990901EIS_RR_Instru.1 The Instrument: US Subsystems and Requirements Dr. Clarence M. Korendyke US...

30
0901EIS_RR_Instru.1 The Instrument: US Subsystems and Requirements Dr. Clarence M. Korendyke US Project Scientist Naval Research Laboratory 202-767-3144 e-mail: [email protected] Dr. Charles M. Brown EIS US Instrument Scientist Naval Research Laboratory 202-767-3578 e-mail: [email protected]

Transcript of 990901EIS_RR_Instru.1 The Instrument: US Subsystems and Requirements Dr. Clarence M. Korendyke US...

990901EIS_RR_Instru.1

The Instrument: US Subsystems and Requirements

Dr. Clarence M. Korendyke

US Project Scientist

Naval Research Laboratory

202-767-3144

e-mail: [email protected]

Dr. Charles M. Brown

EIS US Instrument Scientist

Naval Research Laboratory

202-767-3578

e-mail: [email protected]

990901EIS_RR_Instru.2

Plan View

Elevation

EIS Optical-Mechanical Layout

990901EIS_RR_Instru.3

MIR/SLA/GRA Electrical Interfaces

MechanismSubassembly

Translation Actuator Encoder Average DutyCycle

Peak InternalPower

AveragePower

CoarsePosition

Size 16, 4phase stepper

motors

Resolver 2 (20 sec)operations per

day

10 W 0.0046 WMIRPrimary MirrorSubassembly

Fine Position PiezoelectricTransducer

Strain gauge 0.5V step perfive seconds

0.29 W <0.05 W

Slit/SlotExchange

Size 12, 4phase stepper

motors

Resolver 2 operationsper hour

3 W 0.0042 WSLASlit/Slot

SubassemblyShutter Brushless DC

motorOpticalencoder

1 operationevery 5seconds

2.65 W 0.0122 W

GRAGrating

Subassembly

FocusMechanism

Size 16, 4phase stepper

motors

OpticalEncoder

2 (20 sec)operations per

month

10 W 0.0046 W

NOTE: Duty cycle, peak internal power, and average dissipated power values are preliminary estimates.

990901EIS_RR_Instru.4

Lifecycle Requirements

Mechanism Duty Cycle Lifecycle Requirement

(Number of Cycles)

Coarse mirror drive 2/day 2,700

Fine mirror drive continuous continuous

Slit/slot carousel 2/hour 53,000

Shutter 1/5 seconds average 19 million exposures

Grating focus 1/month 540NOTE: These are preliminary values.

990901EIS_RR_Instru.5

Articulated Telescope Mirror (MIR) Requirements

• Mount the Optic With Minimal Distortion Over the Applicable Temperature Range

• Tilt the Optic to Move the Solar Image (±4’) Perpendicular to the Slit

• Sense the Relative Position of the Optic Tilt With <1 Arcsec Accuracy

• Translate the Optic ±8 mm Perpendicular to the Optical Axis

• Sense the Position of the Optic to <20 Microns

990901EIS_RR_Instru.6

MIR Hardware Description/Summary

PZT

Mirror

Linear Ball Slide

Flexpivot Translation Motor and Drive Assy

990901EIS_RR_Instru.7

Focussing Grating (GRA) Requirements

• The GRA Shall Mount the Grating With Minimal Distortion Over the Operational Temperature Range

• The GRA Shall Provide a Focussing Capability of ±1 cm to Permit Adjustment of the Spectrometer Focus

• The EIS Grating Will Be Bonded Into a Cell Mounted Onto a Crossed Roller Slide Translation Stage

• Translation Stage Will Be Driven With a Geared Stepper Motor and Ball Screw Combination. The Mechanism Will Be Operated in Open Loop Mode. The Position Will Be Sensed With Optical Encoders

990901EIS_RR_Instru.8

GRA Hardware Description/Summary

Grating

Motor and Ball Screw Assy

Crossed Roller Bearing Slide

990901EIS_RR_Instru.9

Slit Assembly (SLA) Requirements

• The SLA Shall Support the Shutter Assembly

• The SLA Shall Be Able to Position the Spectrometer Slits and Slots to Be Reproducible in the Telescope Focal Plane

• The Spectrometer Slits Shall Be Reproducibly Positioned to <2 Microns Perpendicular to the Optical Axis and <26 Microns Along the Optical Axis. A Performance Goal for the Mechanism Will Be <1 and <13 Microns, Respectively

• Positioning Will Be Accomplished Using a Geared Stepper Motor With the Direction of Motion Along the Optical Axis

990901EIS_RR_Instru.10

Slit Assembly (SLA) Requirements (Continued)

• The Load Position Will Be Sensed Utilizing a Shaft Resolver

• The Present Optical Design Does Not Permit the Resolver to Be Directly Attached to the End of the Shaft, and the Resolver Is Instead Coupled to the Output Shaft With Anti-backlash Gearing; This Approach Should Suffice to Meet Specified Goals. The Backlash Inherent in the System Is Expected to Be ±3 Arcminutes With a ±15 Arcminute Step Size. This Corresponds to an Uncertainty of ±10 Microns in the Position of the Slit Along the Optical Axis With a 50 Micron Step Size

• The Resolver Will Have an Absolute Accuracy of <15 Arcminutes Sufficient to Discriminate Between Individual Steps

990901EIS_RR_Instru.11

SLA Hardware Description/Summary

ShutterSlit Paddle Wheel

Slit Motorand Encoder

Shutter Motorand Encoder

990901EIS_RR_Instru.12

Shutter Mechanism Requirements

• The SLA Shall Include the EIS Instrument Shutter

• The Shutter Shall Be Able to Take a 50 ms Exposure

• <5% Photometric Error Over the Slit for These Short Exposures

990901EIS_RR_Instru.13

Shutter Assembly Hardware Description/Summary

990901EIS_RR_Instru.14

Requirements for the Filter Clamshell

• Vacuum Tight Enclosure

• P <1 Torr for Launch [TBD] 140 dB Acoustic Loads Expected

• Hold Time >1 Week [TBD]

• Reliable Calibrated Internal Pressure Sensor

• Clean

• Minimal Central Obstruction

• Pumpout/Backfill Valve With Filter and Throttle

• No Pressure Differential Allowed Front/Back (Air Passages)

• Sunshade for Filter Frame

• No Shock on Opening

• Vacuum Harness for Pre-Launch Ops

990901EIS_RR_Instru.15

Front Filter Assembly (FFA) Requirements

• A FFA Shall Be Provided to Block Heat and Visible Light From the EIS Instrument

• The FFA Shall Also Serve As a Bandpass Filter for the EUV Range of Interest

• The Filter Will Consist of a 1500 Å Thick Aluminum Film Mounted on a Nickel Mesh. The Aluminum May Be Coated With a Few Å of Carbon to Reduce Oxidation and to Improve Rejection of Light in Unwanted Solar Lines

• The FFA Will Provide a ±1% Transmittance Uniformity

• The FFA Shall Be Compatible With Ultra High Vacuum (UHV), and It Shall Provide the Necessary Mechanical Strength, and the Capability to Withstand Torr-Level Pressure Differentials

990901EIS_RR_Instru.16

Front Filter Assembly (FFA) Requirements (Continued)

• The Front Filter Will Be a ~200 mm Clear Aperture Diameter and It Will Be Segmented Into Four Quadrants, Each Separately Replaceable

• A Lightweight Aluminum Frame Shall Support the Mesh

• A Clamping Frame Shall Secure the Filters to the Clamshell Assembly. The Frames Will Be Designed to Minimize the Central Obstruction

990901EIS_RR_Instru.17

Requirements for the Al Filters

• For the Entrance Filter:

– <1500 Å Al on Ni Mesh (>80% Open)

<0.1

– T >30% @ 304 Å

– T <5 X 10-5 for Visible & IR

– 20 cm Clear Aperture, in Quadrants

• For the Spectrometer Entrance Filter:

– <1500 Å Al on Ni Mesh (>80% Open)

– T >30% @ 304 Å

– T < 5 X 10-7 for Visible & IR

– 0.5 cm X 1.5 cm Rectangular

990901EIS_RR_Instru.18

FFA Hardware Description/Summary

Quadrant of Trace Entrance Filter

990901EIS_RR_Instru.19

Spectrometer Entrance Filter (SEF) Requirements

• A Small Diameter Aluminum Filter Shall Be Provided to Mount Behind the EIS Spectrometer Slit

• The SEF Shall Provide Additional Reduction of the Visible Light Within the Spectrometer, Especially in the Event That the FFA Degrades Due to Orbital Debris and Micrometeorites

• The SEF Shall Have a Clear Aperture of ~20 mm. It Shall Be Placed Near the Slit, but Far Enough Away (>8 mm) That the Mesh Will Be Totally Out of Focus at the Detector

• Table 3-6 of the EIS Subsystems and Components Contract End Item Specification, EIS_Comp_Spec, Lists the Required Filter Properties

990901EIS_RR_Instru.20

SEF Hardware Description/Summary

Luxel TF Aerospace Al filter

990901EIS_RR_Instru.21

EIS Instrument Classification Mission Classification

DoD HDBK-343Design, Construction, and Testing

Requirements for One-of-a-Kind SpaceEquipment (1 February 1986)

NRL’s Space Systems DevelopmentProgram Elements(7 December 1995)

NASA 311-INST-001 (Rev. A)Instructions for EEE Parts Selection, Screening,

and Qualification(August 1996)

Class A - HighPriority, MinimumRisk Effort

Long Life; HighComplexity; FullyRedundant; QualificationItems; Flight Spares;Highest Cost

Level A -OperationalSatellite

Long Mission Duration(>5 Years) withRedundancy and HighReliabilityRequirements

Level 1 -LowestAcceptableLevel Of Risk

High Visibility Programs WithMultiple, Interrelated Objectives;Duration = 5 Years; Functional OrBlock Redundancy With Mgmt.Approval Of Single Point Failures

Class B - RiskWith CostCompromise

Medium Life; HighComplexity; Cost-SavingsIn Areas Other ThanDesign And Construction(Protoflight Qualification,Limited Redundancy AndSparing, ShortenedSchedule)

Level B -Scientific orExperimentalSatellite

1 - 3 Years MissionDuration; Redundancyon Critical Elements

Class C -EconomicallyReflyable OrRepeatable

Short Life; Low ToMedium Complexity;Single String; LimitedFlight Spares; ShortSchedule.

Level C -SignificantExperimentalPackage orSecondaryPayload onboardOperationalSatellite

Limited Redundancy

Level 2 - LowTo ModerateRisk BalancedBy Cost AndMissionObjectives.

Duration Of 1-5 Years. Multiple OrSingle Purpose Mission, WithRepeat Mission Possible.Functional Or BlockRedundancy For PrimaryObjectives, But Single StringDesign Allowable.

Class D -MinimumAcquisition Cost

Short Life; LowComplexity; Small Size;Single String; No Spares;Short Schedule; LowestCost

Level D - ShortDurationExperiment

Mission duration inDays with NoRedundancy

Level 3 -Moderate RiskAcceptable, AsPermitted ByCostConstraints.

Mission Duration <1Year. Typically Single PurposeOr Routine Mission, With RepeatMission Possible. Single StringDesign Acceptable.

Recommended Guidelinesfor EIS Instrument Components

990901EIS_RR_Instru.22

Mission Analysis Approach

EEE PartsSelection

GSFC 311-INST-001AGuidelines

EEEParts

DeratingAnalysis

EEEPartsWorstCase

Analysis(WCA)

FMECA(per MIL-

STD-1546/1547

Guidelines)

SafetyAnalysis(per EWR

127-1Guidelines)

RadiationHardnessAnalysis

ThermalAnalysisper MIL-

STD-1540Guidelines

VibrationAnalysisMIL-STD-

1540C

VentingAnalysis

EMCAnalysisMIL-STD-

461D/462D

SinglePoint

FailureMIL-STD-1543B /

MIL-HDBK-217F

ReliabilityAnalysisMIL-STD-1543B /

MIL-HDBK-

217

Level 1

=5 YearsRedundantw/ No SPFs

4 4 4 4 4 4 4 4 4 4 4 4

Level 2

1-5 YearsDuration w/Functional

Redundancy

4 4 4 4Redundancy &

ElectricalInterfaces Only

4 4 4 4Optional

4 Optional ? 4

Level 3

=1 YearDuration“SingleString”

4ConsistentWith Cost &Schedule

Constraints

4 4 4Interface s Only

4 Optional 4 Optional 4 Optional 4 Optional

Tailored to Meet Guidelines ofEIS Instrument Component

Contract End Item (CEI) Specification

Tailored to Meet Guidelines ofEIS Instrument Component

Contract End Item (CEI) Specification

Recommended Approachfor EIS Instrument Components

Independent Agent

990901EIS_RR_Instru.23

Safety, Reliability, and Quality Assurance (SR&QA) Requirements

• SR&QA and Verification Compliance Matrix (VCM) Requirements Defined in EIS Instrument Component CEI Specification (EIS_comp_spec)

• Configuration Management Plan uses MSFC MPG 8040.1Guidelines for Flight Models (DRD 874CM-001)

• Contamination Control & Implementation Plan in Consonance with UK’s EIS Instrument Requirements (DRD 872MP-001)

• Product Assurance Program for Flight Models Meets ISO 9000 Guidelines (DRD 872QE-001)

– Includes Preliminary/Final Hazard Analysis Inputs to UK’s EIS Instrument Safety Plan

– Includes Reliability Assurance and Parts/Materials/Processes Approach

• Verification Plan Defines Verification Approach, Structure, and Description (DRD 872VR-001)

990901EIS_RR_Instru.24

Other Factors

• Parts, Materials, and Processes (PMP) Selected to Assure Maximum Reliability and Performance in Space Environments

– Vacuum Stability via Total Mass Loss (TML) of >1.0% and Volatile Condensable Material (VCM) of >0.1% Per NRP-1124

– Traceability Achieved by Categorizing EEE Parts Into Sets Groups and Tracing Parts Through Fabrication, Assembly, Test, and Delivery

• Electrostatic Discharge (ESD) Control According to Processes Implementing MIL-STD-1686 Guidelines

• Closed-Loop Failure Reporting and Corrective Action System (FRACAS) for Failures Occurring During the Flight Model Acceptance Testing Phases

• Deliverable Shipping Container Compatible With the Anticipated Transportation Environmentals

• Documentation Uses Established Practices for Spaceflight Equipment

– Deliverable “As-built” Engineering Drawings for Flight Models

– Schematics, Assembly Drawings, Parts Lists, Test Procedures/Reports, and Calibration Data

990901EIS_RR_Instru.25

Project Planning and Control (1 of 3)

• During Phase B, the Following Management Tools (Delivery Dates) Will Be Developed to Allow Adequate Definition of the Hardware, Services, Materials, Subcontracts and Other Services of the Project:

– Configuration Management Plan (31 December 1999)

– EIS Component Specification Contract End Item (Updates A/R; Under Configuration Management)

– Preliminary Design Review Package (15 February 2000)

– Interface Control Documents (15 February 2000)

– Project Management Plan (31 December 1999)

– Monthly Progress Reports (Monthly)

990901EIS_RR_Instru.26

Project Planning and Control (2 of 3)

• Phase B Management Tools Continued:

– Financial Management Reports (Monthly)

– Work Breakdown Structure and Dictionary (30 November 1999)

– Risk Management Plan (31 December 1999)

– Contamination Control and Implementation Plan (15 February 2000)

– Product Assurance Plan (31 December 1999)

– System Error Budget (15 February 2000)

– Verification Plan (31 December 1999)

990901EIS_RR_Instru.27

Project Planning and Control (3 of 3)

• During Phase C/D, the Following Management Tools (Delivery Dates) Will Be Developed to Allow Adequate Definition of the Hardware, Services, Materials, Subcontracts and Other Services of the Project:

– All Management Tools Developed Under Phase B Shall Be Updated As Necessary

– Critical Design Review Package (15 February 2001)

– Pre-Environmental Review Package (15 February 2002)

– Flight Readiness Review Package (15 September 2002)

– Verification Test Report (15 September 2002)

990901EIS_RR_Instru.28

Product Assurance

• EIS Instrument Component Product Assurance Guidelines Shall Be Defined in the Product Assurance Plan Submitted During Phase B

• The Product Assurance Plan Shall Address:

– Safety: Implementation of Industrial and System Safety Throughout the Project Lifecycle

– Quality: Implementation of All Elements of the Quality Assurance Program Throughout the Lifecycle of the Project

– Reliability: Definition of the Procedures and Controls for Implementing the Programmatic Reliability and Maintainability Requirements

990901EIS_RR_Instru.29

EIS Instrument Component Work Breakdown Structure (WBS)

Science Support1.2.3.1.5

Configuration Management1.2.3.1.4

Procurement Management1.2.3.1.3

Project Planning and Control1.2.3.1.2

Project Management1.2.3.1.1

Management1.2.3.1

Grating Subassembly (GRA)1.2.3.2.5

Spectrometer Entrance Filter (SEF)1.2.3.2.4

Slit and Shutter Assembly (SLA)1.2.3.2.3

Mirror Assembly (MIR)1.2.3.2.2

Front Filter Assembly (FFA)1.2.3.2.1

EIS Instrument Components Flight System1.2.3.2

Mockups and Simulators1.2.3.3.5

Mechanical Ground Support Equipment1.2.3.3.4

Electrical Ground Support Equipment1.2.3.3.3

Mechanical/Thermal Proto Models1.2.3.3.2

Electrical Proto Model1.2.3.3.1

Ground Support Equipment and Proto Models1.2.3.3

EIS Integration and Test Support1.2.3.4.3

EIS Instrument Components Test and Verification1.2.3.4.2

Systems Engineering1.2.3.4.1

System Engineering and Integration1.2.3.4

Mission Operations Support1.2.3.5.2

MO Definition and Planning1.2.3.5.1

Operations1.2.3.5

Reliability1.2.3.6.3

Quality1.2.3.6.2

Safety1.2.3.6.1

Product Assurance1.2.3.6

EUV Imaging Spectrometer1.2.3

990901EIS_RR_Instru.30

EIS Instrument Component Schedule Summary

PROJECT ELEMENT DELIVERY DATE

Start of Phase B 1 November 1999

Proto-Models of MIR, GRA, FFA and SEF February 2000

Preliminary Design Review March 2000

Start of Phase C/D 1 May 2000

Electrical Prototype Model December 2000

Mechanical and Thermal Developmental Models April 2001

Critical Design Review March 2001

Pre-Environmental Review March 2002

Flight Readiness Review September 2002

Flight Models October 2002

Launch August 2004