6. Gas Lift - Analisis
-
Upload
fernando-aybar -
Category
Documents
-
view
67 -
download
0
Transcript of 6. Gas Lift - Analisis
-
7/16/2019 6. Gas Lift - Analisis
1/37
Gas lift Modelling and Design Ex 61
Example 6
FloSystem User CourseExample 6
Gas lift Modelling and Design
-
7/16/2019 6. Gas Lift - Analisis
2/37
Gas lift Modelling and Design Ex 62
Summary of Work-Flowfor Gas Lift Design
Check if well is naturally flowing
Design with Deepest Poin tto get basicparameters of design
Sensitivity to changing reservoir performancefor bracketing envelope
Select design parameters, valve type and setdesign margins
Do Spacing calculations Do Sizing options - edit required changes
Check un-loading at different conditions - useRe-Calc. Modify design if required
Predict performance with real valves installed
-
7/16/2019 6. Gas Lift - Analisis
3/37
Gas lift Modelling and Design Ex 63
Data Preparation: ReservoirControl
File Example6.wfl
Black Oil, Test Point PI Entry, Vertical Well
-
7/16/2019 6. Gas Lift - Analisis
4/37
Gas lift Modelling and Design Ex 64
Reservoir Control: Oil Fluidparameters
35 API, 0.65 Gas Gravity, 300 scf/bbl GOR
50% w.c, 70,000 ppm salinity
Match any known data - in this case untuned
PVT correlations will be used.
-
7/16/2019 6. Gas Lift - Analisis
5/37
Gas lift Modelling and Design Ex 65
Reservoir Control: InflowPerformance
Test Data : BHFP 1800 psia: 7200 stb/day
Pres 3600 psia, Tres 190 oF
-
7/16/2019 6. Gas Lift - Analisis
6/37
Gas lift Modelling and Design Ex 66
Inflow Performance: IPRModel
Straight Line, Vogel, Norm Pseudo Pressure
Plot Inflow Curve
-
7/16/2019 6. Gas Lift - Analisis
7/37
Gas lift Modelling and Design Ex 67
Inflow Performance:IPR Plot
Comparative Plot for Report Purposes,showing changing performance below Pb
Choose Norm. Pseudo Pressure
-
7/16/2019 6. Gas Lift - Analisis
8/37
Gas lift Modelling and Design Ex 68
Data Preparation: WellDeviation
Enter Deviation Data (survey)
Last Entry to be Mid-Perf depth
-
7/16/2019 6. Gas Lift - Analisis
9/37
Gas lift Modelling and Design Ex 69
Data Preparation: EquipmentData
Install Completion as shown
-
7/16/2019 6. Gas Lift - Analisis
10/37
Gas lift Modelling and Design Ex 610
Analysis: Natural FlowPerformance
Operating Point Calculation
-
7/16/2019 6. Gas Lift - Analisis
11/37
Gas lift Modelling and Design Ex 611
Natural Flow Performance:Inflow/Outflow Plot
No flow without artificial lift
-
7/16/2019 6. Gas Lift - Analisis
12/37
Gas lift Modelling and Design Ex 612
G/L Design: Base CaseDesign Parameters
Gaslift Supply Volume
Gas Supply Pressure
Valve Differential Pressure
Max. depth of Gas Injection
Note: max. depthset to bottom of 4.5
tubing
-
7/16/2019 6. Gas Lift - Analisis
13/37
Gas lift Modelling and Design Ex 613
Gas Lift Base Case - UsingDeepest Point of Injection
Note: Depth of
Injection is output
-
7/16/2019 6. Gas Lift - Analisis
14/37
Gas lift Modelling and Design Ex 614
Gas Lift Design ParameterSensitivity Analysis
Sensivity to Qgi - 1,2,3 and 4 MMscf/day
Sensitivity to CHP - 1000,1200,1400 psia
-
7/16/2019 6. Gas Lift - Analisis
15/37
Gas lift Modelling and Design Ex 615
Results of Design ParameterSensitivity Analysis
Note:
Payback
Ratio
-
7/16/2019 6. Gas Lift - Analisis
16/37
Gas lift Modelling and Design Ex 616
Full Results of DesignParameter Sens. Analysis
Note: Qgi more
crucial than CHP,
but both increase
depth of injection
Depth of injection vs Qgi
7000
8000
9000
10000
11000
12000
13000
14000
0 1 2 3 4
1000
1200
1400
-
7/16/2019 6. Gas Lift - Analisis
17/37
Gas lift Modelling and Design Ex 617
Reservoir Decline SensitivityAnalysis
Target Gas Lift CHP 1200 psia, Qgi 2.5MMscf/day
Reservoir Depleted 800 psi
Increasing Watercut: 50% to 75% 90%
Set Qgi to 2.5 MMscf/day and CHP to 1200psia.
Run a sensistivity analysis with layerpressures of 3600 and 2800 psia forsensitivity 1 and water-cuts of 50,75 and 90%for sensitivity 2.
still using deepest
point of injection
-
7/16/2019 6. Gas Lift - Analisis
18/37
Gas lift Modelling and Design Ex 618
Reservoir Decline SensitivityAnalysis
Results
Inj. Depth increases from 11052 to 13295 asPlayerdrops for 50% water-cut
Inj. Depth decreases by up to 391 ft as Fwincreases (for less Qgi, effect is more)
depth at 50% vs 90% for Pl=2800
If less gas in future then the injection point
will move upwards more severely -tryreducing the lift gas rate to 1 MMscf/day
Note bracketing envelope 11000-13000 ft.
-
7/16/2019 6. Gas Lift - Analisis
19/37
Gas lift Modelling and Design Ex 619
G/L Design: CasingControlled Valves Spacing
Go to Analysis - Gas L if t Design
Design rate 4600 b/d from Deepest Point runs
Deepest Injection 13000 ft. - enter margins
-
7/16/2019 6. Gas Lift - Analisis
20/37
Gas lift Modelling and Design Ex 620
Design Margins
Select Design -Gas lift valve locations nowcalculated.
-
7/16/2019 6. Gas Lift - Analisis
21/37
Gas lift Modelling and Design Ex 621
Example Valve Spacing
Unloading Casing
Pressure(include closing
pressure margin)
Objective Tubing Pressure
(does not include transfer
pressure margins)
Output (at op valve)
-
7/16/2019 6. Gas Lift - Analisis
22/37
Gas lift Modelling and Design Ex 622
Valve where Pc-Pt>Pdiffincluding transfer margins
Valve where Pc-Pt>Pdiffexcluding transfer margins,
ie operating condiditons
Dummy mandrels (Inactive
valves) down to max. depth
- Output (at op. valve)
- Design (to unload)Terminology
-
7/16/2019 6. Gas Lift - Analisis
23/37
Gas lift Modelling and Design Ex 623
Accept Design
To accept design OK from Gas Lif t ValvePosi t ioning- go to Data Preparation - Gas li f tData- gas lift valves now in place.
CHP Updated From
Design
-
7/16/2019 6. Gas Lift - Analisis
24/37
Gas lift Modelling and Design Ex 624
Casing- andTubing-Controlled: orifice sizing
Can edit gas rate (red) Can edit Valve Manufacturer and Model.
(yellow)
Calculates orifice size: can over-write (green)
NOTE: USES THORNHILL-CRAVER ONLY
-
7/16/2019 6. Gas Lift - Analisis
25/37
Gas lift Modelling and Design Ex 625
Casing- andTubing-Controlled: orifice sizing
Can edit pressures (eg, to inc lude margins)and temperature from plot (red)
Calculates if orifice in critical flow
-
7/16/2019 6. Gas Lift - Analisis
26/37
Gas lift Modelling and Design Ex 626
Casing-Controlled: DomePressure Setting
Input valve model required (catalogue). WellFlo will sizeit so that R is approximately 0.2
Calculates Surface Open Pressure, downhole ClosingPressure = PDome, Surface Closing Pressure, and TestRack & setting pressure
Check that upper valves will close at operating pressurefordesign valveoperation
Design valve defaultsto orifice with Pop = Ptube + Pdiff
-
7/16/2019 6. Gas Lift - Analisis
27/37
Gas lift Modelling and Design Ex 627
Casing-Controlled: DomePressure Setting - cont.
Alternative method : specify P surface closeand calculate the operating pressures(ensures that a pressure drop will be seen as
each valve closes)
Note: If spring valve type, no temperature
correction is made to the dome and test rack
pressures
-
7/16/2019 6. Gas Lift - Analisis
28/37
Gas lift Modelling and Design Ex 628
G/l Design: Final DesignPressure/Depth
Example Fluid-
Controlled Design
Increments to ensure fluid
controlled valves will close
-
7/16/2019 6. Gas Lift - Analisis
29/37
Gas lift Modelling and Design Ex 629
Fluid-controlled design -setting increments
Transfer pres margin
Margin at valve 1
Obj. tubing pressure
Increment per valve
-
7/16/2019 6. Gas Lift - Analisis
30/37
Gas lift Modelling and Design Ex 630
Fluid-controlled Valves -Orifice Sizing
For Orifice Sizing need to over write closingpressure (Pt close) by adding P closing transfer margin
Pt close= ob ject ive tubing p ressure+closing pressuremargin+transferclosing pressure margin
The calculation will under-size the orificeneeded on throttling valves: consult Gas LiftCompany supplying valves
Qgas
P tubing
P transfer
P close
P casing
Qgi actual
Qgi Tho.-Crav.
-
7/16/2019 6. Gas Lift - Analisis
31/37
Gas lift Modelling and Design Ex 631
Fluid-controlled Valves -Orifice Sizing
The casing pressure (Pcasing) is calculatedby adding the valve dif ferent ial pressu re:
Pt clos e + valve dif ferent ial pressure This will give the designer input for the
spreadsheet Pt close and P casing
See previous terminology
-
7/16/2019 6. Gas Lift - Analisis
32/37
Gas lift Modelling and Design Ex 632
Any Design: Check Un-loading at Other Conditions
Verify un-loading at other conditions,especially lower Qgi (if full gas not able to beinjected), higher water cut etc.
In these pessimistic cases, can eliminateDesign Margins . Use Re-Calculate
Example with Qgi
reduced to 1.5 and Qlreduced to 3000 bpd
Well not unloaded to
original design valve
Any Design: Check if Reservoir Use any spreadsheet - input
-
7/16/2019 6. Gas Lift - Analisis
33/37
Gas lift Modelling and Design Ex 633
Any Design: Check if ReservoirFluid is Entering Tubing
Projected Kill
Fluid Gradients
At this valve, reservoir fluid
will not enter tubing
Here, reservoir fluid
will enter tubing
Use any spreadsheet input
Ptransfer, TVD and TVD res., and
kill fluid gradient. Check if
Pkill fluid < Pres at datum.
See previous slide forunloading ability check
-
7/16/2019 6. Gas Lift - Analisis
34/37
Gas lift Modelling and Design Ex 634
Gaslift Design Performance -under Operating Conditions
Decide on casing head pressure for operation
Do Not use Forced Gas Entry: WellFlo willcalculate which valve will operate
Make Valves active/inactivein order to modelchange of dummy mandrels for real valves infuture.
Sensisitivity analysis for further completiondesign or for forecasting
Performance Curves vs. Qgi for use inoptimisation (eg FieldFlo)
-
7/16/2019 6. Gas Lift - Analisis
35/37
Gas lift Modelling and Design Ex 635
Gaslift Design Performance -Operating Point
Effect of CHP on production - actual valves:
more CHP => deeper valve => more production
-
7/16/2019 6. Gas Lift - Analisis
36/37
Gas lift Modelling and Design Ex 636
Gaslift Design Performance -Pressure Profiles
Effect of CHP on production-
actual valves: more CHP =>
deeper valve => more product.
Operating valve = solid line
-
7/16/2019 6. Gas Lift - Analisis
37/37
Gas lift Modelling and Design Ex 637
Summary of Work-Flowfor Gas Lift Design
Check if well is naturally flowing
Design with Deepest Poin tto get basicparameters of design
Sensitivity to changing reservoir performancefor bracketing envelope
Select design parameters, valve type and setdesign margins
Do Spacing calculations Do Sizing options - edit required changes
Check un-loading at different conditions - useRe-Calc. Modify design if required
P di t f ith l l i t ll d