    Cost Estimation and Budgeting

    W S William

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    2/16

    Copyright 2010 PearsonEducation, Inc. Publishing as

    Prentice Hall

    8-2

    Cost Estimation

    Ballpark (order of magnitude) 30%

    Comparative 15%

    Feasibility 10%

    Definitive

    5%

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    3/16

    Copyright 2010 PearsonEducation, Inc. Publishing as

    Prentice Hall

    8-3

    Problems with Cost Estimation

    Low initial estimates

    Unexpected technical difficulties

    Lack of definition

    Specification changes

    External factors

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    4/16

    Cost Estimating and the Systems Development Life

    Cycle

    Cost

    estimate

    Contingency

    fund

    C

    umulativeco

    st

    Time

    Regions of time-

    cost uncertainty

    At project

    initiation

    At project

    definitionAt project

    execution

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    5/16

    Estimating Process

    Estimating Methods

    1. Expert opinion

    2. Analogy + compensation for differences

    3. Parametric: Formula or Cost Function, e.g.,

    Cost, engine A = (Cost, engine B)

    Cost, cabling = 150 (total area + 10%)+ 300 (number of rooms)

    + 125 (number of floors)

    Thrust, engine A

    Thrust, engine B( )0.7

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    6/16

    Estimating Methods (contd)

    4. Cost engineering

    Detailed cost breakdown of labor, materials, etc.

    at the work package or task level.

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    7/16

    Estimation Process

    1. PM: Uses WBS to identify work packages

    2. FM: Subdivide work packages into identifiable

    tasks; determine labor, material, facilities, andresources requirements for each

    3. Supervisors/team leads: Estimate number of labor

    hours and quantities of materials needed

    Functional Management

    Work team

    Project Management

    WBS

    information

    2.

    3.

    1.

    Procedure for larger projects, steps 1-3

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    8/16

    Functional Management

    Work team

    Project Management

    WBS

    informationEstimation Process

    4. FM: check and aggregate time and material

    estimates

    5. FM: convert time estimates into costs

    6. PM: checks over and approves all estimatesaggregates costs; added in overhead costs:

    Project cost = direct costs + overhead costs

    6.

    4., 5.Procedure for larger projects, steps 4-6

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    9/16

    Estimating Process (contd)

    7. PM: Adds in contingency amounts.

    Two possible contingencies

    1. Base estimate = (WP estimates + WP contingency)

    (to handle known-unknowns)

    2. Final estimate = Base estimate + overheads + project contingency

    (to handle unknown unknowns; PM controls this)

    8. PM: Compares bottom-up estimates to top-down targets or

    goals. Attempt to reconcile differences.

    Functional Management

    Work team

    Project Management

    WBS

    information

    7., 8..

    Procedure for larger projects, steps 7-8

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    10/16

    Estimating Process

    Estimates can be made at any level

    project

    work package

    task

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    11/16

    Project Budget

    Specific for each project

    Subdivided into Control Accounts, one for each work

    package

    Each control account is a portion of the project total

    budget

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    12/16

    Project budget subdivided into control accounts

    ROSEBUD

    $ 356,755

    Projectmanagement

    Basicdesign

    Hardware Software FinalTests

    $ 12,550$31,362 $179,868 $122,118

    $10,857

    Assembly

    InstallationMaterials

    Procedures

    Specifications SystemTest

    User

    Test

    $138,571

    $20,945 $21,272

    $4,235

    $6,622$20,352$100,846

    J

    M

    V

    L W

    Y Q X

    Project Budget

    Cost

    Accounts

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    13/16

    Project Budget

    The best project budgets are time-phased to allow

    cost tracking vs. time

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    14/16

    Copyright 2010 Pearson

    Education, Inc. Publishing as

    Prentice Hall

    8-14

    Budget Contingencies

    The allocation of extra funds to cover

    uncertainties and improve the chance of finishingon time.

    Contingencies are needed because

    Project scope may change

    Murphys Law is present Cost estimation must anticipate interaction costs

    Normal conditions are rarely encountered

  • 8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx

    15/16

    Estimating Pitfalls

    Misinterpretation of the statement of work

    Improperly defined scope

    Overly optimistic schedule Inaccurate WBS

    Applying improper skill level to tasks

    Failure to account for risks

    Failure to account for cost escalation and inflation

    Failure to use correct estimating technique