A Guide to Good CNP Submission (original) - epd.gov.hk · Construction Noise Permit (GW)...
Transcript of A Guide to Good CNP Submission (original) - epd.gov.hk · Construction Noise Permit (GW)...
CNP Processing TimeCNP Processing Time-- mainly essential works with excavation permit (~ 40%)mainly essential works with excavation permit (~ 40%)
Year 2010 Year 2011(up to August 11)
% within 14 days 82 % 79 %
% between 15 and 18 days
14 % 15 %
% > 18 days 4 % 6 %
CNP TargetCNP Target
CNP Target
Performance Pledge 18 days (90 %)
“Good” submission 10 -14 days
Percussive Piling General Works
Hours General Holidays
Weekdays General Holidays
Weekdays
0000-0700 X X CNP CNP
0700-1900 X CNP CNP √
1900-2400 X X CNP CNP
The CNP SystemThe CNP System
Construction Noise Control PhilosophyConstruction Noise Control Philosophy
• Day time (weekdays) - no CNP control on GW
• Night time - people have theright of peace for rest
• No CNP granted unlessreally necessary
CNP ApplicationsCNP Applications
• Fully utilize the less noisesensitive hours
• Apply only if really necessary
• Self-assess before applying
• Apply well in advance
• Provide all relevant information and supportingdocument – e.g. essential works
CNP AssessmentCNP AssessmentTechnical memoranda for assessment
Meeting noise requirements
No prohibited activities
Special Case - unavoidable constraints on workinghours e.g. roadworks with excavation permit atbusy street• Justification required
• Quietest means + Practical noise mitigationmeasures
Checklist for a Good CNP SubmissionChecklist for a Good CNP Submission
1. Joint Venture / Consortium company –provide the names of all the concerned incorporated mother companies
PMM JV (trading as ABC Co. and XYZ Co. Ltd)
Form 1Construction Noise Permit (GW) Application
(Mainly focus on unavoidable constraints on working hours, essential permits)
Checklist for a Good CNP SubmissionChecklist for a Good CNP Submission
2. Provide copyof the BRC of theapplicant
Checklist for a Good CNP SubmissionChecklist for a Good CNP Submission3. Show the previous CNP no.
ABC Construction Co. Ltd.
Checklist for a Good CNP SubmissionChecklist for a Good CNP Submission4. Provide copy of the Works Order /
Excavation permit no., if any5. A site plan of appropriate scale (preferably
1:1000)
Checklist for a Good CNP SubmissionChecklist for a Good CNP Submission
XXXXXXX
Works Order No. HD003524 from Hyd.
XXXXXXXXXXXXXXXXXXXX
XXXXXX
XXXXXXXXXXXX
Checklist for a Good CNP SubmissionChecklist for a Good CNP SubmissionHyd’s Term Maintenance Contract No. 20/HY/2004
(for blanket permit submission)
Checklist for a Good CNP SubmissionChecklist for a Good CNP Submission
6. Actual working days required – fill in Part E.2 e.g. the use of multiple breakers resulting in shortening the actual excavation period
The excavation together with the rectification works will last for one week only, i.e. 2.11.2011 to 8.11.2011.
XXXXX
Checklist for a Good CNP SubmissionChecklist for a Good CNP Submission
7. Provide clear 3R size color photograph
Clear color photo
Unclear photo
√
Checklist for a Good CNP SubmissionChecklist for a Good CNP Submission
8. Provide NEL / QPME copy, if any
NEL (breaker) QPME label
Checklist for a Good CNP SubmissionChecklist for a Good CNP Submission
9. Fixed location PME - e.g. fixed generator, tower crane and material hoist
provide relative distances of such equipment to the site boundary on the submitted plan to facilitate EPD’s assessment
10. Identify practicable working hours that cause the least noise nuisance
• Refer to “Checklist to explore the feasibility of daytime roadwork”
Checklist for a Good CNP SubmissionChecklist for a Good CNP Submission
http://www.epd.gov.hk/epd/english/application_for_licences/guidance/files/roadwork_checklist.pdf
Checklist to explore the feasibility of Checklist to explore the feasibility of daytime roadworksdaytime roadworks
1. Non-restricted hours (day hours of normalweekdays)
2. Day hours on general holidays (preferablyafter 9 or 10 a.m.)
3. Evening hours outside general holidays
4. Overnight
Feasibility of daytime roadworks ?Feasibility of daytime roadworks ?
Feasibility of daytime roadworks ?Feasibility of daytime roadworks ?
11.11. Essential work Essential work - unavoidable constraints onworking hours
• No acceptance of CNP application in generalwithout supporting document
• Provide supporting documents
TD/Police’s comment
TMLG meeting notes
Results of trial lane closure
Checklist for a Good CNP SubmissionChecklist for a Good CNP Submission
XXXX
12.12. Essential work Essential work - unavoidable constraints on working hours
• Require the use of quietest practicable construction
method
• Use of Quiet Construction Equipment for Road Opening Works during non-Sociable Hours
http://www.epd.gov.hk/epd/english/resources_pub/publications/files/pn96_1.pdf
Checklist for a Good CNP SubmissionChecklist for a Good CNP Submission
ProPECCPN1/96
• Hydraulic crusher for demolition 20 dB(A) lower than excavator mounted breaker
• others, e.g. QPME
Modern wire saw for concrete cutting 16 dB(A) lower than excavator mounted breaker
√
√
Quiet Construction Equipment
Enclosure / Barriers
Acoustic enclosure for breaker reduce 3-5 dB(A)
6m barrier for pre-bored machines reduce 3 dB(A)
√
√
•• Emergency Emergency ≠≠ ““planned planned ““ urgent worksurgent works
• Emergency work shall satisfy requirements Emergency work shall satisfy requirements of defence provisions under S. 33 of NCOof defence provisions under S. 33 of NCO
• ““PlannedPlanned”” urgent works require a CNP urgent works require a CNP (CNP could be issued in a shorter time if all info. is available(CNP could be issued in a shorter time if all info. is available))
• Fallacy of Fallacy of ““blackspotsblackspots”” where CNP will where CNP will never be grantednever be granted
ReminderReminder
• “How to complete and submit CNP application forms”
http://www.epd.gov.hk/epd/english/application_for_licences/guidance/cnp.html
• “Checklist to explore the feasibility of daytime roadwork”
http://www.epd.gov.hk/epd/english/application_for_licences/guidance/files/roadwork_checklist.pdf
• “Use of Quiet Construction Equipment for Road Opening Works during non-Sociable Hours”
http://www.epd.gov.hk/epd/english/resources_pub/publications/files/pn96_1.pdf
• “Guidelines for preparation of noise measurement report for PME”
http://www.epd.gov.hk/epd/english/application_for_licences/guidance/files/guidelines_nm_pme.pdf
Useful EPD’s Website :
Thank YouThank You!!