5/1/2015W. Fish, Portland State University Marathon Site Marathon Battery Cold Spring, NY CERCLA...
-
Upload
ryan-bartell -
Category
Documents
-
view
216 -
download
1
Transcript of 5/1/2015W. Fish, Portland State University Marathon Site Marathon Battery Cold Spring, NY CERCLA...
04/18/23W. Fish, Portland State
University
Marathon Site
Marathon Battery
Cold Spring, NY
CERCLA Cleanup
Project Goals
Project Description
Competitive Analysis
Technology
Resources
Procedures
Schedules & Status
Related Documents
04/18/23W. Fish, Portland State
University
Site Description
On the Hudson River in NY; Two components:
East Foundry Cove Marsh (EFCM) Constitution Marsh
Click for Details
04/18/23W. Fish, Portland State
University
History: US Army
1952: U.S. Army Corps of Engineers Constructed
1953, under Contract with the Army Signal Corps, Sonotone Corporation operated plant to produce nickel-cadmium batteries for use in the Nike missile program
Run under Army ownership 1953-1962; declared “excess proprty in 1962.
Click for Data Sheet
04/18/23W. Fish, Portland State
University
Private Owners
1962: U.S. sold it to Sonotone Corporation.
1967: Sonotone Corporation became a wholly-owned subsidiary of Clevite Corporation
04/18/23W. Fish, Portland State
University
Marathon
1969, Clevite Corporation Merged with Gould, Inc.
1969, Gould, Inc. sold the Plant to Business Fund, Inc.; later changed its name to Marathon Battery Company (MBC)
MBC operated the plant until March 1979.
04/18/23W. Fish, Portland State
University
After the Battery Era
Plant inactive from 3/79 until 11/80 Battery manufacturing equipment
removed and shipped to an MBC plant in Waco, Texas
Sold to the current owner, Merchandise Dynamics, incorporated, for use as a book storage facility
Click for Details
04/18/23W. Fish, Portland State
University
Contaminants of Concern
Cadmium: Cd Toxic to humans, animals and plants Carcinogenic Waste stream had huge amounts of
Cd, mostly as Cd hydroxide (10’s-100’s mg/L)
Also caustic wastes (pH 12-14)
04/18/23W. Fish, Portland State
University
Original Wastewater Treatment System A lift station and piping for transfer of all
process wastewater into the Cold Spring sewer (100,000-200,000 gal/day)
Discharged directly into the Hudson River Bypass Valve Was Installed When the Lift Station Was Shut down or
Overloaded, direct Gravity Discharge Could Be Made into a Storm Sewer
Click for Detailed Schedule
04/18/23W. Fish, Portland State
University
Discharges to EFCM
High dissolved solids and pH 12-14 of the effluent resulted in extreme fouling within the pump and piping
Pumps required shut down and maintenance
Bypass valve was opened and the flow diverted to EFCM about twice a week
04/18/23
Cadmium Load: Approximately 50,000 kg
(over 52 tons) of cadmium may have been discharged to the cove during the life of the plant
About half the metal purchased did not make in into batteries
04/18/23
New Sewage Plant 1965: New York State Department of
Health said Cold Spring must build sewage treatment plant
Battery Plant effluent could not be handled: too toxic
Sonotone ordered to disconnect from sewer
Entire waste flow diverted to storm sewer USACE (1966) told company to quit
discharging to the Hudson
04/18/23
Attempts at Treatment January 1967: NY Dept of Health advised
Sonotone it was in violation Plant given Jan 1, 1970 deadline to
comply with state discharge regulation Sonotone installed treatment equipment Never really worked, Cd kept on flowing NY found lots of Cd in marsh, river
04/18/23
70 Civ. 4110 Judgement of Federal Court Suit brought under Federal Water
Pollution Control Administration against Marathon (pre-EPA)
Enforcement then shifted to new EPA
04/18/23
Relief Sought by U.S. Permanent injunction against
further discharge of Cd and other metals into Foundry Cove
Demanded removal of Cd in sediments
Sept. 1971: Complaint amended, named Sonotone, Cleveite and Gould as additional defendants
04/18/23
Final Judgment (70 Civ.4110) June 1972: Remove all sediment with
Cd >900 ppm (mg/kg) 1971: Discharge was stopped; routed
back to sewer after treatment 1972-1973: Hydraulic dredging by
GOULD Design: Dr. Harry Gregor, Columbia U.
04/18/23
1st Dredging Operation Hydraulic dredging of “hot” areas Dr. Gregor instructed crew to
remove all soft sediment from outfall area (~2-4 ft deep)
Gravel base fairly clean In Cove, Gregor delineated with
stakes 22 acres with Cd > 1000 ppm
04/18/23
On-Site Soil Handling Spoils dewatered in parking lot inside
a temporary dike dewatering leaked all over the place Effluent settle overnight, discharge to
marsh Solids mixed with limestone, scored in
underground vault on site
04/18/23
Areas Dredged Outfall area Channel leading to the marsh Cove:Winter ’72 ice uprooted
stakes and Gregor had to redelineate and finish in spring 1973
About 4000 cu.m. stored in vault
04/18/23
“Satisfaction” April 24, 1974: US Attorney issues
“satisfaction of judgment” Site is off the hook…or isi it? Agreement included monitoring by
NYS Dept. of Environmental Conservation (NYSDEC)
Studies by NYSDEC, EPA, NYU
04/18/23
Whoops, There it Is Studies showed much of area was
still > 900 mg/kg Channel area was recontaminated In fact in 1973 Gregor had to have
channel redredged, but he did not worry about surrounding marsh
Only about 10% of Cd had been removed
04/18/23
Dr. Theo Kneip, NYU 1974: Found the recontamination Found the 1000 ppm zone was 50%
larger than Gregor’s zone just one year before
>50,000 ppm within the area dredged the prior year! (= 5% Cd by weight)
135,000 pmm near the outfall
04/18/23
MBC Internal Memos: “He told Jack that he was working
on a Federal grant and, as a matter of courtesy wanted us to know the Cd background level of the Hudson River is higher in many cases after the dredging than before”
04/18/23
MBC Internal Memos [10 days later] “At any rate he
now reports increased Cd levels in the cove and the river due to the dredging. This does not necessarily bother or surprise us, since this was our prediction and which was basically ignored by the Final Jedgment [sic].”
04/18/23
CERCLA 1980: CERCLA Passed 1981: First National Priority List
(NPL) Prepared Guess what was one of the first
sites proposed for the interim NPL? 1983 went on Final NPL Also OSHA found high Cd dust
inside book warehouse
04/18/23
CERCLA Units
1986 Record of Decision (ROD): Three “Operating Units” (OU’s) Area I: EFCM & Constitution Marsh Area II: Plant, grounds, vault Area III: Cove itself and Hudson
04/18/23
Cd Accumulation in Biota High levels of Cd found in a number of
organisms (e.g., Limnodrilus hoffmeisterii)
04/18/23
ROD Plan: 1986 Dredge Hudson near old sewer
outfall Dredge Cove and EFCM, dewater,
haul offsite Re-vegetate EFCM Leave Constitution Marsh alone
Monitored Natural Attenuation (MNA) 2 other RODS issued ‘88, ‘89
04/18/23
Final Consent Decrees
Marathon, Gould, USACE are Responsible Parties (RP’s)
Total cost $109 million Gould $57M ACOE $43 M Marathon $9M
Insurance paying much of Gould and MBC
04/18/23
Dredging Began 1993 Dredging removed 55,000 cu.yd
sediment to depth of 1 ft. Assumed to get about 95% of Cd this
way Unlike 1972-73, did not shoot for a
specific target concentration Dredging completed in 1994
04/18/23
Marsh Cleanup 1800’ dike, 6-7 ft high 31,000 cu.yd soil excavated,
treated, shipped of site Reconstructed and revegetated
the marsh
04/18/23
Marsh Cleanup
DikeDike
Treatment
Dewatering Pond
Drainage
Stored Sludge
RR Line
Rail Transfer
FoundryCove