6. signalized Intersectionssite.iugaza.edu.ps/wp-content/uploads/file/TMC2012/chapter...
Transcript of 6. signalized Intersectionssite.iugaza.edu.ps/wp-content/uploads/file/TMC2012/chapter...
1
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
6. signalized Intersections
1
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
1. HCM 2000, chapter 162. safety.fhwa.dot.gov/intersection/signalized/sig_int_pps051508
References
/short/sigint_short.ppt3. mason.gmu.edu/~aflaner/CEIE_360/Signalized%20Intersectio
n_ch7_part_1_student.ppt 4. Sarraj, Y. and Almasri , E. 2007, Advanced traffic engineering,
lecture notes.Note: - some slides are quoted from given references.
- text is from HCM.
2
2
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
4-way Intersection Conflicts
32conflict points
3
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Objectives of Signal Timing
• Minimize delay• Minimize delay• Minimize conflicts• Maximize capacity• Reduce crashes
Each objective leads to a different solutionWe must find an appropriate compromise
4
3
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Warrants for the use of traffic signals
A decision on the installation of traffic signals mayA decision on the installation of traffic signals may be made on the basis of:
Traffic flowPedestrian safetyAccident experienceAnd the elimination of traffic conflict.
5
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Warrants for the use of traffic signals
Quick guide: 3Quick guide:For traffic flow:Traffic signals are justified if the following traffic flow exists for eight hours on an average day.
1
2
4
Flow on the major road (1+2) ≥ 900 vehicles/hour and Flow on the minor road (3) or (4) ≥ 100 vehicles/hour.
6
4
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Warrants for the use of traffic signals
For Pedestrian safety:For Pedestrian safety:Signal control offers considerable assistance to pedestrian movements.The Department of Transport in the UK advises that a pedestrian stage is required:
1. if pedestrians across any arm of the junction is ≥ 300 ped./hourped./hour
2. or if turning traffic flow into any arm has an average headway of < 5 seconds and conflicting with a pedestrian flow of ≥ 50 pedestrian/hour
7
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Signal aspectsThe indication given by a signal is known as the signal aspect.g y g g p
The usual sequence of signal aspects or indications in the UK and USA is:
In UK• Red• Red/Amber
In USA• Red• Green and
• Green and• Amber
• Amber
8
5
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Meaning of traffic signal indications
Color Red Red-Amber Green Amber
Signal indication
MeaningStop & keep
stopping
Prepare to go but do not
moveGo
Clear the intersection but do not
cross the stop line
Duration (s) 2 3 9
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Cycle: a complete rotation through all the indications provided. Every legal movement
Terms
p y greceives a “green”Cycle Length (C): time (seconds) for the signal to complete one full cycle. Interval: an interval of time during which none of the lights at a signalized intersection changesCh i t l ll i di ti f iChange interval: yellow indication for a given movement
10
6
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
TermsClearance interval: all red, after yellowGreen interval: green indication for aGreen interval: green indication for a particular movementRed interval: red indication for a particular movementAll-Red: red indication for all approachesPhase: the aspect of a cycle allocated to one the aspect of a cycle allocated to one or more streams of trafficor more streams of traffic
11
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Example: “T” intersection of two one-way streets
Cycle: a complete rotation through all the indications gprovided. Every legal movement receives a “green”
Cycle length: 20 + 3 + 30 sec = 53 sec
12
7
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Permitted Left Turns: a permitted left turn receives a
Terms
p“green” ball but must yield right of way to opposing movements, used when left turn movements are reasonable and gaps in opposing traffic flow are adequate http://www.drivingschool.ca/drivereducation/page16.html
13
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Protected Left Turns:
Terms
provided separate phase, left turn movements are protected by arrow, left turns on one-way or T-intersection are considered “protected” within that phase
http://www.drivingschool.ca/drivereducation/page16.html
14
8
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Protected/Permitted :left turns are given
Terms
left turns are given permitted for part of the cycle and then protected for another part of the cycle or protected and then permitted
Image source: http://www.fhwa.dot.gov/aard/signals.gif 15
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Types of Signal Timing• Isolated Signals:
• Fixed / Pretimed• Fixed / PretimedSignals which have a designated cycle which does not change regardless of flow or time of day
• Semi-actuatedSignals in which a major flow sees green unless: a detector on a minor approach is triggered AND a preset, minimum green time is exceeded on the major approach
F ll t t d• Fully actuatedSignals in which current flow sees green unless: a detector is triggered AND the preset, minimum green time is exceeded on the current approach OR the preset, maximum green time is exceeded
16
9
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Design Process (Webster’s Method)
• Collect Traffic Variables:• Hourly volume• Peak hour volumes for all movements• Peak 15-min volumes for all movements
• Design• Design
17
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Isolated Intersections• Basic Timing Elements:
• Green: Green timeGreen: Green time• Yellow: Yellow time• Effective Green: Green + Yellow – time vehicles are
discharging• All-Red: All movements have red• Intergreen time: Yellow + All-Red• Pedestrian WALK: 4-7 seconds when sign says WALK• Pedestrian crossing time (PCT): time required for a
pedestrian to cross the intersection
18
10
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
General Approach for Signal Timing (step1)
Select phasing plan• Select phasing plan• Calculate design flow rate using peak hour
volume and PHF
19
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Peak Hour Factor (PHF)• Design Hourly Volume (DHV):
DHV = (Peak-Hour Volume / PHF)
Design Hour Volume is the one hour traffic volume used as the basis of designvolume used as the basis of design (usually as a prediction of a future condition)
20
11
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Design Hour Volume
PHF Adjusts volume to match peak 15 minutesj pPHF = 0.85Calculated Volume = 1200 v/hr
DHV=1,200 vph = 1,411 vph0.85
21
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
General Approach for Signal Timing (Step2)
• Find the critical movements or lanes and calculate the critical flow ratios
22
12
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Lane Group• Separates traffic into consecutive movements• Lane groupg p
– set of movements that has same green phase and move together
– Can be one or more lanes• Guidelines for deciding lane groups:
– use separate lane groups for exclusive left-turn lane(s) unless a shared left-through also exists for theunless a shared left-through also exists for the approach
– use separate lane groups for exclusive right-turn lane(s) unless a shared right-through also exists for the approach
23
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Lane Group
24
13
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Saturation Flow Rate
service rate: maximum vehicles that canservice rate: maximum vehicles that can be served in 1 hour assuming continuous green and a continuous queue of vehicles
• Represents capacity for the lane grouph i l t ti d• when signal turns green – reaction and
delay time as vehicles start up, then flow becomes uniform – headway becomes uniform
25
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Saturation Flow Rate
• sat. flow can be determined directly in the field or calculated
• ideal so = 1,900 pcphgpl (passenger cars per hour of green per lane)cars per hour of green per lane)
• adjust so to reflect non-ideal conditions
26
14
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Saturation Flow RateNumber of vehicles that could enter the intersection after initial startup if constant queue p qexisted and constant green
s = _3600_(sec/hour)h
where:s = saturation flow rate in vehicles per hour of
green per lane(vphgpl)green per lane(vphgpl)h = saturation headway (seconds)
27
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
28
15
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
prevailing saturation flow for a specific lane group:
s = so * N * fw * fHV * fg * fp * fbb * fa * fLU * fLT * fRT * fLbp * fRbp
N = number of lanes in lane groupfw = lane width adjustment factorfHV = heavy vehicle adjustment factorfg = grade adjustment factorfp = parking adjustmentfbb = bus blockage factorffa = area type
Ideal saturation flow rate is adjusted to represent all the factors for the lane group which decrease capacity (non-ideal conditions)
LU = lane utilization factor fLT = left turn adjustment factorfRT = right turn adjustment factorfLbp = pedestrian and bike adjustment factor for left turn movementfRbp = pedestrian and bike adjustment factor for right turn movement
)
29
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
30
16
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
31
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
See Appendix D in Chapter 16 of HCM of more details for pedestrian and bicycle blockage
32
17
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Example of pedestrian blockage
33
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Critical Lane Group
• For a given phase: several lanes of traffic on one orFor a given phase: several lanes of traffic on one or more approaches move simultaneously
• One of those movements has the most intense traffic• One lane (movement) requires the most time, all
others require less• Becomes the “design” lane• If sufficient time is given to the critical lane, all otherIf sufficient time is given to the critical lane, all other
lanes moving within the phase will be accommodated• Only one critical lane (movement) per phase
34
18
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Critical Movement or Lane• Movement that requires the most time to
executeexecute• If phase is long enough for the most
critical movement, other movements in phase will be serviced as well
• Can be determined using flow ratios• Movement with highest flow ratio is critical
movement (ratio of flow to saturation flow)
35
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Flow Ratio
• Flow ratio = actual flow• Flow ratio = ___actual flow___saturation flow rate
Flow = 1,200 vph
Saturation flow = 1500 vph
Flow ratio = ____1,200 vph_____ = 0.80
1,500 vph
Same as volume/capacity36
19
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Critical Lane ExampleCritical Lane ExampleFind critical lanes for each phase
(v/s)north = 250/1700 = 0.15Phase 1
Phase 2
(v/s) t = 750/1700 = 0 44 ( / ) 600/1700 0 35(v/s)west 750/1700 0.44
(v/s)south = 300/1700 = 0.18
(v/s)east = 600/1700 = 0.35
37
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Critical Lane ExampleCritical Lane Examplev/s for critical lane group
(v/s) = 0 44(v/s)west 0.44
(v/s)south = 0.1838
20
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
ExampleFor a NB/SB phase the following flows and saturation flow rates are available
Movement Design Flow Rate (pcu/hr) Sat Flow Rate (pcu/hr)Movement Design Flow Rate (pcu/hr) Sat Flow Rate (pcu/hr) NB L,T 600 1200NB R,T 500 1700SB L,T 450 1330SB R,T 720 1600
Which is the critical lane movement?What is the critical flow ratio?
Solution: for NB L,T flow ratio = 600/1200 = 0.5
Movement Flow RatioNB L,T 0.50NB R,T 0.29SB L,T 0.34SB R,T 0.45 39
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
General Approach for Signal Timing (step 3)
• Calculate intergreen time
40
21
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Intergreen Time
Determined based on
The intergreen period of a phase consists of both the yellow (amber) indication and the all-red indication
Determined based on:Stopping Sight DistanceIntersection clearance timePedestrian crossing time – if there are no pedestrian signals (will discuss under minimum green)g ee )
41
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Examples of inter-green periods at a two-phase traffic signal
Intergreen Time
42
22
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Examples of inter-green periods at a two-phase traffic signal
Intergreen Time
43
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
First we calculate the minimum safe stopping
Calculation of Intergreen Time
First, we calculate the minimum safe stopping distance. The equation for this distance is given below .
Minimum Safe Stopping Distance:SD = 1.47*Vo*tr + (1.47*Vo)2/(30*[f ± G])Where:
SD = Min safe stopping dist (ft)SD = Min. safe stopping dist. (ft)Vo = Initial velocity (mph)tr = Perception/Reaction time (sec)f = Coefficient of frictionG = Grade, as a percentage
44
23
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Next, we calculate the time required for a vehicle to
Calculation of Intergreen Time
Next, we calculate the time required for a vehicle to travel the minimum safe stopping distance and to clear the intersection. This is simple kinematics as well.
Intersection Clearance Time:T = (SD + L + W)/(1.47*Vo)
Where:Where:T = Intersection clearance time (sec)Vo = Initial velocity (mph)L = Length of the vehicle (ft)SD = Min. safe stopping dist. (ft)W = Width of the intersection (ft) 45
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Calculation of Intergreen Time
Now that you’ve determined the first two elements of the intergreen period length
•stopping distance and •intersection clearance time
you need to consider the pedestrians.
The intergreen time for intersections that have signalized pedestrian movements is the same as the intersection clearance time.
46
24
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Calculation of Intergreen Time
If you have an intersection where the pedestrian movements y pare not regulated by a separate pedestrian signal, you need to protect these movements by providing enough intergreentime for a pedestrian to cross the intersection.In other words, if a pedestrian begins to cross the street just as the signal turns yellow for the vehicular traffic, he/she must be able to cross the street safely before the next phase y pof the cycle begins.
47
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Calculation of Intergreen Time
The formula for this calculation is shown below.Pedestrian Crossing Time:PCT = W/VWhere:
PCT = Pedestrian crossing time (sec)W = Width of the intersection (feet)V = Velocity of the pedestrian (usually 4 ft/sec)
The intergreen time is equal to whichever is larger, the pedestrian crossing time or the intersection clearance time.48
25
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
General Approach for Signal Timing (step 4)
• Calculate the optimum cycle length
49
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Cycle Length• Cycle should be long enough to serve
critical movements but no longer• If cycle is too short inefficient because of• If cycle is too short -- inefficient because of
time lost to too many changes high compared to usable green time
• If too long, delays will be lengthened as vehicles wait
• Several ways to calculate optimum cycle y p ylength
• Webster's:– most common– minimizes intersection delay– Gives optimum cycle length as a function of lost time
and critical flow ratio 50
26
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Cycle LengthCo = 1.5L + 5
1 - Σ(Yi)where:
Co = optimum cycle lengthL = sum of the lost time for all phasesYi = ratio of the design flow rate to the saturation flow rate for the critical approach or lane in each phase
cycle length should be increased to the nearest multiple of 5 secondsonce have cycle length subtract intergreen time allocate green based on critical movements
51
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Lost Time
• Some time is “lost” as vehicles start upSome time is lost as vehicles start up from a stop until vehicles are progressing at the saturation flow rate through the intersection
• Vehicles utilize some the yellow interval so this adds to the actual time available to vehicles
52
27
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Start up lost time
• Average headway• Average headway is greater than h
• First 3 or 4 vehicles at signal require more time qto react and accelerate than subsequent
53
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Start up lost time• h = saturation headway (seconds)• Average headway for first few vehicles in
queue > h• Start up lost time• l1 = ∑∆i
h– where– l1 = start-up lost time (sec/phase)– ∆i = incremental headway (time > h) for
vehicle i54
28
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Time to discharge Queue• Green time to discharge queue of vehicles• T = l1 + nhTn l1 + nh• Where• Tn = GREEN time to move queue of n
vehicles through signalized intersection for phase
• l1 =start-up lost time• n = number of vehicles in queue• n = number of vehicles in queue• h = saturation headway (s/veh)
55
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Clearance Lost time• Lost time associated with stopping queue
t d f GREEN i l (l2)at end of GREEN signal (l2)• Difficult to observe in field• Time between last vehicle’s front wheels
crossing stop line and initiation of GREEN for next phasefor next phase
56
29
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Total lost time• Lost time due to vehicles starting up at
beginning of green and vehicles stopping at endbeginning of green and vehicles stopping at end of green
• tL = l1 + l2• Where:• tL = total lost time (sec/phase)tL total lost time (sec/phase)• l1 = start-up lost time (sec/phase)• l2 = clearance lost time (sec/phase)
57
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Lost Time for Phase ili = G i + y – G ili = Gai + y Gei
Where:li = lost time for phase iGai = actual green time for phase iy = yellow interval for phase IGei = effective green time for phase iei
58
30
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Lost time includes start-up delay plus any portion of yellow not used for vehicle movement
Image source: http://hcmdev.kittelson.com/Case1/popup_terms/effgreen_popup.htm 59
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Effective green time• Amount of time during cycle that vehicles are moving for
a particular movementp– g1 = Gi + Yi – tLi– Where:– g1 = effective green time (sec) for movement i– Gi = actual green time (sec) for movement i– Yi = sum of yellow interval for movement i
• tLi = total lost time for movement i
• Yi = yi + ari• Where:• yi = yellow interval for movement i• ari = all red interval for movement i
60
31
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Effective Red time
• Amount of time vehicles for a particular t t imovement are not moving
61
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Total Lost Time
• Total lost time for a cycle is given by:
L = Σli + RWhere
L = lost time per cycleli = lost time for phase ii pR = total all red during cycle
62
32
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
ExampleGiven: 3 phases, Calculate the optimum cycle length based on the following information
Phase Critical Flow Ratio Lost Time (sec)1 0.23 62 0.13 43 0.26 7
Solution:
Co = 1.5L + 5 = __1.5(6+4+7) +5___ = 1.5(17) + 51 - Σ (V/s) 1 - (0.23+0.13+0.26) 1 - 0.62
Co = 80.3 sec, use 80 sec63
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
General Approach for Signal Timing(step5)
• Allocate available green based on critical flow ratios
64
33
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Green Split Calculations
• With Co, allocate available green to phasesAll t d b iti l fl ti• Allocated by critical flow ratios
• Each phase receives green consistent with it's ratio of critical flow compared to that for other phases
65
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Green Split Calculations• For phase I:
gi = (V/s)i * GteΣ (V/s)
where:gi = length of green interval for phase i (sec)(V/s)i = critical flow ratio for phase iGte = available green for the cycle (sec)
66
34
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Total Available Green
• Gte = C – L
Where:Gte = total effective green time per cycleC = actual cycle lengthL = total lost time
67
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Example
Given:Given:2 phase cycles = same for both phases= 900 pcu/hravailable green time = 60 sec
Phase 1: critical flow rate = 500 pcu/hrPhase 2: critical flow rate = 250 pcu/hr
68
35
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
ExampleGiven:2 phase cycles = same for both cycles = 900 pcu/hr
il bl ti 60available green time = 60 sec
Phase 1: critical flow rate = 500 pcu/hr, flow ratio = 0.56Phase 2: critical flow rate = 250 pcu/hr, flow ratio = 0.28
Solution for phase I:
g (V/s) * G 0 56 * 60 4040 secsecg1 = __(V/s)1_* GTE___ = __0.56 * 60____ = 40 40 secsecΣ (V/s) (0.56+0.28)
69
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
General Approach for Signal Timing (Step 6)
• Calculate length of minimum green time
70
36
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Minimum Green Interval
• Pedestrian crossing time is the minimum green that can be giventhat can be given
• Pedestrians can only cross intersection as long as no conflicting movements are present (with the exception of permitted left and right turns)
• Sum of green and intergreen must provide time for ped. to cross approach
71
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Minimum Green Interval
• With pedestrian signal Assumptions:• With pedestrian signal Assumptions:– pedestrian walk signal will be on for approx. 7
sec– a pedestrian may begin crossing the street as
DON'T WALK begins to flash– pedestrians walk about 4 ft/secp– WALK interval is contained in the green
interval of the corresponding approach
72
37
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Minimum Green IntervalPt = 3.2 + _L_ + 2.7(Nped) for WE > 10 ft
Sp WEp E
Pt = 3.2 + _L_ + 2.7(Nped) for WE <= 10 ftSp
where:Pt = pedestrian crossing time (sec) for pedestrian signalL = width of intersection (feet)Sp = velocity of the pedestrian (usually 4 ft/sec) --depends on ped.Nped = number of pedestrians crossing during an intervalped p g g3.2 = pedestrian start-up timeWE = effective crosswalk width (feet)
73
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Minimum Green Interval
gmin = Pt - Igmin twhere:gmin = minimum green time (sec)Pt = pedestrian crossing time (sec)I = clearance interval (sec)I clearance interval (sec)
74
38
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
ExampleGiven:Intersection width = 60 feet 12 peds/intervalSp = 4 feet/sec 9 ft crosswalkClearance time is 6 sec.
Gt = 3.2 + _L_ + 0.27(Nped) for WE <= 10 ftSp WE
G = 3 2 + 60 ft + 0 27(12) = 18 6 secGt 3.2 + _60 ft__ + 0.27(12) 18.6 sec4 ft/sec 9
75
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
ExampleGiven:Intersection width = 60 feet 12 peds/intervalSp = 4 feet/sec 9 ft crosswalkClearance time is 6 sec.
gmin = Pt - I = 18.6 sec - 6 sec = 12.6 sec
Pt = 18.6 sec
76
39
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
General Approach for Signal Timing
• Allocate available green based on criticalAllocate available green based on critical flow ratios
• Calculate the capacity• Check design flow rates /capacity and
green intervals/minimum green intervalsg g• Adjust cycle timing if necessary
77
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Adjustments
• Once done need to see if results workM k t i t dj t• Make sure green meets requirements or adjust until it does (ped crossing)
• Check capacity• If significantly below capacity, reduce green time• If close increase• Compute LOS and delay and check
78
40
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Determination for Left Turn Phasing
79
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Left turn phasing• Additional phases increase lost time• Consider protected or protected/permitted:• Consider protected or protected/permitted:
– VLT >= 200 veh/hr– VLT*(vo/No) >= 50,000
Where– VLT = left-turn flow rate– Vo = opposing thru movement flow rates– No = number of lanes for opposing through
movement
80
41
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Left turn phasing
• Usually not provided when Vlt < two hi l l ( k )vehicles per cycle (sneakers)
• When protected left is used for opposing left, consider even if not needed
81
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Protected
• Safest• Recommended when 2 of following are
met– Left-turn flow rate > 320 veh/h– Opposing flow rate > 1,100 veh/hr– Opposing speed limit >= 45 mph– Opposing speed limit >= 45 mph– Two or more left turn lanes
82
42
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Protected
• Recommended when 1 of following is metThree opposing traffic lanes with > 45 mph speed– Three opposing traffic lanes with >= 45 mph speed limit
– Left turn flow rate > 320 and % of HV > 2.5%– >= 7 left turn accidents in 3 years have occurred – Average stopped delay to left turning traffic is
accepatble for fully protecte phasing and engineer judges that additional left-turn accidents will occur
83
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
anua
l 200
0fro
m H
ighw
ay C
apac
ity M
a
43
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Baseline Assumptions
• D/D/1 queuing (deterministic (D) arrival/• D/D/1 queuing (deterministic (D) arrival/ deterministic (D) departure/ 1 server.
• Approach arrivals < departure capacity– (no queue exists at the beginning/end of a
cycle)
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Quantifying Control Delay
• Two approaches– Deterministic (uniform) arrivals (Use D/D/1)
– Probabilistic (random) arrivals (Use empirical equations)
• Total delay can be expressed as• Total delay can be expressed as– Total delay in an hour (vehicle-hours, person-hours)
– Average delay per vehicle (seconds per vehicle)
44
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
D/D/1 Signal Analysis (Graphical)
ArrivalDeparture
Rate ArrivalRate
Rate
Vehi
cles
Queue dissipation
Time
Maximum delay
Maximum queue
Total vehicle delay per cycle
Red Red RedGreen Green Green
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Signal Analysis – Random ArrivalsWebster’s Formula (1958)
45
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Definition – Level of Service (LOS)
• Chief measure of “quality of service”– Describes operational conditions within a
traffic stream– Does not include safety
Different measures for different facilities– Different measures for different facilities• Six levels of service (A through F)
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Signalized Intersection LOS• Based on control delay per vehicle
How long you wait on average at the stop– How long you wait, on average, at the stop light
from Highway Capacity Manual 2000
46
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Typical Approach
• Split control delay into three partsP 1 D l l l d i if i l– Part 1: Delay calculated assuming uniform arrivals (d1). This is essentially a D/D/1 analysis.
– Part 2: Delay due to random arrivals (d2)– Part 3: Delay due to initial queue at start of analysis
time period (d3). Often assumed zero.
( ) ddPFdd ++( ) 321 ddPFdd ++=
d = Average signal delay per vehicle in s/veh
PF = progression adjustment factord1, d2, d3 = as defined above
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Uniform Delay (d1)
⎞⎜⎛ gC 150
( ) ⎥⎦⎤
⎢⎣⎡−
⎠⎜⎝−
=
CgX
CgC
d,1min1
15.01
d = delay due to uniform arrivalsd1 = delay due to uniform arrivals (s/veh)
C = cycle length (seconds)g = effective green time for lane group
(seconds)X = v/c ratio for lane group
47
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Meaning of signal progression
Simple Progression On A One-way Street
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Progression adjustment factor
48
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Progression adjustment factor
2012/3/11 Traffic Control Design TC6 95
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Incremental Delay (d2)( ) ( ) ⎥
⎦
⎤⎢⎣
⎡+−+−=
cTkIXXXTd 811900 2
2⎦⎣
d2 = delay due to random arrivals (s/veh)
T = duration of analysis period (hours). If the analysis is based on the peak 15-min. flow then T = 0.25 hrs.
k = delay adjustment factor that is dependent on signal controller mode. For pretimed intersections k = 0.5. For more efficient intersections k < 0.5.
I t filt i / t i dj t t f t Adj t fI = upstream filtering/metering adjustment factor. Adjusts for the effect of an upstream signal on the randomness of the arrival pattern. I = 1.0 for completely random. I < 1.0 for reduced variance.
c = lane group capacity (veh/hr)
X = v/c ratio for lane group
49
Dr. Essam almasriTraffic Management and Control (ENGC 6340)
Initial Queue Delay (d3)
• Applied in cases where X > 1.0 for the l i i danalysis period
– Vehicles arriving during the analysis period will experience an additional delay because there is already an existing queue
• When no initial queue…– d3 = 0