Reinforcement work
• Factors to be considered: materials,
wastage and storage.
• Various sizes.
• Need to store properly – rusty
• Labour constant – unload (carry),cut and
bend and assemble into the formwork
example1
• Calculate the cost of steel reinforcement bar Y
12 in a concrete beam.
Solutions:
Materials:
Cost of 1 tonne steel reinforcement = RM2,100
Weight of 1 m length Y12 = 0.994 kg
Labour:
Labour cost for steel fixer RM40/day
No. of labour 1 labourer
To calculate cost of materials
Cost of 1 kg steel RM2.10/kg
Add 5% wastage RM 0.11
Cost of tie (0.5kg/100 kg steel @RM2.50/kg) RM 0.02
RM 2.23
To calculate labour constant
Cost of steel fixer (assume 1 labourer)
Labour constant for unloading, cut and bend =0.25 hrs/kg
Labour constant for fixing =0.1hr/kg
Wages per day RM 40/day =RM5.00/hr
Time to unload, cut and bend (1 kg) 0.25 hr
Then cost to carry, cut and bend =RM5.00 x 0.25 hr
= RM 1.25
Time for fixing (1 kg) = 0.1 hr
cost for fixing ( 1 kg) = RM5.00 x 0.1 hr
= RM 0.50
Rate for 1 kg of steel
RM2.23 +RM 1.25 + RM0.50
=RM 3.98
+ 10% profit = RM4.38
Exercise 2
Calculate the cost 1 kg of Y12
Cost steel per tonne = RM2300
Weight Y12 for 1 m = 0.995kg
Wages per day RM45.00
Profit 20%
If the steel 40m long= ????
Exercise 3 Calculate the cost of 1 kg R6 links in a concrete
column.Numbers of links are 9 and the length for
each is 0.89m.
Cost 1 tonne of R6 RM1600
Labour cost RM40/day
Lab. Cons to unload, cut and bend 0.25 hrs/kg
Lab. Cons to fix 0.1hr/kg
Wastage 5%
Profit 10%
Weight 1 m R6 0.222kg
To calculate the cost of materials
Weight of links = 0.222kg x 0.89m x 9
=1.79 kg
Cost of 1 kg R6 = 1.79 x RM 1.60 =RM2.85
Add wastage 5% =RM0.14
=RM2.99
To calculate labour cost
Lab. Cons to unload, cut and bend 0.25hr/kg
Wages per hr RM5.00
Total cost RM 5 x 0.25 hr/kg x 1.79 kg RM2.24
Labour constant to fix = 0.1 hr/kg
Cost for fixing = 0.1 x RM5 x 1.79
= RM 0.90
Cost of material + labour
RM2.99 + RM2.24 + RM0.90
=RM6.13
Cost + 10% profit = RM6.75
Exercise 4 Calculate the cost of 1 kg reinforcement Y10
Details:
Wt of 1 ton of reinf bar = 1016kg
Cost of 1 ton Y10 =RM1200
Wastage 2 ½ %
Tie wire 0.5kg every 100kg of reinf. Bar
cost of tie wire RM2.50/kg
steel fixer to unload, cut and bend and fix 100kg of
reinforment bar requires 12 hours
Steel fixer’s wage per day RM 35
Profit 20%
To calculate the cost of materials
1 ton of reinf (1016kg) RM1200
100 kg = 1200/1016 x 100 RM118.11
wastage 2 ½ % RM2.95
Tie wire 0.5kg for every 100kg [email protected]/kg
100 kg reinf use 0.5kg x RM2.50 RM1.25
Total RM122.31
To calculate the cost of labour
1 steel fixer need 12 hrs to unload, cut , bend and fix
Cost of labourer = RM35/8 x 12 hrs = RM52.50
Total cost: materials + labour
=RM 122.31 + RM52.50
= RM 174.81
+ 20% profit = 34.96
rate for 100 kg =RM209.77
1 kg =RM2.10
formwork
• To support the concrete
• Selection of formwork depend on
quality,safety and economy.
• Must strong enough to support the wet
concrete.
• Can reuse for several times
• Labour constant for making, fixing and
stripping (eg: 1.5hr/m2)
Cost of materials
• Plywood
• Strut (to support the formwork)
• Nails and shutter oil to formwork
labour Constant
- fixing and stripping
- multiply by wage per hour
Example 1
To calculate the cost of 1 m2 of formwork:
Details:
-25mm thick plywood (2.44 m x 1.22m)@ RM 40/pc
-Can be reuse for 5 times
-Cost of nails and oil to formwork RM2.00/time
-1m2 formwork need 0.07m3 strut @260/m3
-1 labourer to fix and stripping 1m2 for 2 hrs
- wage per day RM40
-wastage 10%
- profit 10 %
To calculate the cost of materials
1 m2 of plywood RM40/(2.44 x 1.22) =RM 13.44
0.07m2 struts RM260 x 0.07 =RM 18.20
use 5 times RM 31.64
1 time RM 6.33
Wastage 10% RM6.33 x 10 % RM 0.63
Cost of nails and shutter oil RM 2.00
total cost RM 8.96
To calculate labour cost
Labour wage RM40/8 RM5/hr
Time to fix and strip 1 m2 formwork 2 hrs
Workman cost RM5/hr x 2 hrs RM10
Toatal cost : material + labour
= RM 8.96 + RM 10.00
= RM18.96
Profit (10%) RM 1.90
cost for 1 m2 = RM 20.86
Exercise 1 Calculate cost of 1 m2 of formwork:
-Plywood (2.44m x 1.22 m) @ RM35.00 /pc
-1m2 formwork need 0.06m3 strut @250/m3
- Reuse for 5 times
- Cost of nail and oil RM1.00/time
- 1 carpenter needs 1 ½ hrs to fix and strip 1 m2 of
formwork
- Carpenter’s wage RM35/day
- Working hrs 8 hrs/day
- Wastage 10%
- Profit 20%
solutions
Materials
plywood
1 m2 = RM35/(2.44 x 1.22) RM11.78
Strut 0.06 x RM 250.00 RM15.00
Cost for 5 times RM26.78
for 1 time RM 5.36
wastage 10% RM 0.54
cost of nail + oil RM1.00
cost of materials RM 6.90
Labour
1 ½ hrs to fix and strip 1 m2 form
wage per day RM35.00
Payment to carpenter 1 ½ x (35/8) =RM6.56
Material + labour = RM6.90 + RM6.56
=RM13.46
+ 20% profit = RM2.69
cost for 1 m2 formwork = RM16.15