6 TH-53
-
Upload
devsoth-naresh -
Category
Documents
-
view
1 -
download
0
description
Transcript of 6 TH-53
-
Proceedings of Indian Geotechnical Conference
December 22-24,2013, Roorkee
Page 1 of 6
SOIL IMPROVEMENT USING ACCELERATED CONSOLIDATION
TREATMENT TO IMPROVE LOAD BEARING OF SOFT SOIL
S. Sahu ,* Manager (India), Menard Asia, New Delhi, [email protected]
P.J.Rao,* Consulting Engineer, Faridabad, [email protected]
K.Yee, * Regional Director, Menard Asia, KaulaLampur, [email protected]
ABSTRACT: Roads constructed on high embankments underlain by soft strata are susceptible to long term
settlements which may lead to the recurring maintenance requirements. The utilization of conventional method of
removal and replacement of unsuitable material with suitable compacted fill for embankment construction over
shallow marginal ground has been common practice in India, in the past. Due to the need for speedy and
economical construction, and current stringent environmental requirements, more options need to be considered. In
many such cases, Ground Improvement proved to be a good solution by modifying the soil characteristics with or
without the addition of imported materials.
The paper describes the case study of a project executed in Malaysia where the height of the embankment varies
from 5m to 16m. It was initially envisaged to remove and replace the unsuitable materials to depth up to 6m with
ground water table at the surface. Due to construction constraints, cost of fill materials and the non-favorable
environmental impact assessment (EIA), an alternative ground improvement solution using a combination of
dynamic replacement (DR) and prefabricated vertical drains (PVD) was carried out to provide the necessary
foundation treatment for the road embankment.
INTRODUCTION
Putrajaya Road network in Malaysia involved
construction of an embankment on marginal
ground. The height of the embankment varies from
5m to 16m. It was envisaged to remove and replace
the unsuitable materials to a depth up to 6m with
ground water table at the surface. Due to
construction constraints, cost of fill materials and
the non-favorable environmental impact
assessment (EIA), an alternative ground
improvement solution using a combination of
dynamic replacement (DR) and prefabricated
vertical drains (PVD) was carried out to provide
the necessary foundation treatment for the road
embankment.
PRINCIPLE OF DYNAMIC REPLACEMENT
AND VERTICAL DRAINS
Dynamic replacement (DR) is a ground
reinforcement technique whereby stiff elements
are introduced as inclusions in the ground by heavy
tamping with the main benefit resulting from the
structural aspect of the elements themselves. A
composite soil-element structure, interacting
through friction and adhesion, increases the
bearing capacity, improves stability and reduces
settlement. Inclusion materials are granular
materials such as sand, aggregate, stone and/or
rock pieces (up to 300mm size).The technique
starts out by creating a crater with light tamping.
The craters are then backfilled with granular
materials that will lock together under subsequent
heavy tamping. This technique essentially results
in large columns of compacted granular material
up to 2.53m in diameter. Because of the higher
permeability of this granular backfill material,
pore-water pressure from the underlying and
surrounding soft soils will dissipate quickly.
Hence, DR columns besides being load bearing
columns (with bearing capacity even up to 80 tons)
also serve as large vertical granular drains. Since
spacings of DR columns are typically between 4m
to 7m, prefabricated vertical drains (PVD) were
installed between columns to further speed up
therate of consolidation. Unlike DR columns, PVD
do not serve any structural function. A typical
dynamic replacement process is show in Figure 1.
-
S. Sahu, P. J. Rao & K. Yee
Page 2 of 6
Fig. 1 Dynamic Replacement Process
GROUND CONDITIONS
The site was located in a low-lying broad valley
between low hills. Ground water table was about
0.3m below surface. Exploratory boreholes and
cone penetration tests (CPT) (Figure 2) were
carried out which indicated an upper layer of very
soft soils varied from46m thick with organic peat
interspersed in places up to 2m thick; overlying
stiff silt/clay layer down to refusal depth at about
11m. A summary of soil properties is given in
Table 1.
Field vane shear tests were carried out and the
results are shown in Figure 3. The Suvane values
were corrected according to Bjerrum (1972) with
correction factor l = 0.8 based on plasticity index
of 50. The average Su= 13 kN/m2 was used and it
is compared with the average CPT qc= 0.23MPa
for the soft layer which corresponds to Su= 15
kN/m2.
Fig: 2 Cone penetration test result
Fig. 3 Field vane shear test result
Table 1: Ground Condition and SPT Results
Depth Material SPT N Atterberg
Limits
UU Triaxial
compression
1-D
Consolidation
0-4 m Very soft silty clay with
organic material (peat) and
traces of sand
0 Wn ~ 75%
LL ~ 79%
PL ~ 29%
PI ~ 50%
C ~ 9-13kN/m2
= 0o
Pc ~ 36-50 kPa
Cc ~ 0.43-0.7
4-5 m Soft clayey silt 2-4
5-11 m Firm sandy silt /
stiff silty clay
6-11
> 24
-
Soil Improvement using accelerated consolidation treatment to improve load bearing of soft soil
Page 3 of 6
The coefficient of vertical consolidation (Cv)
varied from 1.17 to 1.91m2/y with an average of
1.5m2/y. Based on the liquid limit of
79%,NAVFAC(1982) suggests a Cv= 1.36m2/y.
For design, Cv= 1.5m2/y and Ch= 3Cv= 4.5m
2/y
(Chbeing the coefficient of horizontal
consolidation) were adopted. The CPT dissipation
test results suggested an in-situ Ch= 4.1 to 5.1m2/y
based on Houlsby&Teh (1988).
PERFORMANCE CRITERIA
The height of the embankment varies from 5m to
16m with a crest width of 49m to 250m, wider
towards the interchange. The slope was at 1V:2H
with intermediate berm at every 6m height.
The performance criteria are as follows:
a) Total settlement within the first 7 years of
service shall not exceed 10%of the sum of the total
theoretical primary settlement and secondary
settlement, the later being assessed for a period of
20 years;
b) Settlement within the first 7 years of service
shall nowhere exceed 400mm;
c) In areas of transition between piled approach
embankments and general low embankments,
differential settlement within the first 7 years of
service shall not exceed 100mm within a length of
50m. In areas remote from structures and transition
zones, differential settlement shall not exceed
100mm within a length of 100m.
d) The factor of safety against instability during
construction shall not be less than 1.2 and after
construction not less than 1.5.
DESIGN SCHEME
Since the construction period was limited to 12
months, in order to achieve the required
performance criteria in such a short duration it
became important to accelerate the consolidation
process which was not possible to achieve just by
placing surcharge or using only PVDs with
surcharge. A combination of DR columns and
PVD is deemed necessary. The required drainage
is provided by the DR columns and PVD. In
addition, the DR columns also serve as a bearing
support to the embankment so that the required rate
of filling of embankment can be achieved with
adequate support of the embankment by its
foundation during the construction stage as well as
end-of-construction stage. Without DR columns,
the rate of filling as well as the final height of the
embankment may be limited.A closer grid of DR
columns and PVD was constructed below the slope
of the embankment to provide edge reinforcement
for stability. It followed by a wider grid of DR
columns and PVD constructed below the crest of
the embankment for normal bearing support.
FIELD CALIBRATION
A field calibrationwas carried out on an area of
500m2 to determine the operational parameters
(e.g. nos. of blows, drop height, etc.) and to
validate design assumptions prior to
commencement of full production works. PVDs
were installed to an average depth of 56m
followed by the construction of the DR test
columns.
Length of DR columns varied from 4m to 5m. Pre
and post treatment pressuremeter tests (PMT) and
CPT were carried out inside the DR columns and
in-between the columns. The post treatment tests
were carried out after 14 days. The characteristic
PMT and CPT values are as given in Table 2.
Table 2: Characteristic PMT and CPT Values
Description
PMT CPT
Limit
Pressure
PL
Pressure-
meter
modulus
Cone
Resistance
qc
Inside DR
Columns 1070 kPa 7500 kPa 9MPa
In-between
DR Columns 620 kPa 3950 kPa 2MPa
FIELD TESTING IMPLEMENTATION &
EVLUATION
The depth of treatment, as defined by the
pretreatment CPT and PMT results; followed by
installation of PVD and DR works; and post
treatment PMT for quality control and assurance.
The total treatment area was about 102,000m2. A
total of 78 CPTs and 36 PMTs were carried out
prior to PVD and DR works. The post-treatment
PMT tests were carried out, 14 days after the
completion of works but, before commencement of
embankment filling. During embankment
-
S. Sahu, P. J. Rao & K. Yee
Page 4 of 6
construction, settlement readings from settlement
plates placed at 50m distance were analyzed using
Asoaka (1978) method to predict the final
settlement. Lateral deformations from
inclinometers were analyzed usingMatsuo &
Kawamura (1977) method for stability assessment.
The criterion of b < 0.25 being the ratio of lateral
to vertical movement was used for embankment
stability control.
Settlement analysis was carried out based on Eq.
(1) and (2) given by Terzaghi (1967). The soil was
assumed to be normally consolidated.
(
)
(
)
(2)
Where, Cr= recompression index; Cc= compression
index; pc= maximum past pressure; = overburden effective stress; = final pressure; eo= initial void ratio and LL = liquid limit.
Based on the above equations, the computed
settlement without DR columns (SW/ODR) varies
from 95 cm to 150 cm for embankment height
ranging from 5m to 16m. With the DR columns,
the stiffness modulus of the composite soil-column
system is increased and hence, settlement is
reduced. The measured settlement (SDR) obtained
from settlement plates placed along the centreline
of the embankment ranged from 32 cm to 65 cm.
Thus, it is evidenced that the DR columns have
reduced the settlement and improved the
performance of the subsoil in comparison to the
state without DR columns.
Further the field results were compared with the
Priebe (1995) predictions of settlement defined by
an improvement factor n (=SW/ODR/ SDR). The
friction angle of the DR column material was
estimated from the limit pressure, PL (Centre
dEtudes, Menard 1970) measured inside the DR
pillar. The computation for improvement factor n
is given in Table 3.
Maximum settlement of 65 cm was recorded at
chainage 500 (i.e. about center of treatment area)
where the soft layer was at maximum 6m thick and
the embankment height was at 8.4m. The
settlement characteristic is shown in Figure 4. The
computed settlement without DR columns is about
135 cm. Hence, the improvement factor n is 2.07
compared with 1.96 as computed. Hence, the
Priebe (1995) method can provide a reasonable
estimation of settlement reduction with DR
columns in this project.
Table 3: Computation for improvement factor n
DR Columns
Column diameter 2.9 m
Grid spacing (square) 5.5 m
Replacement Ratio (m) 22%
Friction Angle (c) 34o
Area of Column (Ac) 6.61 m2
Grid Area (A) 30.3 m2
Coef. of earth pressure
(KAC)
0.28
F (s, Ac/A) 0.95
Improvement factor n 1.96
The rate of settlement reduced from a peak of
about 10mm per day during the early stage of
construction to 0.1mm per day at later stage of
construction. The ratio of lateral to vertical
movement (b = dhor/dver) was highest at 0.22 during
the early stage of filling and reduced quickly to
0.03 after much consolidation has occurred. The
maximum total lateral movement recorded was
about 13cm at the highest embankment.
BENEFICIAL EFFECTS
Since the rate of consolidation is affected by the
available drainage facilities and the rate of filling
of embankment, the main beneficial effect of using
DR columns in combination with PVD is that the
rate of filling of embankment can be accelerated as
illustrated in Figure4. During the early stage of
construction, 2.5m of fill was placed over a period
of 14 days and 4m of fill was completed in 30
days, averaging about 1m per week. Without DR
columns, the rate of filling may be limited to the
-
Soil Improvement using accelerated consolidation treatment to improve load bearing of soft soil
Page 5 of 6
Fig 4: Settlement Characteristics at Ch. 500
bearing capacity of the soft soil, typically at about
0.4m0.5mperweek evenwith PVD. Also, the
increased rate of consolidation is evidenced by the
gradient of the time-settlement curve. The rate of
settlement (mm/day) shows that most of the
settlement has been achieved during construction
stage. DR columns and the corset effect provided
the necessary stability. Stability analyses indicated
factors of safety greater than 1.25 at all stages of
construction. During construction, lateral stability
with ratio b < 0.25 was maintained. Hence, the
beneficial effect of DR columns to serve as load
bearing columns and providing vertical drainage in
combination with PVD especially during the early
stages of construction has been demonstrated here.
CONCLUSION
The design, implementation and performance of a
combination of dynamic replacement columns and
prefabricated vertical drains for the construction of
a high embankment on marginal ground are
reported. The beneficial effects were demonstrated
through the accelerated built-up of the
embankment, accelerated rate of consolidation,
reduced postconstruction settlement; stability of
the embankment during construction as well as end
of construction and the reduced carbon footprint
compared with the exhibited method of removal
and replacement. This case history has highlighted
a ground improvement scheme that is suitable for
the construction of high embankment founded on
-
S. Sahu, P. J. Rao & K. Yee
Page 6 of 6
shallow deposit of soft soils with time constraint
and promotes sustainable construction.
REFERENCES
1. Bjerrum L. (1972), Embankments on Soft Ground, Proceedings Specialty Conference on
Performance of Earth and Earth Supported
Structures, ASCE, Vol. 2, pp. 154.
2. NAVFAC (1982)., Design Manual 7.01 Soil Mechanics, Alexandria, V.A. Department of
the Navy, Naval Facilities Engineering
Command
3. Houlsby G. T. and Teh C. I. 1988), Analysis of the Piezocone in Clay, Penetration Testing
1988, ISOPT-1,ed. De Ruiter, Balkema (Pubs.),
Rotterdam
4. Asaoka A. (1978), Observational Procedure of Settlement Prediction, Journal of Soils and
Foundations 18(4) 87101.
5. Matsuo M. and Kawamura K. (1977), Diagram for Construction Control of Embankment on
Soft Ground, Journal of Soils and Foundations
17(3) 3752.
6. Priebe H. J. (1995), The Design of Vibro Replacement, Ground Engineering, pp. 3137.
7. Centre dEtudes Menard, Determination de la PousseeExercee par un Sol Su rune Paroi de
Sourenement (1970), Publication D/38/70.
8. Lambe T. W. and Whitman R. V. (1968), Soil Mechanics JohnWiley& Sons (Pubs.), New
York, p. 553.
9. Terzaghi K. and Peck R. B. (1967), Soil Mechanics in Engineering Practice: 2nd
edition, JohnWiley and Sons (Pubs.), New
York, p. 729.