A Half-Inch to Failure (Sept 2009).pdf
-
Upload
ronald-mubanga -
Category
Documents
-
view
4 -
download
0
Transcript of A Half-Inch to Failure (Sept 2009).pdf
August 1, 2007: The I-3spanned the Mississip
5W Bridge that pi River in Minneapolis
145.
tured under the weight of rush ious bridge renovations and
concentrated construction materials.
Underlying Issues: • Inadequate gusset plate design and insufficient review
process. • Added weight from renovations, traffic, and
construction materials. • Lack of attention to gusset plates in inspections and
load ratings. • Communication issues between the construction
contractor and the State.
collapsed, killing 13 and injuring
Proximate Cause: • Weak gusset plates frac
hour traffic, prev
SYSTEM FAILURE CASE STUDIES
SEPTEMBER 2009 VOLUME 3 ISSUE 06
A Half-Inch to Failure
At 6:05 pm, on Wednesday, AugustWest (I-35W) bridge over theMinneapolis collapsed. On the dathe bridge’s eight lanes were closed for planned construction. Four weak connector plates fractured under the combined burden of rush hour traffic, concentrated construction equipment, and previous heavy renovations. The bridge fell 108 feet into the Mississippi River. The police, fire department, and U.S. Coast Guard immediately initiated rescue operations. Of the 190 people on or near the bridge, thirteen died and 145 were injured.
BACKGROUND he I-35W bridge supported a 1,907 foot long, 8-lane
poln
bytorced
bu br
urally deficient proximately 12% of U.S. bridg
uef th
rais
(Fis artes
nnected three beams at each node: two diagonal beams and one vertical beam (Figure 2).
Over the course of forty years, the state of Minnesota conducted significant renovations on the bridge three times. In 1977, the State increased the bridge deck thickness about two inches. This renovation increased the dead load (weight of the structure itself) by 13.4%. In 1998, the State increased the dead load another 6.1% when it installed a median barrier. Together, these two renovations increased the weight of the bridge 19.5% over the original design.
renovations began in June 2007, two months ment of
ired a construction contractor, . (PCI), to resurface the bridge. moving two inches of concrete it with fresh concrete.
on equipment to mix In the weeks leading up to the collapse,
had poured concrete on seven he contractor placed heavy
dge ramps for five concrete some equipment on the bridge
1, 2007, the Interstate-35 Mississippi River in y of the collapse, four of
Figure 1: The I-35W Bridge
wide roadway that served Minneayears. The state inspected the bridge a
the National Bridge Inspection Standards set Highway Administration (FHWA). Inspeclabeling the bridge “structurally deficient” sinlabel indicated that the bridge requiremaintenance and repair to remain in service,was unsafe (inspectors would have closed thebelieved it was unsafe). A struct
T is for forty nually using the Federal s had been 1991. This
significant t not that it
before the collapse. The Minnesota DepartTransportation (MnDOT) hProgressive Contractors, IncThe renovations involved reon the roadway and replacing
Resurfacing required heavy constructiand pour concrete.
A third set of
idge if they rating is not es are rated
ntly labeled e 465 steel
the construction contractor bridge deck sections. Tconstruction equipment on bripours; one pour stationed
uncommon; apstructurally deficient.
Steel truss bridges, like I-35W, were more freqstructurally deficient; approximately 31% otruss bridges in the U.S. were listed as structuat the time of the collapse. Such bridges consbeams of steel formed into triangular units large steel truss bridges, the ends of the beamwith riveted metal plates called gusset plagusset plates co
lly deficient t of straight gure 1). In e connected . I-35W’s
2 | P a g e September 2009 System Failure Case Studies – A Half-Inch to Failure
deck and some on the ramps, and another positioned the equipment and materials on the bridge deck itself.
About a week before the
rin
about post-task cleanupinterpreted the inspectorpermission. However, thenot an engineer, and he permission. He was prescrew used the correct ma
and bfinished ing the
su
ntrn
e bridit for trucks (80,000 lbs.), so the contra
ridge. One cement tanker wughil
andveh. B con
ssetset of the nodes on the south side of the bridge
idge ct fe
oximy plunles. Policents.
pm, the Sherriff’s Department officially switched from rescue to recovery operations. Recovery continAugust 6, when the last victim was found. Of the 190 people on or near the bridge at collapse, 111 had minor injuries, 34 suffered serious injuries, and 13 did not survive.
PROXIMATE CAUSE According to the National Transportation Safety Board, the gusset plates at the nodes that failed were only half as thick as they should have been. In addition to being too thin, some of the gusset plates were bowed, a distortion that further decreased the bridge’s weight bearing capacity. The weak
als, and rush hour traffic finally stressed the bridge ses.
e cause of the collapse to the everal of the gusset plates, at fractured, were only half an
hick. The plates were not designed to support the bridge’s original weight, let alone the additional weight of the 1977 and 1998
ves that the original designers quality control to ensure the
set plates. Although igner’s original calculations before
t, it probably did not have the resources to fully verify the consultant’s work. This was not an unusual
collapse, the contractor was prepathe concrethe foremstate bridginspector and materialplaced on t e The forem
g for one of pours, and asked the
Observers immediately notified 9-1-1. Apprpeople nearby began rescue efforts; over thirtthe river to help those in submerged vehicminutes after the collapse, the Minneapolis followed by area Fire and Sherriff’s Departm
gusset plates fractured under the concentrated weight of the construction materials, the buincreased load from previodiagonal steel beam
te an e construction if equipment
an (worried turf
in toe conn
bo
s could be h
the rbridge.
al loading) concern as spector was grant such onstruction tract terms. tractor had th sides of
UNDERLYING ISSUESNo single element caused theseveral issues led to the failuroriginal gusset plate design was incorrdesigned, the plates are stronconnect. Inspectors, unawarthe gusset plates were unliketo
rather than struc’s expressed lack o bridge constructionlacked the authorityent to ensure that thterials and fulfilled cy August 1, the cotwo outside lanes on
the bridge, leaving the four inner lanes to be re
WHAT HAPPENED? On August 1, the day of the collapse, the coequipment to mix and pour the eighth sectioTwo cement tankers weighed more than th
Work proceeded resurfac
rfaced. ymateri
rden of rush hour traffic and the us bridge modifications. The
s within the failed nodes shifted to the west and fractured the gusset plates around the ends of the diagonals (Figure 3). Once the diagonal beams separated,
est of the truss fell.
I-35W bridge collapse. Rather,e of the weak gusset plates. The
ect. When correctly ger than the steel beams they
e of the design error, assumedly to fail and paid little attention
them during inspections. On the day of the collapse, the heav renovations, concentrated placement of construction
Figure 2: I-35WGusset Plate
actor set up of concrete. ge’s posted ctor did not eighed less t it on the
enough to reveal its weaknes
FAULTY DESIGN The Safety Board traces thoriginal bridge design. Sincluding the gusset plates thinch thick when they should have been a full inch t
legal limbring them onto the bthan the legal limit, and the contractor brobridge along with four piles of sand and four pa water tanker truck, a small excavator, propelled buggies. The material and concentrated in a section of two closed lanesall the equipment was set up, ready for thewhich was scheduled to begin at 7 pm.
The bridge collapsed at 6:05 pm, when the gu
es of gravel, four self-icles were y 2:30 pm,
renovations. The Board belieprobably did not exercise
crete pour, calculations were correct for these gusthe State reviewed the desthe bridge was buil
plates at a fractured.
ould not Once the gusset plates broke, the rest of the brsupport the extra weight; within seconds, iMississippi river.
ll into the
ately 100 ged into
Just five e arrived, At 7:27
ued until
Figure 3: Artist’s Rendering of a Fracturing Gusset Plate
3 | P a g e September 2009 System Failure Case Studies – A Half-Inch to Failure
Figure 4: I-35 him of any W Bridge on August 2, 2007, the day after the collapse
situation; states commonly lacked sufficient resources for thorough design review.
GUSSET PLATE BOWING AND INSPECTIONS The Safety Board could not determine when the gusset plates bowed. Photographs taken in 1999 show that they were bowed at least eight years prior to the collapse. One safety
bobutruc
ofete dodd
cause he had learned ed
er time. ied the
previous materials, Inspector
o zed the
lates, or s hazard. f these
e bridge’s , gusset ents that
ith little material
he foreman asked the r permission to
aterials on the bridge deck, er should r day-to-eer relied struction
supervisor to informproblems, but the project construction supervisor was not onsite on August 1. Afterwards, he said he was not sure if he would have voiced concern about putting heavy materials on the bridge. “My best guess is it would have been a 50-50 chance that I might have done something,” he said.
tractor had formally requested materials on the bridge deck, the state
model used to determine bridge load ratings. Model calculations, however, did not include gusset plates because engineers expected beams to fail prior to gusset plates. According to the state’s model, the bridge was capable of bearing the August 1 loads. The
ed the collapse.
Transportation Safety Board’s commends that bridge owners ver planned modifications may
significantly increase stresses.”
also increased design review nts for new bridge construction isting bridge inspections. a now requires that all bridges
by consultants undergo an independent design review.
pections in Minnesota were The State examined all 25
s bridges in the state and found ate problems in four bridges.
paired the gusset plates on bridges, closed the fourth
d accelerated its replacement ther states also re-inspected
l truss bridges, paying special gusset plates.
ABILITY TO NASA a number of parallels between NASA facilities. The I-35W dured forty years of use and
modifications. Many NASA are several decades old and
have been modified to house different ts.
king design error of thin gusset aped notice during its design he consequences of a design t be considered when allocating
resources and time to expert internal and ent design reviewers. If a had conducted a more review of the I-35W designs in s, they might have caught the
gusset plate design flaw and prevented the 2007 tragedy. The design process at NASA is subject to oversights in the
review process as well. Like state departments of transportation, NASA often hires design consultants and verifies their work internally or through third party review.
a If the construction conpermission to place might have referred to a technical
inspection engineer remembered noticing theplates during his inspection in the late 1990s, bowing occurred during the original constbridge. He did not report his observations plates because “our inspections are to find dfindings of deterioration on maintenance. Wedescribe construction or design problems.” Adid not think gusset plates were critical to bridge safety be
wed gusset thought the tion of the the gusset rioration or not note or itionally, he
unaware that the project enginehave been asked instead. Foday concerns, the project enginheavily on the project con
model would not have predict
AFTERMATH As a result of the National findings, the FHWA now reinspect gusset plates “whene
in college that gusset plates are designto support 2 to 3 times the expected bridge loads.
The gusset plates did not worry other bridge inspectors either. Inspectors’ reports since 1994 noted rust, corrosion, and section loss in the gusset plates, but did not measure changes ovOften, inspectors simply copgusset plate description from areport. Inspector training such as the FHWA’s Bridge Reference Manual, did not address gusset plates in steel truss bridges. Ntraining materials emphasiimportance of gusset pidentified distortion as a seriouThe cumulative effect ooversights was that, despite thstructurally deficient ratingplates were not one of the elemworried inspectors.
COMMUNICATION AND LOADRATINGS The state provided contractors wguidance on construction placement. Tconstruction inspector foplace m
MnDOT requiremeand exMinnesotdesigned
Bridge insrevamped. steel trusgusset plThe State rethree of thebridge anschedule. Otheir steeattention to
APPLICThere are I-35 and bridge enthree major facilities
projec
I-35’s lurplates escreview. Terror mus
independMinnesotthorough the 1960
4 | P a g e September 2009 System Failure Case Studies – A Half-Inch to Failure
reviewand access they nee
alwdedy bt
ere sound, butly s
rmined hazard idadt et hans a
tors’ cursory d not quantify
nd they often n, providing an
d and incomplete review. “You get whmto
ou the checklist.
anho structure. d to measure the weighty modified to for hazardous y. Conduct an agement best
practices to mitigate unexpected problems from modified infrastructure.
A final lesson from the bridge collapse comes from the communication issues between the State and the construction contractor. The State did not clearly communicate who could authorize the placement of equipment and materials on
the bridge. While it is not clear whether the authorities would have refused the contractor’s request to place heavy equipment on the bridge, the confusion contributed to the contractor’s belief that they had the state’s permission when, in fact, they did not. We should use clear lines of authority to communicate safety-critical information both internally and externally. Verify who is empowered to accept a risk
is needed.
REFERENCES ridge Types - Truss. In The Basic
2009 from http://www.matsuo-ics/truss.shtm.
portation. (2007). Aerial Photos ne Image. 2 Aug. 2007. Accessed ot.state.mn.us/i35wbridge/photos/
ortation Safety Board. (2008, November). Highway Accident Report: Collapse of I-35W Highway Bridge,
st 1, 2007 (NTSB/HAR-08/03). May 2009 from
.gov/publictn/2008/HAR0803.pdf
E CASE STUDIES
NASA project managers must ensure thatknowledge, experience, time
ers have the d to conduct
ays feasible sign. There
Matsuo Bridge Co., Ltd. (n.d). BBridge Types. Accessed 27 Maybridge.co.jp/english/bridges/bas
Minnesota Department of Transof I-35W Bridge Collapse. Onli27 May 2009 from http://www.daerial/aug-2/index.htm
National Transp
a thorough review.
When a structure is already in place, it is not to conduct a complete review of the original are other ways, however, that the I-35 tragebeen prevented. Inspectors did not recognizeplates as a serious safety concern. Hindsighfalse assumption that these gusset plates wprior to the collapse, inspectors were probabany such failure mode. Previous successebiased inspections and unde
could have owed gusset exposes the
Minneapolis, Minnesota, AuguWashington, D.C. Accessed 27http://www.ntsb
unaware of and failures entification
SYSTEM FAILUR
skills. The model used to determine bridge loalso biased by the assumption that gussestronger than beams; it did not include gusscalculations. At NASA, we must recognize cbaseline configuration and question assumptiosystems.
An object lesson is the bridge inspecobservation of the gusset plates. Inspectors digusset plate changes from year-to-year, amerely recycled the previous year’s descriptiooutdate
ratings was plates were plates in its nges to any bout aging
at you inspect” and a repetitive, narrow checklist lihazard discoveries. At NASA, we need encourage system and process knowledge in and reward active hazard identification beyond
Each I-35 bridge renovation presented opportunity to assess the current state of the w
its potential train and r inspectors,
excellent le
Safety inspectors should have been expectenew (and explain old) changes caused byrenovations. At NASA, where facilities areaccommodate new projects, we must check effects a change might have on an aging facilitimpact analysis and follow change man
before a time-critical decision
QUESTIONS FOR DISCUSSION • How do you ensure design reviewers have adequate
resources (funding, expertise, experience) to be thorough?
• Can you think of other examples of when something was incorrectly assumed to be safe?
How do you chang ctions as infrastructoo much on checkl
you employ odifying a facility?
w the c?
• e inspeDo your inspections rely t
ure ages? ists?
• What change management practices do when m
• How do personnel and contractors kno orrect authority to go to if they have a question
Executive Editor: Steve Lilley [email protected] Developed by ARES Corporation
This is an internal NASA safety awareness training document based on information available in the public domain. The findings, proximate causes, and contributing factors identified in this case study do not necessarily represent those of the Agency. Sections of this case study were derived from multiple sources listed under References. An proper use of source material is unintentional.
se studies online or to essage.
y misrepresentation or im Visit http://pbma.nasa.gov to read this and other casubscribe to the Monthly Safety e-M