Cost Estimation and Budgeting
W S William
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
2/16
Copyright 2010 PearsonEducation, Inc. Publishing as
Prentice Hall
8-2
Cost Estimation
Ballpark (order of magnitude) 30%
Comparative 15%
Feasibility 10%
Definitive
5%
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
3/16
Copyright 2010 PearsonEducation, Inc. Publishing as
Prentice Hall
8-3
Problems with Cost Estimation
Low initial estimates
Unexpected technical difficulties
Lack of definition
Specification changes
External factors
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
4/16
Cost Estimating and the Systems Development Life
Cycle
Cost
estimate
Contingency
fund
C
umulativeco
st
Time
Regions of time-
cost uncertainty
At project
initiation
At project
definitionAt project
execution
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
5/16
Estimating Process
Estimating Methods
1. Expert opinion
2. Analogy + compensation for differences
3. Parametric: Formula or Cost Function, e.g.,
Cost, engine A = (Cost, engine B)
Cost, cabling = 150 (total area + 10%)+ 300 (number of rooms)
+ 125 (number of floors)
Thrust, engine A
Thrust, engine B( )0.7
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
6/16
Estimating Methods (contd)
4. Cost engineering
Detailed cost breakdown of labor, materials, etc.
at the work package or task level.
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
7/16
Estimation Process
1. PM: Uses WBS to identify work packages
2. FM: Subdivide work packages into identifiable
tasks; determine labor, material, facilities, andresources requirements for each
3. Supervisors/team leads: Estimate number of labor
hours and quantities of materials needed
Functional Management
Work team
Project Management
WBS
information
2.
3.
1.
Procedure for larger projects, steps 1-3
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
8/16
Functional Management
Work team
Project Management
WBS
informationEstimation Process
4. FM: check and aggregate time and material
estimates
5. FM: convert time estimates into costs
6. PM: checks over and approves all estimatesaggregates costs; added in overhead costs:
Project cost = direct costs + overhead costs
6.
4., 5.Procedure for larger projects, steps 4-6
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
9/16
Estimating Process (contd)
7. PM: Adds in contingency amounts.
Two possible contingencies
1. Base estimate = (WP estimates + WP contingency)
(to handle known-unknowns)
2. Final estimate = Base estimate + overheads + project contingency
(to handle unknown unknowns; PM controls this)
8. PM: Compares bottom-up estimates to top-down targets or
goals. Attempt to reconcile differences.
Functional Management
Work team
Project Management
WBS
information
7., 8..
Procedure for larger projects, steps 7-8
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
10/16
Estimating Process
Estimates can be made at any level
project
work package
task
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
11/16
Project Budget
Specific for each project
Subdivided into Control Accounts, one for each work
package
Each control account is a portion of the project total
budget
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
12/16
Project budget subdivided into control accounts
ROSEBUD
$ 356,755
Projectmanagement
Basicdesign
Hardware Software FinalTests
$ 12,550$31,362 $179,868 $122,118
$10,857
Assembly
InstallationMaterials
Procedures
Specifications SystemTest
User
Test
$138,571
$20,945 $21,272
$4,235
$6,622$20,352$100,846
J
M
V
L W
Y Q X
Project Budget
Cost
Accounts
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
13/16
Project Budget
The best project budgets are time-phased to allow
cost tracking vs. time
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
14/16
Copyright 2010 Pearson
Education, Inc. Publishing as
Prentice Hall
8-14
Budget Contingencies
The allocation of extra funds to cover
uncertainties and improve the chance of finishingon time.
Contingencies are needed because
Project scope may change
Murphys Law is present Cost estimation must anticipate interaction costs
Normal conditions are rarely encountered
-
8/14/2019 8722_eetCost Estimation and Budgeting-v-1.0.pptx
15/16
Estimating Pitfalls
Misinterpretation of the statement of work
Improperly defined scope
Overly optimistic schedule Inaccurate WBS
Applying improper skill level to tasks
Failure to account for risks
Failure to account for cost escalation and inflation
Failure to use correct estimating technique
-