    C E A CSolar Open lead batteries

    Exploitation andmaintenance of solar openlead batteries

  • 8/7/2019 4_Solar Battery Maintenance

    2/13

    2

    C E A CSummary

    OPzS Solar batteries

    Reminder

    Charging profile.

    Maintenance.Level topping up

    Density checking

    Check cleaness and connectionsDestratification charge

    Cure charge

    Discharge curves

  • 8/7/2019 4_Solar Battery Maintenance

    3/13

    3

    C E A CReminder

    Capacity of OPzS Solar elements is in 120H

    Optimum DOD: 15 20% of C120.

    Exceptional DOD = 80% of C120.

    The energy balance of the system must be positive

    End of discharge voltage in C120 = 1,85V. (Load cut off)

    Safety voltage:Safety low voltage = 1,90V.

    Safety high voltage = 2,50V.

    Electrolyte stratification to be avoided by eletrolyte mixing withovercharging or mixing device

    Deep discharge could lead to cure charging

  • 8/7/2019 4_Solar Battery Maintenance

    4/13

    4

    C E A Charging profile for OPzS solar batteries

    Charging profile with switch

    technology

    Without mixing device: Energy efficiency of thecharging is 81%

    Setpoint between 2,45Vand2,30V.

    Value for 20C (Correction of0,003V per

    C)

    1.90V

    2.00V

    2.10V2.20V

    2.30V

    2.40V

    2.50V

    Day Night

  • 8/7/2019 4_Solar Battery Maintenance

    5/13

    5

    C E A C

    Charging profile with

    destratification

    Energy efficieny of the chargingis 83%

    Morning charging for 1 hour at2,45V

    Then at 2,30V (or 2,30V and2,10 to 2,23V)

    Value for 20C (Correction of0,003V per

    C)1.90V

    2.00V

    2.10V

    2.20V

    2.30V

    2.40V

    2.50V

    Day Night

    Charging profile for OPzS solar batteries

  • 8/7/2019 4_Solar Battery Maintenance

    6/13

    6

    C E A COPzS Solar maintenance

    Maintenance for OPzS solar batteries consist of

    Level topping up

    Density checking before topping up

    Cleaness check

    Connection check

    Destrtaification load if necessaryCure charge if necessary

  • 8/7/2019 4_Solar Battery Maintenance

    7/13

    7

    C E A C

    Level topping up

    The mantenance frequency for solar batteries is very low, it is

    inferior to the maintenance required by the charge controller

    But at each visit to the site it will be good to top up the batteries

    Switch charging profile including morning gas charge

    1 year

    Switch profile with set points at 2,23Vand 2,27V, with use ofFulmix device

    Frequency 2 to 5 years

    OPzS Solar maintenance

  • 8/7/2019 4_Solar Battery Maintenance

    8/13

    8

    C E A C

    Befor topping up batteries you must check the batteryelectrolyte density

    Density must be as follows:Level at MAXI and full SOC estimated = 1,240 0,01

    Level at MAXI and 80% OSC estimated = 1,210 0,01

    Level at AVERAGE and full SOC = 1,260 0,01

    Level at AVERAGE and 80% SOC = 1,230 0,01

    If the values are below it means, either that the SOC is lower orthat there is an electrolyte stratification

    A destratification charge must be conducted, if not sufficient acure charge must be conducted

    OPzS Solar maintenance

  • 8/7/2019 4_Solar Battery Maintenance

    9/13

    9

    C E A C

    Cleaness and connection checking

    When topping up the batteries :

    Clean the cells lid

    AND

    Check connectionsRemove sulfatation tracks with water or Ammonia solution (4%)Grease the connections with silicon grease

    Checck the tightening torque of the connections.

    OPzS Solar maintenance

  • 8/7/2019 4_Solar Battery Maintenance

    10/13

    10

    C E A C

    Destratification charge :

    At least weekly when no Fulmix or morning gassing

    Levels :

    Leave voltage up to 2,60V or maintain over 2,45V during 3 to 5hours

    OPzS Solar maintenance

  • 8/7/2019 4_Solar Battery Maintenance

    11/13

    11

    C E A C

    Cure charging

    If the battery is deeply discharged > 35% DOD, a cure chargingmust be conducted

    In case the battery remains discharged for a long period, a curecharge is required.

    OPzS Solar maintenance

  • 8/7/2019 4_Solar Battery Maintenance

    12/13

    12

    C E A C

    Cure charging procedure

    Charge the battery between 0,02 and 0,04 C100 until end ofcharge signs

    Voltage stabilisation of decrease due to temperature effect.

    Density close to start up values

    Electrolyte temperature must not exceed 45C during charge.Otherwise reduce the charging current or stop the charge untilcooling

    OPzS Solar maintenance

  • 8/7/2019 4_Solar Battery Maintenance

    13/13

    13

    C E A C

    lment SOLAR

    Dcharges diffrents rgimes

    Densit 1,240 25C au niveau maxi

    1 10 100 1000

    1.80

    1.85

    1.90

    1.95

    2.00

    2.05

    2.10

    Rgimes de dcharge

    0.004 C100

    0.008 C100

    0.01 C100

    0.014 C100

    0.019 C100

    0.035 C100

    0.0075 C100

    CEAC SAV Central 02/03/94

    OPzS Solar Discharge curves