Sandbag Construction
US Army Corps of EngineersBUILDING STRONG®
![Page 2: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/2.jpg)
Emergency ConstructionSandbagsSandbags
Typical uses:
• Where a low and relatively short barrier is required
• Constricted areas where there is no room for earthfill levees• ex. back yards, buildings close to channel
• Closures / temporary closures• ex. Roads, railroad tracks
BUILDING STRONG®
![Page 3: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/3.jpg)
Emergency ConstructionSandbagsSandbags
Design section:
• 1:3 cross section (1 foot high for 3 foot width)
5 f t i h i ht• 5 foot maximum height
• 3 foot or less height preferred
BUILDING STRONG®
![Page 4: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/4.jpg)
Filling Sandbags
Fill sacks approximately ½ full
Do not tie sacks
BUILDING STRONG®
![Page 5: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/5.jpg)
Placement of Sandbags
Start upstream
Where possible strip sod / topsoilWhere possible, strip sod / topsoil
Where possible, excavate bonding trench 1 sack deep by 2 sacks widesacks wide
Alternate direction of placement of bags with bottom layer parallel to flowp
Lap unfilled portion of sandbag under new sack
BUILDING STRONG®
![Page 6: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/6.jpg)
Placement of Sandbags (cont.)
Overlap unfilled portion of sack with filled portion of next sack
BUILDING STRONG®
![Page 7: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/7.jpg)
dth: 3 t imes heightdth: 3 t imes height
Placement of Sandbags (cont.)Width: 3 t imes
Height
Width: 3 t imes
Height
Bonding trench:1sackdeep byBonding trench:1sackdeep by
Water side Strip sod before layingbottom layer, if possible
1 sack deep by2 sacks wideWater side Strip sod before laying
bottom layer, if possible
1 sack deep by2 sacks wide
BUILDING STRONG®
![Page 8: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/8.jpg)
Placement of Sandbags (cont.)
Sandbags as weightsSandbags as weights
PolyPoly
Place poly on wet side of sandbag closure to prevent / reduce seepage
BUILDING STRONG®
![Page 9: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/9.jpg)
Placement of Sandbags (cont.) Number of sandbags required per foot of closure vs.Number of sandbags required per foot of closure vs.
sandbag closure height
Height in Feet Bags Required
1 52 103 214 365 55
BUILDING STRONG®
![Page 10: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/10.jpg)
Sandbag placement exercise
BUILDING STRONG®
Sandbag placement exercise
![Page 11: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/11.jpg)
Sandbag ring levee with poly on inside face to
BUILDING STRONG®
prevent seepage
![Page 12: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/12.jpg)
Sandbag ring le ee to contain seepage
BUILDING STRONG®
Sandbag ring levee to contain seepage
![Page 13: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/13.jpg)
BUILDING STRONG®
Sandbags placed at apartment building
![Page 14: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/14.jpg)
Seepage/Erosion Protection:Polyethylene Sheeting and
SandbagsSandbags
BUILDING STRONG®
![Page 15: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/15.jpg)
Seepage/Erosion Protection:Polyethylene Sheeting and SandbagsPolyethylene Sheeting and Sandbags Polyethylene (poly) Sheeting - ~6 mil thick
Sandbags used to anchor poly in place
Pl t i f i l i k Placement is fairly quick
Materials inexpensive
Place materials in the dry or in the wet
BUILDING STRONG®
![Page 16: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/16.jpg)
Seepage/Erosion Protection:Seepage/Erosion Protection:Poly Sheeting and Sandbags (cont)
Placement of poly sheeting and sandbags in the dry
BUILDING STRONG®
Placement of poly sheeting and sandbags in the dry
![Page 17: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/17.jpg)
Seepage/Erosion Protection:Seepage/Erosion Protection:Poly Sheeting and Sandbags (cont)
Placement of pol sheeting and sandbags in the dr
BUILDING STRONG®
Placement of poly sheeting and sandbags in the dry
![Page 18: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/18.jpg)
Seepage/Erosion Protection:Poly Sheeting and Sandbags (cont)
Placement of poly sheeting and sandbags in the wet
BUILDING STRONG®
p y g g
![Page 19: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/19.jpg)
Placement of poly on riverward side of levee to prevent seepage / erosion Poly weighted down with sandbags
BUILDING STRONG®
seepage / erosion. Poly weighted down with sandbags
![Page 20: 5Sandbag Construction 2011 - United States Army Corps of ... Center... · Placement of Sandbags Start upstream Where possible strip sod / topsoilWhere possible, strip sod / topsoil](https://reader034.fdocuments.us/reader034/viewer/2022050203/5f569f1eb8cc9b5b1d18c81c/html5/thumbnails/20.jpg)
Placement of poly on riverside of levee to prevent erosion / seepage
BUILDING STRONG®
erosion / seepage