5 Reliability Modeling for Utilities Projects –Scouting Phase -- Shell

download 5 Reliability Modeling for Utilities Projects –Scouting Phase -- Shell

of 23

Transcript of 5 Reliability Modeling for Utilities Projects –Scouting Phase -- Shell

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    1/23

    Reliability Modeling for Utilities Projects Scouting Phase

    Ryan Stephens

    Celesta White

    Nazim Nathoo

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    2/23

    Outline

    Introduction & RM Overview

    RM for Utilities Example: Decision-making for Scouting Phase

    Cogen Project

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    3/23

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    4/23

    What is a Reliability Modeling Study? Reliability Modeling Study is a

    - structured process to mathematically simulate the stochasticperformance of plant hardware and process systems as well as

    local/global network of systems. Results can be used by project teams to .

    - ensure current, new and revamped plants can meet definedoperating/project premises such as production levels, availabilitytargets, environmental regulations, etc. For new and revamped

    plants, ensure design meets premise for the lowest capitalinvestment.

    - make objective data-driven decisions around appropriate equipmentcapacity, sparing philosophy and system/hardware selection optionsto meet project premises get the emotion out!

    - assist with defining feed and product contracts as well as security ofsupply

    - determine storage and logistics requirements.

    - assure project funding entities or lenders that their investment willresult in the expected return (production).

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    5/23

    5

    Definition of Terms RM

    Up TimeAvailability = ----------------------------------

    Up Time + Down Time

    Actual (Projected) Production

    Capacity Utilization Production Efficiency = -------------------------------------------Production Capacity*

    *Design, Maximum, Business Plan

    Copyright 2008 by Shell Oil Company. All rights reserved.

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    6/23

    Plant-Wide Reliability

    Individual Product Efficiency Individual Product Volumes

    Traditional

    RAM Modelling

    MaintenanceStrategies

    Unit Availability

    Equipment Availability

    Storage and Inventory Management

    Unit Interdependency

    Operational Flexibilitye.g. Revised Slate

    Slowdowns Back-up Routes

    Component Reliability

    MTTF RCA

    FMEA

    UnitConfiguration

    MTTR

    Sales Strategy / Logistics

    System Configuration

    Reliability Modeling

    Unit

    Restarts

    Unit Capacities

    Utilities

    Unit Utilization PerformanceForecasting

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    7/23

    Applications and Scope This methodology is applied to a wide range of assets, such as:

    - Refineries

    - Petrochemical complexes

    - Gas production and distribution networks- Utility production and distribution networks

    - Systems involving product transport and logistic (shipping, rail,trucks, pipelines)

    - Upstream extraction and processing Depending on the asset and the objectives of the study, the

    scope of the project might include:- Feedstock availability

    - Multiple production plants (down to equipment level)

    - Intermediate tanks

    - Product tanks

    - Product export

    - Utility systems

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    8/23

    Performance Analysis: Typical

    Objectives Quantifying the future performance of the system

    and its components (production and utilization).

    Optimization of the system design (e.g.configuration, redundancy, storage, capacity,equipment sparing, etc).

    Optimization of the asset operations (e.g.

    maintenance philosophy, inventory management,product export, load shedding rules, etc).

    Identification of bottlenecks and key performancedrivers (e.g. where to focus reliability improvement

    efforts). Evaluation and prioritization of investment

    opportunities (based on life cycle cost analysis).

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    9/23

    Reliability Modelingfor Utilities

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    10/23

    10

    RM vs. Excel-based Analyses

    Excel or spreadsheet-based analyses of utility

    systems do not provide a complete, in-depthview of likely outcomes- Such analyses may under or overestimate sparing done via

    N+1, N+2 type approaches.

    Operating reality, of course, involves random,unplanned and stochastic events.

    - RM attempts to emulate real-life behavior by taking into

    account the stochastic operational behavior of bothproducers and users in a utility (or any production) system.

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    11/23

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    12/23

    Background Shell site must comply with upcoming regulations

    limiting emission of NOx, SOx and dust, which cannot

    be done with current equipment and employed fuelmix.

    The objective of the Cogen Scouting Study was to

    identify the future steam balance and optimal steam &

    power generation facilities for the site, in order to:- Comply with emissions regulations,

    - Increase steam & power generation efficiency,

    -Reduce CO2 footprint,

    - Increase reliability,

    - Increase operational flexibility,

    - Allow capability for integration with a potential JV project in

    proximity to the site.

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    13/23

    Scope of Reliability Modeling

    Several options were screened for ranking

    based on NPV, reliability, CO2 efficiency,CAPEX, JV integration, and flexibility of steambalance. These options were narrowed down

    to 3 scenarios for further investigation.

    Shell Global Solutions was asked to conduct a

    more detailed reliability analysis of these

    options to help the project team to betterunderstand the impacts of these options on

    HP steam reliability.

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    14/23

    Basic Assumptions The reliability study was limited to the following scope:

    - HP Steam System Only: The impacts to the MP and LP

    system are impacted by the HP steam demand as defined bythe individual HP steam users.

    - In practice, as much of the scheduled maintenance aspossible will be forced to coincide with plant turnarounds. Asthe turnaround schedule is not yet confirmed, the studylooked at the impacts if all scheduled maintenance could notbe done in conjunction with plant TAs.

    - Cracker trip scenario was included.

    - System Life was 19 years (3 full GT maintenance cycles).

    - Simulation Start Year = 2010.

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    15/23

    Option Descriptions

    Option Description

    Option 0.1

    Base Case: 1 Fr6B GT + 2 end-of-life HP Steam

    Boilers with stand-alone capability + 1 stand-alone HPsteam boiler

    Option 2aMinimum Export Cogen Case: 2 parallel Cogen Trains+ 1 new Auxilliary Boiler

    Option 2b 3P Integration Cogen Case: 1 Cogen Train + 1 newAuxilliary Boiler + 3rd Party Steam Import

    Option 2cInterim Case: 1st Cogen Train + old GT + 2 old HPSteam Boilers

    Option 3Maximum 3rd Party Integration: 2 new Auxilliary

    Boilers + Steam & Power import

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    16/23

    Failure & Scheduled Maintenance DataComponent Failure Mode MTTF (yr) MTTR (hr) Impact (%)Heavy Duty GTs (old) Trip 0.02 2 100

    Unplanned Shutdown 1.00 72 100

    Offline GT Wash 0.17 4 100

    Heavy Duty GTs (new) Trip 0.08 3 100

    Unplanned Shutdown 1.00 72 100

    Offline GT Wash 0.25 4 100

    Heavy Duty GTs (IGCC, syngas) Trip 0.02 2 100

    Unplanned Shutdown 1.00 72 100

    Offline GT Wash 0.17 4 100

    Boilers (old) Trip 0.25 3 100

    Unplanned Shutdown 3.00 144 100

    Boilers (new) Trip 0.50 2 100

    Unplanned Shutdown 3.00 144 100

    HRSG Trip 0.50 2 100

    Unplanned Shutdown 2.00 72 100Offline GT Wash 0.17 1 100

    Cracker Trip 1.00 2 100

    Public HV grid Blackout 25.00 24 100

    Unscheduled Failures

    Component Activity Frequency (yr) Duration (hr)

    Heavy Duty GTs Combustor Inspection 1.0 72

    Hot Gas Path Inpsection 3.0 168Major Overhaul 6.0 504

    IGCC GTs Combustor Inspection 0.5 72

    Hot Gas Path Inpsection 3.0 168

    Major Overhaul 6.0 504

    Boilers (old) Preventative Maintenance 2.0 672

    Boilers (new) Preventative Maintenance 4.0 504

    HRSG (with cold air fan) Preventative Maintenance 4.0 336

    Scheduled Activities

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    17/23

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    18/23

    Overall Plant Availability

    # /

    (/)

    ()

    *

    0. 1 11.

    0. 1 2.

    2. 10 . .% .%

    . 1 . .0% .%

    2. 1 .1 .% .%

    2. 11 . .% .%

    .2%

    .2%

    *

    .

    While the system will operate at 100% steam demandfor over 99% of the time, when there is an outage it isimportant to understand the duration and extent of theexpected outages in order to plan mitigation (i.e., loadshedding) accordingly.

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    19/23

    Results Summary

    While the system will operate at 100% steam

    demand for over 99% of the time, when there

    is an outage it is important to understand theduration and extent of the expected outages in

    order to plan mitigation (i.e., load shedding)

    accordingly.

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    20/23

    Expected Shortfall Duration

    0%

    10%

    20%

    0%

    0%

    0%

    0%

    0%

    0%

    0%

    02 2 2 2 2 2

    0.1

    2

    2

    2

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    21/23

    Expected Shortfall Size

    0%

    10%

    20%

    0%

    0%

    0%

    0%

    0%

    0%

    0%

    12 1210 101 1200 20020 2000 000 0

    0.1

    2

    2

    2

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    22/23

    Conclusions The majority of the outages for Option 0.1

    occur when one boiler is down for

    maintenance (either scheduled or unplanned)and another boiler trips. For this case, GT

    trips do not impact steam production, and is

    therefore the most reliable scenario even withthe less reliable old boilers.

    For the three new cases, most of the outages

    occur when a GT trips (2 hrs) or requires anoff-line wash (4 hours) during an extended

    outage of another steam producer.

  • 8/13/2019 5 Reliability Modeling for Utilities Projects Scouting Phase -- Shell

    23/23

    Conclusions (2) The reliability model provided quantitative

    insight into the differences in both power and

    steam reliability of the various optionsexamined, including expected downtime

    duration & extent so that the project team

    could begin thinking of mitigation and loadshedding options.