COST ESTIMATION FOR 6 MW POWER PROJECT WITH TRAVELLING GRADE BOILER S. No. Description Quoted (Rs. in Lacs) 1.0 Traveling Grade Boiler 30 TPH 400.00 2.0 Feed Water Systems (Deaerator) 20.00 3.0 ESP for Boiler 100.00 4.0 MS Chimney 20.00 5.0 D M Plant 22.50 6.0 Fuel Handling System 80.00 7.0 Cooling Tower 55.00 8.0 Ash Handling System 30.00 9.0 PLC 40.00 10.0 T G set 450.00 11.0 Air Compressor 15.00 12.0 P/P Integral Piping 125.00 13.0 Power Plant Integral Electrical System 125.00 14.0 H O T Crane 10.00

description

calculation

Transcript of 6 MW Travelling Grade 30 TPH 17-1-05

Page 1: 6 MW Travelling Grade 30 TPH 17-1-05

COST ESTIMATION FOR 6 MW POWER PROJECT

WITH TRAVELLING GRADE BOILER

S. No. Description Quoted (Rs. in Lacs)

1.0 Traveling Grade Boiler 30 TPH 400.00

2.0 Feed Water Systems (Deaerator) 20.00

3.0 ESP for Boiler 100.00

4.0 MS Chimney 20.00

5.0 D M Plant 22.50

6.0 Fuel Handling System 80.00

7.0 Cooling Tower 55.00

8.0 Ash Handling System 30.00

9.0 PLC 40.00

10.0 T G set 450.00

11.0 Air Compressor 15.00

12.0 P/P Integral Piping 125.00

13.0 Power Plant Integral Electrical System 125.00

14.0 H O T Crane 10.00

15.0 Lab Equipment 7.50

TOTAL 1500.00

Page 2: 6 MW Travelling Grade 30 TPH 17-1-05

1.0 Power Plant Equipment Cost 1500.00

2.0 Civil Work 200.00

3.0 Erection Work 75.00

4.0 Engineering and Consultancy Charges 30.00

5.0 Miscellaneous charges 10.00

6.0 Taxes and Duties EXTRA

Page 3: 6 MW Travelling Grade 30 TPH 17-1-05

Unit Cost of Power Generation

Sl.No Description 6MW

01 Power Plant Equipment cost in Lacs 1500

02 Civil Cost in Lacs 200

03 Erection Cost in Lacs 75

04 Consultancy Charges in Lacs 30

05 Miscellaneous Charges in Lacs 10

06 Total Project Cost in Lacs 1815.00

07 Annual Power generation (mw x 0.9 x 24 x 330) Units 42768000

08 Power Plant Self Consumption in Units 5132160

09 Power available in downstream in Units 37635840

10 Fuel Requirement in Tones/annum See Break-up

11 Variable Cost (Fuel Cost) Rs750/Tonne in crores See Break-up

12 Fixed Cost (O & M 2.0% of project cost,Interest charges 10%,Depreciation 7.0%,Overheads and others) in crores

Unit Cost of Power Generation In Rupees [100% Husk] =1.71

Unit Cost of Power Generation In Rupees [100% Bagasse] =2.04

Unit Cost of Power Generation In Rupees [50% Husk + 50% Bagasse]=1.88

Page 4: 6 MW Travelling Grade 30 TPH 17-1-05

BREAK UP

i) ANNUAL POWER GENERATION: -

(Capacity (Mw) X Loading Factor X Hours X Shifts in Annum) x 1000= 6 x 0.9 x 24 x 330 x 1000 = 42768000 Units.

ii) POWER PLANT SELF-CONSUMPTION: -

(Mw) X 12% Consumption X Loading Factor X Hours X Shift in Annum X 1000= 6 x 0.12 x 0.9 x 24 x 330 x 1000 = 5132160 Units.

iii) POWER AVAILABLE IN DOWN STREAM: -

Annual Power Generation - Power Plant Self consumption. = 37635840 Units.

iv) FUEL REQUIREMENT: -

As Per Design = Qty Kg/Hr. => Qty x 24 x 330 = Qty Tonnes / Annum1000

v) VARIABLE COST (FUEL COST): -

=> Rs./T x Qty = Crs (Husk cost = Rs. 500/Ton).106 (Bagasse cost = Rs. 500/Ton).

100% Husk =7786 Kg/Hr = 61665 T/Annum= 3.08 Crs.100% Bagasse =10966 Kg/Hr = 86850 T/Annum=4.34Crs.50% Husk =3893 Kg/Hr = 30833 T/Annum=1.54 Crs.50% Bagasse =5483 Kg/Hr = 43425 T/Annum=2.17 Crs.

vi) FIXED COST: -

O & M [2.0 % project cost] => 1815 X 0.020 = 36.30Interest [10 % of project cost] => 1815 X 0.10 = 181.50Depreciation [5 % of project cost] => 1815 X 0.05 = 90.75Overheads & Others [1.5 % of project cost] => 1815 x 0.015 = 27.22

335.77 Lakhs = 3.36 Cr

vii) UNIT COST OF POWER GENERATION: -

= Variable cost + Fixed cost Power Available at Downstream

Page 5: 6 MW Travelling Grade 30 TPH 17-1-05

FUEL QUANTITY REQUIREMENT FOR 30 TPH BOILER

BOILER CAPACITY =30000 kg/hr.

Husk GCV =3200 kcal/hr.

Bagasse GCV =2272 Kcal/hr

Feed Water Temp in Deg.C =130

[1] HUSK REQUIREMENT =(Boiler Capacity X (Steam h1- Feed Water h2) Efficiency X GCV of Husk

= 30000 X (811-130) 0.82 X 3200

= 7786 KG/HR

[2] BAGASSE REQUIREMENT=(Boiler Capacity X (Steam h1- Feed Water h2) Efficiency X GCV of Bagasse

Results:

100% Husk = 7786 Kg/Hr

100% Bagasse = 10966 Kg/Hr

50% Husk = 3893 Kg/Hr

50% Bagasse = 5483 Kg/Hr