6FA Generator Major Overhaul

download 6FA Generator Major Overhaul

of 17

Transcript of 6FA Generator Major Overhaul

  • 8/11/2019 6FA Generator Major Overhaul

    1/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    6FA Generator Major Overhaul and Transformer

    Depolarization - Lavera Energies

  • 8/11/2019 6FA Generator Major Overhaul

    2/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Equipment :

    2 turbines GE frame 6 FA/6B 109 MW elec

    2 HSRG with post combustion, output steam flowpower 240t/h at 80 bars

    Cogeneration - Lavra Energies

  • 8/11/2019 6FA Generator Major Overhaul

    3/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    6FA Generator identity card

    Constructor : Alsthom

    Power : 68,9 MVA

    Voltage : 11,5 kV,

    Speed 3 000 tr/h,

    52 300 FFH in 2011

  • 8/11/2019 6FA Generator Major Overhaul

    4/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Generator MO strategy

    Diversity in approach and practice in use internationally :

    Source : Generator maintenance inspection and test programmes, working group

  • 8/11/2019 6FA Generator Major Overhaul

    5/17

  • 8/11/2019 6FA Generator Major Overhaul

    6/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Extraworks

    The bearings generator side and gear box side are damaged : High temperature impacts, one hole detected

    For both bearings clearance out of range

    Replacement of the bearings and several bolts

    Clearance adjusted to 0,6 mm on the base of the new calculation Rotor alignment between load gear and the generator on the base of the

    new clearance value.

  • 8/11/2019 6FA Generator Major Overhaul

    7/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Extraworks

    The slot wedges are moving excessively :

    Risks of damages to the rotor windings

    Vibration risks during the start up

    AEW and Alsthom advice to remove retaining rings and

    resize the slot wedges So the rotor balancing becomes necessary

  • 8/11/2019 6FA Generator Major Overhaul

    8/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Extraworks

    High pollution at the windings surface above the

    retaining rings :

    dry cleaning

  • 8/11/2019 6FA Generator Major Overhaul

    9/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Some global figures

    Cost

    MO order : 128 k

    Scaffolding for the rotor 12 k

    Exciter maintenance 18 k

    CSF maintenance 8 k Craning 8 k

    Retaining rings removal/balancing 76 k

    Miscellaneous 10 k

    TOTAL 260 k

    Planning

    Base : 6 weeks

    Extraworks 6 weeks

    TOTAL 12 weeks

  • 8/11/2019 6FA Generator Major Overhaul

    10/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Extent of problem transformer depolarization

    The report of the working group A2-32, Copper Sulphide inTransformer Insulation describes the issue

    The problem of copper sulphide in transformer insulation is quiteold. However, it is only in the last 15 years that it has gotten very

    much attention, No one has a really good grasp of the extent of the problem.

    Estimates vary, but we can estimate the number of sulphide-related failures are in the range 50 to 100.

    Transformers from several different manufacturers have beeninvolved, and also several different suppliers of oi l.

    The connection with corrosive sulphur in oi ls implemented 10-15years before became evident.

    There is a correlation between e.g.high disulphide contents in

    general (and DBDS content in particular) and the formation ofcopper sulphide. This is complex, and far from well understoodtoday.

  • 8/11/2019 6FA Generator Major Overhaul

    11/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Extent of problem transformer depolarization

    Copper sulphide is a semiconductor. It will normally not be good

    to have such a substance in the insulation. But the presence of

    copper sulphide will not necessarily lead to failure. It will surely

    depend on the amount, as well as the location.

    It seems that basically we have 2 main routes:

    1 Progressively lowered insulation withstand as copper sulphide

    penetrates the insulation. The paper get more or less

    impregnated. In the end it is not insulation any more.

    2. However, it may not always be necessary to have very large

    amounts of sulphide or failures to occur.

    There may be other failure modes as well. Failures often destroy

    the evidence , leaving the field open for speculation

  • 8/11/2019 6FA Generator Major Overhaul

    12/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Extent of problem transformer depolarization

    The approach is to use chemical analysis, to detect the presence

    of potentially harmful sulphur species.

    Some are known to be relevant, such as DBDS content, or total

    disulphide content.

    The important thing to know, is that such tests may not in

    themselves be enough for assessing if an oil is potentially

    harmful or not.

  • 8/11/2019 6FA Generator Major Overhaul

    13/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Mitigation technique

    Four techniques exist : additives

    Oil treatment (for example depolarization)

    Oil exchange

    Modified operating conditions

    The selective depolarization process is used in Italy and France

    since summer 2005, to remove DDBS and reduce corrosiveness.

    We applied this technology to treat the Lavera transformer.

  • 8/11/2019 6FA Generator Major Overhaul

    14/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Depolarization task

    Contractual points : Dalkia started the specific audit / campaign since 2007 for all transformers

    The contractual points / warranty are defined via specific global contract

    13 days off-load treatment maximum

    50 k cost

    DDBS concentration at the end < 10 mg/kg

    DDBS concentration after 6 months < 10 mg/kg. In case of deviation, thesupplier will achieve the additional treatment free of charge

    Historic : 56,7 mg/kg DDBS before and 9 mg/kg after the depolarization

    31 mg/kg after 6 months (additional depolarization implemented)

    Now i ts OK since 12 months

    Leaks on the transformer seal during the start-up, Immediate seals replacement

    3 months later the preventive thermograph control discovered the hotpoint on the transformer connections (154 C instead of 45C)

    Decision to stop the machine (5h)

    Connection cleaning, bol t replacement

    Proper bol t and nut torque process

    Start up and new thermograph control => OK

  • 8/11/2019 6FA Generator Major Overhaul

    15/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Thermograph report

  • 8/11/2019 6FA Generator Major Overhaul

    16/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Hot spot on the connections

  • 8/11/2019 6FA Generator Major Overhaul

    17/17

    ENERGIESLAVERA

    6FA Generator MO and Transformer depolarization

    Thank you for your attention