Eliminate any over-dues in payment to Mazda Japan to achieve a maximum of
14 days between the document dispatching date and the TTR date.
By: 1- Asmaa Metwally 2- Islam Abu Elelaa3- Ahmed El Komy4- Abdelfattah Elghawaby5- Mohamed Amr6- Hend Hesham
![Page 2: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/2.jpg)
1-Define:
1.1 - Identify Project:1.1.1 -Nominate:
Nominated Projectsa Decrease the variation of lead time for sea orders from 9 months to 3 months b Eliminate any over-dues in payment to Mazda Japan
b
Enhance order processing time from the day of receiving the order to be 3 days maximum, instead of 7 days.
![Page 3: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/3.jpg)
1-Define:
1.1 - Identify Project:1.1.2 – Evaluate :
b c a0123456789
10
051015202530354045
Project Evaluation
Importance to Partner Satsfaction from 10percentage
![Page 4: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/4.jpg)
1- Define1.2 Establish The Project1.2.1 Mission Statement: Eliminate any over-dues in payment to Mazda Japan to achieve a maximum of 14 days between the document dispatching date and the TTR date. 1.2.2 Select TeamAsmaa Metwally Islam Abu ElelaaAhmed El KomyAbdelfattah ElghawabyMohamed AmrHend Hesham
![Page 5: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/5.jpg)
1- Define
6 8 10 12 14 16 18 20 22 240
0.02
0.04
0.06
0.08
0.1
0.12
Bell Chart – Days from docs received to TTR
![Page 6: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/6.jpg)
1-Define1.3 Project Charter:
Business caseThis project support Ghabour goal to achieve
supplier and customers satisfaction.
Opportunity StatementAn opportunity to enhance payment to Mazda Japan not to exceed the 14 days payment facility, as the current situation is exceeding the due date in 66.6% of the invoices, to avoid orders delays, enhance credibility, and to enhance customer satisfaction through product availability. Current Sigma Level 1.12
Goal StatementEliminate any over-dues in payment to Mazda Japan
to achieve a maximum of 14 days between the document dispatching date and the TTR date.
To enhance sigma level from 1.12 to 3
Project ScopeFrom document dispatching date to the due of TTR
date
Project Plan Team Selection1- Asmaa Metwally Champion2- Islam Abu Elelaa 3- Ahmed El Komy4- Abdelfattah Elghawaby5- Mohamed Amr6- Hend Hesham
Activity Start EndDefine 1-Feb 8-FebMeasure 8-Feb 15-FebAnalyze 15-Feb 22-FebImprove 22-Feb 27-FebControl
![Page 7: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/7.jpg)
2- Measure: 2.1 SIPOC
Suppliers Inputs Process Outputs CustomersMazda -Soft Copy of
Invoice.-Software
Receive Documents by email
Bank Transfer Mazda
TNTMazda
- Courier - Hardcopy
Receive hardcopy after 2 days
Ghabour - Planning & Stock Control
Revise P.O ,P.R and Amount
Ghabour Admin Deliver to accounting For Approvals
Ghabour Accounting Deliver to treasury for approvals
Ghabour Treasury Bank transfer
![Page 8: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/8.jpg)
2- Measure:
2.2 VOC2.2.1 Critical customer requirements (CCR): To Pay within the 14 days2.2.2 Critical to process: Accuracy of documents
![Page 9: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/9.jpg)
2- Measure:2.3 Define Boundaries2.3.1 Process map2.3.1.1 High Level Flow Diagram
Process
Receive Documents by email
Receive hardcopy after 2 days
Revise P.O ,P.R and Amount
Deliver to accounting For Approvals
Deliver to treasury for approvals
Bank transfer
![Page 10: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/10.jpg)
2- Measure:2.3 Define Boundaries2.3.1 Process map2.3.1.2 Detailed Flow Diagram
Soft Copy Of Invoice
Hard Copy By
TNT
S.P. Revie
w
Bank Transfer Docume
nt
Invoice value
Cash In Advance Docume
nt
S.P. SignReview P.R & P.O
Admin
Account Approva
lAdmin
Treasury dept
review
Treasury Signatur
eAdmin
Acc Dep
Review amountBank
SWIFT Treasury Customer
![Page 11: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/11.jpg)
2- Measure
Value Added Non-Value AddedReceive Documents Spare Parts Department Invoice
decisionsBank Transfer Review PR & POSend Bank SWIFT Print PR & PO
Approvals by S.P.Dept.Review and approvals by Accounting Dept.Review and approvals by Treasury Dept.
Send Documents to Bank
2.3.3 Value Added & Non-Value Added
![Page 12: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/12.jpg)
2- Measure
Bank Acount dep Dhl treasure dep S.part0
20
40
60
80
100
120
0123456789
50
6981
94100
Pareto Diagram
days percentage
2.4 Concentrate on the vital few: (Pareto)
![Page 13: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/13.jpg)
2.Measure
• Focus problem statementDecrease the lead time of the banking and the accounting steps which represent around 70 % of the whole time of the process.
![Page 14: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/14.jpg)
3.Analyze
• Brainstorming• 1- Accounting: • a- long approval cycle (2-5 days)• B- using original document (2days)• C- poor document tracking (no tracking system)• D- no Software available for approvals • E- The KPIs do no reflect the presence of the delay
![Page 15: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/15.jpg)
3.Analyze
• 2-Banking• a- only one bank available (QNB)• B- No credit available (No Letter of credit)• C- Currency constraint (Only Yen)• D-Swift Delay
![Page 16: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/16.jpg)
3.Analyze
• 5 whys tools:• 1-currency availability:
a-need yens b-low flow of this currency in bank
![Page 17: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/17.jpg)
3.Analyze
0 2 4 6 8 10 12 140
5
10
15
20
25
18
1516
8
17
20
1615
13
23
1413
Days To Pay
![Page 18: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/18.jpg)
3.Analyze
• 5 why’s tools:• 1-long approval cycle:• A-Depend on people• B-These people are not available all the time in the building• C- All approvals are done in a hard copy
![Page 19: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/19.jpg)
5.Improve
![Page 20: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/20.jpg)
5.Improve
Item Potential Failure
Potential Effect
Severity
Potential cause of failure
concurrency
current controls
detection
RPN
Recommended action
Target date and resp.
1
Internet connection
problemDelay in
approvals 10 Server problems 3 UPS 3 90
No Mail Follow up Delay in approvals 10 So many mails 5 no 8 40
0Deputy System by first of May
Vacancies Delay in approvals 8 no backup 4 no 8 25
6 Delegation by first of May
2
Vacations Egypt
Wrong counting
from Mazda for the 14
days
8
No communication with Mazda with
the official vacations in
Egypt
5 no 6 240
Communicating annual official
vacations with Mazda
Immediately after getting
Mazda approvals
3
Send documents to Wrong Bank
Delay in Transfer 8
No visual indication on the
bank name8 no 5 32
0
Printing 2 different colors of
envelops with clear big Bank
name
Directly after signing the
contract with the new bank
FMEA
![Page 21: 6 sigma project](https://reader035.fdocuments.us/reader035/viewer/2022070515/5875cef01a28ab8f438b4e3f/html5/thumbnails/21.jpg)
5.Controle
Item Potential Failure
Potential Effect
Severity
Potential cause of failure
concurrency
current controls
detection
RPN
Recommended action
Target date and resp.
1
Internet connection
problemDelay in
approvals 10 Server problems 3 UPS 3 90
No Mail Follow up Delay in approvals 10 So many mails 5 no 8 40
0Deputy System by first of May
Vacancies Delay in approvals 8 no backup 4 no 8 25
6 Delegation by first of May
2
Vacations Egypt
Wrong counting
from Mazda for the 14
days
8
No communication with Mazda with
the official vacations in
Egypt
5 no 6 240
Communicating annual official
vacations with Mazda
Immediately after getting
Mazda approvals
3
Send documents to Wrong Bank
Delay in Transfer 8
No visual indication on the
bank name8 no 5 32
0
Printing 2 different colors of
envelops with clear big Bank
name
Directly after signing the
contract with the new bank
FMEA