densification process for the engineered fill must be increased to 100% of
the maximum Standard Proctor compaction.
5. If the engineered fill is to be left over the winter months, adequate earth cover,
or equivalent, must be provided for protection against frost action.
6. The engineered fill must extend over the entire graded area; the engineered fill
envelope and the finished elevations must be clearly and accurately defined in
the field, and they must be precisely documented by qualified surveyors.
Foundations partially on engineered fill must be reinforced by two
15-mm steel reinforcing bars in the footings and upper section of the
foundation walls, or be designed by a structural engineer, to properly distribute
the stress induced by the abrupt differential settlement (estimated to be
15± mm) between the natural soils and engineered fill.
7. The engineered fill must not be placed during the period from late November
to early April, when freezing ambient temperatures occur either persistently or
intermittently. This is to ensure that the fill is free of frozen soils, ice or snow.
8. Where the ground is wet due to subsurface water seepage, an appropriate
subdrain scheme must be implemented prior to the fill placement.
9. Where the fill is to be placed on sloping ground steeper than 1 vertical:
3 horizontal, the face of the sloping ground must be flattened to 3 + so that it is
suitable for safe operation of the compactor and the required compaction can
be obtained.
Reference No. 1701-S023 21
10. The fill operation must be inspected on a full-time basis by a technician under
the direction of a geotechnical engineer.
11. The footing and underground services subgrade must be inspected by the
geotechnical consulting firm that inspected the engineered fill placement. This
is to ensure that the foundations are placed within the engineered fill envelope,
and the integrity of the fill has not been compromised by interim construction,
environmental degradation and/or disturbance by the footing excavation.
12. Any excavation carried out in certified engineered fill must be reported to the
geotechnical consultant who supervised the fill placement in order to
document the locations of the excavation and/or to supervise reinstatement of
the excavated areas to engineered fill status. If construction on the engineered
fill does not commence within a period of 2 years from the date of
certification, the condition of the engineered fill must be assessed for
re-certification.
13. Despite stringent control in the placement of the engineered fill, variations in
soil type and density may occur in the engineered fill. Therefore, the strip
footings and the upper section of the foundation walls constructed on the
engineered fill may require continuous reinforcement with steel bars,
depending on the uniformity of the soils in the engineered fill and the
thickness of the engineered fill underlying the foundations. Should the
footings and/or walls require reinforcement, the required number and size of
reinforcing bars must be assessed by considering the uniformity as well as the
thickness of the engineered fill beneath the foundations. In sewer
construction, the engineered fill is considered to have the same structural
proficiency as a natural inorganic soil.
Reference No. 1701-S023 22
6.3 Basement and Slab-On-Grade
The soil parameters outlined in Section 6.8 can be used for calculating the lateral
earth pressure imposed on the basement walls. In order to prevent water ponding
against the perimeter walls and wetting the basement, perimeter subdrains should be
installed and the walls should be dampproofed or waterproofed. If groundwater
seepage is encountered during basement excavation, the conditions must be further
assessed and under-floor subdrains consisting of filter-sleeved weepers connecting
into a positive outlet will be required.
The subgrade for slab-on-grade construction should comprise sound natural soils or
properly compacted earth fill. The existing topsoil must be removed. Any soft or
loose areas detected must be subexcavated and replaced with inorganic fill,
compacted to at least 98% of its maximum Standard Proctor dry density prior to
placement of the granular base.
If the subgrade has been loosened due to construction traffic, it must be proof-rolled
before placement of the granular base.
The slab should be constructed on a granular base 20 cm thick, consisting of
20-mm Crusher-Run Limestone, or equivalent, compacted to 100% of its maximum
Standard Proctor dry density.
A Modulus of Subgrade Reaction of 25 MPa/m can be used for the design of the floor
slab.
Reference No. 1701-S023 23
The ground around the buildings must be graded to direct water away from the
structure to minimize the frost heave phenomenon generally associated with the
disclosed soils.
6.4 Underground Services
The subgrade for the underground services should consist of sound natural soil or
properly compacted, organic-free earth fill. Where badly weathered or loose soils are
encountered, they should be subexcavated and replaced with the bedding material
compacted to at least 95% or + of its Standard Proctor compaction.
A Class ‘B’ bedding is generally recommended for the underground services
construction. The bedding material should consist of compacted 20-mm Crusher-Run
Limestone, or equivalent. In areas where the subgrade is saturated, a Class ‘A’
bedding should be considered or anti-seepage collars will be required.
In order to prevent pipe floatation when the sewer trench is deluged with water, a soil
cover at least equal in thickness to the diameter of the pipe should be in place at all
times after completion of the pipe installation.
Openings to subdrains and catch basins should be shielded with a fabric filter to
prevent blockage by silting.
Sewer excavation must be sloped at 1 vertical:1 or + horizontal for stability.
Alternatively, a trench box can also be used for the construction of the sewer.
The water main should be protected against corrosion. In determining the mode of
protection, an electrical resistivity of 3000 ohm∙cm should be used. This, however,
should be confirmed by testing the soil along the water main alignment at the time of
sewer construction.
Reference No. 1701-S023 24
6.5 Backfilling in Trenches and Excavated Areas
The on-site inorganic soil is mostly suitable for trench backfill. However, the earth
fill should be sorted free of any topsoil, deleterious materials and foreign matter prior
to the backfilling. In addition, most of the existing earth fill and saturated sand are
wet and will require aeration or mixing with drier soils prior to structural compaction.
The sandy silt till should be sorted free of boulders, if encountered, for backfilling.
The backfill in the trenches should be compacted to at least 95% of its maximum
Standard Proctor dry density and increased to 98% or + below the floor slab. In the
zone within 1.0 m below the road subgrade, the materials should be compacted with
the water content 2% to 3% drier than the optimum, and the compaction should be
increased to at least 98% of the respective maximum Standard Proctor dry density.
This is to provide the required stiffness for pavement construction. In the lower zone,
the compaction should be carried out on the wet side of the optimum; this allows
wider latitude of lift thickness. Backfill below any slab-on-grade which is sensitive
to settlement must be compacted to at least 98% of its maximum Standard Proctor
dry density.
In normal construction practice, the problem areas of settlement largely occur
adjacent to manholes, catch basins, services crossings, foundation walls and columns.
In areas which are inaccessible to a heavy compactor, imported sand backfill should
be used. Unless compaction of the backfill is carefully performed, the interface of the
native soils and the sand backfill will have to be flooded for a period of several days.
The narrow trenches for services crossings should be cut at 1 vertical:
2 or + horizontal so that the backfill can be effectively compacted. Otherwise, soil
arching will prevent the achievement of proper compaction. The lift of each backfill
Reference No. 1701-S023 25
layer should either be limited to a thickness of 20 cm, or the thickness should be
determined by test strips.
One must be aware of the possible consequences during trench backfilling and
exercise caution as described below:
• When construction is carried out in freezing winter weather, allowance should
be made for these following conditions. Despite stringent backfill monitoring,
frozen soil layers may inadvertently be mixed with the structural trench
backfill. Should the in situ soils have a water content on the dry side of the
optimum, it would be impossible to wet the soils due to the freezing condition,
rendering difficulties in obtaining uniform and proper compaction.
Furthermore, the freezing condition will prevent flooding of the backfill when
it is required, such as in a narrow vertical trench section, or when the trench
box is removed. The above will invariably cause backfill settlement that may
become evident within 1 to several years, depending on the depth of the trench
which has been backfilled.
• In areas where the underground services construction is carried out during the
winter months, prolonged exposure of the trench walls will result in frost
heave within the soil mantle of the walls. This may result in some settlement
as the frost recedes, and repair costs will be incurred prior to final surfacing of
the new pavement and the slab-on-grade.
• To backfill a deep trench, one must be aware that future settlement is to be
expected, unless the side of the cut is flattened to at least 1 vertical:
1.5+ horizontal, and the lifts of the fill and its moisture content are stringently
controlled; i.e., lifts should be no more than 20 cm (or less if the backfilling
conditions dictate) and uniformly compacted to achieve at least 95% of the
Reference No. 1701-S023 26
maximum Standard Proctor dry density, with the moisture content on the wet
side of the optimum.
• It is often difficult to achieve uniform compaction of the backfill in the lower
vertical section of a trench which is an open cut or is stabilized by a trench
box, particularly in the sector close to the trench walls or the sides of the box.
These sectors must be backfilled with sand. In a trench stabilized by a trench
box, the void left after the removal of the box will be filled by the backfill. It
is necessary to backfill this sector with sand, and the compacted backfill must
be flooded for 1 day, prior to the placement of the backfill above this sector,
i.e., in the upper sloped trench section. This measure is necessary in order to
prevent consolidation of inadvertent voids and loose backfill which will
compromise the compaction of the backfill in the upper section. In areas
where groundwater movement is expected in the sand fill mantle, anti-seepage
collars should be provided.
6.6 Sidewalk, Interlocking Stone Pavement and Landscaping
Due to the high frost susceptibility of on site soils, heaving of the pavement and
sidewalk is expected to occur during the cold weather.
Interlocking stone pavement, slab-on-grade and landscaping structures in areas which
are sensitive to frost-induced ground movement, such as in front of building
entrances, must be constructed on a free-draining, non-frost-susceptible granular
material such as Granular ‘B’. This material must extend to at least 0.3 to 1.2 m
below the slab or pavement surface, depending on the degree of tolerance of ground
movement, and be provided with positive drainage, such as weeper subdrains
connected to manholes or catch basins. Alternatively, the landscaping structures,
slab-on-grade and interlocking stone pavement should be properly insulated with
50-mm Styrofoam, or equivalent.
Reference No. 1701-S023 27
The grading around structures must be such that it directs runoff away from the
structures.
6.7 Pavement Design
The on site soils are poor to fair pavement-supportive materials; the recommended
pavement designs for the proposed roads are presented in Table 4.
Table 4 - Pavement Design
Course Thickness (mm) OPS Specifications
Asphalt Surface 40 HL-3
Asphalt Binder 60 HL-8
Granular Base 150 OPSS Granular ‘A’ or equivalent
Granular Sub-base 350 OPSS Granular ‘B’ or equivalent
In preparation of the subgrade, the topsoil must be removed. The final subgrade must
be proof-rolled. Any soft subgrade as identified should be subexcavated and replaced
by properly compacted, organic-free earth fill.
In the zone within 1.0 m below the pavement subgrade, the backfill should be
compacted to at least 98% of its maximum Standard Proctor dry density, with the
water content 2% to 3% drier than the optimum. In the lower zone, a 95% or +
Standard Proctor compaction is considered adequate.
All the granular bases should be compacted to their maximum Standard Proctor dry
density.
Reference No. 1701-S023 28
The pavement subgrade will suffer a strength regression if water is allowed to
saturate the mantle. The following measures should, therefore, be incorporated in the
construction procedures and pavement design:
• If the pavement construction does not immediately follow the trench
backfilling, the subgrade should be properly crowned and smooth-rolled to
allow interim precipitation to be properly drained.
• Areas adjacent to the pavement should be properly graded to prevent ponding
of large amounts of water during the interim construction period.
• Curb subdrains will be required. The subdrains should consist of filter-sleeved
weepers to prevent blockage by silting. The subdrains should be installed to a
depth of at least 0.4 m below the pavement subgrade surface and then
backfilled with free-draining granular material.
• If the pavement is to be constructed during wet seasons and extensively soft
subgrade occurs, the granular sub-base should be thickened in order to
compensate for the inadequate strength of the subgrade. This can be assessed
during construction.
In the paved areas, catch basins should be provided; they should drain into the storm
sewer or a suitable outlet. The trenches for the connections to the catch basins should
be backfilled with free-draining granular material such as Granular ‘B’, and filter-
sleeved weeper stubs should be installed at the manholes and catch basins into the
granular backfill. This will allow water in the trenches to drain into the storm sewers.
Reference No. 1701-S023 29
6.8 Soil Parameters
The recommended soil parameters for the project design are given in Table 5.
Table 5 - Soil Parameters
Unit Weight and Bulk Factor Unit Weight (kN/m3)
Estimated Bulk Factor
Bulk Submerged Loose Compacted
Earth Fill 20.5 11.5 1.20 0.98
Sand 20.0 10.0 1.25 1.00
Silty Clay 21.0 11.5 1.30 1.00
Sandy Silt Till 22.5 12.5 1.33 1.05
Lateral Earth Pressure Coefficients
Active Ka
At Rest K0
Passive Kp
Compacted Earth Fill/Silty Clay 0.45 0.60 2.20
Sand 0.35 0.52 2.80
Sandy Silt Till 0.30 0.46 3.30
6.9 Excavation
Excavation should be carried out in accordance with Ontario Regulation 213/91.
For excavation purposes, the types of soils are classified in Table 6.
Reference No. 1701-S023 30
Table 6 - Classification of Soils for Excavation
Material Type
Sound Silty Clay, Sandy Silt Till 2
Earth Fill, drained Sand 3
Saturated Sand 4
In excavation, the groundwater yield from the clay and till, due to their low
permeability, is expected to be small and limited, while the yield from the sand is
expected to be moderate to appreciable and likely persistent. Any groundwater
seepage can be collected in to sumps and removed by conventional pumping.
Prospective contractors must assess the in situ subsurface conditions prior to
excavation by digging test pits to at least 0.5 m below the sewer subgrade. These test
pits should be allowed to remain open for a period of at least 4 hours to assess the
trenching conditions.
LIST OF ABBREVIATIONS AND DESCRIPTION OF TERMS The abbreviations and terms commonly employed on the borehole logs and figures, and in the text of the report, are as follows: SAMPLE TYPES
AS Auger sample CS Chunk sample DO Drive open (split spoon) DS Denison type sample FS Foil sample RC Rock core (with size and percentage
recovery) ST Slotted tube TO Thin-walled, open TP Thin-walled, piston WS Wash sample PENETRATION RESISTANCE
Dynamic Cone Penetration Resistance:
A continuous profile showing the number of blows for each foot of penetration of a 2-inch diameter, 90° point cone driven by a 140-pound hammer falling 30 inches. Plotted as ‘ • ’
Standard Penetration Resistance or ‘N’ Value:
The number of blows of a 140-pound hammer falling 30 inches required to advance a 2-inch O.D. drive open sampler one foot into undisturbed soil. Plotted as ‘’
WH Sampler advanced by static weight PH Sampler advanced by hydraulic pressure PM Sampler advanced by manual pressure NP No penetration
SOIL DESCRIPTION
Cohesionless Soils:
‘N’ (blows/ft) Relative Density
0 to 4 very loose 4 to 10 loose
10 to 30 compact 30 to 50 dense
over 50 very dense
Cohesive Soils:
Undrained Shear Strength (ksf) ‘N’ (blows/ft) Consistency
less than 0.25 0 to 2 very soft 0.25 to 0.50 2 to 4 soft 0.50 to 1.0 4 to 8 firm 1.0 to 2.0 8 to 16 stiff 2.0 to 4.0 16 to 32 very stiff
over 4.0 over 32 hard
Method of Determination of Undrained Shear Strength of Cohesive Soils:
x 0.0 Field vane test in borehole; the number denotes the sensitivity to remoulding
Laboratory vane test
Compression test in laboratory
For a saturated cohesive soil, the undrained shear strength is taken as one half of the undrained compressive strength
METRIC CONVERSION FACTORS 1 ft = 0.3048 metres 1 inch = 25.4 mm 1lb = 0.454 kg 1ksf = 47.88 kPa
0.0
(No geotechnical data retained)
This borehole was sampled for the environmental scope of work.
8
7
6
5
4
3
2
1
00
1LOG OF BOREHOLE NO.:1701-S023JOB NO.:
Proposed Residential DevelopmentPROJECT DESCRIPTION:
2024 and 2026 Altona Road and 200 Finch Avenue City of Pickering
PROJECT LOCATION:
1FIGURE NO.:
ShovelMETHOD OF BORING:
February 3, 2017DRILLING DATE:
Ground Surface
El.(m)
Depth(m)
SOILDESCRIPTION
SAMPLES
Num
ber
Type
N-V
alue
Dep
th S
cale
(m)
Atterberg LimitsPL LL
WA
TER
LE
VE
L
Dynamic Cone (blows/30 cm)
9070503010
Penetration Resistance(blows/30 cm)
9070503010
Shear Strength (kN/m2)
20015010050
Moisture Content (%)40302010
Soil Engineers Ltd.1 of 1Page:
0.0
0.3
1.2
6.3
139.1
138.2
133.1
END OF BOREHOLE
30 cm TOPSOIL
EARTH FILL
brown silty sand, some gravel, cobble and rootlets
Grey, compact to very dense
SANDY SILT TILL
a trace to some clay and gravel occ. sand and clay seams and layers, cobbles and boulders
10
15
21
50/15
60/15
50/15
55/15
DO
DO
DO
DO
DO
DO
DO
1A
1B
2
3
4
5
6
7
8
7
6
5
4
3
2
1
0 4620
16
7
6
7
6
7W
.L. @
El.
137.
6 m
on
com
plet
ion
139.4
2LOG OF BOREHOLE NO.:1701-S023JOB NO.:
Proposed Residential DevelopmentPROJECT DESCRIPTION:
2024 and 2026 Altona Road and 200 Finch Avenue City of Pickering
PROJECT LOCATION:
2FIGURE NO.:
Flight-AugerMETHOD OF BORING:
February 3, 2017DRILLING DATE:
Ground Surface
El.(m)
Depth(m)
SOILDESCRIPTION
SAMPLES
Num
ber
Type
N-V
alue
Dep
th S
cale
(m)
Atterberg LimitsPL LL
WA
TER
LE
VE
L
Dynamic Cone (blows/30 cm)
9070503010
Penetration Resistance(blows/30 cm)
9070503010
Shear Strength (kN/m2)
20015010050
Moisture Content (%)40302010
Soil Engineers Ltd.1 of 1Page:
0.0
0.3
1.2
6.6
139.1
138.2
132.8
END OF BOREHOLE
30 cm TOPSOIL
EARTH FILL
brown silty sand, some clay and gravel, occ. cobble and organics
Grey, compact to very dense
SANDY SILT TILL
a trace to some clay and gravel occ. sand and clay seams and layers, cobbles and boulders
4
22
16
50/15
53/15
74
63
DO
DO
DO
DO
DO
DO
DO
1A
1B
2
3
4
5
6
7
8
7
6
5
4
3
2
1
0 2213
13
11
5
6
7
7
W.L
. @ E
l. 13
8.2
m o
n co
mpl
etio
nC
ave-
in @
El.
137.
9 m
on
com
plet
ion
139.4
3LOG OF BOREHOLE NO.:1701-S023JOB NO.:
Proposed Residential DevelopmentPROJECT DESCRIPTION:
2024 and 2026 Altona Road and 200 Finch Avenue City of Pickering
PROJECT LOCATION:
3FIGURE NO.:
Flight-AugerMETHOD OF BORING:
February 3, 2017DRILLING DATE:
Ground Surface
El.(m)
Depth(m)
SOILDESCRIPTION
SAMPLES
Num
ber
Type
N-V
alue
Dep
th S
cale
(m)
Atterberg LimitsPL LL
WA
TER
LE
VE
L
Dynamic Cone (blows/30 cm)
9070503010
Penetration Resistance(blows/30 cm)
9070503010
Shear Strength (kN/m2)
20015010050
Moisture Content (%)40302010
Soil Engineers Ltd.1 of 1Page:
0.0
1.4
2.2
2.5
6.7
138.5
137.7
137.4
133.2
END OF BOREHOLE
Installed 50 mm Ø monitoring well to 5.2 m. (3.1 m screen) Sand backfill from 1.6 m to 5.2 m. Bentonite seal from 0.2 m to 1.6 m. Provided with monument protective casing.
EARTH FILL
dark brown to brown sand and gravel some debris of wood and plastic occ. topsoil and organics
Brown, compact
SAND
fine grained, some siltBrown, stiff
SILTY CLAY occ. seams of silty sandGrey, compact
SANDY SILT TILL
a trace to some clay and gravel occ. sand and clay seams and layers, cobbles and boulders
9
10
17
13
10
12
22
16
28
DO
DO
DO
DO
DO
DO
DO
DO
DO
1
2
3
4
5
6
7
8
9
8
7
6
5
4
3
2
1
0 12
13
7
19
12
11
11
10
10 W.L
. @ E
l. 13
6.2
m o
n co
mpl
etio
nC
ave-
in @
El.
135.
9 m
on
com
plet
ion
W.L
. @ E
l. 13
7.2
m o
n Fe
brua
ry 1
0, 2
017
139.9
4LOG OF BOREHOLE NO.:1701-S023JOB NO.:
Proposed Residential DevelopmentPROJECT DESCRIPTION:
2024 and 2026 Altona Road and 200 Finch Avenue City of Pickering
PROJECT LOCATION:
4FIGURE NO.:
Flight-AugerMETHOD OF BORING:
February 2, 2017DRILLING DATE:
Ground Surface
El.(m)
Depth(m)
SOILDESCRIPTION
SAMPLES
Num
ber
Type
N-V
alue
Dep
th S
cale
(m)
Atterberg LimitsPL LL
WA
TER
LE
VE
L
Dynamic Cone (blows/30 cm)
9070503010
Penetration Resistance(blows/30 cm)
9070503010
Shear Strength (kN/m2)
20015010050
Moisture Content (%)40302010
Soil Engineers Ltd.1 of 1Page:
0.0
0.8
1.7
2.2
6.7
138.2
137.3
136.8
132.3
END OF BOREHOLE
Installed 50 mm Ø monitoring well to 5.5 m. (3.1 m screen) Sand backfill from 1.9 m to 5.5 m. Bentonite seal from 0.2 m to 1.9 m. Provided with monument protective casing.
EARTH FILL
dark brown silty sand mixed with topsoil
Brown, compact
SAND
fine grained, some silt
Brown, firm
SILTY CLAY occ. seams of silty sandCompact to dense
SANDY SILT TILL
a trace to some clay and gravel occ. sand and clay seams and layers, cobbles and boulders
browngrey
8
11
7
20
16
26
25
35
29
DO
DO
DO
DO
DO
DO
DO
DO
DO
1
2
3
4
5
6
7
8
9
8
7
6
5
4
3
2
1
0 19
17
21
16
10
9
9
11
8 W.L
. @ E
l. 13
5.3
m o
n co
mpl
etio
nC
ave-
in @
El.
135.
0 m
on
com
plet
ion
W.L
. @ E
l. 13
7.7
m o
n Fe
brua
ry 1
0, 2
017
139
5LOG OF BOREHOLE NO.:1701-S023JOB NO.:
Proposed Residential DevelopmentPROJECT DESCRIPTION:
2024 and 2026 Altona Road and 200 Finch Avenue City of Pickering
PROJECT LOCATION:
5FIGURE NO.:
Flight-AugerMETHOD OF BORING:
February 2, 2017DRILLING DATE:
Ground Surface
El.(m)
Depth(m)
SOILDESCRIPTION
SAMPLES
Num
ber
Type
N-V
alue
Dep
th S
cale
(m)
Atterberg LimitsPL LL
WA
TER
LE
VE
L
Dynamic Cone (blows/30 cm)
9070503010
Penetration Resistance(blows/30 cm)
9070503010
Shear Strength (kN/m2)
20015010050
Moisture Content (%)40302010
Soil Engineers Ltd.1 of 1Page:
0.0
0.3
1.0
4.7
138.6
137.9
134.2
END OF BOREHOLE
Refusal to augering on probable boulder
30 cm TOPSOIL
EARTH FILL dark brown to brown sand and gravel, some silt, trace of organics
Grey, compact to very dense
SANDY SILT TILL
a trace to some clay and gravel occ. sand and clay seams and layers, cobbles and boulders
10
20
12
50/15
53/15
50/15
DO
DO
DO
DO
DO
DO
1A
1B
2A2B
3
4
5
6
8
7
6
5
4
3
2
1
0 2215
1311
11
7
7
6
Cav
e-in
@ E
l. 13
8.0
m o
n co
mpl
etio
n
138.9
6LOG OF BOREHOLE NO.:1701-S023JOB NO.:
Proposed Residential DevelopmentPROJECT DESCRIPTION:
2024 and 2026 Altona Road and 200 Finch Avenue City of Pickering
PROJECT LOCATION:
6FIGURE NO.:
Flight-AugerMETHOD OF BORING:
February 3, 2017DRILLING DATE:
Ground Surface
El.(m)
Depth(m)
SOILDESCRIPTION
SAMPLES
Num
ber
Type
N-V
alue
Dep
th S
cale
(m)
Atterberg LimitsPL LL
WA
TER
LE
VE
L
Dynamic Cone (blows/30 cm)
9070503010
Penetration Resistance(blows/30 cm)
9070503010
Shear Strength (kN/m2)
20015010050
Moisture Content (%)40302010
Soil Engineers Ltd.1 of 1Page:
0.0
0.8
4.7
138.3
137.8
133.9
END OF BOREHOLE
Refusal to augering on probable boulder Installed 50 mm Ø monitoring well to 3.7 m. (3.1 m screen) Sand backfill from 0.3 m to 3.7 m. Bentonite seal from 0.2 m to 0.3 m. Provided with monument protective casing.
25 cm TOPSOIL
EARTH FILL brown silty clay, some sand trace of organics
Compact to very dense
SANDY SILT TILL
a trace to some clay and gravel occ. sand and clay seams and layers, cobbles and boulders
browngrey
1
20
27
63
105
90/15
70/15
DO
DO
DO
DO
DO
DO
DO
1A
1B
2A
2B
3
4
5
6
7
8
7
6
5
4
3
2
1
017
15
10
10
7
10
W.L
. @ E
l. 13
7.8
m o
n co
mpl
etio
n
W.L
. @ E
l. 13
8.4
m o
n Fe
brua
ry 1
0, 2
017
138.6
7LOG OF BOREHOLE NO.:1701-S023JOB NO.:
Proposed Residential DevelopmentPROJECT DESCRIPTION:
2024 and 2026 Altona Road and 200 Finch Avenue City of Pickering
PROJECT LOCATION:
7FIGURE NO.:
Flight-AugerMETHOD OF BORING:
February 3, 2017DRILLING DATE:
Ground Surface
El.(m)
Depth(m)
SOILDESCRIPTION
SAMPLES
Num
ber
Type
N-V
alue
Dep
th S
cale
(m)
Atterberg LimitsPL LL
WA
TER
LE
VE
L
Dynamic Cone (blows/30 cm)
9070503010
Penetration Resistance(blows/30 cm)
9070503010
Shear Strength (kN/m2)
20015010050
Moisture Content (%)40302010
Soil Engineers Ltd.1 of 1Page:
0.0
0.3
0.7
2.9
6.3
138.2
137.8
135.6
132.2
END OF BOREHOLE
33 cm TOPSOIL
EARTH FILL dark brown to brown sand and gravel, some silt, trace organicsBrown, compact to dense
SAND
fine grained, a trace to some silt
Grey, very dense
SANDY SILT TILL
a trace to some clay and gravel occ. sand and clay seams and layers, cobbles and boulders
boulder
4
28
31
24
30/0
53/15
50/15
DO
DO
DO
DO
DO
DO
DO
1A
1B
2
3
4
5
6
7
8
7
6
5
4
3
2
1
0 2414
15
20
16
10
7
5W
.L. @
El.
137.
6 m
on
com
plet
ion
Cav
e-in
@ E
l. 13
7.3
m o
n co
mpl
etio
n
138.5
8LOG OF BOREHOLE NO.:1701-S023JOB NO.:
Proposed Residential DevelopmentPROJECT DESCRIPTION:
2024 and 2026 Altona Road and 200 Finch Avenue City of Pickering
PROJECT LOCATION:
8FIGURE NO.:
Flight-AugerMETHOD OF BORING:
February 3, 2017DRILLING DATE:
Ground Surface
El.(m)
Depth(m)
SOILDESCRIPTION
SAMPLES
Num
ber
Type
N-V
alue
Dep
th S
cale
(m)
Atterberg LimitsPL LL
WA
TER
LE
VE
L
Dynamic Cone (blows/30 cm)
9070503010
Penetration Resistance(blows/30 cm)
9070503010
Shear Strength (kN/m2)
20015010050
Moisture Content (%)40302010
Soil Engineers Ltd.1 of 1Page:
0.0
0.3
0.8
1.8
6.6
137.8
137.3
136.3
131.5 END OF BOREHOLE
Installed 50 mm Ø monitoring well to 4.0 m. (3.1 m screen) Sand backfill from 0.6 m to 4.0 m. Bentonite seal from 0.2 m to 0.6 m. Provided with monument protective casing.
28 cm TOPSOIL
EARTH FILL dark brown to brown silty sand, some gravel, trace of organicsBrown, compact
SAND fine to medium grained some silt, a trace of gravel occ. cobbles
Grey, compact
SANDY SILT TILL
a trace to some clay and gravel occ. sand and clay seams and layers, cobbles and boulders
tr. gravel
browngrey
5
21
29
13
24
19
18
DO
DO
DO
DO
DO
DO
DO
1A
1B
2
3A3B3C
4
5
6
7
8
7
6
5
4
3
2
1
014
20
21810
12
9
11
10
W.L
. @ E
l. 13
6.9
m o
n co
mpl
etio
nC
ave-
in @
El.
136.
7 m
on
com
plet
ion
W.L
. @ E
l. 13
7.2
m o
n Fe
brua
ry 1
0, 2
017
138.1
9LOG OF BOREHOLE NO.:1701-S023JOB NO.:
Proposed Residential DevelopmentPROJECT DESCRIPTION:
2024 and 2026 Altona Road and 200 Finch Avenue City of Pickering
PROJECT LOCATION:
9FIGURE NO.:
Flight-AugerMETHOD OF BORING:
February 2, 2017DRILLING DATE:
Ground Surface
El.(m)
Depth(m)
SOILDESCRIPTION
SAMPLES
Num
ber
Type
N-V
alue
Dep
th S
cale
(m)
Atterberg LimitsPL LL
WA
TER
LE
VE
L
Dynamic Cone (blows/30 cm)
9070503010
Penetration Resistance(blows/30 cm)
9070503010
Shear Strength (kN/m2)
20015010050
Moisture Content (%)40302010
Soil Engineers Ltd.1 of 1Page:
Reference No: 1701-S023
U.S. BUREAU OF SOILS CLASSIFICATION
COARSE
UNIFIED SOIL CLASSIFICATION
COARSE
Project: Proposed Residential Development BH./Sa. 2/6 3/3 5/5
Location: 2024 and 2026 Altona Road and 200 Finch Avenue Liquid Limit (%) = - - -
City of Pickering Plastic Limit (%) = - - -
Borehole No: 2 3 5 Plasticity Index (%) = - - -
Sample No: 6 3 5 Moisture Content (%) = 6 11 10
Depth (m): 4.6 1.7 3.4 Estimated Permeability Elevation (m): 134.8 137.7 135.6 (cm./sec.) = 10-6 10-6 10-6
Classification of Sample [& Group Symbol]: SANDY SILT TILL, some clay, a trace of gravel
GRAIN SIZE DISTRIBUTION
SAND
V. FINE
GRAVELSILT
COARSE FINEFINE
SILT & CLAY
Figure: 10
COARSE
MEDIUM
FINE
CLAY
SAND
MEDIUMFINE
GRAVEL
3" 2-1/2" 2" 1-1/2" 1" 3/4" 1/2" 3/8" 4 8 10 16 20 30 40 50 60 100 140 200 270 325
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.1110100
Perc
ent P
assi
ng
Grain Size in millimeters
BH.2/Sa.6
BH.5/Sa.
BH.3/Sa.3
Soil Engineers Ltd. Reference No: 1701-S023
U.S. BUREAU OF SOILS CLASSIFICATION
COARSE
UNIFIED SOIL CLASSIFICATION
COARSE
Project: Proposed Residential Development
Location: 2024 and 2026 Altona Road and 200 Finch Avenue Liquid Limit (%) = -
City of Pickering Plastic Limit (%) = -
Borehole No: 8 Plasticity Index (%) = -
Sample No: 3 Moisture Content (%) = 20
Depth (m): 1.7 Estimated Permeability
Elevation (m): 136.8 (cm./sec.) = 10-3
Classification of Sample [& Group Symbol]: FINE SAND, traces of silt and medium sand
FINE
GRAVELSILT & CLAY
MEDIUM
FINE
CLAY
SAND
MEDIUM
Figure: 11GRAIN SIZE DISTRIBUTION
SAND
V. FINE
GRAVELSILT
COARSE FINEFINE
COARSE
3" 2-1/2" 2" 1-1/2" 1" 3/4" 1/2" 3/8" 4 8 10 16 20 30 40 50 60 100 140 200 270 325
0
10
20
30
40
50
60
70
80
90
100
0.0010.010.1110100Perc
ent P
assi
ng
Grain Size in millimeters
BH1
BH3
BH4
BH5
BH9
BH8
BH2
BH7
BH6
90 WEST BEAVER CREEK, SUITE #100, RICHMOND HILL, ONTARIO L4B 1E7 · TEL: (416) 754-8515 · FAX: (905) 881-8335
Soil Engineers Ltd.CONSULTING ENGINEERS
GEOTECHNICAL | ENVIRONMENTAL | HYDROGEOLOGICAL | BUILDING SCIENCE
SITE:
DESIGNED BY: CHECKED BY: DWG NO.:
SCALE: REF. NO.: DATE:
REV
1
Adrian Lo
2024 and 2026 Altona Road and 200 Finch Avenue
1
1 1701-S023 November 2017