6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

27
6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT Presented by Eyob Yehayis

description

6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT. Presented by Eyob Yehayis. 1. Project Area Description. Bililo spate is located at 42.75 N and 9.233E The average altitude is 1450 m. The annual mean rain fall is 757.15 mm. The annual effective RF=579.4mm - PowerPoint PPT Presentation

Transcript of 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Page 1: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

6.12aDESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Presented by Eyob Yehayis

Page 2: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT
Page 3: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

1. Project Area Description

Bililo spate is located at 42.75 N and 9.233E The average altitude is 1450 m. The annual mean rain fall is 757.15 mm. The annual effective RF=579.4mm T max=31.6 and T min=15.6 oc The Annual mean ETo=1902.77mm

Page 4: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

1. Project Area Description Continued… The cropping season starts in 15th

march dominantly they produce sorghum.

The crop water required during the cropping season 579.14 mm.

The total effective rainfall during the cropping season is 338 mm.

Irrigation required = CWR-ERF = 259.69 mm

Page 5: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

1. Project Area Description Continued…

The watershed Area is 157 km2 of which above 70% of it is covered by forest and scattered bushes, the rest is farmland.

About 25% of the cathment has a slope>28 %

The Project is almost it is a newly designed spate irrigation scheme.

Page 6: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

2 The basic assumptions used for the

project. The system should be easy for farmers to

operate and not require the large inputs of labor or other resources to maintain.

The system should prevent large and uncontrolled flood flows from damaging canals and field systems.

The system should Continue to function with high rates of sedimentation on the fields and canal beds.

Page 7: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

3 Structural Component of The System

4.1 Weir (Diversion Head work)

4.2 Canal and Canal Structures

Page 8: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

3.1 Weir (Diversion Head work)

The head work is modified to discharge the excess flood that is expected to come in 50 year return period.

Accordingly , the maximum flood for 50 years Return period is 110 3/s.

Designed to provides the required head to command the Farmland.

The intake canal sill level is 0.3 m above under sluice level.

Page 9: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

3.2 Canal and Canal Structures

3.2.1 Flood Canal (Main canal)The design canal capacity is determined by the following assumptions: The recession flood stays for 5 days The farm land is provided with 25 cm flood water

on one irrigation. Farm land have chance of getting 2 flood water

irrigation during the growing season. The resulting design capacity is 3 m3/s for 500ha.

Page 10: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

4.2. Flood Canal cont’ed…

The canal cross section and bed slope is designed on the maximum permissible velocity which satisfy 60% design flow to avoid the silt deposition on canal bed at lower flow.

Some of the canal cross section which passes porous and cliff formation is lined with masonry.

The secondary canal capacity is designed by proportioning the hectare it develops and multiplying by flood duration day ( 5 days).

Page 11: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

4.2.1 Flood Canal cont’ed…

Generally The System has:

-Earthen canal

on main canal 5 km

on secondary canal 10.5km, 11 in number

-Lined canal

on main canal 2.3 km

Page 12: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

4.2.2 Canal Structures

The system is provided with different farm structures which satisfies the hydraulic performance and structural stability depending on the land topography.

Accordingly, on the main canal there are: 4 vertical drops 32 inclined drops 7 of which on secondary canal 1 flume 5 division box 4 chute 2 of which on SC1 3 Road crossing culverts

Page 13: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

5 Water Management

It is assumed that only 1/5 of the command area is irrigated in one day starting from upstream toward the down stream. This could be changed based on the community interest.

Page 14: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

6 Problem encountered

Estimating the frequency, amount and duration of the flood water in un gauged rivers.

Estimating the sediment yield with the respective runoff.

Page 15: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Head Work

Page 16: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Downstream face of Weir

Page 17: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Downstream of Headwork

Page 18: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Flood water entering the canal

Page 19: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Rejection spillway

Page 20: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Lined canal

Page 21: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Canal running along the cliff

Page 22: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Flume upstream

Page 23: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Division box with drop

Page 24: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT
Page 25: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Secondary canal under construction

Page 26: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Recession flow

Page 27: 6.12a DESIGN APPROACH ON BILILO SPATE IRRIGATION PROJECT

Canal Silting