9-10 December 2010 1GPAR Luang Prabang ARM 2010
GPAR LP IIGPAR Luang Prabang Phase II:
Decentralized Participatory Governance and Service Delivery
Reform Project2006-2010ID 00045991
Annual Project Review Outputs 2010
09-10 December 2010 2GPAR Luang Prabang ARM 2010
GPARLP - Phase 2
Phase 2 Project began 1/1/2006 and will end 31/12/2010.
Total Budget (US$):o Sida: 2,500,000 o UNDP : 589,000o Total: 3,089,000 o Remaining: 6,850
(estimate) 2010 Budget:
o UNDP + Sida 414,957
09 - 10 December 2010 3GPAR Luang Prabang ARM 2010
GPARLP - Phase 2
Focus areas during 2010: Complete activities as defined in AWP 2010 Phasing out and prepare for closing
consolidation for sustainability or smooth closing down of activity
Documentation Lessons learned GPAR beyond 2010
09 - 10 December 2010 4GPAR Luang Prabang ARM 2010
GPARLP – Outcome
Expected outcome:Sustainable improvements in provincial policies, administrative practices and capacities which will: (1) improve availability, reliability and responsiveness of pro-poor services (2) enable greater transparency and citizens’ participation in governance, and (3) strengthen clarity and accountability in delivering services to citizens
09 -10 December 2010 5GPAR Luang Prabang ARM 2010
“ The achievement of the project in terms of its intended outcome has been very substantial in terms of improvements in administrative practices and capacities. This has resulted in more visible, reliable, responsive, accountable, pro-poor services delivery occurring within the districts, Kumbans and villages where the project has been operating.” (Evaluation Report, 2010)
GPARLP – Overall Outcome achievements
09 - 10 December 2010 6GPAR Luang Prabang ARM 2010
GPAR LP II Outputs
Six outputs have contributed to the outcome:
1. Strengthened decentralized administration
2. Public service delivery reforms in H and E
3. Business Facilitation Centre (BFC) 4. Provincial oversight (SDIS)5. GPAR support facility (SDF)6. PAR Resource Centre
09 - 10 December 2010 7GPAR Luang Prabang ARM 2010
GPARLP – Output 1:Strengthened Decentralised
Administration Installed fibre-optic cabling within
DoF Computer training on PIMS Retraining of staff in LP on ODS Capacity building of PCAW at Prov.
and Dist. Provincial socio-economic review
meetings Capacity building of district cabinet
offices Kumban socio-economic
development
09 - 10 December 2010 8GPAR Luang Prabang ARM 2010
GPARLP – Output 2:Public Service Delivery Reform –
Health and Education
Training on office administration for health staff in 12 districts
Training on strategic Planning skills at provincial
and district level for DoH Primary mother-child health care
services by mobile team in five districts
Volunteer teacher training in five districts
09 - 10 December 2010 9GPAR Luang Prabang ARM 2010
GPARLP – Output 3:Business Facilitation Centre in DPI
Establishment of Web Site for business promotion, accessible directly from www
Lessons learning workshop on business promotion for DPI
Workshop on job descriptions for DPI
09 - 10 December 2010 10GPAR Luang Prabang ARM 2010
GPARLP – Output 4:Provincial oversight - SDIS
Provincial workshops with all district on SDIS operational modalities and strengths & weaknesses
7 weeks national consultancy on clarification and strengthening SDIS for future sustainability
Training of leadership on use and application of SDIS information for strategic planning
09 - 10 December 2010 11GPAR Luang Prabang ARM 2010
GPARLP – Output 5:Service Delivery Fund (SDF)
12 project contracted and implemented, mostly clean water and sanitation projects, but also agriculture, schools, and support to LWU
102 % of budget spent (target was 80 %)
09 - 10 December 2010 12GPAR Luang Prabang ARM 2010
GPARLP – Output 6:GPAR Resource Centre (GRC) at OoG
No specific activities to establish GRC as it was already established
Other activities under output 6:o Lessons learned workshopo LP Administrative Improvement
Plan and proposal for GPAR in LP after 2010
o Review meeting with all TOTs and training manuals review
o ICT training and web site for GRC
09 - 10 December 2010 13GPAR Luang Prabang ARM 2010
GPARLP: Sustainability Sustainability of systems:
GFIS, PIMS ongoing and well mainstreamed
SDIS less well integrated and needs further attention to be sustainable
ODS (LP) and BFC well functioning and mainstreamed
Training activities: All training activities completed (outputs achieved); sustainability depends on future staff transfers and institutionalization of enhanced capacity
09 - 10 December 2010 14GPAR Luang Prabang ARM 2010
GPARLP: Sustainability
Organisational development with job descriptions in DOH and DOE is well integrated and sustainable SDF supported projects are all completed and in most cases useful vis-a-vis their purposes GPAR Resource Centre in OoG is established and mainstreamed – future usefulness and sustainability depends on budget allocations.
09 – 10 December 2010 15GPAR Luang Prabang ARM 2010
GPARLP: Documentation for Closing
Lessons learned report prepared and a 3
pages summary as per UNDP requirement
Final Project Report prepared Inventory of equipment prepared
and verified Last budget review with
calculation of unspent balance
09 - 10 December 2010 16GPAR Luang Prabang ARM 2010
GPARLP: Final Accounting
The Project Accountant will be retained for 5 months, January – May 2011, for anyAdministrative issue, final accounting and facilitation of auditing
All Project activities expected to be finalisedby 31 December 2010.
09 - 10 December 2010 17GPAR Luang Prabang ARM 2010
GPARLP: - after 2010
Great stakeholder interest in LP whether
a successor project/programme will materialise
Administrative Improvement Plan for LP
with list of identified needs and priority
interventions prepared in 2009 and updated in
2010 based on participatory process
Preliminary proposal for GPAR in LP 2011 –
15 prepared on basis of Improvement Plan