70 by 30 Implementation Plan - IWEA...70 by 30 Implementation Plan IWEA Autumn Conference 24th...
Transcript of 70 by 30 Implementation Plan - IWEA...70 by 30 Implementation Plan IWEA Autumn Conference 24th...
70 by 30 Implementation PlanIWEA Autumn Conference 24th October 2019
Paul Blount, BE CEng, Portfolio Director Coillte, [email protected], Chair of the 70by30 Committee
• Provide an evidence basis and support the
delivery of a 70% RES-E target in 2030
The role of the 70by30 committee
• Is this a credible proposition?
• Provide an evidence basis and support the
delivery of a 70% RES-E target in 2030
The role of the 70by30 committee
• Is this a credible proposition?
• Can it be cost effective?
• Provide an evidence basis and support the
delivery of a 70% RES-E target in 2030
The role of the 70by30 committee
• Is this a credible proposition?
• Can it be cost effective?
• Will it be supported by society?
• Can it be done in just 10 years?
IWEA 70 by 30 Implementation
Plan Working Group
70% Renewable Electricity
0
5
10
15
20
25
30
35
40
45
50
2020 2030
TWh
Conventional Generation (TWh) Renewable generation (TWh)
40% RES-E
Double the renewables in half the time = time is of the essence!
70% RES-E
Forecast 50% increase in demand
BaU “Typical” Project timelines
9 years of work + high risk dev ex to be ready to bid into an auction
Start transmission development here?
Or here?
i-PAT (IWEA pipeline analysis tool)
• Location
• Status
• Attrition
IWEA Developer Survey
• SID / LA
• Success Rates
• Durations
Consenting process • Batch size
• Frequency
• Prioritisation
Grid Offer process
• Allocate available capacity
• Apply delays when full
Transmission Capacity • Oversubscription
• Frequency
Route to Market
• Project finance
• Grid delivery
Finance & Build
Populate model with BauAssumptions
Determine MW’s consented and
energised in each year
Implement Policy Improvement
Assumptions (PI 1 –8)
Determine improvements in
MW’s consented and energised in each
year
i-PAT Preliminary Results
Onshore Wind Planning Consents
0
1000
2000
3000
4000
5000
6000
7000
2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
MW
's c
on
sen
ted
Year
MW's onshore wind consented 2020 - 2030
BaU
PI 1
PI 2
PI 3
BaU assumptions:• 33% pre planning
attrition• 38% SID success rate• 80% LA success rate• 1.9 year average
consenting duration
PI 1 assumptions:• 15% pre planning
attrition
PI 2 assumptions:• 75% SID success
rates• 1.6yr average
consenting duration
PI 3 assumptions:• 1.1yr average
consenting duration
Min planning consents required with no competition, no post planning attrition
i-PAT Preliminary Results
Onshore Wind Energisations
BaU assumptions:• ECP date order of
planning grant, 50 offers p.a.
• Transmission development starts post WF planning
• 2nd application for grid connection planning
• 2.5 year finance and build period
4000
4500
5000
5500
6000
6500
7000
7500
8000
8500
2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
MW
's o
nsh
ore
win
d e
ner
gise
d
Year
MW's onshore wind energised 2020 - 2030
BaU
PI 4
PI 5
PI 6
Pi 7
PI 8
Climate Action Plan 2030 onshore wind target
All scenarios assume a route to market for 66% of the MW’s available to contract every year
Intermediate targets?
i-PAT Preliminary Results
Onshore Wind Energisations
PI 4 assumptions:• ECP – 1st 25 offers
each year to largest projects
PI 5 assumptions:• Parallel development
of the transmission system
PI 6 assumptions:• Parallel consenting of
shallow grid connection
4000
4500
5000
5500
6000
6500
7000
7500
8000
8500
2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
MW
's o
nsh
ore
win
d e
ner
gise
d
Year
MW's onshore wind energised 2020 - 2030
BaU
PI 4
PI 5
PI 6
Pi 7
PI 8
PI 7 assumptions:• Less onerous ECP
long stop dates
PI 8 assumptions:• Shorter finance &
build period
Climate Action Plan 2030 onshore wind target
All scenarios assume a route to market for 66% of the MW’s available to contract every year
Intermediate targets?
Offshore Wind
3.5
GW
+ b
y 2
03
0
Climate Action Plan sets a blueprint to achieving 2030 targets – actions must be complete
25 MW currently
Co
nse
nts
Gri
d
Ro
ute
to
Mar
ket
MPDM bill enacted
Connection decisions + pragmatic regulatory framework
Timely offshore specific RESS round with sufficient volumes
Shared challenges
• Parallel development of the transmission system
• Timely grid connection offers + connection offer long stop dates
• Parallel consenting of shallow connection assets
• Grid delivery timelines
• Route to market – RESS / cPPAs
• ABP decision timelines
• Curtailment
Curtailment vs Operational
Constraints
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
45.00%
0 200 400 600 800 1000 1200 1400
Tota
l Win
d C
urt
ailm
ent
(%)
All Island Minimum Conventional Generation (MW)
70% RES-E Scenarios - Total Wind Curtailment vs SNSP & Min Gen
75% SNSP
80% SNSP
85% SNSP
90% SNSP
95% SNSP
100% SNSPBaringa 2030– 90% SNSP, 700MW Min Gen
Eirgrid Strategy 2030 –95% SNSP, Min Gen = ?
2020
https://www.youtube.com/watch?v=XGHk1PfdEfg
Curtailment vs Operational
Constraints
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
45.00%
0 200 400 600 800 1000 1200 1400
Tota
l Win
d C
urt
ailm
ent
(%)
All Island Minimum Conventional Generation (MW)
70% RES-E Scenarios - Total Wind Curtailment vs SNSP & Min Gen
95% SNSP
Eirgrid Strategy 2030 –95% SNSP, Min Gen = ?
Eirgrid strategy on operational constraints could address 2/3rds of the curtailment challenge on its own
2020
https://www.youtube.com/watch?v=XGHk1PfdEfg
Curtailment vs Operational
Constraints
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
45.00%
0 200 400 600 800 1000 1200 1400
Tota
l Win
d C
urt
ailm
ent
(%)
All Island Minimum Conventional Generation (MW)
70% RES-E Scenarios - Total Wind Curtailment vs SNSP & Min Gen
75% SNSP
80% SNSP
85% SNSP
90% SNSP
95% SNSP
100% SNSPBaringa
Eirgrid
Curtailment vs Storage &
Interconnectors
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
30.0%
35.0%
40.0%
45.0%
50.0%
0 500 1000 1500 2000 2500 3000
Tota
l Win
d C
urt
ailm
ent
(%)
Additional Interconnection / Storage (MW)
All Island Wind Curtailment Vs Additional Idealised Interconnection and Storage
3hr Battery Storage
6hr PHES
15h PHES
30h PHES
In energy storage terms this would be the equivalent of 50 Turlough hill projects
Curtailment vs Storage &
Interconnectors
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
30.0%
35.0%
40.0%
45.0%
50.0%
0 500 1000 1500 2000 2500 3000
Tota
l Win
d C
urt
ailm
ent
(%)
Additional Interconnection / Storage (MW)
All Island Wind Curtailment Vs Additional Idealised Interconnection and Storage
Idealised Interconnection
Greenlink
Celtic
50% average export solves c.a. ¼ of the problem
But is it possible to do more with better market design?
100% exports during curtailment events
50% exports during curtailment events
Ingredients for success
• Healthy development pipelines on & offshore
Ingredients for success
• Healthy development pipelines on & offshore
• Timely grid connection offers
Ingredients for success
• Healthy development pipelines on & offshore
• Timely grid connection offers
• Manage Curtailment
• Manage Constraint
Ingredients for success
• Healthy development pipelines on & offshore
• Timely grid connection offers
• Manage Curtailment
• Manage Constraint
• Route to market
Ingredients for success
• Healthy development pipelines on & offshore
• Timely grid connection offers
• Manage Curtailment
• Manage Constraint
• Route to market
• Partnerships / Cooperation / Collaboration /
information sharing
“Work with partners for positive change”
Key take aways
• Transmission system development could be the
greatest challenge – we need to start now
Key take aways
• Transmission system development could be the
greatest challenge – we need to start now
• 2030 is just a waypoint on a longer journey
Key take aways
• Collaboration / partnerships across all
stakeholders is key to success and what we do
together in the next 1-2 years will determine
whether we succeed or fail.
– REI proposal to bring SOs, CRU, Industry, DCCAE,
DHPLG, and ABP together regularly to monitor progress
/ remove road blocks.
• Transmission system development could be the
greatest challenge – we need to start now
• 2030 is just a waypoint on a longer journey