    G1 Chile May 15-18, 2006: Structural elements and excavations 2

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Plates and shells

    3 or 5 noded line elements

    3 degrees of freedom per node

    Elastic or elastoplastic behaviour

    To model walls, floors, tunnels

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Input parameters for plates

    Flexural rigidity (b=1 m)

    Normal stiffness (b=1 m)

    Element thickness

    12

    3 bhEEI =

    bhEEA =

    EA

    EIhd 12==

    b

    hh

    b

    b = 1 m in plane strain

    b = 1 meter in axisymmetry

  • 7/22/2019 7 1605 1615 1715 Structural Elements Excavations

    3/13

    G1 Chile May 15-18, 2006: Structural elements and excavations 3

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Plate weights

    Compensate for overlap:

    For soil weight use:unsat above phreatic level

    satbelow phreatic level

    realsoilconcrete dw = )(

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Plate weights for tunnels

    Overlap is only for half the lining thickness

    rinsideroutside

    lining soil

    r

    d real

    ( )outsideinside rrr += 21

    ( ) ( )realsoilrealconcrete ddw 21=

  • 7/22/2019 7 1605 1615 1715 Structural Elements Excavations

    4/13

  • 7/22/2019 7 1605 1615 1715 Structural Elements Excavations

    5/13

    G1 Chile May 15-18, 2006: Structural elements and excavations 5

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Anchor material properties

    Normal stiffness, EA (for one anchor) [kN]

    Spacing, Ls (distance between anchors) [m]

    Maximum anchor force for compression

    and tension, |Fmax,comp| and |Fmax,tens| [kN]

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Pre-stressing of anchors

    Defined in Staged construction phase

    Both tension (grout anchor) or

    compression (strut) possible

  • 7/22/2019 7 1605 1615 1715 Structural Elements Excavations

    6/13

  • 7/22/2019 7 1605 1615 1715 Structural Elements Excavations

    7/13

  • 7/22/2019 7 1605 1615 1715 Structural Elements Excavations

    8/13

    G1 Chile May 15-18, 2006: Structural elements and excavations 8

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Interfaces

    Suggestions for Rinter

    :

    Interaction sand/steel = R inter 0.6 0.7

    Interaction clay/steel = R inter 0.5

    Interaction sand/concrete = R inter 1.0 0.8

    Interaction clay/concrete = R inter 1.0 0.7

    Interaction soil/geogrid = R inter 1.0

    (interface may not be required)

    Interaction soil/geotextile = Rinter 0.9 0.5(foil, textile)

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Interfaces

    Try to omit stress oscillations at corners

    of stiff structures

    Inflexible corner

    points, causing bad

    stress results

    Flexible corner

    points with

    improved stress

    results

  • 7/22/2019 7 1605 1615 1715 Structural Elements Excavations

    9/13

    G1 Chile May 15-18, 2006: Structural elements and excavations 9

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Excavations in Plaxis

    Dennis WatermanPlaxis BV

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Material behaviour

    Unloading due to excavation

    Primary loading due to pre-stressing

    Hardening Soil model is preferred

    Non-linear elastic unloading/reloading behaviour

    Sometimes better to use Mohr-Coulomb with

    known parameters than HS with unverified

    parameters.

    When using MC: Eurshould be used rather than E50

  • 7/22/2019 7 1605 1615 1715 Structural Elements Excavations

    10/13

    G1 Chile May 15-18, 2006: Structural elements and excavations 10

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Material behaviour: Stress paths

    K

    K=1v0

    passivePoint B K

    Kactive

    h

    III III

    Point APoint A

    Point B

    Construction phases: I 1st excavation

    II Pre-stressing anchor

    III Final excavation

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Dewatering

    Wet excavation

    Impermeable (concrete) excavation floor

    Dry excavation Undisturbed water table outside excavation

    Drawdown outside excavation

  • 7/22/2019 7 1605 1615 1715 Structural Elements Excavations

    11/13

  • 7/22/2019 7 1605 1615 1715 Structural Elements Excavations

    12/13

    G1 Chile May 15-18, 2006: Structural elements and excavations 12

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Dewatering: dry excavation

    Undisturbed water table outside excavation

    For every excavation phase do

    Excavate soil

    Set excavated area dry

    Define area just below excavation floor as

    interpolate between lines or clusters

    Suitable for short- term excavations in lowpermeability soils

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Dewatering: dry excavation

    Undisturbed water table outside excavation

    dry

    interpolate

    GPL

  • 7/22/2019 7 1605 1615 1715 Structural Elements Excavations

    13/13

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Dewatering: dry excavation

    Drawdown outside excavation

    For every excavation phase do

    Excavate soil

    Define boundary conditions (heads)

    Perform groundwater flow analysis.

    Suitable for long-term excavations or excavations in

    high permeability soils

    Simplified alternative:

    Draw GPL according to expected groundwater level and

    generate pore pressures based on GPL.

    PLAXIS FINITE ELEMENT CODE FOR SOIL AND ROCK ANALYSES

    Dewatering: dry excavationDrawdown outside excavation

    Groundwater flow calculation gives steady-state solution,

    so for time is infinite!