4933ch1-2zgfd

6
Engineering Economic Analysis - Newnan Lavelle and Ted G. Eschenbach Chapter 1-2 INTRODUCTION A. Decision Making and Problem Solving 1. Simple Problems: C can generally be worked in one's head without extensive analysis. 2. Intermediate Problems: C primarily economic and the principal subject of this course. C They are sufficiently important to justify serious thought and action. C They can't be worked in one's head; the solution must be organized. C The economic aspects are a significant component in the analysis leading to a decision. C The economic situation is assumed to be in equilibrium. C Single criteria decision making is generally adequate providing the equilibrium assumption holds. 3. Complex Problems: C Such problems represent a mixture of economic, political and humanistic elements. They are beyond the scope of this course from a decision making criteria point of view, but the economic aspects of complex problems will be discussed.

description

dfgdzf

Transcript of 4933ch1-2zgfd

Page 1: 4933ch1-2zgfd

Engineering Economic Analysis - Newnan Lavelle and Ted G. Eschenbach Chapter 1-2

INTRODUCTION

A. Decision Making and Problem Solving

1. Simple Problems:

C can generally be worked in one's head without extensive analysis.

2. Intermediate Problems:

C primarily economic and the principal subject of this course.

C They are sufficiently important to justify serious thought and action.

C They can't be worked in one's head; the solution must be organized.

C The economic aspects are a significant component in the analysis leading to a decision.

C The economic situation is assumed to be in equilibrium.

C Single criteria decision making is generally adequate providing the equilibrium assumption holds.

3. Complex Problems:

C Such problems represent a mixture of economic, political and humanistic elements. They are beyond the scope of this course from a decision making criteria point of view, but the economic aspects of complex problems will be discussed.

C Classic economic theory assumes that the whole economy is in equilibrium (steady state).

C However, Santa Fe Institute studies (Waldrop1, Gell-Mann2) and current economic research indicates that the economy is a self-organizing complex adaptive system which is evolutionary in nature.

1 ?Waldrop, M. Mitchell, COMPLEXITY, The Emerging Science at the Edge of Order and Chaos, Simon and Schuster, New York, 1992.

2 ?Gell-Mann, Murray, The Quark and the Jaguar, Adventures in the Simple and the Complex, W. H. Freeman and Co., New York, 1994.

Page 2: 4933ch1-2zgfd

Engineering Economic Analysis - Newnan and Levelle Chapter 1- 2 The Decision Making Process

A. Recognition of the Problem and Definition of the Goal or Objective

B. Assembly of Relevant Data on Costs and BenefitsManufacturing (Product) Costs: The following cost categories are included in the estimation of manufacturing costs for a production facility. When deciding whether to accomplish a task "in house" or whether to "contract out", for example, failure to account for these categories for both alternatives can bias the decision. 1. Direct Labor and Salary Costs: Estimated labor hours times hourly wage for each

worker. Generally this is a variable cost if the work force can be adjusted to meet volume requirements.

2. Direct Materials and Supplies: A variable cost with overhead and profit added for each handler: jobber, wholesaler, distributor, sub-contractor, etc.

3. Manufacturing Overhead Costs: All costs of manufacturing a product other than Direct Materials and Direct Labor. These costs include Indirect Materials, Indirect Labor (including design and engineering costs), Utility Costs, and Depreciation.

The above costs can also be categorized on the basis of cost-volume considerations:1. Fixed costs: Costs unaffected by production volume: Property taxes, interest on

borrowed capital, insurance, rent, and many overhead costs.

2. Variable costs: Groups of costs that vary proportionately to changes in production volume, including direct labor, materials, direct utilities, sales commissions, shipping costs, etc.

In addition, the following costs should be considered, when applicable:

1. Sunk costs: Past expenditures and investments which cannot be recovered. Sunk costs should be ignored in before tax economic comparisons.

2. (Lost) Opportunity costs: The cost of revenue forgone by failing to use available investment capital to pursue the best rejected project.

3. With and Without costs: Compare what will happen with and without the new investment from various viewpoints.

A primary problem in any engineering project is making good cost estimates in the absence of a readily available cost model and cost data base for various system costs.

C. Identification of Feasible Alternatives for accomplishing the goals and objectives.

Page 3: 4933ch1-2zgfd

D. Selection of the Criteria for Judging which is the Best Alternative: Use of a single criteria vs a weighted average of several criteria.

1. Initial Cost per unit (sometimes used in political decisions to hold down apparent cost)

2. "Life Cycle Cost" per unit is a reasonable criteria when data is available to calculate Equivalent Uniform Annual Cost (EUAC) or Net Present Worth (NPW).

3. Total cost of satisfying mission requirements (unfortunately, not generally used by DOD)

4. Spread the work around to various contractors. (frequently used by DOD to make Congress happy)

5. Accomplish the mission as soon as possible regardless of cost. (ex.: Desert Storm)

E. Prediction of the Outcome for each Alternative: Prepare a cash flow table and make appropriate comparisons based on lifetimes and other known variables.

F. Choice of the Best AlternativeFor strictly economic decisions1 For fixed input situations,

maximize the benefits or other outputs, i.e. get the most "bang for the buck".

2. For fixed output situations,minimize the costs or other inputs

3. For neither input or output fixed,maximize benefits - costs, i.e. profit

For situations where the profit motive is not primary, one is faced with making rational vs political decisions1. Suggested approach for decision support situations: Present at least two

alternatives, both of which are acceptable to your engineering team.

G. Post Audit of Results: Evaluate the analysis model in terms of actual performance.