7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream...

30
7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream Crossings

Transcript of 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream...

Page 1: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

7 Sep 2011: Progress Meeting

0-6549 Hydraulic Performance of Staggered-Barrel Culverts for Stream

Crossings

Page 2: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Agenda

• Introductions

• By-Task Progress

• Problems

• Miscellaneous

• Lab Visit

Page 3: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Introductions

• Researchers:

• Project Management Committee:

• Visitors:

Page 4: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Project Background

• Develop knowledge to address the issue of solids accommodation in Texas Department of Transportation low-water crossing structures (not bridges).

• To develop design guidelines to assist in building multiple barrel systems that mimic the necessary stream behavior to facilitate solids migration.

Page 5: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Progress by Tasks

• Brief by-task report.– Task 1: Literature Review– Task 2: Screening Tools– Task 3: Quantitative Modeling– Task 4: Data Analysis– Task 5: Reporting

Page 6: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Task 1: Literature Review

• TM1 submitted.– Copies on server

• Database(s) assembled.– QA/QC complete.

Page 7: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Task 2: Screening tool(s).

• Database dependent– QA/QC on-going as just reported– Prototype screening tool exists

– USGS is programming for team deployment.– Prototype runs OK on PC, will not run on Mac

(but should)

– TM2 was due July 2011– PD reminded RS about TM2. TM2 to be

completed before end of CY 2011, probably sooner.

Page 8: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Task 2: Screening tool(s).

• Database dependent– QA/QC on-going as just reported– Prototype screening tool exists

– USGS is programming for team deployment.– http://tx.cr.usgs.gov/jvrabel/WATER_index.html

#guiTaskItem2_demo– TM2 was due July 2011

– PD reminded RS about TM2. TM2 to be completed before end of CY 2011, probably sooner.

Page 9: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Task 3: Quantitative modeling.

• Laboratory system functional.– Have solids in-place and will demonstrate

today.

– Experimental program ended August 31– Large fraction of planned experiments

were conducted.– Data interpretation FY12 (CY11-12)

Page 10: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Task 3: Quantitative modeling.

• Certain experiments were omitted• Sand – entirely omitted, could not keep

sand in model.

• Gravel sizes changed to reflect mobility from first few months of experimental program.

• Slopes different to fit actual model capabilities.

Page 11: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Task 4: Data Analysis.

• 2-D/2-phase computer program (UH researchers) to guide experiments.

• FaSTMECH CFD computer program (TTU) to extrapolate to larger scales.

• CAP-R (Culvert Analysis Program – R) to provide design and performance guidance.

Page 12: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Task 4: Data Analysis.

• 2-D/2-phase computer program (UH researchers) to interpret experiments.

Page 13: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

UH Activities

1D coupled morphodynamics profile modelPeople: Ruosen Qian (MS), Kyle Strom

Database refinement for screening toolPeople: Kyle Strom (Task 2)

HEC-RAS modeling of Real County crossingPeople: Miguel Albuja (UG), Guillo Machado

(UG), Kyle Strom

Page 14: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

1D Morphodynamic Model

Purpose of modelDynamic modeling of culvert reach that

accounts for deposition/erosion (data analysis)

Upscaling of lab model results (data analysis)

Page 15: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

1D Morphodynamic Model

Page 16: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

1D Morphodynamic ModelProgress

Validated modelPure open channel with movable bed and variable

width (transcritical flow)

Open/pressured flow in a circular pipe

Ruosen graduated in August

Page 17: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

1D Morphodynamic Model

EquationsContinuity:

Saint Venant:

Exner:

Methods

MacCormack Finite Difference

TVD

Modification to sources terms

Page 18: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

1D Morphodynamic Model

Transcritical flow

Page 19: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

1D Morphodynamic Model

Bed aggradation due to sediment overloading

Page 20: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

1D Morphodynamic Model

Bed degrading due to base level drop

Page 21: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

1D Morphodynamic Model

Page 22: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Remaining work

•1D morphodynamic model– Use culvert equations as internal boundary

conditions with dynamic bed equation to capture changes in culvert geometry.

•Screening tool

– Aid TTU and USGS in tool development

•HEC-RAS

– Finish analysis of Real County and a hypothetical case to determine extent to which HEC-RAS can be helpful in analysis.

Page 23: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Real County LWC still looks good

looking downstream

Page 24: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

upstream

downstream

Page 25: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Task 4: Data Analysis.

• FasTMECH CFD computer program (TTU) to extrapolate to larger scales.

Page 26: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Task 4: Data Analysis.

• CAP-R (Culvert Analysis Program – R) to provide design and performance guidance.

Page 27: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Task 5: Reporting.

• SAR submitted end of August

• Monthly reports on server; Project start to June 2011 should be there.

• TM1 submitted

• TM2 in-progress

• TM3, TM4 pending.

• Final Report FY12 (Draft August 2012)

Page 28: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Problems Encountered

• Took longer to start experiments than anticipated.– Weir calibration

– Leaks, computers failing, etc.

• Boundary conditions in 1D not continuous from free-surface to pressure flow

• Screening Tool• MatLab compiler not producing architecture

independent application)

Page 29: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Miscellaneous

• Present provisional results at ASCE/EWRI in ABQ next May.

Page 30: 7 Sep 2011: Progress Meeting 0-6549 Hydraulic Performance of Staggered- Barrel Culverts for Stream Crossings.

Laboratory Tour

• Visit laboratory and see demonstration of how experiments were conducted.• Underwater video, ADV• Solids motion