7.3.3 - Cost Variance Analysis

download 7.3.3 - Cost Variance Analysis

of 6

Transcript of 7.3.3 - Cost Variance Analysis

  • 7/22/2019 7.3.3 - Cost Variance Analysis

    1/6

    PMGT501; WBS 6.4Project Control

    David Bolton

    Page 1

    WBS 6.4.1: Solve Problem #3 found on page 467 of the Meredith and Mantel text.

    A software development project at day 70 exhibits an actual cost of $78,000 and a

    scheduled cost of $84,000. The software manager estimates a value completed of

    $81,000. What are the cost and schedule variances and CSI? Estimate the time

    variance.

    AC = $78,000

    PV = $84,000

    EV = $81,000

    AT = 70 days

    Cost Variance = EV AC = $81000 - $78000

    Cost Variance = $3,000

    Schedule Variance = EV PV = $81,000 - $84,000

    Schedule Variance = -$3000

    CPI = EV/AC = 1.03

    SPI = EV/PV = 0.96

    Cost Schedule Index = EV2/(AC)(PV) = ($81,000)2/($78,000)($84,000)

    Cost Schedule Index = 6,561,000,000 / 6,552,000,000

    Cost Schedule Index = 1.001

    Time Variance = ST AT = (AT)(CSI) AT = (70)(1.001) 70

    Time Variance = 0.07 days

    This is good. The project is a little under budget (CPI = 1.03) and a little behind

    schedule (SPI = 0.96). In theory, the PM could spend a little extra and make up that

    minor schedule variance. In our PM shop, CPI and SPI between 0.95 and 1.05 is

    green so theres no problem here.

  • 7/22/2019 7.3.3 - Cost Variance Analysis

    2/6

    PMGT501; WBS 6.4Project Control

    David Bolton

    Page 2

    WBS 6.4.2: Solve problem #4 found on page 467 of the Meredith and Mantel text.

    A project to develop a county park has an actual cost in month 17 of $350,000, a

    planned cost of $475,000 and a value completed of $300,000. Find the cost and

    schedule variances and the three indices.

    AC = $350,000

    PV = $475,000

    EV = $300,000

    AT = 17 months

    Cost Variance = EV AC = $300,000 - $350,000

    Cost Variance = -$50,000

    Schedule Variance = EV PV = $300,000 - $475,000

    Schedule Variance = -$175,000

    Cost Performance Index = EV/AC = $300,000/$350,000 = 0.857

    Schedule Performance Index = EV/PV = $300,000/$475,000 = 0.632

    Cost Schedule Index = (CPI)(SPI) = 0.857 * 0.632Cost Schedule Index = 0.542

    This is bad. The project has spent more than scheduled and is still far behind where it

    should be. CPI is yellow and SPI is red. Expect to be on the Directors radar with

    performance like this.

  • 7/22/2019 7.3.3 - Cost Variance Analysis

    3/6

    PMGT501; WBS 6.4Project Control

    David Bolton

    Page 3

    WBS 6.4.3: Solve problem #5 found on page 467 of the Meredith and Mantel text.

    A consulting project has an actual cost in month 10 of $23,000, a scheduled cost of

    $17,000 and a value completed of $20,000. Find schedule and cost variances and the

    three indices.

    AC = $23,000

    PV = $17,000

    EV = $20,000

    AT = 10 months

    Cost Variance = EV AC = $20,000 - $23,000Cost Variance = -$3,000

    Schedule Variance = EV PV = $20,000 - $17,000

    Schedule Variance = $3,000

    Cost Performance Index = EV/AC = $20,000/$23,000 = 0.87

    Schedule Performance Index = EV/PV = $20,000/$17,000 = 1.18

    Cost Schedule Index = (CPI)(SPI) = 0.87 * 1.18

    Cost Schedule Index = 1.027

    This one is a mixed bag. The PM has overspent (CPI=.87) and is over his earned value

    projection but is way ahead of schedule (SPI =1.18).

  • 7/22/2019 7.3.3 - Cost Variance Analysis

    4/6

    PMGT501; WBS 6.4Project Control

    David Bolton

    Page 4

    WBS 6.4.4: Solve problem #13 found on page 468 of the text.

    The following project is at the end of its sixth week. Find cost and schedule variances

    and the CPI, SPI, ETC and EAC.

    First, the activity chart:

    Activity Predecessor DurationBudget

    ($)

    Actual Cost

    ($)

    %

    Complete

    a - 2 300 400 100.00% BAC : 1750

    b - 3 200 180 100.00%

    c a 2 250 300 100.00%

    d a 5 600 400 20.00%

    e b, c 4 400 200 20.00%

  • 7/22/2019 7.3.3 - Cost Variance Analysis

    5/6

    PMGT501; WBS 6.4Project Control

    David Bolton

    Page 5

    Then the Plan Chart showing 50/50 EV reporting for the tasks.

    Plan! Week:

    Activity 1 2 3 4 5 6

    a 150 150

    b 100 0 100

    c 125 125

    d 300

    e 200

    PV 250 150 525 125 200 0

    Cum

    PV250 400 925 1050 1250 1250

    EV 250 150 286 125 40 0

    Cum EV 250 400 686 811 851 851

    Actual

    Cost 0 400 180 300 0 600

    Cum

    A/C0 400 580 880 880 1480

  • 7/22/2019 7.3.3 - Cost Variance Analysis

    6/6

    PMGT501; WBS 6.4Project Control

    David Bolton

    Page 6

    Finally, the analysis:

    Plan! Week:

    Activity 1 2 3 4 5 6

    CV 250 0 106 -69 -29 -629

    SV 0 0 -239 -239 -399 -399

    CPI 1 1.000 1.183 0.922 0.967 0.575

    SPI 1.000 1.000 0.742 0.772 0.681 0.681

    ETC 1750 1350 899.59184 1018.890259 929.6357227 1563.478

    EAC 1750 950 319.59184 138.8902589 49.63572268 83.47826

    The project appears to be going OK during the first two weeks. Problems surface in the

    third week when task D reports 50% of the planned $600 task value but only completes

    20% of the work. The problem worsens in week 5 when task E starts and also reports

    50% of task value but only completes 20% of the work.

    I think the critical input method of EV reporting might give a more accurate picture of the

    project status but it is still going to show the obvious: The project is slipping schedule

    (decreasing SPI) and overrunning budget (decreasing CPI, increasing ETC). Notice

    EAC in week 6 is $83 and there are still two weeks to go in the program. Not good.