48 Factors Influence Labour Productivity and the Impacts on Construction Industry-1 (1)
description
Transcript of 48 Factors Influence Labour Productivity and the Impacts on Construction Industry-1 (1)
Seediscussions,stats,andauthorprofilesforthispublicationat:http://www.researchgate.net/publication/272093000
FactorsInfluenceLabourProductivityandtheImpactsonConstructionIndustry
ARTICLE·MARCH2013
1AUTHOR:
SitiHafizanHassan
UniversitiTeknologiMara(PulauPinang)
9PUBLICATIONS4CITATIONS
SEEPROFILE
Availablefrom:SitiHafizanHassan
Retrievedon:31August2015
Caspian Journal of Applied Sciences Research, 2(AICCE'12 & GIZ' 12), pp. 349-354, 2013
Available online at http://www.cjasr.com
ISSN: 2251-9114, ©2012 CJASR
349
AWAM International Conference on Civil Engineering & Geohazard Information Zonation
Factors Influence Labour Productivity and the Impacts on Construction
Industry
Nurulzatushima Abdul Karim
1, SitiHafizan Hassan
2, JuzailahNur Yunus
3, MohamadZain Hashim
4
1Lecturer, UniversitiTeknologi MARA Pulau Pinang: [email protected]
2Lecturer, UniversitiTeknologi MARA Pulau Pinang: [email protected]
3Lecturer, UniversitiTeknologi MARA Pulau Pinang: juzailah.nur@ ppinang.uitm.edu.my
4Lecturer, UniversitiTeknologi MARA Pulau Pinang: mzain.hashim@ ppinang.uitm.edu.my
The construction industry plays an important role in any developing country. This sector will promote the
infrastructure required in socioeconomic development which also a major contributor to the overall economic
growth. One of the main factors that had influence in the construction industry growth is productivity which
mainly associated with the labor performance. Labor in construction industry could be defined as all workforces
involve in the process that had to carry out to accomplish and to achieve goal. The labor productivity
insufficiency will affect the performance of the overall project. This study was carried out to identify the factor
that influences the labour productivity in construction industry and to identify the impacts of labour
productivity in construction. The study is focused on experienced company which is involved in construction and
listed in Pusat Khidmat Kontraktor (PKK). The method adopted was by distributing 100 set of questionnaire to
respondents from contractor Class A until Class C which is listed in PKK and there were only 37 responses
received. The analysis done showed that project management skill was the most important factor that affects the
labour productivity. The positive impact influenced by labour was technology exploration meanwhile project
delay is the negative impacts influenced by productivity of labour in construction industry. By identifying the
factors influencing labour productivity and the impacts in construction, this can help the construction players to
improve the productivity and project performance.
Keyword: labour productivity, factors influence labour productivity, impacts of labour productivity
1. INTRODUCTION
Productivity has been generally defined as the ratio
of outputs to inputs. Construction projects are
mostly labour based with basic hand tools and
equipment, as labour costs comprise 30 % to 50 %
of overall projects cost. Therefore, while numerous
construction labour productivity research studies
have been undertaken, only a few have addressed
the productivity issue in developing countries
factors affecting productivity in the construction.
Productivity in economics refers to measures of
output from production processes, per unit of
input. Productivity may be conceived of as a
measure of the technical or engineering efficiency
of production (Saari, 2006).
There are many factors that influence the
productivity in construction industry. Labour
productivity is one of the most important factors
that affect the physical progress of any
construction project. Construction labourers are
responsible to operate a variety of equipment. To
perform their jobs effectively, construction
labourers must be familiar with the duties of other
craft workers and with the materials, tools, and
machinery they use.
In Malaysia, one of the greatest challenging
faced by the construction industry is to attract and
to attain skilled labour. Low productivity among
the labour will give impacts to the construction
industry such as cost overruns and schedule delays.
Besides that the foreigner labour which is
estimated to constitute 70% of the construction
workforce were reported to be involved in such
social problem, lack of skill and communication
problem. In order to expand the economic growth
and to compete globally, the construction industry
has to continuously improving the standards of
construction especially regarding quality of labour
performance because productivity is part of a key
performance indicator to determine the success of
the project.
Methods for improving construction
productivity among the workers are not possible
without identifying factors that influence
productivity among them. Therefore there are
Abdul Karim et al.
Factors Influence Labour Productivity and the Impacts on Construction Industry
350
important to study about the labour productivity
because this is important factor that contributes to
the productivity which is affected the reputation of
the Malaysian construction industry.
1.1. Factors Influencing the Labour
Productivity in Construction Industry
There are some factors that affect the productivity
of labour in construction industry: (1) Project
Uniqueness; (2) Technology exploration; (3)
Project Management skill; (4) Labour
Organization; (5) Real wage trends; (6) Skill and
development.
Projects in construction are never designed or
built exactly in the same manner as previous
projects due to environmental factors such as the
landscape, weather and physical location and also
aesthetic factors. Project uniqueness requires
modifications in the construction processes where
workers are required to go through a learning curve
at the beginning stages of each project activity
(Tucker et al., 1999).
According to Tucker et al., 1999, lack of
technical and managerial skills is often identified
as one of the major problems of contractors in
developing countries resulting in poor
competitiveness with their well developed and
industrialized counterparts. Technology has a
tremendous effect on overall productivity. Tools
and machinery have increased both in power and
complexity.
Management complicates progress in
productivity within the construction industry. Past
studies found that poor management was
responsible for over half of the time wasted on a
job site. Good management is required for
profitability and success (Tucker et al., 1999). Toor
and Ofori, 2007 have identified that labour morale
is also affected by extensive numbers of changes.
Cross-training and multiskilling can reduce unit
labour costs (Burleson, 1997). Contracts that create
flexible work rules on the job site promise
productivity benefits as well. Barriers between
trades have historically been a source of problems
in construction. Reduction in the percent of the
workforce comprised of organized labour and
improved project agreements with remaining
construction labour organizations have reduced
this problem (Tucker et al., 1999).
Low wages for construction jobs, for instance
very few local labours want to work in
construction industry. Based on studies conducted
by Construction Industry Development Board
(CIDB), the average wage rate in 2007 was RM
70.00 per day for skilled workers and RM 51.00
per day for semi-skilled. An increasing percentage
of open and merit shop work partially drove this
downward trend. Additionally, total compensation
rates may compare with other industries even less
favourably than wage rates suggest, since
construction industry work is have retired, and
younger entrants to the labour pool increasingly
choose career paths other than construction,
creating a skilled labour shortage which is
plaguing the industry.
Based on the research done by Ofori (1991),
training for construction industry in developing
countries is generally contributed to the
performance and effectiveness of both employer
and employees. Training is essential to developing
countries because effective manpower planning
and development plays a crucial role in support of
a flexible and dynamic labour force coping with
the fast technology transfer and industrial growth.
1.2. Impacts of Labour Productivity in
Construction Work
The construction process results in relatively high
costs and labour becomes a more important input
in the production phase. Moreover, the labour cost
is somewhere between 20% and 50% of the total
project cost and reduction of these costs can be
best carried out by the productivity improvement.
At the same time, the success of a construction
company in today’s competitive market largely
depends on accurate estimation of productivity,
and a reasonably correct assessment of the labour
cost is fundamental to the accuracy of any estimate
might be obtained. In addition, the effect of the
factors on productivity may vary from task to task.
Although some factors could have similar
influences on the productivity of a number of
tasks, their rate of impact on productivity may be
different (Kazaz and Ulubeyli, 2003).
There are some ways to overcome the bad
impacts of labour productivity in construction
industry:
(1)increasing skills and experience of
workforce; (2) good management in construction
work; (3) improve motivation among the labour;
(4) reduce the lack of material availability; (5)
decrease the number of foreign labour.
2. MATERIALS AND METHODS
To capture the perception of construction players, a
questionnaire survey was conducted. The
questionnaire is divided into two parts, the first
Caspian Journal of Applied Sciences Research, 2(AICCE'12 & GIZ' 12), pp. 349-354, 2013
351
part requires respondents to provide their personal
particulars including the status of the company,
class of contractor, respondent position, respondent
involvement in construction industry, company
involvement in the construction industry and also
types of contracting activities that the company
involved while the second part focuses on the term
of labour, countries of foreign labour in
companies, factors related to labour productivity in
construction industry, impacts of labour
productivity, management issues that related to
labour productivity and improve the productivity
among the labour.
The questionnaires were sent to the
construction companies who have experience in
construction industry within the list provided by
PKK. Hundred set of questionnaire had distributed
during this research.
Microsoft Excel for Microsoft Professional
Windows XP and SPSS were used to analyses data
collected. The technique of descriptive statistics
was used to describe and make sense of the data.
The data of the analysis focuses on the
interpretation of the output to make predictions
which lead to findings and discussion. The results
of analysis were presented in table and graphical
chart.
There are some assumptions in this study which
refer to difficulties involving the respondents such
as: (1) the ability and readiness knowledge of
respondents to answer the questionnaire. (2) The
questionnaires were sent to the wrong address and
not arrived in time. (3) Respondents are not
interested and cannot give fully cooperate.
3. RESULTS AND DISCUSSION
3.1. Respondents and company background
In the first part of the fieldwork, a total of 100
survey questionnaire was distributed, 37 valid
replies were received from bumiputera and non –
bumiputera contractors, which represents a
response rate of 37% of all questionnaires sent.
Intended for 91.89% of the respondents were
Bumiputera Company followed by only 8.11%
non-bumiputera Company. The large number set of
questionnaire were distributed to the bumiputera
company rather than non- bumi. Table 3.1 shows
the percentage of three classes of contractor
registered with PKK that act as respondent. The
results show the ability or readiness of respondents
is differing from one class to another class. This
also refers to their willingness to answer the
questionnaire which contractor Class A has given
the highest feedback.
Table 3.2 shows the percentage of respondents’
position in the company while Table 3.3 shows the
percentage of year of respondents’ involvement in
construction industry. The fact that they were
senior personnel rendered further validity to the
survey results and most of the respondents had
more than 4 years of relevant experience.
Table 3.1: Analysis on Class of Contractor
Class of contractor Respondent Percentages (%)
Class A 16 43.24
Class B 12 32.43
Class C 9 24.32
Table 3.2: Analysis of Respondent’s Position in The Company
Position Number of Respondents
N
Percentage
%
Chief Executive Officer 4 10.81
Project Manager 11 29.73
Assistance Project Manager 7 18.92
Project Engineer 4 10.81
Site Engineer 6 16.22
Supervisor 2 5.41
Safety Officer 0 0.00
Others 3 8.11
Abdul Karim et al.
Factors Influence Labour Productivity and the Impacts on Construction Industry
352
Table 3.3: Analysis on Respondents’ Year of Involvement in Construction Industry
Year of Involvement Number of Respondents
N
Percentage
%
Less than 3 year 6 16.22
4 to 10 years 16 43.24
11 to 15 years 10 27.03
More than 10 years 5 13.51
3.2. The opinions on the factor that affect
labour productivity in construction
The next results were determined using mean value
data based on the following rating scale:
(1=Strongly Disagree 2=Disagree 3=Natural
4=Agree 5=Strongly Agree)
Mean is a technique to compute the strength of
index familiarity, frequencies and agreements of
specific question. The collected data were analysed
using mean index which is used specifically for the
ordinal scale measurement. The mean index can be
computed by using the SPSS.
All the key factors related to the labour
productivity construction were calculated and
arranged based on the indicate mean response and
whichever values that indicating near to the 1 will
be considered as the highest entry modes decision
of mean response. The mean response for mean
Value was allocated as the following with the
rating scale as below:
1.00 ≤ Mean < 1.50 (Strongly disagree)
1.50 ≤ Mean < 2.50 (Disagree)
2.50 ≤ Mean < 3.50 (Neutral)
3.50 ≤ Mean < 4.50 (Agree)
4.50 ≤ Mean < 5.00 (Strongly agree)
Table 3.4 shows level of agreement for the
factors affecting the productivity of labour in
construction. Analysis shows that all respondents
were agree with the factors listed.
Project management skill was the most
important factor that affects labour productivity in
the construction industry where they deal with
time, money, equipment, technology, people and
materials in managing a construction project.
Proper management will make the labour work
more systematically and more motivation among
them.
Meanwhile, tools and machinery are also
important in influencing labour productivity in a
construction project. Advancement in technology
can significantly modify skill requirements.
Exploration and application of technology will
increase the skill and experienced to the labour
about the machinery, tools and equipment.
Expertise in technology will improve the
productivity among the labour and also will give
good performance of the project.
The other factors agreed by respondents which
would affect labour productivity are skill and
training, project uniqueness and labour
organization. More skill and experience among the
labour will increase the productivity. In addition,
skill will also help the labour to be more confident
when doing their job and at the same time they can
share to each other to increase the productivity. For
a construction project, uniqueness refers to the
environmental factors such as weather and physical
location. This factor is important because a good
condition on workplace can avoid the risk of
accident on site. If the safety and health is high, the
productivity of labour also will increase. Besides
that, contracts that create flexible work rules on the
job site promise productivity benefits.
Data showed that the lowest factor that
influenced the labour productivity is real wage
trends. Basically, the wages of labour depend on
their skill and experience in construction work.
The contractors normally try to minimize the wage
of labour in order to maximize their profit. But, the
reality if the labour get good wages, they are
willing to work hard and at the same time will
increase the productivity.
3.2. Impacts of labour productivity in
construction
From the analysis shown in the Table 3.5, all
respondents were strongly agree that with the
application of new technology in construction
would give positive impacts to labour productivity
where the labours will be trained to the new
technology and this will increase skills among
them. In the other hand, the respondents agree that
low labour productivity will give negative impacts
to the project which is delay in project
development. Low in labour productivity indicates
that there are no proper project management,
Caspian Journal of Applied Sciences Research, 2(AICCE'12 & GIZ' 12), pp. 349-354, 2013
353
Table 3.4: Mean Response for Factors Related to the Productivity of Labour in Construction Industry Factors that influence the labour productivity Mean Value Classification Rank
Project management skill 4.51 Strongly Agree 1
Expand the technology 4.08 Agree 2
Skill and training 3.95 Agree 3
Labour organization 3.78 Agree 4
Project uniqueness 3.62 Agree 5
Real wage trends 3.51 Agree 6
Table 3.5: Mean response for factors that can related as the impact of labour productivity in construction
industry Impacts of labour productivity Mean value Classification Rank
Application new technology by labour can
increase productivity
4.11 Strongly Agree 1
Low labour productivity can causes project delay 4.05 Agree 2
material shortage and other problems in that
particular project.
4. CONCLUSION
The productivity growth in the construction
industry may have considerable effects on the
economic development and stability. Project
management skills were acceptable as the most
important factor that influenced the productivity
among the labour a part of the other factors such as
technology exploration, skill and training, labour
organization, project uniqueness and wage trends.
Project management skill is a major factors
influence the labour productivity. So that, proper
planning is really need to make sure that the
project completed successfully. The project
manager should train themselves to be more
leadership, more innovative, and creative. As a
good leader, they should being a good role model
to their employees. Try to make good relationship
between employee and employer.
The impacts on labour productivity was
identified where it is strongly agree that
technology exploration will increase the
productivity while low labour productivity will
cause delaying of project. Explorations of new
technology or transfer technology are very
essential to develop better performance of project
in line with globalization in construction industry.
Company can send their labour to other develop
country to learn more about the technology from
them. Hence, the new technology knowledge and
skills can be shared and fully practiced in our
country and consequently our construction industry
players would compete globally.
The significant drawn from this study could be
used by the project managers to take into account
of these factors at an early stage. Consequently, it
can increase the productivity of the project besides
minimising the time and cost overrun.
REFERENCES
Abdulllah F, Chiet CV, AnuarK ,Shen TT (2004).
An overview on The Growth and
Development of The Malaysian
Construction Industry.Workshop on
Construction Contract
Management.UniversitiTeknologi Malaysia.
Abdel Razek RH, ElshakourH , Abdel-Hamid M
(2006). Labor Productivity: Benchmarking
and Variability in Egyptian Projects.
International Journal of Project
Management, 25:189–197.
Boswortha D, Massinib S, Nakayamab M (2003).
Quality Change and Productivity
Improvement in the Japanese Economy.
Japan and the World Economy, 17:1–23.
Burleson Rebecca C (2007). An Analysis of
MultiskilledLabor Strategies in
Construction.Dissertation Department of
Civil Engineering, University of Texas,
Austin.
Chan D ,Kumaraswamy MM (1996). A
Comparative Study of Causes of Time
Overruns in Hong Kong Construction
Projects, Department of Civil and Structural
Engineering, University of Hong Kong,
Pokfulam Road, Hong Kong.
CIDB (2008). Malaysian Construction Industry
Master Plan, CIDB Malaysia.
Abdul Karim et al.
Factors Influence Labour Productivity and the Impacts on Construction Industry
354
Davidson M, GuildingC, Timo N (2006).
Employment Flexibility and Labour Market
Practices of Domestic and MNC Chain
Luxury Hotels in Australia: Where has
Accountability Gone? Hospitality
Management, 25:193–210.
Eliufoo HK (2006). Gendered Division of Labour
in Construction Sites in Zanzibar.Women in
Management Review 22.
Enshassi A (1996). Training for Palestinian
Engineers to Face The Challenges of
Multinational Enterprises in the Gaza Strip.
Building Research and Information,
24(4):222−227.
GhoshBN (1998). Malaysia the Transformation
within a Socioeconomic
Perspective.Addison Wesley Longman
Malaysia Sdn Bhd.
Grip AD,Sieben I (2003). The Effects of Human
Resource Management on Workers' Wages
and Firm Productivity, Faculty of
Economics and Business Administration
Maastricht University.
Haas CT, Borcherding J D, Allmon E,Goodrum P
M (1999). U.S. Construction Labor
Productivity Trends, 1970-1998. Center for
Construction Industry Studies the University
of Texas, Austin.
Kaming PF, Holt GD, KometaSK ,Olomolaiye PO
(1998). Severity Diagnosis of Productivity
Problems A Reliability Analysis.
International Journal of Project
Management, 16(2):107-113.
KazazA,Ulubeyli S (2003). A Different Approach
to Construction Labour in Turkey:
Comparative Productivity Analysis.
Building and Environment, 39:93 – 100.
Kuismanen M (1997). Labour Supply,
Unemployment and Income Taxation: An
Empirical Application, Government Institute
for Economic Research.
Mei Y (2006). Extended Overtime and the Effect
to Labour Productivity in Construction:
Workers Perspective, Faculty of Civil
Engineering UniversitiTeknologi Malaysia.
MojahedS,Aghazadeh F (2006). Major Factors
Influencing Productivity of Water and
Wastewater Treatment Plant Construction:
Evidence from the deep south USA.
International Journal of Project
Management, 26:195–202.
Ofori G (1991). Programmes for Improving the
Performance of Contracting Firms in
Developing Countries: A review of
Approaches and Appropriate Options.
Construction Management and Economics,
9(1):19−38.
Tucker R., Haas C, Borchedung J , Pail EA
(1999). U.S. Construction Labor
Productivity Trends, 1970-1998, From the
center for construction industry Studies,
Report No.7.