5 Phases PMP

download 5 Phases PMP

of 20

Transcript of 5 Phases PMP

  • 7/28/2019 5 Phases PMP

    1/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project Management

  • 7/28/2019 5 Phases PMP

    2/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementWhat is a Project?

    Complex and numerous

    activities.

    Uniquea one-time set of

    events

    Finitewith a begin and

    end date.

    Limited resources and

    budget

    Many people involved,

    usually across several

    functional areas in the

    organizations.

    Sequenced activities.

    Goal-oriented.

    End product or service

    must result.

  • 7/28/2019 5 Phases PMP

    3/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementWhat is a Project Management?

    PLANNING INVOLVES THE ESTABLISHMENT OF CLEAR AND PRECISE

    OBJECTIVES IN ORDER TO REACH A FINAL, STATED GOAL

    ORGANIZING ASSEMBLY OF NECESSARY RESOURCES FOR CARRYING OUT

    THE WORK DEFINED IN THE PLAN

    CONTROLLING MONITOR AND MAINTAIN AS THE PROJECT PROGRESSES

    CHANGE

    INSTITUTING MECHANISMS NEEDED FOR SITUATIONS THATREQUIRE CHANGE

  • 7/28/2019 5 Phases PMP

    4/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementThe 5-Phase Method

    The 5-Phase Method contains specific steps thatexpand the general process into a detailed set ofprocedures.

    1. Define (5 Action Steps)

    2 Plan (5 Action Steps)

    3. Organize (5 Action Steps)

    4. Control (5 Action Steps)

    5. Close (5 Action Steps)

    1 & 2 = Planning; 3, 4 & 5 = Implementation

  • 7/28/2019 5 Phases PMP

    5/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementCauses of Project Failure

    1. The Project is a solution in search of a problem.

    2. Only the project team is interested in the end result.

    3. No one is in charge.

    4. The project plan lacks structure.5. The project plan lacks detail.

    6. The project is under budgeted.

    7. Insufficient resources are allocated.

    8. The project is not tracked against its plan.

    9. The project team is not communicating.

    10. The project strays from its original goals.

  • 7/28/2019 5 Phases PMP

    6/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementProblem Identification

    What is theproblem/opportunity?

    What is to be done? Who is responsible for the

    project?

    When must the project be

    completed?

  • 7/28/2019 5 Phases PMP

    7/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementProject Goals - Identification

    Prepare and launch the new shuttle line Atlantisfrom Earthto the Moon Colony by March 5, 2025.

    Connect Italy with Sicily via the new G.Garibaldiworld'slongest single-span suspension bridge and have it open for

    traffic no later then July 2008. Design and complete testing by April, 2005, of MS Project

    2005, Project Management software.

    Obtain an MSc. Degree in the EESI program from theRoyal Institute of Technology by spring next year.

  • 7/28/2019 5 Phases PMP

    8/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementObjectives Milestones

    The S.M.A.R.T. methodSpecif ic: Be specif ic in targeting an objective

    Measurable: Establish a measurable indicator(s) of progress.

    Aassignable: Make the objective capable of being assigned tosomeone for completion.

    Reali stic: State what can be realistically achieved withinbudgeted time and resources.

    Time-related: State when the objective can be achieved, that is,the duration.

  • 7/28/2019 5 Phases PMP

    9/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementResources, Assumptions and Risks

    Determine preliminary resources:1. The resources were determined without project manager input.

    2. The project manager determined the needed resources based on the plan.

    Identify Assumptions and risks:1. What resources are required to realistically complete this objective? What risks

    are associated with obtaining any of these resources in a timely manner?

    2. What problems and delays are likely to occur in completing this objective?

    3. What effect(s) will delays have on the budget and overall project schedule andplan?

    4. What are the probable time, money, and personell cost overruns to completethis project?

    5. What assumptions can be made to realistically correctfor delays in completing

    this objective within given resources and constraints?

  • 7/28/2019 5 Phases PMP

    10/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementWBS Work Breakdown Structure (1)

    WBS is a simple decomposition process, i.e. a

    hierarchical representation of the project.

    WBS identifies the activities that must be done tobegin

    and complete a project.

    WBS involves the envisioning of the project as a

    hierarchy of a goal, objectives, activities, subactivities

    and work packages.

    Milestones are events that signify the accomplishment or

    completion of major deliverables during a project.

  • 7/28/2019 5 Phases PMP

    11/20

  • 7/28/2019 5 Phases PMP

    12/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementSteps Work Breakdown Structure (3)

    Step 1:

    Divide the project into its major objectives such that the project is fullydefined by the objectives.

    Step 2:

    Partition each objective into the activities that must be done in order toaccomplish the objective.

    Step 3:

    For each activity having one or more missing characteristics divide thatactivity into the subactivities comprising it.

    Step 4:

    Repeat step 3 until all subactivities have the characteristics desired.

    Step 5:

    The lowest-level subactivities in the hierarchy will be the basis of the workpackages that must be done in order to complete the project.

  • 7/28/2019 5 Phases PMP

    13/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementGantt Charts (1)

    History

    developed by Henry Gantt (1861-1919)

    First used in Frankford ammunition shops

    in 1914 (World War I Naval Ships) Milestone markers, time outlines

    Took 80 years to add task dependecies

    popular since inception and is widely used

    today

    precusor of CPM/PERT

  • 7/28/2019 5 Phases PMP

    14/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementGantt Charts (2)

    Project management tool

    Horizontal line or bar chart

    Time ordered listing of planned

    events

    Visual representation of an

    organizations schedule for

    milestones

    Graph with bar representing

    time for each activity

    Ideal for starting project work

    description schedules and plans activities

  • 7/28/2019 5 Phases PMP

    15/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementGantt Charts (3)

    Helps identify

    start of activities

    end of activities

    slack time

    amount of time an activity can be

    delayed without delaying the project

    precedence relationships betweenactivities

  • 7/28/2019 5 Phases PMP

    16/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementPERT Charts (1)

    What is a PERT Chart? Program Evaluation and Review Technique

    Project management tool

    Complex network diagrams

    Used to schedule, coordinate and organize tasks within a project

    History of PERT Charts United States Navy (Polaris Program) 1958

    RAND Corporation Missile Development

    Post World War II (1950s) Critical Path Method/Analysis (CPM) Developed by Du Pont 1957

    Gives managers greater control of larger projects

  • 7/28/2019 5 Phases PMP

    17/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementHow Charts Are Made

    Gantt Charts

    Time across the

    top Tasks listed

    down the sides

    Lines connecting

    dependent tasks

    PERT Charts

    Grouped by most critical

    path Dependencies are

    clearly identified

    Task times are included

    in boxes / circles

  • 7/28/2019 5 Phases PMP

    18/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    The Critical Path for a project is that sequence of dependent tasks thathave the largest sum of most likely durations. The critical pathdetermines the earliest possible completion date of the project.

    Tasks that are on the critical path cannot be delayed without delayingthe entire project schedule.

    The slack time available for any noncritical task is the amount of delay

    that can be tolerated between the starting time and completion time of atask without causing a delay in the completion date of the entire project.

    For each path, sum the durations of all tasks in the path.The path withthe longest total duration is the Critical Path.The critical path for aproject is that sequence of dependent tasks that have the largest sum ofmost likely durations. The critical path determines the earliestcompletion date of the project.The slack time available for any

    noncritical task is the amount of delay that can be tolerated between thestarting time and completion time of a task without causing a delay inthe completion date of the entire project.

    5-Phase Project ManagementSteps Critical Path Method (CPM)

  • 7/28/2019 5 Phases PMP

    19/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementCritical Path Method (CPM)

    The criticalpath is

    highlightedin red

    TASKC

    Fri 2/9/01 2 days

    Fri 2/9/01 0 days

    TASKD

    Tue 2/20/017 days

    Tue 2/20/010 days

    TASKI

    Tue 2/27/015 days

    Tue 2/27/010 days

    TASKE

    Mon 2/19/016 days

    Tue 2/20/011 day

    TASKB

    Wed 2/7/01 2 days

    Wed 2/7/01 0 days

    TASKA

    Mon 2/5/01 3 days

    Mon 2/5/01 0 days

    TASKH

    Thu 2/15/011 day

    Tue 2/20/013 days

    TASKF

    Wed 2/14/013 days

    Fri 2/16/01 2 days

    TASKG

    Fri 2/16/01 2 days

    Tue 2/20/012 days

    Duration

    Slack Time

  • 7/28/2019 5 Phases PMP

    20/20

    Weiss & Wysocky, 1992. Sustainable

    Project Management, 2005

    5-Phase Project ManagementTime, Cost and Project Activities

    Estimating Activity Time: Optimistic completion time

    Pessimistic completion time

    Most likely completion time

    So we can use this formula to

    calculate the EExpectedcompletion time of activity:

    Average activity completion time=E = (O+4M+P)/6

    Formula gives the weighted average

    Estimating Activity Cost:

    Labor

    Materials

    Other direct (travel, telephone,

    contracted services, etc.)

    Indirect (overhead)

    CPM = Critical Path Method

    (sequencing and identifying

    critical project activities)