TRP Chapter 6.6 1 Chapter 6.6 Land disposal

description

NOTES

Transcript of 6.6 With Notes Final

Page 1: 6.6 With Notes Final

TRP Chapter 6.6 1

Chapter 6.6 Land disposal

Page 2: 6.6 With Notes Final

TRP Chapter 6.6 2

Structure of chapter

Introduction

Part A: Key principles of a landfill site

Part B: Handling industrial wastes in municipal landfills as an interim solution - Co-disposal

Part C: Purpose-designed industrial waste landfill sites

Page 3: 6.6 With Notes Final

TRP Chapter 6.6 3

Introduction: Current status of landfill

Many industrialising countries are still practising open dumping

Uncontrolled disposal of hazardous waste on municipal and sanitary landfills

Many sites are unlined, with little management of landfill gas or treatment of leachate

Poor operational standards of sites poses threats to public health and environment

• Short term priorities: •to raise standards•eliminate uncontrolled dumping

• Long term:•some land disposal will still be needed

Page 4: 6.6 With Notes Final

TRP Chapter 6.6 4

Risks of uncontrolled landfillLeachate leakage into groundwater or riversContaminated surface water run-off into soil, watercoursesUncontrolled burningGas migration into soil and air Landslip of unstable wastesFlies and vermin Dust and odoursPoor disposal practices can cause:

•harm to human health - workers, site neighbours and scavengers

•damage to flora•explosions and fires

Page 5: 6.6 With Notes Final

TRP Chapter 6.6 5

Risk mitigationMeasures to mitigate risks include:

• prohibition of certain wastes

• proper site selection

• waste compaction and daily cover

• landfill liners

• gas & leachate collection/treatment

• design & engineering to control waste deposition, water ingress

Page 6: 6.6 With Notes Final

TRP Chapter 6.6 6

Uncontrolled landfill: landslip

Payatas dumpsite, Philippines 2000 Source: http://www.dr-koelsch.de/html/payatas__gb_.html

Page 7: 6.6 With Notes Final

TRP Chapter 6.6 7

Need to raise standards

Chemical fire on European dump site 1993 - example of the risks of mixing hazardous wastes with MSW

Source: David C Wilson

Page 8: 6.6 With Notes Final

TRP Chapter 6.6 8

Part A: Key principles of a landfill site

Page 9: 6.6 With Notes Final

TRP Chapter 6.6 9

Stages in improving landfills

Open dump

Semi controlled landfill

Designated dump

Sanitary landfill

No controls

Dumping kept within designated area; no control over operation

Site supervised; controls over wastes accepted/ waste placement; periodic waste cover

Engineering & operational control measures in place

Industrial waste landfill

Page 10: 6.6 With Notes Final

TRP Chapter 6.6 10

Components of a well-managed landfill operation

Well chosen, properly designed site Bottom liner - to protect soil and groundwater Leachate collection and treatment - to prevent

contamination of groundwater Gas management - to prevent damage to soil and

escape to air Waste placement in cells - for operational control and

to reduce rainfall infiltration Waste compaction - to limit access by vermin and to

reduce risk of fires Daily and intermediate cover Final cover

Page 11: 6.6 With Notes Final

TRP Chapter 6.6 11

Choosing a site

In a depression

- preferred

On level ground

On a slope

Page 12: 6.6 With Notes Final

TRP Chapter 6.6 12

Improving municipal landfill practice:

site considerations

Need to take into account:•geological & hydrological characteristics

eg drinking water sources in vicinity, areas liable to flooding or erosion

•proximity to urban areas

Preferred sites may include: •sites containing thick clay layer •sites above unusable groundwater

Page 13: 6.6 With Notes Final

TRP Chapter 6.6 13

Siting a landfill: example

Suitable for site with: level land surfacelow groundwater tablesoil layer thicker than 2 metres

Solid waste management for economically developing countries, ISWA, 1996

Page 14: 6.6 With Notes Final

TRP Chapter 6.6 14

Site design - liner systems Single liner Clay or synthetic liner Composite or double lined One clay liner and one synthetic liner Two synthethetic liners

Liner selection criteria:CostLocal geology and hydrogeologyAvailability of appropriate materialsDesired degree of protection against leachate escapeLiner durability

Page 15: 6.6 With Notes Final

TRP Chapter 6.6 15

Site design - liner materials

Natural lining materials Synthetic lining materials Clay Polyethylene Bentonite liners - HDPE Pulverised Fuel Ash (PFA) - LDPE

Polyvinyl chlorine (PVC) Chlorinated polyethylene

Page 16: 6.6 With Notes Final

TRP Chapter 6.6 16

Cross-section of multiple liner system

Geotextile filter

Stone/ gravel layerPrimary geomembrane layer

Primary and secondary leachate collection piping

Secondary geomembrane layer

Secondary leachate collection layer acts as leak detection

Compacted clay

Page 17: 6.6 With Notes Final

TRP Chapter 6.6 17

Drainage pipes in a composite liner system

Source: Landfill of hazardous wastes, Technical report No 17, UNEP

Site design - leachate control

Page 18: 6.6 With Notes Final

TRP Chapter 6.6 18

Site design - landfill gas management

Gas components Typical values % RisksMethane 63.8 ExplosionCarbon dioxide 33.6 AsphyxiationNitrogen 2.4Oxygen 0.16 Fire Hydrogen 0.05Other trace gases Toxicity

Gas monitoring by:•surface and sub-surface

monitoring•excavated pits•boreholes and wells

Gas end uses: Fuel eg in vehicles, boilers,

kilns & furnaces

Power eg gas turbines, diesel engines

Page 19: 6.6 With Notes Final

TRP Chapter 6.6 19

Site preparation

Fencing to control access

Page 20: 6.6 With Notes Final

TRP Chapter 6.6 20

Site operation

Key factors:

•Waste placement in cells

•Waste compaction

•Daily and intermediate cover

•Final cover

Page 21: 6.6 With Notes Final

TRP Chapter 6.6 21

Cellular structure

Source: ISWA, Solid waste management for economically developing countries, 1996

Page 22: 6.6 With Notes Final

TRP Chapter 6.6 22

Waste compaction

•Maximises void space

•Reduces risk of fires in waste

•Deters vermin

Page 23: 6.6 With Notes Final

TRP Chapter 6.6 23

Purpose of

cover

Improves site appearanceMinimises wind-blown litterReduces landfill odoursInhibits colonisation by vermin & vectorsReduces rainwater infiltration thus reducing leachateControls gas and leachate migrationReduces soil erosion

Page 24: 6.6 With Notes Final

TRP Chapter 6.6 24

Final cover

Vegetation

Top cover

Drainage layer

Clay layer

Aims:• to stabilise site• improve its

appearance • enable post-

closure use

Final cover must be: •durable •flexible

•weather resistant•regularly inspected & maintained

Page 25: 6.6 With Notes Final

TRP Chapter 6.6 25

Completed landfill - cross section

Page 26: 6.6 With Notes Final

TRP Chapter 6.6 26

Part B:Handling industrial wastes in

municipal landfills as an interim solution - Co-disposal

Page 27: 6.6 With Notes Final

TRP Chapter 6.6 27

Basic requirements for co-disposal

• Control the waste that comes in• require pretreatment of some wastes • exclude some wastes eg flammable liquids • test wastes • keep detailed records

• Improve waste reception and handling systems • Employ skilled, trained staff

Page 28: 6.6 With Notes Final

TRP Chapter 6.6 28

Testing and record keeping • Important to know what is being handled• A testing and record keeping regime should be introduced when upgrading an existing site or starting a new one

• Enables detailed tracking of wastes from point of generation to location in completed site

Hazardous wastes should be tested:• prior to acceptance to ensure appropriate disposal and

waste compatibility • again on delivery to verify composition

Waste details must be recorded and records stored safelyRecords should provide:

• details of sources - waste generator, transport contractor• composition, form and quantity of wastes• date of placement• exact location in site

Page 29: 6.6 With Notes Final

TRP Chapter 6.6 29

Compatibility of hazardous wastes

One of the reasons for upgrading is to reduce the potential for harm from the uncontrolled mixing of incompatible hazardous wastes

Page 30: 6.6 With Notes Final

TRP Chapter 6.6 30

Co-disposalCo-disposal is the disposal of selected hazardous wastes with other heterogeneous wastes such as biodegradable municipal solid waste, industrial & commercial wastes • it takes place in properly managed sanitary landfill• it is a highly skilled and technically controlled operation• it is suitable for selected solid and sludge wastes at controlled

rates of application• it uses the physical, chemical and biological processes

within an MSW landfill to ‘treat’ hazardous constituents• it is not the same as uncontrolled mixing of hazardous wastes

and MSW

Page 31: 6.6 With Notes Final

TRP Chapter 6.6 31

Co-disposal - considerations & status

Co-disposal needs great care because: – both hazardous wastes and MSW are variable and

complex – it is difficult to predict chemical & biological

reactions Co-disposal: has been discredited by uncontrolled past practice has been widely practised in parts of Europe eg UK is being phased out under EU Landfill Directive requirements is worth considering as short-medium term option is better than uncontrolled disposal

Page 32: 6.6 With Notes Final

TRP Chapter 6.6 32

Wastes suitable for co-disposal

Bottom ash from waste incineration Contaminated soils Heavy metal hydroxides (pH > 8) Slag, bitumen waste Oil sludges, paint sludges, tannery sludges

AVOID aqueous wastes, bulk liquid wastes AVOID mixing incompatible wastes CHECK wastes compatible with liner material

Page 33: 6.6 With Notes Final

TRP Chapter 6.6 33

Co-disposal - maximum concentrations

Waste ConcentrationAcid wastes 0.1m3 acid / tonne of MSW

Heavy metals waste 100g soluble chromium, copper, lead,

arsenic, nickel or zinc /tonne of MSW

10g cadmium / tonne of MSW

2g soluble mercury / tonne of MSW

Phenolic wastes 2kg of total phenols / tonne of MSW

Cyanide wastes 1g/ tonne of MSW

Total organic carbon 5kg / tonne of MSW

Oil, grease and 2.5 kg waste/ tonne of MSW

hydrocarbon wastesSource: World Bank Technical paper 93

Page 34: 6.6 With Notes Final

TRP Chapter 6.6 34

Components of a well-managed co-disposal operation

A continuing supply of municipal waste Trained operational manager and staff Sufficient mobile equipment for site preparation No scavenging should be permitted No direct burning of waste on site Ensure only suitable waste types are deposited -

need to test all wastes prior to acceptance Check and record waste types and their origin at

the site entrance Supervised disposal at landfill face or in trenches

or pits dug into MSW at least 6 months old Regular inspections on site

Page 35: 6.6 With Notes Final

TRP Chapter 6.6 35

Co-disposal site infrastructure 1Separate areas of landfill should used for different hazardous waste typesRoadways should be clearly signpostedTrenches should be clearly marked and fencedWheel cleaners should be provided for vehicle entrance and exitLaboratory facilities should be available on site for simple analysisHolding area is needed for lorries to be checkedStorage area

Page 36: 6.6 With Notes Final

TRP Chapter 6.6 36

Co-disposal site infrastructure 2

Source: World Bank Technical Paper No 93

Area for future co-disposal in trenches

Page 37: 6.6 With Notes Final

TRP Chapter 6.6 37

Hazardous waste placement - practicalities

At landfill face:

•suitable only for small quantities of solid waste

Trenches or pits dug into MSW:

•MSW at least 6 months old

•thick layer of MSW below pit

•cover after deposit

•for particuarly difficult wastes, seal pit after each deposit

•all operations must be supervised

Page 38: 6.6 With Notes Final

TRP Chapter 6.6 38

Co-disposal case study Asbestos waste

Aim:

Containment, preventing human contact with, or airborne release of, asbestos

Process: •All wastes must be delivered in double-wrapped, sealed bags

or containers

•No mechanical handling or compaction which may damage containment

•Pits should be excavated in advance

•Bags/containers should be placed into pit

•Pit covered and sealed immediately

•Location recorded to prevent future re-excavation

Page 39: 6.6 With Notes Final

TRP Chapter 6.6 39

Part C:Purpose-designed industrial waste

landfill sites

Page 40: 6.6 With Notes Final

TRP Chapter 6.6 40

Option 1: multi-disposalRequires secure landfill site dedicated to disposal of hazardous wasteSite must be:

•Highly engineered•Have discrete cells for different waste types, separated

by barriers•Designed to:

•resist leakage•segregate incompatible wastes•contain waste in a safe manner•prohibit contact between landfill contents and

surrounding environment

Method commonly used in USA

Page 41: 6.6 With Notes Final

TRP Chapter 6.6 41

Wastes suitable for disposal in multi-disposal site

• Drummed and bulky solids

• Pretreated sludges

• Metal-finishing wastes eg lead-, chromium-, copper- and nickel-bearing wastes

• Contaminated soils

• Incinerator ash

Page 42: 6.6 With Notes Final

TRP Chapter 6.6 42

Multi-disposal site design

Source: Hazardous wastes, sources, pathways, receptors, Richard J. Watts, 1997

Page 43: 6.6 With Notes Final

TRP Chapter 6.6 43

Multi-disposal site operationCheck waste compatibility Control types of HW waste to be buried Place chemical HW in groups of stacked

containersSeparate cells from each other by fillRecord different HW types and their originDevise emergency plan for spills and accidentsRequire the use of heavy machineryProvide training for all personnelEnsure health and safety of operators

Page 44: 6.6 With Notes Final

TRP Chapter 6.6 44

Source ???

Section through multi-disposal site

Page 45: 6.6 With Notes Final

TRP Chapter 6.6 45

Option 2: Secure landfill of stabilised wastes

Driven by regulationsAccepts only cement-stabilised wastes,

possibly certain other solid wastes

Simplifies managementEnables higher level of regulatory control

Standard practice in EU and increasingly in other countries

Page 46: 6.6 With Notes Final

TRP Chapter 6.6 46

Basic principles of secure landfill of stabilised wastes

Similar to sanitary landfill:

•engineered, lined, top cover

•cellular design/layout

Each cell filled with stabilised wasteExamples of secure landfill for stabilised hazardous waste include: •Ratchaburi secure landfill, Thailand Capacity 100,000 tonnes of HW

Shenzhen secure landfill, China Capacity 23,000 cubic metres of HW

Page 47: 6.6 With Notes Final

TRP Chapter 6.6 47

Adaptation of secure landfill of stabilised hazardous wastes

Relies on structural properties of stabilised waste

• Cement-stabilised wastes built up either in discrete blocks or monolithic ‘celluar hills’

• Each batch left for a period to monitor structural strength before continuing to build the landfill

Page 48: 6.6 With Notes Final

TRP Chapter 6.6 48

Option 3: The ‘ultimate’ landfillConsists of:

• lined concrete basin

• movable roof

• wastes placed by overhead crane

• may accept a variety of solid wastes

• each cell topped by concrete

Pictures show AVR site in The Netherlands

Page 49: 6.6 With Notes Final

TRP Chapter 6.6 49

Chapter 6.6 Summary

•Need to control landfill, to mitigate risks - open dumping not acceptable

•Stages in upgrading and design, and operational standards necessary

•Co-disposal as an interim solution - requires good management, skilled staff

•Purpose-designed landfill for hazardous wastes