6 TH-53

6
Proceedings of Indian Geotechnical Conference December 22-24,2013, Roorkee Page 1 of 6 SOIL IMPROVEMENT USING ACCELERATED CONSOLIDATION TREATMENT TO IMPROVE LOAD BEARING OF SOFT SOIL S. Sahu ,* Manager (India), Menard Asia, New Delhi, [email protected] P.J.Rao,* Consulting Engineer, Faridabad, [email protected] K.Yee, * Regional Director, Menard Asia, KaulaLampur, [email protected] ABSTRACT: Roads constructed on high embankments underlain by soft strata are susceptible to long term settlements which may lead to the recurring maintenance requirements. The utilization of conventional method of removal and replacement of unsuitable material with suitable compacted fill for embankment construction over shallow marginal ground has been common practice in India, in the past. Due to the need for speedy and economical construction, and current stringent environmental requirements, more options need to be considered. In many such cases, Ground Improvement proved to be a good solution by modifying the soil characteristics with or without the addition of imported materials. The paper describes the case study of a project executed in Malaysia where the height of the embankment varies from 5m to 16m. It was initially envisaged to remove and replace the unsuitable materials to depth up to 6m with ground water table at the surface. Due to construction constraints, cost of fill materials and the non-favorable environmental impact assessment (EIA), an alternative ground improvement solution using a combination of dynamic replacement (DR) and prefabricated vertical drains (PVD) was carried out to provide the necessary foundation treatment for the road embankment. INTRODUCTION Putrajaya Road network in Malaysia involved construction of an embankment on marginal ground. The height of the embankment varies from 5m to 16m. It was envisaged to remove and replace the unsuitable materials to a depth up to 6m with ground water table at the surface. Due to construction constraints, cost of fill materials and the non-favorable environmental impact assessment (EIA), an alternative ground improvement solution using a combination of dynamic replacement (DR) and prefabricated vertical drains (PVD) was carried out to provide the necessary foundation treatment for the road embankment. PRINCIPLE OF DYNAMIC REPLACEMENT AND VERTICAL DRAINS Dynamic replacement (DR) is a ground reinforcement technique whereby “stiff” elements are introduced as inclusions in the ground by heavy tamping with the main benefit resulting from the structural aspect of the elements themselves. A composite soil-element structure, interacting through friction and adhesion, increases the bearing capacity, improves stability and reduces settlement. Inclusion materials are granular materials such as sand, aggregate, stone and/or rock pieces (up to 300mm size).The technique starts out by creating a crater with light tamping. The craters are then backfilled with granular materials that will lock together under subsequent heavy tamping. This technique essentially results in large columns of compacted granular material up to 2.53m in diameter. Because of the higher permeability of this granular backfill material, pore-water pressure from the underlying and surrounding soft soils will dissipate quickly. Hence, DR columns besides being load bearing columns (with bearing capacity even up to 80 tons) also serve as large vertical “granular” drains. Since spacing’s of DR columns are typically between 4m to 7m, prefabricated vertical drains (PVD) were installed between columns to further speed up therate of consolidation. Unlike DR columns, PVD do not serve any structural function. A typical dynamic replacement process is show in Figure 1.

description

6thtc

Transcript of 6 TH-53

  • Proceedings of Indian Geotechnical Conference

    December 22-24,2013, Roorkee

    Page 1 of 6

    SOIL IMPROVEMENT USING ACCELERATED CONSOLIDATION

    TREATMENT TO IMPROVE LOAD BEARING OF SOFT SOIL

    S. Sahu ,* Manager (India), Menard Asia, New Delhi, [email protected]

    P.J.Rao,* Consulting Engineer, Faridabad, [email protected]

    K.Yee, * Regional Director, Menard Asia, KaulaLampur, [email protected]

    ABSTRACT: Roads constructed on high embankments underlain by soft strata are susceptible to long term

    settlements which may lead to the recurring maintenance requirements. The utilization of conventional method of

    removal and replacement of unsuitable material with suitable compacted fill for embankment construction over

    shallow marginal ground has been common practice in India, in the past. Due to the need for speedy and

    economical construction, and current stringent environmental requirements, more options need to be considered. In

    many such cases, Ground Improvement proved to be a good solution by modifying the soil characteristics with or

    without the addition of imported materials.

    The paper describes the case study of a project executed in Malaysia where the height of the embankment varies

    from 5m to 16m. It was initially envisaged to remove and replace the unsuitable materials to depth up to 6m with

    ground water table at the surface. Due to construction constraints, cost of fill materials and the non-favorable

    environmental impact assessment (EIA), an alternative ground improvement solution using a combination of

    dynamic replacement (DR) and prefabricated vertical drains (PVD) was carried out to provide the necessary

    foundation treatment for the road embankment.

    INTRODUCTION

    Putrajaya Road network in Malaysia involved

    construction of an embankment on marginal

    ground. The height of the embankment varies from

    5m to 16m. It was envisaged to remove and replace

    the unsuitable materials to a depth up to 6m with

    ground water table at the surface. Due to

    construction constraints, cost of fill materials and

    the non-favorable environmental impact

    assessment (EIA), an alternative ground

    improvement solution using a combination of

    dynamic replacement (DR) and prefabricated

    vertical drains (PVD) was carried out to provide

    the necessary foundation treatment for the road

    embankment.

    PRINCIPLE OF DYNAMIC REPLACEMENT

    AND VERTICAL DRAINS

    Dynamic replacement (DR) is a ground

    reinforcement technique whereby stiff elements

    are introduced as inclusions in the ground by heavy

    tamping with the main benefit resulting from the

    structural aspect of the elements themselves. A

    composite soil-element structure, interacting

    through friction and adhesion, increases the

    bearing capacity, improves stability and reduces

    settlement. Inclusion materials are granular

    materials such as sand, aggregate, stone and/or

    rock pieces (up to 300mm size).The technique

    starts out by creating a crater with light tamping.

    The craters are then backfilled with granular

    materials that will lock together under subsequent

    heavy tamping. This technique essentially results

    in large columns of compacted granular material

    up to 2.53m in diameter. Because of the higher

    permeability of this granular backfill material,

    pore-water pressure from the underlying and

    surrounding soft soils will dissipate quickly.

    Hence, DR columns besides being load bearing

    columns (with bearing capacity even up to 80 tons)

    also serve as large vertical granular drains. Since

    spacings of DR columns are typically between 4m

    to 7m, prefabricated vertical drains (PVD) were

    installed between columns to further speed up

    therate of consolidation. Unlike DR columns, PVD

    do not serve any structural function. A typical

    dynamic replacement process is show in Figure 1.

  • S. Sahu, P. J. Rao & K. Yee

    Page 2 of 6

    Fig. 1 Dynamic Replacement Process

    GROUND CONDITIONS

    The site was located in a low-lying broad valley

    between low hills. Ground water table was about

    0.3m below surface. Exploratory boreholes and

    cone penetration tests (CPT) (Figure 2) were

    carried out which indicated an upper layer of very

    soft soils varied from46m thick with organic peat

    interspersed in places up to 2m thick; overlying

    stiff silt/clay layer down to refusal depth at about

    11m. A summary of soil properties is given in

    Table 1.

    Field vane shear tests were carried out and the

    results are shown in Figure 3. The Suvane values

    were corrected according to Bjerrum (1972) with

    correction factor l = 0.8 based on plasticity index

    of 50. The average Su= 13 kN/m2 was used and it

    is compared with the average CPT qc= 0.23MPa

    for the soft layer which corresponds to Su= 15

    kN/m2.

    Fig: 2 Cone penetration test result

    Fig. 3 Field vane shear test result

    Table 1: Ground Condition and SPT Results

    Depth Material SPT N Atterberg

    Limits

    UU Triaxial

    compression

    1-D

    Consolidation

    0-4 m Very soft silty clay with

    organic material (peat) and

    traces of sand

    0 Wn ~ 75%

    LL ~ 79%

    PL ~ 29%

    PI ~ 50%

    C ~ 9-13kN/m2

    = 0o

    Pc ~ 36-50 kPa

    Cc ~ 0.43-0.7

    4-5 m Soft clayey silt 2-4

    5-11 m Firm sandy silt /

    stiff silty clay

    6-11

    > 24

  • Soil Improvement using accelerated consolidation treatment to improve load bearing of soft soil

    Page 3 of 6

    The coefficient of vertical consolidation (Cv)

    varied from 1.17 to 1.91m2/y with an average of

    1.5m2/y. Based on the liquid limit of

    79%,NAVFAC(1982) suggests a Cv= 1.36m2/y.

    For design, Cv= 1.5m2/y and Ch= 3Cv= 4.5m

    2/y

    (Chbeing the coefficient of horizontal

    consolidation) were adopted. The CPT dissipation

    test results suggested an in-situ Ch= 4.1 to 5.1m2/y

    based on Houlsby&Teh (1988).

    PERFORMANCE CRITERIA

    The height of the embankment varies from 5m to

    16m with a crest width of 49m to 250m, wider

    towards the interchange. The slope was at 1V:2H

    with intermediate berm at every 6m height.

    The performance criteria are as follows:

    a) Total settlement within the first 7 years of

    service shall not exceed 10%of the sum of the total

    theoretical primary settlement and secondary

    settlement, the later being assessed for a period of

    20 years;

    b) Settlement within the first 7 years of service

    shall nowhere exceed 400mm;

    c) In areas of transition between piled approach

    embankments and general low embankments,

    differential settlement within the first 7 years of

    service shall not exceed 100mm within a length of

    50m. In areas remote from structures and transition

    zones, differential settlement shall not exceed

    100mm within a length of 100m.

    d) The factor of safety against instability during

    construction shall not be less than 1.2 and after

    construction not less than 1.5.

    DESIGN SCHEME

    Since the construction period was limited to 12

    months, in order to achieve the required

    performance criteria in such a short duration it

    became important to accelerate the consolidation

    process which was not possible to achieve just by

    placing surcharge or using only PVDs with

    surcharge. A combination of DR columns and

    PVD is deemed necessary. The required drainage

    is provided by the DR columns and PVD. In

    addition, the DR columns also serve as a bearing

    support to the embankment so that the required rate

    of filling of embankment can be achieved with

    adequate support of the embankment by its

    foundation during the construction stage as well as

    end-of-construction stage. Without DR columns,

    the rate of filling as well as the final height of the

    embankment may be limited.A closer grid of DR

    columns and PVD was constructed below the slope

    of the embankment to provide edge reinforcement

    for stability. It followed by a wider grid of DR

    columns and PVD constructed below the crest of

    the embankment for normal bearing support.

    FIELD CALIBRATION

    A field calibrationwas carried out on an area of

    500m2 to determine the operational parameters

    (e.g. nos. of blows, drop height, etc.) and to

    validate design assumptions prior to

    commencement of full production works. PVDs

    were installed to an average depth of 56m

    followed by the construction of the DR test

    columns.

    Length of DR columns varied from 4m to 5m. Pre

    and post treatment pressuremeter tests (PMT) and

    CPT were carried out inside the DR columns and

    in-between the columns. The post treatment tests

    were carried out after 14 days. The characteristic

    PMT and CPT values are as given in Table 2.

    Table 2: Characteristic PMT and CPT Values

    Description

    PMT CPT

    Limit

    Pressure

    PL

    Pressure-

    meter

    modulus

    Cone

    Resistance

    qc

    Inside DR

    Columns 1070 kPa 7500 kPa 9MPa

    In-between

    DR Columns 620 kPa 3950 kPa 2MPa

    FIELD TESTING IMPLEMENTATION &

    EVLUATION

    The depth of treatment, as defined by the

    pretreatment CPT and PMT results; followed by

    installation of PVD and DR works; and post

    treatment PMT for quality control and assurance.

    The total treatment area was about 102,000m2. A

    total of 78 CPTs and 36 PMTs were carried out

    prior to PVD and DR works. The post-treatment

    PMT tests were carried out, 14 days after the

    completion of works but, before commencement of

    embankment filling. During embankment

  • S. Sahu, P. J. Rao & K. Yee

    Page 4 of 6

    construction, settlement readings from settlement

    plates placed at 50m distance were analyzed using

    Asoaka (1978) method to predict the final

    settlement. Lateral deformations from

    inclinometers were analyzed usingMatsuo &

    Kawamura (1977) method for stability assessment.

    The criterion of b < 0.25 being the ratio of lateral

    to vertical movement was used for embankment

    stability control.

    Settlement analysis was carried out based on Eq.

    (1) and (2) given by Terzaghi (1967). The soil was

    assumed to be normally consolidated.

    (

    )

    (

    )

    (2)

    Where, Cr= recompression index; Cc= compression

    index; pc= maximum past pressure; = overburden effective stress; = final pressure; eo= initial void ratio and LL = liquid limit.

    Based on the above equations, the computed

    settlement without DR columns (SW/ODR) varies

    from 95 cm to 150 cm for embankment height

    ranging from 5m to 16m. With the DR columns,

    the stiffness modulus of the composite soil-column

    system is increased and hence, settlement is

    reduced. The measured settlement (SDR) obtained

    from settlement plates placed along the centreline

    of the embankment ranged from 32 cm to 65 cm.

    Thus, it is evidenced that the DR columns have

    reduced the settlement and improved the

    performance of the subsoil in comparison to the

    state without DR columns.

    Further the field results were compared with the

    Priebe (1995) predictions of settlement defined by

    an improvement factor n (=SW/ODR/ SDR). The

    friction angle of the DR column material was

    estimated from the limit pressure, PL (Centre

    dEtudes, Menard 1970) measured inside the DR

    pillar. The computation for improvement factor n

    is given in Table 3.

    Maximum settlement of 65 cm was recorded at

    chainage 500 (i.e. about center of treatment area)

    where the soft layer was at maximum 6m thick and

    the embankment height was at 8.4m. The

    settlement characteristic is shown in Figure 4. The

    computed settlement without DR columns is about

    135 cm. Hence, the improvement factor n is 2.07

    compared with 1.96 as computed. Hence, the

    Priebe (1995) method can provide a reasonable

    estimation of settlement reduction with DR

    columns in this project.

    Table 3: Computation for improvement factor n

    DR Columns

    Column diameter 2.9 m

    Grid spacing (square) 5.5 m

    Replacement Ratio (m) 22%

    Friction Angle (c) 34o

    Area of Column (Ac) 6.61 m2

    Grid Area (A) 30.3 m2

    Coef. of earth pressure

    (KAC)

    0.28

    F (s, Ac/A) 0.95

    Improvement factor n 1.96

    The rate of settlement reduced from a peak of

    about 10mm per day during the early stage of

    construction to 0.1mm per day at later stage of

    construction. The ratio of lateral to vertical

    movement (b = dhor/dver) was highest at 0.22 during

    the early stage of filling and reduced quickly to

    0.03 after much consolidation has occurred. The

    maximum total lateral movement recorded was

    about 13cm at the highest embankment.

    BENEFICIAL EFFECTS

    Since the rate of consolidation is affected by the

    available drainage facilities and the rate of filling

    of embankment, the main beneficial effect of using

    DR columns in combination with PVD is that the

    rate of filling of embankment can be accelerated as

    illustrated in Figure4. During the early stage of

    construction, 2.5m of fill was placed over a period

    of 14 days and 4m of fill was completed in 30

    days, averaging about 1m per week. Without DR

    columns, the rate of filling may be limited to the

  • Soil Improvement using accelerated consolidation treatment to improve load bearing of soft soil

    Page 5 of 6

    Fig 4: Settlement Characteristics at Ch. 500

    bearing capacity of the soft soil, typically at about

    0.4m0.5mperweek evenwith PVD. Also, the

    increased rate of consolidation is evidenced by the

    gradient of the time-settlement curve. The rate of

    settlement (mm/day) shows that most of the

    settlement has been achieved during construction

    stage. DR columns and the corset effect provided

    the necessary stability. Stability analyses indicated

    factors of safety greater than 1.25 at all stages of

    construction. During construction, lateral stability

    with ratio b < 0.25 was maintained. Hence, the

    beneficial effect of DR columns to serve as load

    bearing columns and providing vertical drainage in

    combination with PVD especially during the early

    stages of construction has been demonstrated here.

    CONCLUSION

    The design, implementation and performance of a

    combination of dynamic replacement columns and

    prefabricated vertical drains for the construction of

    a high embankment on marginal ground are

    reported. The beneficial effects were demonstrated

    through the accelerated built-up of the

    embankment, accelerated rate of consolidation,

    reduced postconstruction settlement; stability of

    the embankment during construction as well as end

    of construction and the reduced carbon footprint

    compared with the exhibited method of removal

    and replacement. This case history has highlighted

    a ground improvement scheme that is suitable for

    the construction of high embankment founded on

  • S. Sahu, P. J. Rao & K. Yee

    Page 6 of 6

    shallow deposit of soft soils with time constraint

    and promotes sustainable construction.

    REFERENCES

    1. Bjerrum L. (1972), Embankments on Soft Ground, Proceedings Specialty Conference on

    Performance of Earth and Earth Supported

    Structures, ASCE, Vol. 2, pp. 154.

    2. NAVFAC (1982)., Design Manual 7.01 Soil Mechanics, Alexandria, V.A. Department of

    the Navy, Naval Facilities Engineering

    Command

    3. Houlsby G. T. and Teh C. I. 1988), Analysis of the Piezocone in Clay, Penetration Testing

    1988, ISOPT-1,ed. De Ruiter, Balkema (Pubs.),

    Rotterdam

    4. Asaoka A. (1978), Observational Procedure of Settlement Prediction, Journal of Soils and

    Foundations 18(4) 87101.

    5. Matsuo M. and Kawamura K. (1977), Diagram for Construction Control of Embankment on

    Soft Ground, Journal of Soils and Foundations

    17(3) 3752.

    6. Priebe H. J. (1995), The Design of Vibro Replacement, Ground Engineering, pp. 3137.

    7. Centre dEtudes Menard, Determination de la PousseeExercee par un Sol Su rune Paroi de

    Sourenement (1970), Publication D/38/70.

    8. Lambe T. W. and Whitman R. V. (1968), Soil Mechanics JohnWiley& Sons (Pubs.), New

    York, p. 553.

    9. Terzaghi K. and Peck R. B. (1967), Soil Mechanics in Engineering Practice: 2nd

    edition, JohnWiley and Sons (Pubs.), New

    York, p. 729.