7-Part 1-Of Controlling Process

download 7-Part 1-Of Controlling Process

of 56

Transcript of 7-Part 1-Of Controlling Process

  • 8/2/2019 7-Part 1-Of Controlling Process

    1/56

    Monitoring&ControllingProcess

    Group

    (part1)

    PMBOK

    4th

    edition

    By

    PMI

    MENA

    Chapter

    Saturday,October30,2010 PMIMenaChapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    2/56

    Saturday,October30,2010

    PMIMena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    3/56

    Contents

    Saturday,October30,2010

    4.4 Monitor&ControlProjectWork

    4.5 PerformIntegratedChangeControl

    5.4 VerifyScope

    5.5 ControlScope

    6.6 ControlSchedule

    7.3 ControlCost

    8.3 PerformQualityControl

    10.5

    ReportPerformance

    11.6 Monitor&ControlRisk

    12.3 AdministerProcurement

    PMIMenaChapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    4/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    5/56

    Monitor

    and

    Control

    Project

    Work

    Theprocessoftracking,reviewing,andregulatingtheprogresstomeettheperformanceobjectivesdefinedintheprojectmanagementplan.

    Monitoringisperformedthroughouttheproject,andakeyindicatorforprojecthealth.

    Controlincludesdeterminingcorrectiveorpreventiveactionsorreplanningandfollowinguponactionplans

    todetermine

    if

    the

    actions

    taken

    resolved

    the

    performanceissue.

    Saturday,October30,2010 PMIMenaChapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    6/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    7/56

    Monitor

    and

    Control

    Project

    Work

    Saturday,October30,2010 PMIMenaChapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    8/56

    Monitor

    and

    Control

    Project

    Work:

    Inputs

    Performancereports

    Performancereportscanbeusedtoreportthekeyinformationincludingbutnotlimitedto:

    Currentstatus,

    Accomplishments,

    Milestonesstatus,

    Identified

    issues,

    Forecasts

    .

    Saturday,October30,2010 PMIMenaChapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    9/56

    Monitor

    and

    Control

    Project

    Work:

    Inputs

    OrganizationalProcessAssets

    Organizationcommunicationrequirements,

    Financialcontrolsprocedures,

    Issuesanddefectmanagementprocedures,

    Riskcontrolprocedures,

    Processmeasurementdatabaseusedtomakeavailable

    measurementdataonprocessesandproducts, Lessonslearneddatabase.

    Saturday,October30,2010 PMIMenaChapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    10/56

    Monitor

    and

    Control

    Project

    Work:

    Tools

    &

    Tech.

    ExpertJudgment

    Usedbytheprojectmanagementteamtointerprettheinformationprovidedbythemonitorandcontrol

    processes.

    Saturday,October30,2010 PMIMenaChapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    11/56

    Monitor

    and

    Control

    Project

    Work:

    Outputs

    Changerequest

    Changeswhichmayexpand,adjust,orreduceprojectorproductscope,

    Changescanimpacttheprojectmanagementplan,projectdocuments,orproductdeliverables,

    Changesmayincludebutarenotlimitedto:

    Correctiveaction.

    Preventiveaction

    Saturday,October30,2010 PMIMenaChapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    12/56

    Monitor

    and

    Control

    Project

    Work:

    Outputs

    ProjectManagementPlanUpdatesIncludes

    Schedulemanagementplan,

    Costmanagementplan,

    Qualitymanagementplan,

    Scopebaseline,

    Schedulebaseline,and

    Costperformancebaseline

    Saturday,October30,2010 PMIMenaChapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    13/56

    Contents

    Saturday,October30,2010

    4.4 Monitor&ControlProjectWork

    4.5 PerformIntegratedChangeControl

    5.4 VerifyScope

    5.5 ControlScope

    6.6 ControlSchedule

    7.3 ControlCost

    8.3 PerformQualityControl

    10.5

    ReportPerformance

    11.6 Monitor&ControlRisk

    12.3 AdministerProcurement

    PMIMenaChapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    14/56

    PerformIntegratedChangeControl

    Theprocessof:

    Reviewingallchangerequests,

    Approvingchanges,and

    Managingchangestothe:

    Deliverables,

    Organizationprocessassets,

    Projectdocuments,

    and

    Projectmanagementplan.

    Saturday,October30,2010 PMIMenaChapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    15/56

    PerformIntegratedChangeControl

    ThechangemanagementprocessperformedfromprojectInitiationthroughClosing.

    ChangeControlisnecessarybecauseprojectsseldomrunexactlyaccordingtotheprojectmanagementplan.

    Saturday,October30,2010 PMIMenaChapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    16/56

    PerformIntegratedChangeControl

    Theprojectmanagersresponsibilityistomanagechanges.

    Changesdontnecessarilymeannegativeconsequences.

    Changescanproducepositiveresultsaswell.

    Justbecauseachangeisrequesteddoesntmeanthatyouhavetoimplementit.

    Alwaysworktodiscoverthereasonsforthechangeanddetermineiftheyrejustifiable,byknowingthecostofthechange.

    Saturday,October

    30,

    2010

    PMIMenaChapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    17/56

    PerformIntegratedChangeControl

    Thepurposeofthechangemanagementprocessare:

    Identifyingthatachangeneedstooccurorhasoccurred.

    Influencingthefactorsthatcircumventintegratedchangecontrol.

    Reviewingandapprovingrequestedchanges.

    Reviewingandapprovingallrecommendedcorrectiveand

    preventiveactions.

    Documentingthecompleteimpactofrequestedchanges.

    Controllingandupdatingtherequirementsbaseduponapprovedchanges.

    Maintainingtheintegrityofbaselinesbyreleasingonlyapprovedchangesforincorporationintoprojectproductsorservices.

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    18/56

    PerformIntegratedChangeControl

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    19/56

    ChangeControlMeetings

    Achangecontrolboardisresponsibleformeetingandreviewing thechangerequestsandapprovingorrejectingthosechangerequests.

    Therolesandresponsibilitiesofthoseboardsareclearlydefinedandareagreeduponbyappropriate

    stakeholders.

    Allchangecontrolboardsdecisionsaredocumentedand

    communicated

    to

    the

    stakeholders

    for

    information

    and

    followupactions.

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    20/56

    ChangeControlSystem

    Changecontrolsystemsaredocumentedproceduresthatdescribe:

    howtosubmitchangerequests,

    howtomanagechangerequests,and

    themanagementimpactsofthechangesastheypertaintoprojectperformance

    Thechangecontrolsystemdefinesthelevelofauthorityneededtoapprovechanges.

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    21/56

    Therearetwothingsyoushouldrequireatthebeginningofallprojectsregardingchange.

    First,Itisrecommendedthatyourequireallchange

    requeststobesubmittedinwriting.Thisistoclarifythechangeandmakesurenoconfusionexistsregardingwhatisrequested.

    Second,allchangerequestsmustcomethroughtheformalchangecontrolsystem.

    Ifyouallowchangestooccurtotheprojectwhenever

    requested,you

    would

    probably

    never

    complete

    the

    project.

    RequirementsforChange

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    22/56

    ConfigurationManagement

    Configurationmanagementsystemwithintegratedchangecontrolprovideastandardized,effective,andefficientprocesstocentrallymanagechangeswithina

    project.

    Theconfigurationmanagementinclude:

    identifying, documenting,and

    controllingchangestothebaseline.

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    23/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    24/56

    Configurationverificationandaudit

    ensurethecompositionofaprojectsconfigurationitemsiscorrectandthatcorrespondingchangesare:

    registered,

    assessed,

    approved,

    tracked,and

    correctlyimplemented

    ConfigurationManagement

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    25/56

    Configurationstatusaccounting

    informationisrecordedandreportedastowhenappropriatedataabouttheconfigurationitemshouldbe

    provided.

    Thisinformationincludesalistingof:

    approved

    configuration

    identification,

    statusofproposedchangestoconfiguration,and

    theimplementationstatusofapprovedchanges.

    ConfigurationManagement

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    26/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    27/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    28/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    29/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    30/56

    VarianceAnalysis

    Scheduleperformancemeasurements(SV,SPI)areusedtoassessthemagnitudeofvariationtotheoriginal

    baseline.

    Thetotalfloatvarianceisalsoanessentialplanningcomponenttoevaluateprojecttimeperformance.

    Schedulecontrolincludedeterminingthecauseanddegreeofvariancerelativetotheschedulebaselineanddecidingwhethercorrectiveorpreventiveactionisrequired.

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    31/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    32/56

    7CostKnowledgeArea

    7.3 ControlCosts

  • 8/2/2019 7-Part 1-Of Controlling Process

    33/56

    ControlCost

    Influencingthefactorsthatcreatechangestotheauthorizedcostbaseline.

    Assuringthatpotentialcostoverrunsdonotexceedthe

    authorizedfunding.

    Monitoringcostperformancetodetectvariancesfromthecostbaseline.

    Recordingallappropriatechangesaccuratelyagainstthecostbaseline.

    Preventingincorrect,inappropriate,orunauthorizedchanges.

    Informingappropriatestakeholdersofapprovedchanges.

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    34/56

    ControlCost

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    35/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    36/56

    EarnedValue(EV)managementAcronymTermData Element

    PV (BCWS)Planned ValueScheduled Work

    EV (BCWP)Earned ValueEarned Value

    AC (ACWP)Actual CostActualBACBudget at CompletionAuthorized Work

    EACEstimate at CompletionForecasted Cost

    SVSchedule VarianceWork Variance

    CVCost VarianceCost Variance

    VACVariance at CompletionCompletion Variance

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    37/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    38/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    39/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    40/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    41/56

    PerformanceIndex

    CostandScheduleperformanceefficiencycalculations;expressedin$

    CostPerformanceIndex(CPI)

    CPI=EV/AC

    SchedulePerformance

    Index

    (SPI)

    SPI=EV/PV

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    42/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    43/56

    EstimateatCompletion(EAC)

    Themanagementsassessmentofthecostoftheprojectatcompletion

    Aftervarianceanalysis,theestimatedcostatcompletionis

    determine

    AnEACisaforecastofthemostlikelytotalvaluebased

    on

    project

    performance

    and

    risk

    quantification.

    EACistheprojectedoranticipatedtotalfinalvalueforascheduleactivity,WBScomponent,orprojectwhenthe

    definedworkoftheprojectiscompleted.

    Saturday,October

    30,

    2010

    PMIMena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    44/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    45/56

    EACCalculations

    Scenario#2:themostcommonforecastingtechniquesforcalculatingEACusingearnedvaluedataaresomevariationof:

    EACusingremainingbudget.

    EACequalsACCplusthebudgetrequiredtocompletetheremainingwork,whichisthebudgetatcompletion(BAC)minustheearnedvalue(EV).

    Thisapproachismostoftenusedwhencurrentvariancesareseenasatypicalandtheprojectmanagementteamexpectationsarethatsimilarvarianceswillnotoccurinthe

    future. Formula:EAC=ACC+BACEV

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    46/56

    EACCalculations

    Scenario#3:EACusingCPIC.

    EACequalsactualcoststodate(ACC)plusthebudgetrequiredtocompletetheremainingprojectwork,whichis

    theBAC

    minus

    the

    EV,

    modified

    by

    aperformance

    factor

    (oftentheCPIC).

    Thisapproachismostoftenusedwhencurrentvariancesareseenastypicaloffuturevariances.

    Formula:EAC=ACC+((BACEV)/CPIC)

    Eachoftheseapproachescanbethecorrectapproachfor

    anygiven

    project

    and

    will

    provide

    the

    project

    managementteamwithasignaliftheEACforecastsarenotwithinacceptabletolerances.

    Saturday,October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    47/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    48/56

    EarnedValueExample

    CV=EVAC=25002800= 300

    weareoverbudgetby$300

    CPI=EV/AC=2500/2800=0.893

    wearegetting89centsoutofeverydollarweputintheproject

    SV=EVPV=25003000= 500

    wearebehindschedule

    Saturday,

    October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    49/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    50/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    51/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    52/56

    ReportPerformance

    Saturday,

    October

    30,

    2010

    PMI

    Mena

    Chapter

  • 8/2/2019 7-Part 1-Of Controlling Process

    53/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    54/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    55/56

  • 8/2/2019 7-Part 1-Of Controlling Process

    56/56

    ChangeHistoryVer Date Author Reviewe

    rReasonforChange

    1.00 20Nov2009 MohamedAbuSen

    AmalIsmail

    Initialrelease.

    1.10

    30Nov

    2009

    Mohamed

    AbuSen Amal

    Ismail QCslides

    were

    moved

    to

    the

    Quality

    Planningpresentations.

    1.20 6Oct.2010 Amal Dividingcontrollingsessioninto2parts

    Saturday,

    October

    30,

    2010

    PMI

    Mena

    Chapter