8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June...

35
AR EVA

Transcript of 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June...

Page 1: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

AR EVA

Page 2: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

U.S. EPR Protection System:SPND-Based Reactor TripFunctionsShelby Small - I&C Systems EngineerAug. 30,2010

AAREVA

Page 3: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Purpose

Following June 25, 2010 public meeting, AREVA NP:* Evaluated NRC feedback relative to SPND-based functions

* Re-evaluated the relevant regulatory requirements

* Re-evaluated the design of the SPND-based functions

This presentation represents the conclusions of ourevaluation, which include:

* The current design of the SPND-based functions satisfies all regulationsfor independence.

* NRC feedback included some points that are not well understood or mayinaccurately represent the U.S. EPR design.

* More detail is needed regarding exactly which aspects of the system areviewed as non-compliant with exactly which regulations.

Purpose of the presentation:* Clearly convey AREVA NP understanding of independence regulations

and how the SPND-based functions are in compliance.

* Gain a more detailed understanding of NRC concerns to better understandhow to address them.

ASPND RT Functions - U.S. EPR - 8/30/2010 - p.3 AR EVA

Page 4: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Presentation Outline

I&C Implementation of SPND-based RT functions

Independence Regulations

Independence for SPND-Based Reactor Trip Functions

NRC Concerns Conveyed on June 25, 2010

AAREVASPND RT Functions - U.S. EPR - 8/30/2010 - p.4

Page 5: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Overview of I&CImplementation of SPND-

based RT functions

AAREVASPND RT Functions - U.S. EPR - 8/30/2010 - p.5

Page 6: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Relationship between Reactor Core Design andI&C Implementation of SPND Functions

Advantages of using of in-core SPND measurements:

+ Direct measurement of linear power density (LPD).

* Accurate evaluation of DNBR.

+ Protection of SAFDLs based on measurements which directly representthe phenomena that could challenge the SAFDLs.

In the U.S. EPR reactor core design, in-core flux measurementis fundamental to protection of SAFDLs.

) Adequate protection of the SAFDLs depends on use of all 72measurements together, in aggregate.

The availability of 72 SPND measurements in each PS div~ision is a fundamentalIfeature of core protection reflected in the U.S. EPR safety analysis.

ASPND RT Functions - U.S. EPR - 8/30/2010 - p.6 Ag E VA

Page 7: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Holistic Treatment of Requirements

There are multiple types of requirements that must beaddressed:

* Regulatory requirements

* Stakeholder requirements

* Functional requirements

* Performance requirements

* Etc.

Key design requirements/constraints to consider inconjunction with regulatory requirements for independence:

*72 SPND measurements used in each PS division.

* Sensed parameter is spatially dependent, not homogenous throughout thecore.

* Physical core design does not allow for multiple SPND at each location.

* SPND signal is nano-amps. Signal cannot be split until amplified (i.e., hasalready been "divisionalized" for electrical purposes).

I&C implementation of these functions reflects consideration of allrequirements; not just independence requirements.

SPND RT Functions - U.S. EPR - 8/30/2010 - p.7 AR EVAI

Page 8: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

SPND

x18

X18 x18

Range Conversion'.g 0 R ang onesion/II Filteong (01 8) RA A 2 Filteng 01.8)

8 signals to DIV, 2 18 signals to DIV, 2

18 signals to DeIV, 3 R18 signals to Be3• •

8 signalsi 1 signals to DIV 4

tI signal,:s t'ronr 0V 2-18 signals from DIV 3

18 signals from DIV. 4

Other Required SSensor

Measurements

[1F2/4

I iLo IALI __ -oi, j

J

Al

18 signals frle DIV. 218 signals from DIV. 318 signals from DIV 4

PU Al

To otherdivisions

From other

Sdimso

Overview of I&CImplementation

One division represented*18 SPND acquired redundantly by

two RAU. Redundancy is within adivision.

* Each RAU sends 18 SPND to APU ineach of four divisions. Redundancyachieved through network topologies.

* APU selects more conservative oftwo signals for each SPNDmeasurement. DNBR and HLPDcalculations performed. Setpointcomparisons performed.Redundancy is between divisions.

* Results of setpoint comparisons sentfrom APU in each division to ALU inall four divisions. Redundancy isbetween divisions.

* 2/4 voting performed in ALUs in allfour divisions. Redundancy isbetween divisions.

-L A4A~

SPND RT Functions - U.S. EPR - 8/30/2010 - p.8A ANR EVA

Page 9: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Overview of I&C Implementation (Cont.)

*RAL

Important fault-tolerant features designed into SPND-basedfunctions:

J-.* Range monitoring of SPND input signals

* Selection of more conservative of two signals for each SPND.

2 nd min selection between 12 calculated DNB values (1 DNB value perstring).

2 nd max selection between 72 calculated HLPD values (1 HLPD value perSPND).

* Calculation of imbalance between symmetric pairs of SPND.

* Use of more conservative RT setpoints for 1, 2, 3, 4 or 5 invalid SPNDsignals.

* Tech. spec. administrative control to reduce power for 6 invalid SPNDsignals (conservative setpoint for 5 invalid SPND still active).

* Automatic RT for 7 or more invalid SPND signals.

Uf* Detection of rod drops to invoke more conservative setpoints.U * 2/4 voting on setpoint comparison results.

*API

*AL

AAREVASPND RT Functions - U.S. EPR - 8/30/2010 - p.9

Page 10: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Independence Regulations

AAREVASPND RT Functions - U.S. EPR - 8/30/2010 - p.10

Page 11: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Independence Regulations

) GDC 21- Protection system reliability and testability* Redundancy and independence designed into the protection system shall be

sufficient to assure that (1) no single failure results in loss of the protectionfunction and (2) removal from service of any component or channel does notresult in loss of the required minimum redundancy unless the acceptablereliability of operation of the protection system can be otherwise demonstrated.

GDC 22 - Protection system independence* The protection system shall be designed to assure that the effects of natural

phenomena, and of normal operating, maintenance, testing, and postulatedaccident conditions on redundant channels do not result in loss of the protectionfunction, or shall be demonstrated to be acceptable on some other definedbasis.

GDC 23- Protection system failure modes* The protection system shall be designed to fail into a safe state or into a state

demonstrated to be acceptable on some other defined basis if conditions suchas disconnection of the system, loss of energy (e.g., electric power, instrumentair), or postulated adverse environments (e.g., extreme heat or cold, fire,pressure, steam, water, and radiation) are experienced.

ASPND RT Functions - U.S. EPR - 8/30/2010 - p.1 1 AR EVAI

Page 12: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Independence Regulations

10 CFR 50.55a(h)

IEEE 603-1998, Clause 5.6.1 "Independence between redundantportions of a safety system"

* Redundant portions of a safety system provided for a safety function shall beindependent of, and physically separated from, each other to the degreenecessary to retain the capability of accomplishing the safety function duringand following any design basis event requiring that safety function.

IEEE 603-1998, Clause 6.4 "Derivation of system inputs"

* To the extent feasible and practical, sense and command feature inputs shall bederived from signals that are direct measures of the desired variables asspecified in the design basis

ASPND RT Functions- U.S. EPR -8/30/2010 - p.12 AR EVA

Page 13: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Compliance with GDC 21 -

SPND RT FunctionsGDC 21

Redundancy and independence designed into the protection system shall besufficient to assure that (1) no single failure results in loss of the protection functionand (2) removal from service of any component or channel does not result in loss ofthe required minimum redundancy unless the acceptable reliability of operation of theprotection system can be otherwise demonstrated.

No single failure results in loss of RT functions* Demonstrated through FMEA summarized in U.S. EPR FSAR Tier 2, Section 7.2.

Removal from service of any component does not result in loss ofrequired minimum redundancy unless acceptable reliability isdemonstrated

* With exception of RAUs, any PS component can be removed from service withredundancy retained (FMEA including single failure + maintenance audited by NRC in2009)

* RAU removed from service: acceptable reliability of RT function is otherwisedemonstrated

" Technical specification limit of 6 hours or power reduction to <10%, consistent with IEEE 603-1998Clause 6.7

* Described in response to RAI 309, Q 7.09-59 ASPND RT Functions - U.S. EPR - 8/30/2010 - DA13 AR EVA

Page 14: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Compliance with GDC 22-SPND RT Functions

GDC 22

The protection system shall be designed to assure that the effects of naturalphenomena, and of normal operating, maintenance, testing, and postulatedaccident conditions on redundant channels do not result in loss of theprotection function, or shall be demonstrated to be acceptable on someother defined basis.

Natural phenomena do not cause loss of protection function

* PS located in safeguard buildings designed to protect against naturalphenomena (Tier 2, Section 7.1.2.2.2)

* PS equipment seismically qualified (Tier 2, Section 7.1.1.4.1)

Normal operating, maintenance, testing conditions do notresult in loss of the protection function

* Technical specification controls are applied so that normal operating,maintenance, and testing conditions do not result in loss of the protectivefunction (Tier 2, Chapter 16, LCO 3.3.1)

ASPND RT Functions - U.S. EPR - 8/30/2010 - o.1 4 AR EVA.................................. i•

Page 15: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Compliance with GDC 22-SPND RT Functions (Cont.)

Accident conditions do not result in loss of the protectionfunction

* SPND located in the core:* Qualified to accident environment (harsh environment qualification lAW Tier 2, Section

3.11)

* SPND cabling in containment* Qualified to accident environment (harsh environment qualification lAW Tier 2, Section

3.11)

* Remainder of PS:* Location in mild environment protected from effects of accident (Tier 2, Section

7.1.1.4.1)

" Class 1 E equipment qualification (Tier 2, Section 7.1.1.4.1)

ASPND RT Functions- U.S. EPR -8/30/2010 - D.1 5 AR EVA

I

Page 16: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Compliance with GDC 23-SPND RT Functions

GDC 23The protection system shall be designed to fail into a safe state or into a statedemonstrated to be acceptable on some other defined basis if conditions such asdisconnection of the system, loss of energy (e.g., electric power, instrument air), orpostulated adverse environments (e.g., extreme heat or cold, fire, pressure, steam,water, and radiation) are experienced.

> Automatic RT on 7 or more invalid SPND measurements is consistentwith GDC 23.

SPND-based RT functions fail into a safe state in case of:

C Complete disconnection of data communication between divisions (multiple networkfailures or multiple communication processor failures)

C Complete loss of electrical power to one division (failure of normal supply + failure ofbackup batteries + failure of emergency diesels)

* Adverse environment that incapacitates both RAU in a division

No postulated single failure causes the system to revert to the safestate.

All protective functions in the U.S. EPR design revert to the safe statewhen the function can no longer be reliably performed due to

accumulation of detected failures. ASPND RT Functions - U.S. EPR - 8/30/2010 - p.16 AR EVA

Page 17: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Compliance with IEEE 603-1998 Clause 5.6.1- SPND RT Functions

IEEE 603-1998, Clause 5.6.1 (via 10 CFR 50.55a(h))

Redundant portions of a safety system provided for a safety function shall beindependent of, and physically separated from, each other to the degree necessaryto retain the capability of accomplishing the safety function during and following any

design basis event requiring that safety function.

The following are implemented between redundant portions ofPS to assure independence (Tier 2, Section 7.1.1.6.4):

* Physical separation

* Electrical isolation

* Communication isolation

ASPND RT Functions - U.S. EPR -8/30/2010 - D.17 AR EVA..................................... F

Page 18: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Compliance with IEEE 603-1998 Clause 5.6.1- SPND RT Functions (Cont.)

Application of IEEE 603 Clause 5.6.1 must be consistent withGDC 21 and GDC 22 independence requirements.

* GDC 21: no single failure results in loss of protection function.

* GDC 22: postulated accident conditions do not result in loss of protectionfunction.

IEEE 603-1998 Clause 5.6.1 is satisfied if the safety functioncan be performed in the presence of postulated accidentconditions and any credible single failure.

* Compliance is demonstrated by:, Accounting for, or dispositioning, postulated accident conditions.

" Postulating a credible single failure anywhere in the PS.

" Confirming that system design features for independence (i.e., physical separation,electrical isolation, communication isolation) protect redundant portions of the systemfrom the failure, allowing the redundant portions to perform the safety function.

ASPND RT Functions- U.S. EPR -8/30/2010 - p.18 AR EVA

Page 19: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Independence for SPND-BasedReactor Trip Functions

AAREVASPND RT Functions - U.S. EPR - 8/30/2010 - p.19

Page 20: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Independence Assessment

The following slides outline the approach to demonstratecompliance with independence requirements which includes:

* Dispositioning postulated accident conditions

* postulating single failures of the various components involved inperforming the SPND-based RT functions.

* For each failure, identifying mitigation features and independencefeatures that assure performance of the safety function.

SIt is expected that more detailed discussions will be needed tofully elaborate the mitigation and independence aspects forsome failures.

AREVA NP will support such detailed discussion today, to theextent allowed by time. A follow-on audit to inspect detailedanalysis documentation would be prudent.

The focus,,-tOday is to reach agreement that -this analysis -approach, is an,acceptable means to demonstrate sufficient independence~i ii•...

ASPND RT Functions - U.S. EPR - 8/30/2010 - D.20 AR EVA

Page 21: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Disposition of PostulatedAccident Environment

> Accident conditions do not result in loss of the protectionfunction

* SPND located in the core:* Qualified to accident environment (harsh environment qualification lAW Tier 2, Section

3.11)

* SPND cabling in containment* Qualified to accident environment (harsh environment qualification lAW Tier 2, Section

3.11)

* Remainder of PS:" Location in mild environment protected from effects of accident (Tier 2, Section

7.1.1.4.1)

" Class 1 E equipment qualification (Tier 2, Section 7.1.1.4.1)

ASPND RT Functions - U.S. EPR - 8/30/2010 - D.21 AR EVA..................... i

Page 22: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

-gre 6gre - -g - 63 o,, - g

See HandoutSPND

x18

X18

ID 3__7_gna18 rSrgals~ltoDIV 4

18signaýsro DIV. 218 signals to OIV. 318 spgnals to DIV. 4

Other Required

,S=. r

III

APU A1-- J

i To to,di.0- 0•,

I ( oson

r--I l

' ALU Al1

ALU A4

Fu-nclionmalAND

AAREVASPND RT Functions - U.S. EPR - 8/30/2010 - p.22

Page 23: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Single failure: Input channel

Mitigation:" If detected failure: more conservative setpoint used.

* If undetected spurious failure: 2 nd min./2nd max selection in APU

* If undetected blocking failure: Other SPND detect symmetrical event,imbalance functionality accommodates asymmetrical event.

Independence features:* Electrical isolation between RAU input channels.

* Physical separation between RAU input channels.

8 S'g S S s, h1, ,

RAUg~~ 1SS RAU

18 SPNm3 StOngS 6 pCI 5t16g

2 I RAUC8 2S 6na6

18 S•gnals 15 Srgnas

S1SPNN1 18 SpN6s3 s-r,., 6pe tn

I

2 1 .t f18 I~ ns 2 wt, of 18 sg,,l,

1R $ 1s 18 S•gnas IS SIRIS 2R SIISRUS

I A RA A A

ASPND RT Functions - U.S. EPR - 8/30/2010 - p.23 A EVAR EVA

Page 24: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Single failure: RAU 1 or RAU 2

Mitigation:* If detected failure: all outputs flagged faulty, redundant RAU performs function.

* If undetected spurious failure: Multiple spurious values sent (worst case) leadsto spurious RT.

* If undetected blocking failure: Other RAU sends correct values, APU selectsconservative values (which would be the correct values in this case).

Independence features:

* Electrical isolation between RAU 1 and RAU 2.

* Physical separation between RAU 1 and RAU 2.

* No data communication between RAU 1 and RAU 2.

TT. . . .... .. -

RAl 2 F - I.S -

SPND RT Functions - U.S. EPR - 8/30/2010 - p.24

U

RAU2

*uum m W .. W 1 AAREVA

Page 25: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Single failure: RAU - APU network

Mitigation:

* If detected failure: communication flagged faulty, redundant network performsfunction.

* If undetected (spurious or blocking) failure: bounded by failure of sending RAU.

Independence features:

* Electrically isolated network (fiber optic).

* Physical separation between network cabling (lAW IEEE 384).

* Communication isolation between APU and RAUs.

" Previously approved TXS principles for interference free communication.

, Accommodation of communication failures in RAI 286 Supp. 5 Question 7.09-46.

AU / I RAU 2 RAjjU I RAU RAU II

SNRTF -U.S A 83/0- .

ASPND RT Functions - U.S. EPR -8/30/2010 - p.25 AR EVA

I

Page 26: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Single failure: APU

Mitigation (same for all PS functions, SPND-based or not):

* If detected failure: all outputs flagged faulty, downstream vote modified to 2/3.

* If undetected spurious failure: Downstream vote becomes 1/3.

* If undetected blocking failure: Downstream vote becomes 2/3.

Independence features:

* Electrical isolation between APUs.

* Physical separation between APU divisions.

* No data communication between APU divisions.

C Communication isolation APUs and ALUs:

" Previously approved TXS principles for interference free communication.

* Accommodation of communication failures in RAI 286 Supp. 5 Question 7.09-46.

I - l I- AI mii nsLEL_

AnALU Al ALUA ALA Al ALA A2 - 8 / - A2

SPND RT Functions -U.S. EPR - 8/30/2010 - 1).26 AR EVA..... ............... ........ ..... . . F -

Page 27: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Single failure: APU - ALU network

Mitigation (same for all PS functions, SPND-based or not):

* If detected failure: all communication flagged faulty, downstream vote modifiedto 2/3.

* If undetected (spurious or blocking) failure: Bounded by sending APU failure.

Independence features:* Electrical isolation between APU and ALUs (fiber optic).

* Physical separation between network cabling (lAW IEEE 384).

* Communication isolation:

" Previously approved TXS principles for interference free communication.

" Accommodation of communication failures in RAI 286 Supp. 5 Question 7.09-46.

APU Al APUAl APUAI

ill.ALUAi AlU AL.S. AEP ALUAI-3 0 .7E

FN AND Fz;ND AMD ASPND RT Func~tions - U.S. PR 8/3 0I210 0- n.27 AR EVA

Page 28: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Single failure: ALU

Mitigation (same for all RT functions, SPND-based or not):

* If detected failure: Fails into state requesting RT. Redundant ALU performs the

function.

* If undetected spurious failure: Fails into state requesting RT. Redundant ALU

performs the function.

* If undetected blocking failure: Division cannot issue RT. Three redundantdivisions perform the function.

Independence features:

* Electrical isolation between ALU divisions.

* Physical separation between ALU divisions.

* No data communication between ALU divisions.mi l m Igm Im

II 1TA

SPND RT Functions- U.S. EPR -8/30/2010 - p.28 AR EVAI

Page 29: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

NRC Concerns Conveyed on June25, 2010

AAR EVASPND RT Functions - U.S. EPR - 8/30/2010 - p.29

Page 30: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

NRC Concerns Conveyed on June 25, 2010

Following June 25, 2010 public meeting, AREVA:

* Evaluated NRC feedback relative to SPND-based functions

* Re-evaluated the relevant regulatory requirements

* Re-evaluated the design of the SPND-based functions

These evaluations resulted in the following conclusions:

* The current design of the SPND-based functions satisfies all regulatoryrequirements

* NRC feedback included some points that are not well understood or mayinaccurately represent the U.S. EPR design

* More detail is needed regarding exactly which aspects of the system areviewed as non-compliant with exactly which regulatory requirements

By CIarifying NRC staff concerns, a better understanding of how to reach,closure on this issue can be attained.

AQD•fn 12T •,,ne-fin, I_ ,, PP - A/'74l/9n/9nl n- in AR EVA

Page 31: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

June 25 NRC Feedback

"Without independence, failures of one division can affect allsafety divisions, and result in loss of the ability to complete theintended safety functions." (Slide 4)

Consistent with this statement, AREVA NP demonstratesadequate independence by:

* accounting for accident conditions

* postulating single failures

* showing that the redundant portions of the system are protected from thefailures (i.e., are independent) and can still perform the safety function.

ASPND RT Functions - U.S. EPR - 8/30/2010 - p.31 AR EVA

T

Page 32: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

June 25 NRC Feedback - Point 2

The DNBR and HLPD reactor trip functions "requireinformation from outside its own division to accomplish thesafety function." (Slide 6)

In the U.S. EPR design, each division requires information fromoutside the division to perform the DNB and HLPDcalculations, but does not require information from outside thedivision to accomplish its safety function.

ASPND RT Functions - U.S. EPR - 8/30/2010 - D.32 AR EVA................................... i-- --

Page 33: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

June 25 NRC Feedback - Point 2 (cont.)

The safety function is accomplished without information fromoutside the division.

* Each division uses information from outside the division to perform theDNB and HLPD calculations.

* No single failure outside the division prevents these calculations frombeing performed.

" If incorrect information is received from outside the division due to a single failure, thedivision also receives correct information from a redundant source.

" If a loss of information results from single failure outside the division, the division stillreceives correct information from a redundant source.

* If no information is received from outside the division (multiple failuresare required to realize this scenario), the calculations cannot beperformed. However, the division reverts to a safe state and the safetyfunction is accomplished.

* Therefore, each division does not require information from outside thedivision to accomplish its safety function, which is to trip the reactor.

ASPND RT Functions - U.S. EPR - 8/30/2010 - o.33 AR EVA.................................. i

Page 34: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Summary L

I&C implementation of SPND-based RT functions reflects functionalrequirements that are fundamental to the core design and the plantsafety analysis.

I&C implementation of SPND-based RT functions satisfies allregulatory requirements for independence between redundantportions of safety systems.

Compliance with independence requirements is achieved bydemonstrating that the safety function can be performed in thepresence of postulated accident conditions and any credible singlefailure.

Critical need: NRC staff to identify any gaps in the AREVA approachto demonstrating compliance to independence regulations.

ASPND RT Functions - U.S. EPR - 8/30/2010 - p.34 AR EVAI

Page 35: 8-30-2010 AREVA Presentation on EPR Protective System SPND ... · A. AREVA. Purpose. Following June 25, 2010 public meeting, AREVA NP: * Evaluated NRC feedback relative to SPND-based

Path to Closure

AREVA NP will consolidate all I&C information previouslysubmitted on this topic.

NRC audit to inspect consolidated information and detailedanalysis documentation, and to determine what information isneeded on the docket.

Revision to U.S. EPR Protection System Technical Report toinclude the necessary information.

AAREVASPND RT Functions - U.S. EPR - 8/30/2010 - p.35